lhc commissioning and first operationlhc commissioning and first operation ppc 2010, july 12, 2010,...

55
LHC Commissioning and First LHC Commissioning and First Operation Operation PPC 2010, July 12, 2010, Turin, Italy Steve Myers Director for Accelerators and Technology, CERN Geneva (On behalf of the LHC team and international collaborators)

Upload: others

Post on 10-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

  • LHC Commissioning and First LHC Commissioning and First Operation Operation

    PPC 2010, July 12, 2010, Turin, ItalySteve Myers

    Director for Accelerators and Technology,

    CERN Geneva

    (On behalf of the LHC team and international collab orators)

  • � The LHC(reminder)

    � The last 18 months (rapidly)�The Accident�The Repair and consolidation� Initial Commissioning�Present status and plans

    Topics

  • S. Myers QUB March 11, 2009S. Myers QUB March 11, 2009 33

    Superconducting Proton Accelerator and Colliderinstalled in a 27km circumference underground tunnel (tunnel cross-

    section diameter 4m) at CERNTunnel was built for LEP collider in 1985

    The LHC

  • LHC: Some Technical Challenges

    Circumference (km) 26.7 100-150m underground

    Number of superconducting twin-bore Dipoles

    1232 Cable Nb-Ti, cold mass 37million kg

    Length of Dipole (m) 14.3

    Dipole Field Strength (Tesla) 8.4 Results from the high beam energy needed

    Operating Temperature (K) (cryogenics system)

    1.9 Superconducting magnets needed for the high magnetic field

    Super-fluid helium

    Current in dipole sc coils (A) 13000 Results from the high magnetic field1ppm resolution

    Beam Intensity (A) 0.5 2.2.10-6 loss causes quench

    Beam Stored Energy (MJoules) 362 Results from high beam energy and high beam current1MJ melts 1.5kg Cu

    Magnet Stored Energy (MJoules)/octant

    1100 Results from the high magnetic field

    Sector Powering Circuit 8 1612 different electrical circuits

  • S. Myers QUB March 11, 2009S. Myers QUB March 11, 2009 55

    InterconnectionsInterconnections

    During cool-down of the LHC the machine contracts by 80 metres, 10m per octant

    •Vacuum continuity

    •Electrical connections

  • 66

    Accident of September 19Accident of September 19 thth 20082008

    �� Following a very impressive startFollowing a very impressive start --up with beam on up with beam on September 10, 2008September 10, 2008

    �� During a few days period without beamDuring a few days period without beam

    �� Making the last step of dipole circuit in sector 34 , to Making the last step of dipole circuit in sector 34 , to 9.3kA9.3kA

    �� At 8.7kA, At 8.7kA, development of resistive zone in the dipole development of resistive zone in the dipole bus bar splicebus bar splice between Q24 R3 and the neighbouring between Q24 R3 and the neighbouring dipoledipole

    �� Electrical arc developed which punctured the helium Electrical arc developed which punctured the helium enclosureenclosure

  • 88

    Bus bar spliceBus bar splice

  • Absence of soldering

    Resistance 220 nOhm Bad contact with stabilizer

    No sensitive detection on bus bar

    Thermal runaway

    Meltdown, open circuit Power converter fast discharge

    Electrical arc

    Fault tree [1/3]

    Electro-thermal model

    Observed on magnet

  • Fault tree [2/3]

    Electrical arc

    Beam pipe perforationHe vessel perforation Soot

    He discharge in insulation vacuum

    Contamination by sootInadequate sizing of relief devices (MCI)

    Pressurization of vacuum enclosures

    Mechanical damage to MLI

    Contamination by MLI

    ODH in tunnelBlast

    Trip AUG

    Loss of beam vacuum

    Break vent door

  • Fault tree [3/3]

    Pressurization of vacuum enclosures

    Pressure forces on vacuum barriers

    Plastic deformation of shells Buckling of bellows

    Rupture of supports and ground anchors

    Displacement of magnets

    Mechanical damage to interconnects

    Secondary electrical arcs

    Damage to tunnel floor

    Used to estimate max pressure reached

  • 1313

    ConsequencesConsequences

  • Electrical arc between C24 and Q24

    M3 line

    V lines

  • Collateral damage: secondary arcs

    QQBI.27R3 M3 line

    QBBI.B31R3 M3 line

  • 1616

  • + 8 cryogenics!

    Phase 1 +2

  • Pyramid for Splice Mapping

    Current in the Dipoles as function of time

    Maya Pyramid

  • QPS team

    1nΩ

    Splice Mapping of Quadrupoles

  • 20

    A78.RB: Normalized Bus Segment Resistance

    Every single sc splice were measured in 2009

    1nΩ

  • Decided Scenario 2010-2011

    � Run at 3.5 TeV/beam up to a integrated luminosity of around 1fb-1.

    � Then consolidate the whole machine for 7TeV/beam (during a shutdown in 2012)

    � From 2013 onwards LHC will be capable of maximum energies and luminosities

  • 2222

    Why are we limiting the beam energy to 3.5TeV in 2010-2011?

    All the work we have done since November 2008 makes us certain that a repeatof September 19 can NEVER happen.

    The offending connector in this incident had an estimated resistance of 220nΩ. We have measured all 10,000 inter-magnet connectors and the maximum resistance we have seen is 2.8nΩ.

    BUT in April 2009, we have uncovered a different possible failure scenario which could under certain circumstances produce an electric arc in the “copper stabilizers” of the magnet interconnects

  • First Collisions at 7TeV cmMarch 30, 2010

  • March 30 2010

    MOPEC003/4 Fuchsberger et alMOPEC014 White et al

  • 30/3/201030/3/2010 11:15 injected again12:38 : At 3.5 TeV

  • Soon after the first Collisions

  • 2727

    A very good 48 hour period!

  • IP1&5 lumi vs squeeze

    � Raw (online) lumi plots on 10 apr 2010, during the squeeze to 2m in IP1 and IP5

    � Factor gained (raw numbers):� ~4.5 in Pt5 (after min scan)� ~4 in Pt1

    � Not corrected for lumi decay over the ~5h of squeeze and mini scans

    atlasatlas

  • LHC Design Bunch Intensity: Thursday 15.4.2010

    � Higher intensity � Over-injection working well

    � Over-injected 1.1E11, with collimators at nominal 4.5 sigma settings.

    � Emittance at 1E11: 2.5 um H, 2,3 um V.

    29 29

  • Loss map for offLoss map for off --momentum error. All OK. See expected low leakage momentum error. All OK. See expected low leakage to experimental IR's. to experimental IR's. OK for stable beams from coll.OK for stable beams from coll.

    IR1IR1

    IR2IR2

    IR5IR5IR8IR8

    factor 10,000factor 10,000

    Qualification: OffQualification: Off --momentum collimationmomentum collimation

  • Transverse Damper: Damping Beam Excitations

    OFF ON

    Crucial device to keep emittance growth

    under control!

    Wolfgang Hoefle et al

    3131

    Transverse Damper will stabilize against the Hump

  • Collisions with design current at 450GeV

  • Second fill with better lifetime conditions for B1 after RF phase loop adjustment.

    Stable beams at design current per bunch at 450GeV

  • Closing Collimators During Ramp

    LHC statusLHC status 8/6/2010

    R. Assmann

  • Pushing Number of 2e10 Bunches

    LHC statusLHC status 8/6/2010

    48 hours

    2 x 2e10 � 4 x 2e10 6 x 2e10 per beam

    Allowed doubling the integrated luminosity for 2010

    within 48 hours!

  • 13 bunches: 3x1029 !!

    LHC status LHC status -- week 20&21week 20&21

  • Recent progress/Changes� Until 9 June, machine time shared between

    physics and machine studies.� Physics with ~2x1010 protons/bunch� Machine studies to develop 1x1011 protons per bunch

    � Beam Stored energy is the metre stick: (Machine Protection)� Lost particles must end up on collimator or dump

    Following discussions with the 4 spokespersons and the physics coordinator, a decision was unanimously made on 9 June to

    concentrate on “Machine studies to develop 1x1011 protons per bunch” until it was operational. This meant postponing physics data

    taking for around 3 weeks. (Minutes LMC 9th June)2

  • Getting to Stable beams at 1.1x1011.Instabilities in Collision at 3.5TeV/beam

    � longitudinal emittance control� In the SPS� During the ramp in the LHC

    � Transverse damper working� Collimators set up� Injection set up for new high intensity� Beam dump set up for higher intensity

    � Started physics data taking under these conditions on Saturday 26th June (almost a week ahead of estimates)

  • Ramps for Operations set up for 1011 protons/bunch

  • 26th June: 5x1029 with 3 bunches/beam; 1011/b

  • 6-8x1029cm-2s-1 with 3 bunches per beam;1011/b

    29th June, new record

  • 2nd July: Colliding 6 bunches per beam; 1011/b

  • New Record Lumi > 1e30 cm-2 s-1

    LHC statusLHC status 8/6/2010

  • Beam Lifetime

    LHC statusLHC status 8/6/2010

    Collisions

    ALICE

  • Beam Intensity Losses

    LHC statusLHC status 8/6/2010

  • Tune: Coherent Excitation

    LHC statusLHC status 8/6/2010

  • Better but not perfect stability…

    LHC statusLHC status 8/6/2010

    Intensity Luminosity

    Tuni

    ng

  • Integrated Luminosity on 7th July

  • S. Myers QUB March 11, 2009S. Myers QUB March 11, 2009 4949

    Latest News from this morning

  • Summary of Milestones thus far

    � 30 March: first collisions at 3.5TeV/beam

    � 19 April: order of magnitude increase in luminosity � doubling the number of particles/bunch� β * from 11 to 2m (4b/beam) L ~2x1028.� Beam lifetimes of ~1000 hours

    � 22 May another order of magnitude:� 13 bunches in each beam (L~ 3x1029)

    � 26 May: Design intensity bunches were brought into collision at 3.5TeV/beam.

    � 2nd July peak luminosity of 1030cm-2s-1.

  • Presently

    � From experience so far� No fundamental issue for 1e30 luminosity� Further equalize beam parameters (emittance, intensity, …) while

    delivering luminosity. Try to get nominal beam and bunch parameters, including variations.

    � As stability is improved, push up again on luminosity

    � In addition:� Cross calibrate emittance measurement devices.� Push transverse damper into full operation in collision, however,

    possibly needs noise reduction.

    LHC statusLHC status 8/6/2010

    Aim is for 1032 before the end of 2010 which is needed for an integrated luminosity of 1fb-1 before end of 2011

  • Peak lumi (in STABLE BEAMS)(modulo some possible luminometers down time...) Fills 1005-1199Fills 1005-1199

    ~70 days~70 days

    1e32 !!1e32 !!

  • 5353

    The work summarized here is the result of work carried out by hundreds if not thousands of scientists, engineers and technicians both employed by CERN and very importantly by the many institutes which collaborate with CERN.It is a great personal pleasure to acknowledge the incredible contributions and dedication of such a wonderful team.

    Acknowledgements

  • Thank you for your attention

  • Clamped and shunted

    MOPEB042 Bertinelli et al.