LESLIE BARNS & CONNECTION TRACK
Leslieville BIA Meeting May 2, 2014
1
• Communications
• Queen/Leslie Intersection Closure Overview • Next Steps - Coordination of TTC Track Upgrades (Queen streetcar stops between Brooklyn Ave to east of Parliament)
- Queen/Broadview Intersection Construction
OVERVIEW
2
COMMUNICATIONS
3
COMMUNICATIONS
4
Newsletters
• Distributed to 35 000 properties, from Broadview to the Beach, north to Gerrard, south to the Lake
Spring, 2014 - Leslie Barns Newsletter
COMMUNICATIONS
5
“Open During Construction” Postcards and Posters
• Inform community about transit and access during closure, promote BIA • Postcards mailed via Canada Post to over 35 000 homes and businesses • Posters provided to Businesses • Posters for transit stops on Queen East
WORKING WITH THE LESLIEVILLE BIA
6
“Doors Open Event” at Russell Carhouse featuring the New Streetcar • Saturday, May 24, 11am-5pm
COMMUNICATIONS
7
TTC Explainer Video for the Leslie, Victoria, Broadview, and overall Queen Street work • Explain transit plans, including Victoria street • http://www.youtube.com/watch?v=asI-YBCkC8k • Promote local businesses
COMMUNICATIONS
8
Newspaper ads in The Metro, Beach Mirror, Beach Metro
• Highlight local access during Queen/Leslie work, encourage local shopping
TRANSIT ROUTING
9
Replacement bus service during intersection closure travels to University Avenue
• Routing requested at community meetings and by BIA in 2013 • Increase frequency for 72 Pape, 83 Jones and 31 Greenwood buses at
community request
BROADVIEW/QUEEN
10
Broadview intersection construction moved to begin June 30, 2014 after World Pride Staggering Leslie and Broadview provides better service on Queen St East
QUEEN/LESLIE INTERSECTION CONSTRUCTION
11
QUEEN/LESLIE INTERSECTION – UTILITY UPGRADES
12
SEWER WORK EXAMPLE– LESLIE STREET
13
New storm culverts placed under Leslie Street to improve storm sewer operation
QUEEN/LESLIE CLOSURE – SCOPE OF WORK
14
• Replace 80+ year old watermain and water infrastructure
• Install high capacity storm sewer
• Install upgraded Bell chamber (avoids impacts to tracks during utility works in future)
• Install new TTC cables and chamber (access for maintenance)
• Install new TTC tracks
• Install new overhead catenary poles
QUEEN/LESLIE CLOSURE – WATERMAIN UPGRADE
15
• Replacing and upgrading the Watermain has impacts • For water work affecting businesses (not residents), preference to perform
work when businesses are closed overnight, pending Toronto Water approval
• Minimum 2 temporary water shutoffs during closure – to disconnect service from old main and make new connection (details, locations TBC following valve testing)
• Some watermain valves are over 100 years old and need replacement
• Only Toronto Water is permitted to turn off water and must approve timing
• Inform residents and businesses immediately once schedule is set with Toronto Water
• Work is subject to weather (heavy rains)
QUEEN/LESLIE INTERSECTION
16
• Close smallest possible area that allows contractor to complete intersection work efficiently • Maintain pedestrian access to businesses and residences, small interruptions for pole installation • New access to Avondale Parking Lot via Leslie Street (remove and then replace fence) • Waterman south of Queen St on Leslie St advanced to start May 8th
Lane closures
EARLY JUNE – PREPARING FOR TRACK INSTALLATION AT QUEEN AND LESLIE INTERSECTION
17
Flatbed trucks with pre-assembled rail system (King and Sumach example)
• Fastest way to install tracks is pre-assembly • Pre-assembled rail system for Leslie/Queen requires six 80 foot flatbed trucks • Significantly reduces duration of track installation (and duration of road closure) • Requires Police escort, then track system installed like jigsaw puzzle
• Six flatbeds park for approximately 1 week (Carlaw to Greenwood, staggered to maintain side street access) • Removed ASAP after track system installed
CONSTRUCTION PHASING – LESLIE ST CONTEXT
18
May 11 to June 21, 2014
Staggered closure from north of Eastern Avenue - access maintained to Marigold Condo parking garage Utility work – access to The Duke parking maintained from Lane Queen and Leslie closure for utilities and track work – 6 weeks (May 11 – June 21)
Sewer replacement and utility upgrades
Traffic configuration shifts back to south side
TRANSIT SERVICE – MAY 11 TO JUNE 21
19
Replacement bus service during intersection closure travels beyond Parliament Street to University Avenue Increased frequency on Pape, Jones and Greenwood Buses
QUEEN/LESLIE CLOSURE – WORK HOURS
20
- Work is required overnight in order to return regular access as fast as possible
- Per major intersection closures across Toronto, work is planned 24/7
- Police and/or flagpersons will be on site to assist pedestrians
DUST MITIGATION
21
• Wet cutting of concrete
• Truck wheel washing
• Window washing for businesses and residences directly fronting construction
COORDINATING TTC TRACK UPGRADES AT SELECT STOPS ON QUEEN STREET EAST
22
COORDINATING TRACK UPGRADES ON QUEEN EAST
Leslieville BIA Meeting, May 2, 2014 23
• Important track upgrades at some streetcar stops on Queen St
(unrelated to Leslie Street ) are being coordinated during the Leslie/Queen and Broadview/Queen intersection closures
• TTC Operations met with Leslieville and Riverside BIAs and Councillors to develop plans
• Coordinate works this year to avoid future streetcar disruption
COORDINATING TRACK REPLACEMENT - QUEEN STREET
24
• Tracks are worn at some streetcar stops and need replacement • Work during intersection closures (when no streetcars are running on Queen St East) • Track upgrades at stops do not require street closures, do occupy centre track lanes • 4 days per stop
• Not continuous across Queen Street East
Queen Streetcar Stop Rail Replacement Locations
Streets Direction Timeline*
Booth Avenue West May 12 - 15 Logan Avenue East May 20 - 23 Logan Avenue West May 26 - 29
Brooklyn Avenue East May 30 - Jun 2 Brooklyn Avenue West Jun 3 - 6 Carlaw Avenue East Jun 19 - 22 Carroll Street West Jul 1 - 4 River Street East Jul 10 - 13 River Street West Jul 14 -17 Tracy Street East Jul 21 - 24
Three additional stops will be considered if time permits Bright Street East TBD Pape Avenue East TBD
Sackville Street West TBD
Note: There is no track work planned in this area from June 22 to June 30.
• Diego Sinagoga Community Liaison 416-393-2197 [email protected]
STREETCAR STOP – TRACK REPLACEMENT May to July 2014 (Brooklyn Avenue to Tracy Street)
QUEEN/BROADVIEW INTERSECTION
26
BROADVIEW/QUEEN INTERSECTION JUNE 30-JULY 25
27
Bus diverts via Carlaw, Dundas, River Street Scheduled after World Pride
TRAFFIC MANAGEMENT
28
TRAFFIC MANAGEMENT
29
Key changes made to assist traffic flow in Leslieville BIA and vicinity: • Additional east-west green time added to 17 intersections along Queen St & along
Eastern Avenue • 10 Electronic Changeable Message Signs with Traffic Info
• Signal timing changes to improve east-west flow on Dundas and Gerrard during
Queen/Leslie closure
• Ongoing traffic volume monitoring and cameras at key intersections to make signal adjustments
Improvements on Carlaw passed at City Council • Rush hour parking now prohibited on east side of Carlaw from 4pm-6pm to improve flow into
Leslieville • New right turn green arrow added at Lake Shore and Carlaw
THANK YOU