ler magnets major r&d effort
DESCRIPTION
LER Magnets Major R&D Effort. There are 2 distinct sets of magnets: Arc magnets covering ~ 26 km of accelerator circumference LER to LHC transfer line magnets covering total of ~ 1 km of beam path The VLHC low field magnet is proposed - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/1.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
LER Magnets Major R&D Effort
The new injection scheme shows only the path from SPS to LER to LHC
There are 2 distinct sets of magnets:
1. Arc magnets covering ~ 26 km of accelerator circumference
2. LER to LHC transfer line magnets covering total of ~ 1 km of beam path
The VLHC low field magnet is proposedas the base magnet for the LER arc.
The LER-LHC transfer line magnets areviewed as new initiative in magnet design.
![Page 2: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/2.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
VLHC & LER Magnet Count
FNAL
Fermilab cluster:Injection, Extraction,RF, Two Detectors
Typical Stage 1Surface Facility forCryogenics (1 of 6)
Far ClusterLF -> HF Transfer
and Collimation Ring OrientationArbitrary
Stage 1
Required for Stage 2
VLHC: - 233 km accelerator ring - ~ 3200 main arc dipoles - ~ 466 km continued length of transmission line superconductor
LER: - ~27 km accelerator ring - 1232 main arc dipoles - ~ 54 km continued length of transmission line superconductor
![Page 3: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/3.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
Base Magnet of the LER Accelerator
LER Main Arc Dipole Magnet • Magnet cross-section area: 26 cm (height) x 24 cm (width) Pole gap: 20 mm (?)• 1.6 Tesla field (nominal operation) (1.99 T for VLHC)• 0.6 Tesla (beam injection) (0.2 T for VLHC)• Alternating gradient: 12 m (64 m)• 20 mm magnet pole gap ( 25 mm ??)• Energized by 55 kA (87 kA for VLHC), single turn superconductor line• Coolant – supercritical helium (4.2 K, 3 bar, 60 g/s) • Warm beam pipe vacuum system- ante-chambers required
We propose that LER is based on theVLHC low field, combined function dipole magnet
![Page 4: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/4.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
LER Magnet Location in the LHC Tunnel
It fits easily in the space above the LHC magnet
-Vertical distance between LHC and LER beams: 1350 mm
-The holding brackets and the magnets can be installed without disturbing the LHC operations
-The 4 K, 3 bar LHe can be tapped at convenient locations from the QRL line providing 1700 g/s flow
![Page 5: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/5.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
LER Arc Dipole Magnet in LHC Tunnel
Normal tunnel area Area with cryogenic feed tower
![Page 6: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/6.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
VLHC Magnet and B-field Measuring Instrumentation
Magnet view (tangential coil side) Magnet view (Hall station side)
![Page 7: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/7.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
Magnetic Measurements
Gueorgui Velev, TUA07PO02
Probe: 15.2 mm dia. x 754.1 mm longVespel (polyimide) used to form the probe (winding support) and bearings.
Field Harmonics measured to:order 10 at 1.966 Tesla (collisions),and order 6 at 0.1 Tesla (injection)
![Page 8: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/8.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
Magnetic Measurements
Quadrupole component is as designed; ~ -415 units, both atinjection and full field 1.966 T.
102 element Hall Probe confirmsthe +/- 4% gradient.
Sextupole component very small;~ few units, and no change frominjection to the full field 1.966 T.
The b4 – b10, and the a4 – a10 also << 4 units, or << 0.04%.
LER magnet operates at 1.6 T !!
![Page 9: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/9.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
Principle of the LER-LHC Beam Transfer
After the LER ring filling is complete, the pulsing magnets are turned off as soon as the last proton bunch passed through them.
![Page 10: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/10.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
Principle of LER-LHC beam transfer
Cryogenic support for fast pulsing magnets must sustain long-termoperations at 0.45 TeV, and a 100 second long ramping to 1.5 TeV
![Page 11: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/11.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
LER-LHC Transfer Line Boundaries
- Total length of ½ straight section: 260 m- Available free space between D1 and Q7: 176.5 m - To reproduce the LHC optics the LER-LHC transfer line magnets must reach the LER
level of 1100 mm at the D2 LHC dipole (approximately 65 m from the end-face of D1)- A 336 T-m bending power is required to lift a 1.5 TeV beam by 1100 mm above the
LHC nominal beam level, or on average ~5 T magnets are required for a 65 m beam path
- For comparison, to bypass detectors by ~ 40 m in the straight sections of 260 m the transfer line magnets of ~50 T field would be needed
![Page 12: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/12.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
LER-LHC Transfer Line Option 1No re-arrangementof LHC, D1 magnet.
4 vertical bendspreceded by a horizontal bend toprovide enough separation in thefirst pair of vertical dipole magnets forthe “cc” and “cw” LER beams.
Three sets of fast pulsing magnets
are needed!
![Page 13: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/13.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
LER-LHC Transfer Line Option 2
LHC D1 magnet ismoved a bit (or shortened) to make a space for a (5
m?) LER single bore dipole magnet.
Only one set of fastPulsing magnets isneeded!
![Page 14: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/14.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
An Example of Possible Vertical Bend Magnet Arrangement
![Page 15: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/15.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
LER-LHC Transfer Line Magnets
In order to accomplish the LER-LHC beam transfer the beam line must consists primarily of three type of dipole magnets:
- 2 T range, normal conducting, fast pulsing, single bore dipole to
enforce the LER beam circulation in the LHC
- 2 T range, normal conducting, single bore dipole operating with
the LHC LER beam pipe separation of no less than 75 mm (40 mm beam pipe and ~ 30 mm for the magnet yoke)
- 7-8 T, superconducting, two-bore, 1m long vertical dipole to pass
the LER beam through most of the 1.35 m vertical separation
![Page 16: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/16.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
Fast Pulsing Magnets
- For 3 microseconds current decay time, L < 1 uH, so the magnet length is typically < 1 m, and the conductor spacing 40-60 mm.- For B field in 2 T range, the conductor current is in the range of 100 kA.- Magnet operating < 25 K (lowest resistance of Cu) is the only option.
From Martin N. Wilson,Superconducting Magnets,ISBN 0 19 854810 9 (Pbk), 1997
![Page 17: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/17.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
Fast Pulsing LER-LHC Transfer Line Magnets
Horizontal bend of both LER beams. Vertical bend of the LER beams,B-field shaped by laminations, B-field shaped by conductors,conductors are LHe cooled. conductors are LHe cooled.
40 mm gap, 1.5 T max @ 90 kAPulsed or continual operation
60 mm gap, 2.0 T max @ 67 kA pulsed or continual operation. CERN operated WC 0.6 T magnet @ 29 kA
![Page 18: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/18.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
LER-LHC Transfer Line Magnets
A vertically bending magnet –for horizontally separated LERand LHC beams.
Continual or fast pulsing operations.
Laminations are used to contain
magnetic flux, and to minimize fringe field at the LHC beam.
![Page 19: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/19.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
Fast Pulsing Magnet Power Supply
For I = 90 kA and L =1 uH of the magnet system, the voltage drop is 30 kV at
3 microsecond of current decay time. Lowering the operating temperature of the power supply switcher cells to 25 K will eliminate need for the HTS leads.
![Page 20: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/20.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
LER Major Magnet R&D for FY07
1. Dipole, 2T range, single bore (30-50 mm), 0.8 m long, dc, 3 microsecond turn-off time, LHe cooled condcutors: (a) magnetic field shaped by conductor (b) magnetic field shaped by Silicon Steel tape core
Goal for FY07: magnetic and mechanical/cryo design
2. A 100 kA dc power supply with 3 microsecond turn-off time: (a) switcher cells operating below 100 K, possibly down to 25 K (b) fast transformer/heater to turn-off the current (c) superconducting dump resistor to expend
magnetic energy
Goal for FY07: research and preliminary design
![Page 21: LER Magnets Major R&D Effort](https://reader035.vdocuments.us/reader035/viewer/2022062518/56813fe9550346895daadd4c/html5/thumbnails/21.jpg)
April 27, 2006 LARP LBL Meeting Henryk Piekarz
SC Magnetsat Fermilab
LER Major Magnet R&D for FY07
3. Two-bore (40 mm), high field (7-8 T) vertically bending magnet:
set of short (0.8m) 12-15 magnets arranged into a single cryostat
Goal for FY07: magnetic and mechanical/cryo design
4. VLHC combined function magnet, 1.6 T, 25 and 30 mm gaps:
Goal for FY07: magnetic design