lessons learned - bridge concepts (part 1 of 3) · directive from brian blanchard, assistant...
TRANSCRIPT
Lessons Learned - Bridge Concepts(Part 1 of 3)
Tom Andres P.E.
Assistant State Structures Design Engineer
Lessons Learned - Bridge Concepts(Part 1 of 3)
Tom Andres P.E.
Assistant State Structures Design Engineer
This Presentation has been endorsed by FDOT Executive Management
FDOT
Directive From Brian Blanchard,Assistant Secretary for Engineering and Operationsto give this Presentation
Brian’s Statement:
The Department is leader in the use of the Design-Build method of project procurement. Reportedly we have done more projects since 1998 than the rest of the state agencies combined with nearly 500 projects totaling more than $13B. The program has been enormously successful but not without its challenges.
As we develop transportation projects to address the growing concern for congestion in our urban areas we are faced with some of the most difficult projects with the highest volume of traffic in highly constrained areas. These factors lead to complex designs which in turn have led to a growing concern regarding the departure, in some cases, from transparent designs, best practices and sound engineering that has historically made us successful.
I fully support this first of its kind presentation to share our concerns and frustration with our partners to improve the process. I know Tom’s presentation will come as no surprise to anyone involved with these significant structures. The department is concerned with the trend we are seeing and ask that each and everyone involved in the design of our infrastructure have the department’s goal in mind to provide safe and efficient facilities for the traveling public.I fully support this effort and ask that you designers join in supporting our goals.
Brian Blanchard
Lessons Learned - Bridge ConceptsGeneral Trends – Design-Build Process
Bridge Design Innovation/
Efficiency-Cost Managing Measures
ProjectCosts
Design ComplexityAnd Depth of
Required Design Calculations
Lessons Learned - Bridge ConceptsGeneral Trends – Design-Build Process
Bridge Design Innovation/
Efficiency-Cost Managing Measures
ProjectCosts
Design ComplexityAnd Depth of
Required Design Calculations
Lessons Learned - Bridge Concepts
Design-Build:The Tendency is to Sharpen Designs to a Razors Edge –Resulting in Less Structural Reserve Capacity
- COST SAVINGS MEASURES-
Lessons Learned - Bridge Concepts
Design-Build:The Tendency is to Sharpen Designs to a Razors Edge –Resulting in Less Structural Reserve Capacity
- COST SAVINGS MEASURES-
Lessons Learned -Bridge ConceptsDesign-Build:Trend Towards More Complexity to save a Buck
“Intent of Code Compliance” and “Good Engineering” when Code and Contract (SDG etc.) do not directly address an issue.
Lessons Learned -Bridge ConceptsDesign-Build:Trend Towards More Complexity to save a Buck
“Intent of Code Compliance” and “Good Engineering” when Code and Contract (SDG etc.) do not directly address an issue.
Lessons Learned -Bridge ConceptsDesign-Build:Cutting Corners to Save a Buck
VS
Developing an Innovative Comprehensive Design Solution that saves Millions of Dollars
Lessons Learned -Bridge ConceptsDesign-Build:Cutting Corners to Save a Buck
VS
Developing an Innovative Comprehensive Design Solution that saves Millions of Dollars
Lessons Learned -Bridge ConceptsDesign-Build:
- Designer Allegiance has Changed.
- The Black Hat - Hot Potato Game.
Lessons Learned -Bridge ConceptsDesign-Build:
- Designer Allegiance has Changed.
- The Black Hat - Hot Potato Game.
Lessons Learned -Bridge ConceptsDesign-Build:
- Designer Allegiance has Changed.
- The Black Hat - Hot Potato Game.
FDOT
Lessons Learned -Bridge ConceptsDesign-Build:
- Designer Allegiance has Changed.
- The Black Hat - Hot Potato Game.
FDOT
Independent Peer Review of Category 2 Bridges
The peer review is intended to be a comprehensive, thorough independent verification of the original work. An independent peer review is not simply a check of the EOR’s plans and calculations; it is an independent verification of the design using different programs and independent processes than what was used by the EOR.
Independent Peer Review of Category 2 Bridges
Going forward, we are considering that for design-build Category 2 component reviews, that the Peer Reviewer be given access to the Department’s ERC comments and that the Certification Letter(s) include a statement that the Department’s ERC comments have been accounted for in the independent assessment.
Design Complexity – C-Pier/ Footing Connection ①
①Design-Build Detail Traditional Transparent
REF: Standard Plans Instructions
Index 462-000 Series
Design Complexity – C-Pier/ Footing Connection ①
①Design-Build Detail Traditional Transparent
REF: Standard Plans Instructions
Index 462-000 Series
Design Complexity – C-Pier/ Footing Connection ①
①
REF: Standard Plans Instructions
Index 462-000 Series
Wide Two Box Curved Ramp w/ Substringer
Deck System③
During Deck Pour, Screed Rails Raise Up as Boxes Rotate Inward Due to Unbalanced Section
③
Wide Two Box Curved Ramp w/ Substringer
Deck System③
During Deck Pour, Screed Rails Raise Up as Boxes Rotate Inward Due to Unbalanced Section
③
Wide Two Box Curved Ramp w/ Substringer
Deck System③
During Deck Pour, Screed Rails Raise Up as Boxes Rotate Inward Due to Unbalanced Section
③
Wide Two Box Curved Ramp w/ Substringer
Deck System③
③ 59’
26’
If Shear Connection, Potential Cracking at Cope Radius
Is Redundancy Factor of 1.2 Adequate?
New Steel Straddle PierCap
OPTION 2: CONSTRUCT NEW STEEL STRADDLE PIER CAP
Existing Steel Boxes and Ramp to Remain
Existing Hammerhead Pier to be Removed
StiffnessComparison
Pier Reconfiguration Case Study ④
Steel SIP Box Form w/ PT’ed ConcreteStraddle PierCap Infill
OPTION 3: CONSTRUCT NEW CONCRETE STRADDLE PIER CAP INSIDE
SIP STEEL BOX FORM DESIGNED FOR TEMPORARY CONDITION ONLY
Existing Steel Boxes and Ramp to Remain
Existing Hammerhead Pier to be Removed
StiffnessComparison
Pier Reconfiguration Case Study ④
OPTION 3: CONSTRUCT STEEL SIP FORM w/ NEW CONCRETE
STRADDLE PIER CAP
OPTION 2: CONSTRUCT NEW STEEL STRADDLE PIER CAP
OPTION 1: MOVE PIER
Would Require Major Strengthening of the SuperstructureChanges the Boundary Conditions of the Unit Due to the Change in Support Location
Would Require Major Strengthening of the SuperstructureChanges the Boundary Conditions of the Unit Due to the More flexible Cap Element
Would Likely Not Require Major Strengthening of the Superstructure Does Not Appreciably Changes the Boundary Conditions of the UnitPost-tensioning of Cap for both Strength and Clamping ForceSelect a PT Profile that Balances the LoadsProvide Shear Connectors at Existing Box/Cap Interface
Pier Reconfiguration Case Study ④
OPTION 3: CONSTRUCT STEEL SIP FORM w/ NEW CONCRETE
STRADDLE PIER CAP
OPTION 2: CONSTRUCT NEW STEEL STRADDLE PIER CAP
OPTION 1: MOVE PIER
Would Require Major Strengthening of the SuperstructureChanges the Boundary Conditions of the Unit Due to the Change in Support Location
Would Require Major Strengthening of the SuperstructureChanges the Boundary Conditions of the Unit Due to the More flexible Cap Element
Would Likely Not Require Major Strengthening of the Superstructure Does Not Appreciably Changes the Boundary Conditions of the UnitPost-tensioning of Cap for both Strength and Clamping ForceSelect a PT Profile that Balances the LoadsProvide Shear Connectors at Existing Box/Cap Interface
Pier Reconfiguration Case Study ④
Pier Reconfiguration Case Study ⑤
Existing Ramp
At-Grade Roadway
New RampWidening
OPTION 1: CONSTRUCT NEW FRAMED STEEL STRADDLE
PIER CAP TO SUPPORT WIDENING
Pier Reconfiguration Case Study ⑤
Existing Ramp
At-Grade Roadway
New RampWidening
K1(hard)
K1K1K1K2(soft)
K3(soft)
Concern is overstressing existing girder
OPTION 1: CONSTRUCT NEW FRAMED STEEL STRADDLE
PIER CAP TO SUPPORT WIDENING
Concern is overstressing deck
Pier Reconfiguration Case Study ⑤
Existing Ramp
At-Grade Roadway
New RampWidening
K1(hard)
K1K1K1K2(soft)
K3(soft)
Concern is overstressing existing girder
OPTION 1: CONSTRUCT NEW FRAMED STEEL STRADDLE
PIER CAP TO SUPPORT WIDENING
Concern is overstressing deck
Pier Reconfiguration Case Study ⑤
Existing RampNew RampWidening
Other Potential Challenges:
Hammerhead cap strengthening to resist couple;
Through-bolt:- conflicts with stirrups;- local bearing loads;- bearing load distribution and
concern with interface surface softening over time;
Dual girder straddle cap to pier column moment connection details and execution
Load distribution across widening interface associated with temperature gradients of straddle cap.
OPTION 1: CONSTRUCT NEW FRAMED STEEL STRADDLE
PIER CAP TO SUPPORT WIDENING
Pier Reconfiguration Case Study ⑤
Existing RampNew RampWidening
Other Potential Challenges:
Hammerhead cap strengthening to resist couple;
Through-bolt:- conflicts with stirrups;- local bearing loads;- bearing load distribution and
concern with interface surface softening over time;
Dual girder straddle cap to pier column moment connection details and execution
Load distribution across widening interface associated with temperature gradients of straddle cap.
OPTION 1: CONSTRUCT NEW FRAMED STEEL STRADDLE
PIER CAP TO SUPPORT WIDENING
Pier Reconfiguration Case Study ⑤
Existing RampNew RampWidening
OPTION 2: CONSTRUCT NEW NON-INTEGRAL NON-FRAMED
STEEL STRADDLE PIER CAP
NewColumn Cap
New Dual Steel Girder Cap
Pier Reconfiguration Case Study ⑤
Existing RampNew RampWidening
NewColumn Cap
New Dual Steel Girder Cap
OPTION 2: CONSTRUCT NEW NON-INTEGRAL NON-FRAMED
STEEL STRADDLE PIER CAP
Pier Reconfiguration Case Study ⑤
Existing RampNew RampWidening
NewColumn Cap
New Dual Steel Girder Cap
4’ BearingSpacing
Longitudinal Loads
Cap overturning due loading as well eccentric loads due to cap twisting and bending from thermal gradients, fabrication tolerances, bearing placement tolerance, dynamic affects etc.
OPTION 2: CONSTRUCT NEW NON-INTEGRAL NON-FRAMED
STEEL STRADDLE PIER CAP
Pier Reconfiguration Case Study ⑤
OPTION 3: CONSTRUCT NEW CONCRETE STRADDLE PIER CAP
Existing RampNew RampWidening
New Concrete Post-Tensioned
Cap
New bearing
Shear Studs
Typ.
PT Tendons Typ.
OPTION 3: CONSTRUCT NEW CONCRETE STRADDLE PIER CAP
INSIDE SIP STEEL BOX FORM DESIGNED FOR TEMPORAY
CONDITION ONLY
OPTION 2: CONSTRUCT NEW NON-INTEGRAL STEEL STRADDLE
PIER CAP
OPTION 1: CONSTRUCT STEEL I-GIRDERS STRADDLE
PIER CAP TO SUPPORT WIDENING
Stiffness differences between the existing fairly stiff cap carrying the existing girders and the fairly flexible steel cap carrying the widening would require more loads to be shed to the existing girders overstressing them.
Would Require Major Strengthening of the Existing SuperstructureChanges the Boundary Conditions of the Unit Due to the More flexible Cap Element
Would Likely Not Require Major Strengthening of the Superstructure Does Not Appreciably Changes the Boundary Conditions.
Pier Reconfiguration Case Study ⑤
OPTION 3: CONSTRUCT NEW CONCRETE STRADDLE PIER CAP
INSIDE SIP STEEL BOX FORM DESIGNED FOR TEMPORAY
CONDITION ONLY
OPTION 2: CONSTRUCT NEW NON-INTEGRAL STEEL STRADDLE
PIER CAP
OPTION 1: CONSTRUCT STEEL I-GIRDERS STRADDLE
PIER CAP TO SUPPORT WIDENING
Stiffness differences between the existing fairly stiff cap carrying the existing girders and the fairly flexible steel cap carrying the widening would require more loads to be shed to the existing girders overstressing them.
Would Require Major Strengthening of the Existing SuperstructureChanges the Boundary Conditions of the Unit Due to the More flexible Cap Element
Would Likely Not Require Major Strengthening of the Superstructure Does Not Appreciably Changes the Boundary Conditions.
Pier Reconfiguration Case Study ⑤