levelized cost of energy calculation_bv_en
TRANSCRIPT
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
1/16
1:1: LevelizedLevelized Cost of EnergyCost of Energy
CalculationCalculationMethodology and Sensitivity
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
2/16
- 2
What is LCOE?Levelized Cost of Energy (LCOE) is the constant unit cost (per kWhor MWh) of a payment stream that has the same present value as the
total cost of building and operating a generating plant over its life.
Initial Investment and Annual Costs
LCOE
$0
$250,000
$500,000
$750,000
$1,000,000
0 2 4 6 8 1 0 1 2 1 4 1 6 1 8 2 0
Year
A n n u a l
C o s t
( $ )
$50
$75
$100
$125
$150
L C
O E ( $ / M W h )Equity Investment
Debt ServiceOperating ExpensesTaxesLCOE
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
3/16
- 3
Why Use LCOE?
Very useful in comparing technologies with differentoperating characteristics
LCOE Range based on Capacity Factor Range
0 0.5 1 1.5 2
Wind - Onshore
Wind - OffshoreShallow
Wind - Offshore Deep
Solar PV
Solar Thermal
Levelized Cost of Energy (RMB/kWh)
Typically, LCOEs arecalculated over 20 to 40
year life, and are givenin the units of currency
per kWh or MWh
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
4/16
- 4
Different Ways to Calculate LCOE.
Simplified LCOE Approach1. Using a discount rate i , the capital
recovery factor ( CRF ) is:
CRF =
2. The sLCOE is the minimum price atwhich energy must be sold for anenergy project to break even (orhave present value of zero)
sLCOE =
Discount rate
Used to convert futurecosts to present value.
Typically based on marketinterest rates or weightedcost of capital (WACC),with or without adjustmentsfor risk and uncertainty.
Can vary depending on the
entity.Can be Real or Nominal
[(capital cost * CRF)+ fixed O&M cost]
(8.76 * capacity factor)+ (variable O&M cost * output )
i(1 + i) n
[(1 + i) n ]-1
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
5/16
- 5
Different Ways to Calculate LCOE.Financial Model Approach
Financial model that solves forthe required revenue (LCOE) toachieve a certain internal rate ofreturn (IRR).
Captures impacts of taxincentives and depreciation.
Captures more complexfinancing assumptions andrevenue requirements for an IPP
Cost of Generation CalculatorAll inputs are in blue .
Technology Assumptions Financial/Economic AsumptionsProject Capacity (MW) 1 Debt Percentage 50%Capital Cost ($/kW) $2,000 Debt Rate 8.00%Fixed O&M ($/kW) $50 Debt Term (years) 15Fixed O&M Escalation 2.5% Economic Life (years) 25
Variable O&M ($/MWh) $0 Percent 5-year MACRS 0%Variable O&M Escalation 2.5% Percent 7-year MACRS 0%Fuel Cost ($/MBtu) $0 Percent 15-year MACRS 0%Fuel Cost Escalation 2.5% Percent 20-year MACRS 100%Heat Rate (Btu/kWh) 0 Energy Price Escalation 0.0%Capacity Factor 35% Tax Rate 50%Misc Revenue ($/MWh) $0 Cost of Equity 14.00%Misc Escalation 2.5% Discount Rate 9.000%Degradation 1%
Year 0 1 2 3 4 5
Annual Generation (MWh) 3,066 3,035 3,005 2,975 2,945LCOE $139.35 $139.35 $139.35 $139.35 $139.35Misc Revenue $0.00 $0.00 $0.00 $0.00 $0.00Total Operating Revenu $427,249 $422,976 $418,746 $414,559 $410,413
Fixed O&M $50,000 $51,250 $52,531 $53,845 $55,191Variable O&M $0 $0 $0 $0 $0Fuel Cost $0 $0 $0 $0 $0Operating Expenses $50,000 $51,250 $52,531 $53,845 $55,191
Interest Payment $80,000 $77,054 $73,872 $70,435 $66,723Principal Payment $36,830 $39,776 $42,958 $46,395 $50,106Debt Service $116,830 $116,830 $116,830 $116,830 $116,830
Tax Depreciation - 5 $0 $0 $0 $0 $0Tax Depreciation - 7 $0 $0 $0 $0 $0Tax Depreciation - 15 $0 $0 $0 $0 $0Tax Depreciation - 20 $75,000 $144,380 $133,540 $123,540 $114,260Taxable Income $222,249 $150,292 $158,804 $166,739 $174,239PTC $0 $0 $0 $0 $0Taxes $111,124 $75,146 $79,402 $83,370 $87,120
Total (1,000,000) 149,295 179,750 169,984 160,515 151,273
S A M P
L E F I N
A N C I A
L
M O D E
L
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
6/16
- 6
Real or Nominal LCOE?1. Real LCOE (2010 RMB/kWh) Constant stream of values denoted in todays
currency (Real)
2. Real LCOE (with Inflation) (RMB/kWh) Nominal path that maintains Realvalue constant (Nominal)
3. Nominal LCOE (RMB/kWh) Constant stream of values in nominal currency.(Nominal)
Nominal vs. Real LCOE
2.) Real LCOEwith Inflation
(Nominal)
3.) Nominal LCOE
1.) Real LCOE(2010RMB)
0.40
0.50
0.60
0.70
0.80
0.90
1 2 3 4 5 6 7 8 9 1 0 1 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9 2 0
Year
N o m
i n a l ( R M B / k W h )
0.4
0.5
0.6
0.7
0.8
0.9
R e a
l ( 2 0 1 0 R M B / k W h )
Inflation = 2.5%
Discount Rate = 10%
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
7/16
- 7
Real or Nominal LCOE?
Real LCOE
Removes effects of inflationassociated with O&M and fuelcosts
Uses Real Discount Rate
Analogous to the Year 1 price ofa PPA/FIT that increases withinflation each year.
Preferred by government/policymakers
Nominal LCOE
Incorporates assumptionsregarding inflation
Uses Nominal Discount Rate
Analogous to a PPA/FIT pricethat is the constant each year orflat across economic life ofproject.
Preferred by developers/projectowners
Either LCOE is acceptable, but must be clearly communicated.
Example: Real LCOE = 0.50 RMB/kWh and Nominal LCOE = 0.59 RMB/kWh
With 2.5% inflation, Nominal LCOE is 18% higher than Real LCOE
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
8/16
- 8
General Inputs to LCOE Calculation
Determine representative size of
projects and locations toestimate remaining project-related inputs
For example, 10 MW wind farm
vs. 200 MW wind farm
Establish boundaries of system
Capital, O&M, fuel cost
Performance/resourcecharacteristics
Cost of capital (debt/equity) anddiscount rate
Taxes, depreciation and taxincentives (if applicable)
Inflation (optional)Transmission/integration costs(optional)
Externality costs (optional)
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
9/16
- 9
Making Good Assumptions
Use current data (preferably within the past year)
Take the median of data sources
Apply method of developing assumptions consistently
across technologiesSurvey market participants
Reflect tax conditions and incentives in the country
Discuss and agree upon assumptions through stakeholdermeetings
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
10/16
- 10
Sample Base Case Assumptions and LCOE
1.6628%30030,000Solar CSP1.7215%20020,000Solar PV0.5440%2509,000
OnshoreWind
LCOE(RMB/kWh)
CapacityFactor
O&M(RMB/kW-yr)
Capital Cost(RMB/kW)
8%WACC2.5%O&MEscalation
30%Tax Rate20 yearsTax Life forDepreciation
10%Discount Rate20 yearsEconomic Life
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
11/16
- 11
Sensitivity of LCOE to Assumptions
LCOE of renewable energy can be highly sensitive to inputassumptions
Different assumptions can change LCOE by 50% or more.Some of the key assumptions are:
Capacity factor (performance)
Weighted Cost of capital (WACC)
Capital cost
Important to select assumptions in a consistent manneracross technologies
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
12/16
- 12
Sensitivity of LCOE (Busbar Cost) to Assumptionsfor WindOnshore Wind LCOE Sensitivity
20%
6%
7,200
200
30%
8%
9,000
250
40%
12%
10,800
300
-0.2 -0.1 0.0 0.1 0.2 0.3
O&M (RMB/kW)
Capital Cost (RMB/MW)
Costequity-WACC
Capacity Factor
LCOE relative to Base Case (RMB/kWh)
0.3 0.4 0.5 0.6 0.7 0.8
Absolute LCOE (RMB/kWh)
Low High
Base Case
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
13/16
- 13
Sensitivity of LCOE (Busbar Cost) to Assumptionsfor Solar PVSolar PV LCOE Sensitivity
6%
16,000
16%
160
8%
20,000
18%
200
12%
24,000
20%
240
-0.4 -0.3 -0.2 -0.1 0.0 0.1 0.2 0.3 0.4 0.5 0.6
O&M (RMB/kW)
Capacity Factor
Capital Cost (RMB/MW)
Cost equity-WACC
LCOE re lative to Base Case (RMB/MWh)
1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3
Absolute LCOE (RMB/kWh)
Low High
Base Case
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
14/16
- 14
Sensitivity of LCOE (Busbar Cost) to Assumptionsfor Solar CSPSolar CSP LCOE Sensitivity
240
26%
24,000
6%
300
28%
30,000
8%
360
30%
36,000
12%
-0.4 -0.3 -0.2 -0.1 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7
O&M (RMB/kW)
Capacity Factor
Capital Cost (RMB/MW)
Costequity-WACC
LCOE re lative to Base Case (RMB/kWh)
1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3 2.4
Absolute LCOE (RMB/kWh)
Low High
Base Case
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
15/16
- 15
Cost vs. Value Concepts for LCOE
Busbar Cost
+
Transmission Cost
+Integration Cost
-Capacity Value
-Energy Value
Busbar Cost
Delivered Cost
Adjusted DeliveredCost
-
8/3/2019 Levelized Cost of Energy Calculation_BV_EN
16/16
- 16
Summary
LCOE is the constant unit cost (per kWh or MWh) of a
payment stream that has the same present value as thetotal cost of a generating plant over its life.
There are multiple ways to calculate LCOE, depending on
the level of financial detailLCOE can be Real or Nominal
Establishing boundaries of each system for assumptions is
importantAssumptions can have significant impact on the resultingLCOE, so consistent assumptions across technologies are
important