lessons learned from dg integration
TRANSCRIPT
Lessons Learned from DG Integration
Robert F. Arritt, PE
1
Introduction
• Insight to Distributive Generation (DG) interconnection issues
– Perform Interconnection studies
– Multiple Power Quality (PQ), Distributed Resources (DR), and Distribution hotline calls (EPRI Program 1, 174, and 180)
– Industry survey EPRI 3002001277 – “EPRI Survey on Distribution Protection with Emphasis on Distributed Generation Integration Practices”
2
Overvoltage Concerns • 75% of participants selected overvoltages and islanding as
biggest concern
• Over 25% of participants have experienced overvoltage issues and 28% were not sure.
69/34.5
+
34.5/.66
+
V_Source
69kV/_0
Substation DG
DG_Gnd
+
DG
660V
5 MW
Sub_Gnd
+
DTT
Single-Line
To Ground
Fault
Va
Vc Vb
1.73 pu
1.73 pu
Events resulted in sustained overvoltages on the primary side of
the substation transformer
Interconnection Transformer
• Survey Results
4
Overvoltage Concerns • Majority of participants selected system primary
overvoltages as the biggest concern for transformer selection
• Over 40% recommend grounded wye-wye for interface transformer.
Yg/Yg with simple dq0 inverter model
Utility breaker opens in response to SLG Fault
Yg/Δ with simple dq0 inverter model
High Voltage on a Secondary
DG Customer A Customer B
126 v 127 v
127.75 v
128.25 v Distribution Transformer
Primary
Note: voltages shown based on 120 V base voltage
Protection Supervision Concerns • Multiple events of inverters not turning on or cycling off due to
overvoltages associated with high penetration.
• Reported problems of DG operators changing initial protection settings resulting in high voltages at PCC
– Resulted in complaints from other customers of electronic equipment problems/failures
Substation End of Feeder
ANSI Range A Lower Limit
Distance
Voltage
ANSI Range A Upper Limit
After DG
Before DG
Additional Issues Identified • Open-Phase protection
– Open-phase concerns identified in commissioning tests
• Reclosing practices – Some have different reclosing practices for inverter based
system compared to rotating DG systems
• Limitations placed on substation switching • Transformer Inrush, Ferroresonance, etc.
Ferroresonance Problem
• The solar array was not able to come on-line due to the PV system’s protection detecting an overvoltage on Phase A.
9
300kVA
Wye Grounded
5-Legged Core
300ft 15 kV
#4/0 AWG
Phase A = Open
Phase B = Closed
Phase C = Closed
Van
125%
-125%
Ferroresonance Problem
• Concluding this investigation it was discovered that a single-phase fuse was blown but the door failed to fall open.
• The door failing to open did not make it obvious that the A phase fuse was blown.
• The fuse was replaced and the voltages where then checked and verified to be in specification.
10
Harmonic Impact • Used harmonic spectrum of 66% loaded inverter.
• Examined four scenarios of capacitor switching.
0.1
1
10
100
1000
1.1 5.3 9.4 13.6 17.8 21.9 26.1 30.3 34.4
|Z|
oh
ms
Harmonic Number
Driving Input Impedance from DG HSB
No Capacitors
6000kvar
12000kvar
18000kvar
Under certain conditions i.e. loading, capacitor state, and PV output. Voltage distortion on the feeder (MV) can exceed 3% at the 5th and THD can exceed 5%.
Analysis assumes no background distortion.
Inverter Harmonic
Spectrum
Conclusions
• Identify new requirements and challenges associated with protecting the feeder with DG.
• Researching utility practices & technologies and identifying gaps.
• Goal is to assist protection engineers can learn about leading practices for protection schemes and philosophies.
• Industry survey EPRI 3002001277 – “EPRI Survey on Distribution Protection with Emphasis on Distributed Generation Integration Practices”