“let’s make a difference” - nctx-tpwa.org · o. slope stabilization . oalbert atterberg,...

27
“Let’s Make a Difference” Presented by: Samuel Tran, P.E. October 22, 2015

Upload: votuyen

Post on 06-Aug-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

“Let’s Make a Difference”

Presented by: Samuel Tran, P.E.

October 22, 2015

Presenter
Presentation Notes
Photo Taken by AGG

OVERVIEW

o Importance of Geotechnical Engineering

oGeotechnical Foundation Recommendations

oGeotechnical Construction Specifications

“Let’s Make a Difference”

GEOTECHNICAL ENGINEERING o Surface and Subsurface Construction

o Tunneling, Structural Foundation, Earthwork

o Soil Mechanics o Plasticity Index, Moisture, Consolidation, Swell Potential

o Ground Improvement o Lime / Cement Stabilization o Vibro Compaction o Band Drains

Presenter
Presentation Notes
Tunneling – analyze rock consistency, observe water table Structural Foundation – residential homes, commercial buildings, roadways Earthwork – embankments, excavation, filling Soil Mechanics – Soil Properties – moisture content, unit weight, void ratio, shear strength, compressive strength -analyze data to provide recommendations Ground Improvements – -Lime/Cement – Stiffen subgrade (Not recommended in high sulfate concentrated soil) -Vibro Compaction – stabilize by compacting granular soil up to 100 ft -Band Drains – vertical drains install in clay to accelerate consolidation

o Slope Stabilization

o Albert Atterberg, Henry Darcy, Joseph Boussinesq,

William Rankine, Karl Terzaghi o Atterberg Limits Test, Permeability, Stress Distribution,

Earth Pressure, Bearing Capacity for foundations

GEOTECHNICAL ENGINEERING

Presenter
Presentation Notes
Slope Stability –Identify critical slip surface (lowest factor of safety) - extend soil nail, piers, beyond failure plane - model how to improve slope to 1.5 factor of safety http://zhh.slope.com.cn/wp-content/uploads/2012/04/Slope-stability-analysis.jpg

o Shallow Foundation o Spread Footing o Slab-On-Grade o Mat Foundation

FOUNDATION RECOMMENDATIONS

Presenter
Presentation Notes
Slab on grade & Mat Foundation are similar. Mat thickness is uniform and typically design for large loads. Slab & Beam –monolithic slab http://www.everything-about-concrete.com/images/IMG00146-20100528-0719.jpg http://studio-tm.com/constructionblog/wp-content/uploads/2010/11/spread-footings-framing-03.jpg

FOOTING CONSTRUCTION During design the foundation plan and the utility plan should

be cross checked to verify that no utility line excavation (existing and/or proposed) extends beneath the bearing influence of any footing.

Presenter
Presentation Notes
If over-excavation and moisture conditioning and/or replacement with low PI select fill is required beneath the footings, the excavation limits beyond the footings both horizontally and vertically should be verified. After excavation for the footings, Look for soft spots Perform probing of the subgrade Verify that the foundation area is level or suitably benched.

Measurements Verify proper dimensions of the footings (height, width,

depth, etc.) Verify proper rebar sizes and placements Verify proper reinforcing overlaps Verify proper clearance and that chairs are used Verify vapor barrier placement

FOOTING CONSTRUCTION

Prior to Concrete Placement

Verify that the base is free of loose soil and debris

Verify that there is no ponding water Verify that the subgrade has not softened due to being

saturated by rain

FOOTING CONSTRUCTION

Presenter
Presentation Notes
-Proofroll subgrade and Suggest to put in line item in construction budget for soil replacement if soft area is encountered

o Deep Foundation o Straight Shaft Piers o Structural Floor over crawl space or void space o Pier Foundation with slab-on-grade

o Piles o Micropiles, Sheet Piles, Soldier Piles o Timber, Steel, Composite Piles Prestressed Concrete Piles,

FOUNDATION RECOMMENDATIONS

Presenter
Presentation Notes
Prestressed Concrete Piles (18”-24” diameter) – Concrete with rebar/tendons Composite Pile – H steel beams with concrete http://www.ormiston.co.nz/images/gallery/Pile%20Driving.JPG

FOUNDATION RECOMMENDATIONS Straight Shaft Piers

Founded in Rock Skin Friction End Bearing

Bell Piers (Under-reamed) Founded in Clay

End Bearing

Engineering staff reviews the approved structural drawings and geotechnical report Verify Foundation Type, Penetration, Bearing Stratum Identify the pier types and locations

Pre-meeting with the Geotechnical Engineer, Driller, &

Engineering Technician

PIER DRILLING INSPECTION

Presenter
Presentation Notes
-Make sure structural drawings match with geotechnical report -Make sure everyone is on the same page: GC, engineers, subcontractor, client

PIER DRILLING INSPECTION

Presenter
Presentation Notes
-Pier plans are marked with Pier ID and date drilled

Engineering Technician Verify Technician has updated structural plans Verify Diameter and Penetration

Drilling Contractor Required to have a straddle bar, plumb bob and pier tape Follow direction of the engineering technician

PIER DRILLING INSPECTION

PIER DRILLING INSPECTION

Presenter
Presentation Notes
Using the straddle Bar Photo taken by AGG

PIER DRILLING INSPECTION

Presenter
Presentation Notes
Verify the auger bit is the correct size for the pier hole Verify the soil material as the drilling proceeds Make sure the ground surface around the pier hole is clean The technician will verify the bearing stratum once it is encountered and direct the driller to clean out the hole. Verify the hole is clean and then measure the depth to the bearing stratum Verify the bearing material is the same as the penetration proceeds Verify the pier hole is clean prior to measuring the depth of the pier hole to determine the total penetration Photo taken by AGG

PIER DRILLING INSPECTION Excessive water seepage or cave in will require steel casing The casing diameter and length needs to be recorded

Each Steel Casing should be properly identified

Presenter
Presentation Notes
Casing inner diameter MUST BE GREATER THAN Design Shaft Diameter Casings are screwed into the top of the rock using a T-Bar Penetration of rock is counted below the bottom of the casing The auger bit used below the casing should be the proposed design shaft diameter Spray Paint Casing to keep track of the length and diameter

PIER DRILLING INSPECTION

Extremely important to maintain a sufficient head of concrete during casing extraction.

PIER DRILLING INSPECTION

Presenter
Presentation Notes
If minimal seepage occurs during or after drilling, a sump pump can be used to pump out the water versus using a steel casing Dry soil cuttings are not allowed to be push back into the hole to remove the water. This causes a slick surface along the walls of the penetrated rock.

Bell Piers (Under-reamed)

A straight shaft is drilled to the respective depth determined by the engineer.

The depth of the pier is measured before and after the belling process. Verify there are no soil build-up at the bottom of the pier.

PIER DRILLING INSPECTION

PIER DRILLING INSPECTION Bell Piers (Under-reamed) will require a bell checker

Presenter
Presentation Notes
Photo Taken by AGG

Sulfate induced heaves

Expansive Clay – Austin Chalk, Eagle Ford Shale, Woodbine Moisture Conditioning, Water Injection, Chemical Injection

FOUNDATION ISSUES

Presenter
Presentation Notes
Do not LIME/Cement stabilize. Flexbase, crushed concrete or thicken concrete thickness. Blocky nature of clay – hard to do water injection 1) https://encrypted-tbn0.gstatic.com/images?q=tbn:ANd9GcQSBmc6lzbUmi3OPY8Bjpsd8atRvrYB-YH5EuXrK577ZRjDW988 2) https://ftp.dot.state.tx.us/pub/txdot-info/cmd/tech/sulfates.pdf

Excavation Limits beyond building limits/sidewalks

Bait and Switch on Select Fill PI verification per 5,000 sq/lift

CONSTRUCTION SPECIFICATIONS

Presenter
Presentation Notes
-For any excavation/filling project, check excavation limits both vertical and horizontal. -Have the limits of the excavation marked on the plans and agreed upon owner, subcontractor and testing lab -Subcontractor should refer to the geo report or contact the geo representative prior to bidding

Excavation Limits beyond building limits/sidewalks Make sure correct proctors are being used. Percent Compaction per ASTM D698 or Modified Proctor

D1557

CONSTRUCTION SPECIFICATIONS

Presenter
Presentation Notes
-DO NOT to allow the utility contractor to select the areas to be tested; especially if areas are to be tested via test pits/potholes (not recommended). -Do Trench Correction. The nuclear gauge is sensitive to its surrounding. Technicians should understand the limitations/proper way to use the gauge. Photo Taken by AGG
Presenter
Presentation Notes
Proctor Correlations with Pocket Penetrometer -Pocket Pen each proctor points in lab to determine correlation

Typical Moisture and % Compaction Comparison Versus Hand Penetrometer Readings

Pocket Pen High PI Clay Sandy Clay (PI=25) Readings (tsf) Mc % Compaction Mc % Compaction 1.0 +10 90% +5 90% 2.0 + 5 95% +3 95% 3.0 opt. 95-100% opt. 95-100% 4.0 -1 95-100% -1 95-100% 4.5 -3 95-100% -2 95-100%

Presenter
Presentation Notes
Typical Correlation -Establish correlation in the lab Hand Penetrometer is to be used in clay not sand. Hand Penetrometer is QA/QC tool. It is not used to determine design parameters.

o Refer to a Geotechnical Engineer for foundation issues

o Plan Ahead – Make sure everyone is on the same page during the construction phase

o Have qualified and certified inspectors

o There are no dumb questions

Presenter
Presentation Notes
A certified inspector is not always qualified. Look at years of experience. There’s a difference between a technician with 10 years of experiences and a technician with ten 1 year experience. Questions should always be asked.

THANK YOU