legal review - beale & company solicitors llp · rupert had described as a culture of delay and...
TRANSCRIPT
Beale&CompanyLondon | Bristol | Dublin
Legal Review
2013
www.beale-law.com www.beale-law.comLondon | Bristol | Dublin London | Bristol | Dublin2 3
Case References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Foreword . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
Beale & Company News . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7
Professional liability: solicitors, accountants and financial advisers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
+ Property transactions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 – Was there a breach of trust? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 – Relief under section 61 of the Trustee Act . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
+ The White v Jones principle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 – What would have happened? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 – “Loss of a chance” damages? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
+ Duty to explain unusual clauses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
+ A duty to warn . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
+ Application of the SAAMCO principle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
+ Drafting the chief executive’s service contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
+ Solicitors liable for litigation costs? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16 – Solicitors acting under CFAs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 – Further factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
+ Tax advice . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
+ Professional negligence: expert opinion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
+ Statutory and common law duties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
+ Limitation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Professional liability: construction professionals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22
+ Net contribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22
+ Some architect duties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
+ Professional conduct . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
+ The SAAMCO principle not applied . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
+ Common law duty of care (physical injury) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
+ Common law duty of care (economic loss) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .27
Construction
+ Building contracts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 – Meaning of the words used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 – Precedence of contract documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 – Variation omitting work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 – Lump sum . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 – Due diligence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
+ Adjudication . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33 – Compliance with the Act . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34 – The residential occupier exception . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
Table of contents
– Is a collateral warranty a construction contract? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 – Applying for final resolution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36 – An earlier adjudication . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36 – Crystallisation of a dispute . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .37 – Procedural unfairness? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .37 – Procedural irregularities? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38 – The rules of natural justice . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38 – Human rights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
+ The Defective Premises Act . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
Litigation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
+ Jackson reforms: compliance with the Civil Procedure Rules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
+ Costs budgeting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
+ Mediation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
+ Costs on discontinuance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
+ Costs: who is the successful party? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
+ Costs and Part 36 offers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
+ Near miss offers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
+ Interest . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
+ New claims . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
+ Re-litigating old issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
+ Privilege . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
Contracts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
+ Duty of good faith . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
+ Repudiatory breach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
+ Limitation of liability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
Insurers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
+ Blanket notifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
+ Public liability insurance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
+ The order in which multiple claims should be met . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
+ Basis of contract clauses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
+ Rights of subrogation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
+ Disclosure of insurance details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
Health and safety and public liability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
+ The role of reasonable foreseeability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
+ Non-delegable duties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
+ Rules of causation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
+ Ascertaining the cause . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
www.beale-law.com www.beale-law.comLondon | Bristol | Dublin London | Bristol | Dublin4 5
Legal Review 2013 – Case References
Case Name Page
1 ABB Ltd v BAM Nuttall Ltd [2013] EWHC 1983 (TCC) (12 July) 39
2 AIB Group (UK) Plc v Mark Redler & Co [2013] EWCA Civ 45 (8 February) 10
3 AJ Building & Plastering Ltd v Turner [2013] EWHC 484 (QB) (11 March) 29
4 Aldersgate Estates Ltd v Ham Construction Ltd (In Liquidation) & another [2013] EWHC 104 (TCC) (31 January) 26
5 Aldi Stores Ltd v WSP Group PLC [2007] EWCA Civ 1260 (28 November 2007) 50
6 Ampurius NU Homes Holdings Limited v Telford Homes (Creekside) Limited [2013] EWCA Civ 577 (23 May) 54
7 Arcadis UK Ltd v May & Baker Ltd [2013] EWHC 87 (TCC) (29 January) 36
8 Aspect Contracts (Asbestos) Ltd v Higgins Construction Plc [2013] EWHC 1322 (TCC) (23 May) (CA decision = [2013] EWCA Civ 1541 (29 November)
36
9 Atkins Ltd v Secretary of State for Transport [2013] EWHC 139 (TCC) (1 February) 32
10 Berney v Saul [2013] EWCA Civ 640 (5 June) 20
11 Birse Developments Ltd v Co-operative Group Ltd [2013] EWCA Civ 474 (1 May) 50
12 Caribbean Steel Co Ltd v Price Waterhouse [2013] UKPC 18 (9 July) 19
13 Elvanite Full Circle Ltd v AMEC Earth & Environmental (UK) Ltd [2013] EWHC 1643 (TCC) (14 June) 44
14 Feltham v Freer Bouskell [2013] EWHC 1952 (Ch) (15 July) 12
15 Feltham v Freer Bouskell [2013] EWHC 3086 (Ch) (15 July) 48
16 Fermanagh DC v Gibson [2013] NIQB 16 (4 February) 37
17 Finesse Group Ltd v Bryson Products and another [2013] EWHC 3273 (TCC) (29 October) 27
18 Flatman v Germany Weddell v Barchester Health Care Ltd [2013] EWCA Civ 278 (10 April) 17
19 Gabriel v Little [2013] EWCA Civ 1513 (22 November) 14
20 Genesis Housing Association Ltd v Liberty Syndicate Management Ltd (for and on behalf of Syndicate 4472 at Lloyds) [2013] EWCA Civ 1173 (4 October)
61
21 Gladman Commercial Properties v Fisher Hargreaves Proctor [2013] EWHC 25 (Ch) (18 January) 50
22 Green v Royal Bank of Scotland [2013] EWCA Civ 1197 (9 October) 20
23 Halsey v Milton Keynes General NHS Trust [2004] EWCA Civ 576 (11 May 2004) 45
24 Hammersmatch Properties (Welwyn) Ltd v Saint-Gobain Ceramics & Plastics Ltd [2013] EWHC 2227 (TCC) (24 July) 48
25 Harrison v Technical Sign Co Ltd & Ors [2013] EWCA Civ 1569 (4 December) 27
26 Heron v TNT(UK) Ltd [2013] EWCA Civ 469 (2 May) 18
27 Hide v Steeplechase Co (Cheltenham) Ltd [2013] EWCA Civ 545 (22 May) 63
28 Hunt v Optima (Cambridge) Ltd [2013] EWHC 681 (TCC) (29 April) 27
29 Ikbal v Sterling Law [2013] EWHC 3291 (Ch) (30 October) 12
30 John Dowland v The Architects Registration Board [2013] EWHC 893 (Admin) (19 April) 24
31 John Grimes Partnership Ltd v Gubbins [2013] EWCA Civ 37 (5 February) 24
32 Kudos Catering (UK) Ltd v Manchester Central Convention Complex Ltd [2013] EWCA Civ 38 (7 February) 56
33 Magical Marking Ltd v Ware & Kay LLP [2013] EWHC 636 (Ch) (20 March) 47
34 Mathiesen v Clintons [2013] EWHC 3056 (Ch) (11 October) 14
35 McManus and others v European Risk Insurance Co HF [2013] EWHC 18 (Ch) (17 January) 58
36 Mehjoo v Harben Barker [2013] EWHC 1500 (QB) (5 June) 18
37 Michael Nulty (dec’d) and others v Milton Keynes Borough Council [2013] EWCA Civ 15 (24 January) 66
38 Mid-Essex Hospital Services NHS Trust v Compass Group UK & Ireland Ltd [2013] EWCA Civ 200 (15 March) 53
39 Mitchell v News Group Newspapers [2013] EWHC 2179 (QB) (18 June) [2013] EWHC 2355 (QB) (1 August) [2013] EWCA Civ 1537 (27 November)
41
40 M J Gleeson Group Plc v AXA Corporate Solutions Assurance SA [2013] Lloyd's Rep. I.R. 677 (4 June) 59
41 MT Hojgaard A/S v E.ON Climate & Renewables UK Robin Rigg East Ltd [2013] EWHC 967 (TCC) (23 April) 31
42 Murray v Neil Dowlman Architecture Ltd [2013] EWHC 872 (TCC) (16 April) 45
43 National Museums and Galleries on Merseyside Board of Trustees v AEW Architects and Designers Ltd [2013] EWHC 3025 (TCC) (11 October)
49
44 Nelson’s Yard Management Co v Eziefula [2013] EWCA Civ 235 (21 March) 46
45 Newcastle International Airport Ltd v Eversheds LLP [2013] EWCA Civ 1514 (28 November) 16
46 Parkwood Leisure Ltd v Laing O’Rourke Wales & West Ltd [2013] EWHC 2665 (TCC) (29 August) 35
47 PGF II SA v OMFS Ltd [2013] EWCA Civ 1288 (23 October) 45
48 Pioneer Cladding Ltd v John Graham Construction Ltd [2013] EWHC 2954 (TCC) (4 October) 34
49 R (on the application of Prudential plc and another) v Special Commissioner of Income Tax and another [2013] UKSC 1 (23 January)
51
50 Rathbone Brothers Plc and another v Novae Corporate Underwriting & Ors [2013] EWHC 3457 (Comm) (8 November)
61
51 Robbins v Bexley London Borough Council [2013] EWCA Civ 1233 (17 October) 65
52 RWE Npower Renewables Ltd v J N Bentley Ltd [2013] EWHC 978 (TCC) (22 April) 30
53 Sabic UK Petrochemicals Ltd v Punj Lloyd Ltd [2013] EWHC 2916 (QB) (10 October) 32
54 Santander UK Plc v R.A. Legal Solicitors [2013] EWHC 1380 (QB) (23 May) 11
55 St Anselm Development Co Ltd v Slaughter & May [2013] EWHC 125 (Ch) (1 February) 21
56 Sylvia Henry v News Group Newspapers Ltd [2013] EWCA Civ 19 (28 January) 43
57 Teal Assurance Co Ltd v W R Berkley Insurance (Europe) Ltd [2013] UKSC 57 (31 July) 60
58 Tesco Stores v Constable [2008] EWCA Civ 362 (16 April 2008) 60
59 TSG Building Services v South Anglia Housing [2013] EWHC 1151 (TCC) (8 May) 38
60 TSG Building Services Plc v South Anglia Housing Ltd [2013] EWHC 1151 (TCC) (8 May) 54
61 Venulum Property Investments Ltd v Space Architecture Ltd [2013] EWHC 1242 (TCC) (22 May) 42
62 Westfields Construction Ltd v Lewis [2013] EWHC 376 (TCC) (27 February) 34
63 West v Ian Finlay & Associates [2013] EWHC 868 (TCC) (16 April) 22
64 Whyte & Mackay Ltd v Blyth & Blyth Consulting Engineers [2013] CSOH 54 (9 April) 39
65 Willmott Dixon Housing Ltd v Newlon Housing Trust [2013] EWHC 798 (TCC) (9 April) 38
66 Woodland v Essex County Council [2013] UKSC 66 (23 October) 64
67 Wright v Michael Wright (Supplies) Ltd [2013] EWCA Civ 234 (27 March) 46
68 XYZ v Various sub nom Re PIP Breast Implant Litigation [2013] EWHC 3643 (QB) (22 November) 62
69 Yam Seng PTE Ltd v International Trade Corp Ltd [2013] EWHC 111 (QB) (1 February) 52
70 Zennstrom v Fagot [2013] EWHC 288 (TCC) (21 February) 40
www.beale-law.comLondon | Bristol | Dublin 7www.beale-law.comLondon | Bristol | Dublin 6
On the horizon
Although perhaps another difficult year, we hope that 2013 saw the beginning of the end of the recession and a chance to look towards new opportunities. Here I give some thoughts and our predictions on what to look out for in the year ahead.
Construction
This year we advised on a number of new contract forms where clients wanted
to share risk and reduce disputes . This looks set to continue based on the
number of enquiries we are receiving . Will this mean less disputes? We are
seeing some stale claims against professionals coming back to life as we near
the end of the limitation period . Our defendant clients are taking a tougher line
and refusing standstill agreements, which will test claimants’ resolve . We are
also being instructed on fee claims where clients have not been prepared to
invest in lawyers’ fees to recover unpaid fees but they are now . They have often
written these sums off so any monies recovered now are pure profit .
Another trend we are seeing is contractors getting into disputes with their
insurers . Several instructions in the last quarter of 2013 lead us to believe this
is more than a coincidence . Contractors are now beginning to use this route,
having paid chunky premiums . In the past they may simply have looked to their
client or sub-contractors - now they are looking at their insurers .
The efficiency drive by the Courts around costs and punishing parties who
cannot keep up with the pace they set is good for clients and should make
them begin to realise the advantages of the courts over adjudication .
Foreword
2013 saw some important decisions in the area of professional liability. This review will favour on those key decisions affecting a number of different professions including insurance issues faced by professionals and insurers alike.
On 1 April 2013, the much heralded reforms recommended by Sir Rupert
Jackson came into effect, accompanied by a determination to end what Sir
Rupert had described as a culture of delay and non-compliance in the conduct
of litigation . The stricter approach to enforcing the rules was felt by Andrew
Mitchell M .P . whose solicitors were a few days late in filing their client’s costs
budget in his action against News Group Newspapers . As a result, his right to
recover costs if he is successful in his action is limited to court fees . The Court
of Appeal hoped that their decision would send out a clear message .
The requirement to file costs budgets at the first case management conference,
which had already been piloted in some courts, now applies generally . Costs
budgets approved by the court are intended to set a ceiling on costs that can
be recovered . Our report refers to some of the first decisions on applications to
revise the original budget upwards as the case progresses .
Solicitors continued to face claims for breach of trust when property
transactions did not complete as hoped and sometimes turned out to be
fraudulent but the bar for relief for solicitors under section 61 of the Trustee
Act was not set as high as had perhaps been expected . The Court of Appeal
declined to apply the SAAMCO principle in a case against engineers but did so
in a case against solicitors .
We have included several examples of how the more liberal approach to
contract interpretation, pioneered in recent years in a series of high-level
judgments, has been applied to produce more commercially sensible results
than a literal reading might have suggested . Diverging strands of judicial
opinion seemed to be developing on the concept of good faith in contracts .
There was an important Court of Appeal decision on when a breach of contract
can be treated as repudiatory .
In the field of adjudication, there were decisions on whether a collateral
warranty is a construction contract and on the limitation period affecting
proceedings to recover money paid pursuant to an adjudicator’s award . A
Scottish court held, in a particular case, that enforcement of an adjudicator’s
award would be an infringement of human rights .
Section 69 of the Enterprise and Regulatory Reform Act came into force, which
means that, for the most part, breaches of health and safety regulations will no
longer be actionable per se .
“ The Court of Appeal declined to apply the SAAMCO principle in a case against engineers but did so in a case against solicitors
”Antony Smith Senior Partner
Executive Summary
This case involves allegations of professional negligence by the
Claimants who were institutional purchasers of historical mill
buildings in Leeds, Yorkshire following their engagement of the
Defendant surveyors and engineers to survey those buildings prior
to purchase.
Background The Claimants were interested in buying a converted 19th Century mill
building called Marshall Mills together with another building known as
Marshall Court in Leeds. In 2003, during the negotiation period with the
vendor, the Claimant instructed the Defendant to carry out a building
survey. During a site visit the Defendant noticed cracking in three brick
piers at ground floor level and reported that the cracks appeared to be
of recent origin. After a number of meetings between the Claimants, Defendant and
the vendor, the Defendant suggested that remedial wall ties should be
installed as a holding procedure, that the cracks should be monitored
and that a provisional figure of £20,000.00 should be set aside for the
strengthening of the piers if deterioration continued.
In 2005, significant and serious increases in the sizes of the cracks
were recorded. Compression failure was identified as the cause of
the cracking however nothing was done to rectify the cracking and
no further monitoring was carried out. The cost of the urgent repair
work was high and was not carried out until 2008/2009. The Claimant
claimed that the Defendant ought to have recognised that three
cracked brick piers were or might well be subject to compression failure
and that the Defendant should have carried out calculations which
would or might have revealed at least a real risk of compression failure.
Igloo Regeneration Limited
v Powell Williams Partnership
The Claimant claimed that
the Defendant ought to have
recognised that three cracked
brick piers were or might well
be subject to compression
failure
Author’s NameReference to other literature
here
Reference to other literature
here
Reference to other literature
here
Reference to other literature
here
Reference to other literature
here
Reference to other literature
here
Keyfacts:
£20,0000 set-aside for pier
strengthening2003 the Claimant instructed
the Defendant to carry
out a building survey2008/9 urgent repair work
carried out
www.beale-law.com1
London | Bristol | Dublin
Beale&Company
Sheena Sood Partner
Sheena trained with Beale and Company and has been a Partner since
1998. She has over 20 years of experience and specialises in projects and
construction related disputes. She has been involved in a diverse range
of construction and engineering related claims and contractual disputes
as well as civil claims and criminal prosecutions arising under health and
safety and environmental laws.
She has a full breadth of knowledge and experience of all types of dispute
resolution and has a particular expertise in construction adjudications. Her
excellent success record in adjudications enables a tactical approach to be
adapted and methodical preparation of evidence.
On large scale disputes Sheena is adept at utilising electronic management
systems to minimise the costs involved in the management of client
documentation and for e-disclosure purposes. She acts for both Claimants
and Defendants and adapts her approach with keen awareness of the
mindset of the opponent. She adopts a commercially pragmatic approach
to dispute resolution with her client’s aim at the forefront.
She has also advised and represented numerous clients in health and
safety matters in the construction and related industries and has much
experience of dealing with investigations and prosecutions.
Sheena regularly writes articles and speaks at seminars on recent
developments and legal issues of interest to those in the construction field.
Sheena is admitted to practice in Ireland and also admitted in Northern
Ireland.
Beale&Company
Sheena SoodPartner
www.beale-law.comLondon | Bristol | Dublin
DDI: +44 (0) 20 7240 8711
M: +44 (0) 7801 393 589
…is imaginative and shows
sound judgement.
Legal 500 UK 2012
Education Brunel University LLB
Admitted England and Wales 1992 Ireland 2002 Northern Ireland 2006
Expertise Construction, Engineering & Infrastructure Health, Safety & Environment Professional Liability
Beale&CompanyLondon | Bristol | Dublin
London | Bristol | Dublin www.beale-law.com
Beale&Company
LondonBeale and Company Solicitors LLPGarrick House27-32 King StreetCovent GardenLondonWC2E 8JB
DX No. 51632 Covent Garden
T: +44 (0) 20 7240 3474F: +44 (0) 20 7240 9111
Beale and Company Solicitors LLP34 Lime StreetLondonEC3M 7AT
DX No. 517 London/City
T: +44 (0) 20 3544 5060F: +44 (0) 20 3544 5061
BristolBeale and Company Solicitors LLPRoyal Talbot House2 Victoria StreetBristolBS1 6BN DX No. 7809 Bristol
T: +44 (0) 117 311 7474F: +44 (0) 117 311 7475
DublinBeale and CompanyHamilton House28 Fitzwilliam PlaceDublin 2
DX No. 109048 Fitzwilliam
T: +353 (0) 1 775 9505F: +353 (0) 1 775 9506
Welcome to our Legal Review of 2013… .A report from Antony Smith, Senior Partner
www.beale-law.comLondon | Bristol | Dublin 9www.beale-law.comLondon | Bristol | Dublin 8
Insurance
Underwriters on Profin should have a good few years on claims, following the
surveyor and solicitor claims from the property bubble of 2008 . Accountants’
low level of risk seems to continue and as construction booms this year or next
there will be a period of quiet . That will change in two years or so when new
projects throw up claims but make hay now! This particularly applies to the new
entrants who do not have the historical baggage .
Apart from the average incompetent professionals, where could we see new or
unexpected spikes in claims? Cyber is one obvious answer . Instances of data
loss and hacking are on the rise . Christmas saw two major hacking incidents .
Travel insurer Staysure warned approximately 90,000 customers that some of
their sensitive bankcard details may have been stolen . In the second, retailer
Target said that the details of more than 40 million cards were stolen by thieves
who compromised card swipe systems at Target’s tills . The new National
Crime Agency has warned that it is not just retail businesses that are at risk,
professional practices are a prime target for hackers . Whether a policy will
respond to a claim depends on the scope of the cover, but there are likely to
be large losses looming . Our team has developed a response that insurers like
to use where we have teamed up with other experts to provide an incident
response service . This includes legal advice, IT specialists and PR advisors . 2014
could be the year we see businesses taking out cyber cover as part of standard
risk management .
The other area of increased risk is brokers’ negligence . With reduced premiums
during recession, insureds have looked to make savings . Brokers who have
cut back staff may not have the experience to have warned clients about
the dangers of their approach to risk and advised on the wrong response to
cutbacks . All crystal-ball gazing so we will see .
International
Our international work is still largely based on FIDIC and the claims are very
large . The use of Dispute Boards may be a good one in theory but more
disputes seem to be progressing from the DAB to full scale arbitration . Maybe
there needs to be renewed effort to make clients more accepting of DAB
decisions . We see this as an important part of our role in advising at the
beginning of disputes so client expectation and understanding means they
are ready to accept DAB decisions or challenge when appropriate and not just
challenge because they can . We work closely on this theme with many leading
DAB members who we know are concerned about this trend .
Beale & Company News continued Beale & Company News continued
“ I use the team for their in-depth knowledge and experience, supported by an open-minded and well-rounded approach. Chambers UK 2014
”
“The team has a strong focus on international work, particularly in the Middle East and Africa. Chambers UK 2013
”
A selection of our highlights….
A new look and future growth
Last year we unveiled a more modern look for the firm with a re-brand of our
logo and website . With 2013 marking 175 years since the firm was founded, back
in 1838, we felt it time to modernise our image and how we present ourselves in
the market we operate, and also highlight our expertise in our specialist sectors
and the legal services we provide .
Our brand refresh also signified our commitment to developing with our clients
and to our own further growth . In 2013, Will Buckby was promoted to Partner,
reflecting the success of our highly regarded international construction practice .
We also promoted three to Associate in our Dublin office and were pleased to
offer solicitor positions to trainees in London and Bristol .
2014 will see further changes for the firm as our Covent Garden office will be
re-locating to new offices in the City of London – meaning our two London offices
will become one again . We will be based in the heart of the London insurance
market, thus cementing our reputation as one of the leading legal advisers to this
sector and allowing us to work more closely with our clients and contacts . With
offices in London, Bristol and Dublin and a Partner based in Dubai we have the
geographical spread to service our diverse client base both in the UK and overseas .
Collaborative approach
We have made significant investment to our international team and presence
over the last few years . We are structured to advise clients either directly from
our well established offices in the UK and Dublin or in collaboration with our
international partners across jurisdictions including Africa, Europe and the Middle
East . This investment has led to us working on many high profile development
projects and international arbitrations across the year . Our AME Seminars are also
proving popular particularly with Government Departments in Africa and provide
a valued networking opportunity for our clients . We have received recognition of
our achievements from leading legal directory Chambers and Partners and British
Expertise who have shortlisted us for the ‘Outstanding International Business
Award (SME) 2014’ .
Creative Solutions
Our commitment to grow with our clients and put their needs first has seen us
approach specific legal services and opportunities with more creative solutions
– be it through client dedicated extranets, up to date IT solutions or competitive
and innovative fee structures . This approach to our clients and also to new
business seems to be paying off as we have achieved a number of new business
wins and panel positions through competitive pitches . We have also offered
advice and solutions via a number of events held for clients and contacts in the
sectors in which we are operating .
With thanks for your support last year, we wish all our clients and friends a happy
and successful 2014 and look forward to working with you .
www.beale-law.comLondon | Bristol | Dublin 11www.beale-law.comLondon | Bristol | Dublin 10
Professional liability: solicitors, accountants and financial advisers continued
Was there a breach of trust?
The essential question in such situations is whether the solicitors have parted
with the funds without completion of the transaction for which the funds were
provided having taken place . The solicitors in this case did not obtain, when
they parted with the funds, a statement from the existing mortgagee of the
amount required to redeem the existing mortgage and confirmation that the
money would be used for that purpose . The Court of Appeal held therefore
that there had been no completion and so there had been a breach of trust in
parting with the funds .
The court further held, disagreeing with the judge below, that the breach could
not relate only to the amount overpaid to the borrowers (i .e . the extra amount
that should have been paid to discharge the existing mortgage): the breach
could only relate to the whole of the funds .
However, the Court of Appeal held that, under the equitable rules of
compensation, the compensation payable by the solicitors to the lenders should
be limited to the loss that was actually caused by their breach of trust, which in
reality was only the amount of this overpayment . Thus the Court reached the
same result as the judge below by a different route .
The same strict principle that there is a breach of trust if a solicitor parts with
the funds without completion taking place was followed in Santander UK Plc v R.A. Legal Solicitors (23 May), a case concerning a fraudulent transaction,
where the solicitor parted with the funds not realising that the property in
question was not for sale at all . The Court of Appeal has held that in such a
situation, no completion has taken place, because any documents received
by the solicitor in exchange for the money are worthless forgeries and the
transaction itself a nullity .
The solicitors in this case tried to run another argument to the effect that,
even though completion did not in fact take place, the solicitors were not in
breach of trust because they had followed usual and proper procedures and
paid out the funds for the purpose of completion; however, the judge held that
they were in breach of the express terms of the trust contained in the lender’s
instructions to them, which was not to part with the funds save on completion
of the transaction .
Relief under section 61 of the Trustee Act
However, under section 61 of the Trustee Act, the court has a discretion to
relieve a trustee of liability for breach of trust if the trustee has acted honestly
and reasonably and ought fairly to be excused for the breach of trust . There
was no question here but that the solicitors had been honest, and the judge
seems to have had little hesitation in concluding that they had also acted
reasonably and should be excused of liability under section 61 .
This seems to be the most likely defence open to solicitors who get caught up
in fraudulent transactions of this sort which seem to have been all too common
“ The Court of Appeal held therefore that there had been no completion and so there had been a breach of trust in parting with the funds
”
Professional liability: solicitors, accountants and financial advisers
Property transactions
Solicitors instructed to act on the purchase of a property typically act both for the purchaser and for the purchaser’s lender (normally a bank or building society) and are put in funds by the lender to enable them to complete the purchase and obtain a mortgage over the property in favour of the lender.
The solicitors hold the funds on trust to apply them in accordance with their
instructions . If therefore they pay the funds out otherwise than in accordance
with those instructions, they may have acted in breach of trust, not merely been
negligent . In some circumstances, they may not have been negligent at all;
even if they were negligent, the consequences of being in breach of trust are,
potentially, more serious .
This was the situation in AIB Group (UK) Plc v Mark Redler & Co (8 February) .
The solicitors were put in funds in this case to arrange for the remortgage of
a property, in order to secure a new loan by a new lender to the owners of the
property . The solicitors inadvertently paid out too much to the property owners
and not enough to discharge the existing mortgage .
The owners later defaulted, and in the event the lender lost a large part of its
loan due to a fall in the value of the property, which was sold for a substantially
lower price than it was thought to be worth when the loan was made .
The lender argued that the solicitors were in breach of trust in parting with
the funds without obtaining a discharge of the existing mortgage and were
therefore liable to repay all the funds to the lender, less only the amount that
had been recovered for the lender on the sale of the property . If this argument
were to succeed, the lender would be able to recover from the solicitors the
whole of their loss on the transaction, including what they would have lost
anyway even if the transaction had been properly completed, and so would
actually have benefited from the solicitors’ alleged breach of trust .
“ The solicitors inadvertently paid out too much to the property owners and not enough to discharge the existing mortgage
”
www.beale-law.comLondon | Bristol | Dublin 13www.beale-law.comLondon | Bristol | Dublin 12
Professional liability: solicitors, accountants and financial advisers continued
The judge held that the relative whom she had intended to benefit was entitled
to sue the solicitors, under the White v Jones principle .
What would have happened?
This was not the end of the matter, because the claimant still had to satisfy the
court that had the solicitor done what he should have done and acted in time
to take proper instructions from his client, the client would have stuck to her
intention to leave the bulk of her estate to the claimant . This raised a point on
which there appears to be no authority .
The normal rule is that a claimant has to prove that the negligence (or other
wrongdoing) alleged against the defendant caused the loss suffered by the
claimant for which it is claiming redress; but this often involves a hypothetical
question – what would have happened if the defendant had not been negligent?
- and answering it with a sufficient degree of certainty is sometimes difficult .
In a situation where the hypothetical question concerns what the claimant
itself would have done, the claimant must prove its case (that what it would
have done would have avoided the loss that it has suffered) on the balance of
probabilities – the normal standard in civil cases . For example, in a situation
where there has been a negligent failure to give the claimant certain advice
which would have avoided the loss, the claimant must prove, on the balance of
probabilities, that it would have followed that advice had it been given . If it fails
to discharge this burden, the claim will fail .
Loss of a chance damages?
However, if the hypothetical question concerns what some third party would
have done, a more modulated approach may apply . Provided that the claimant
can show that there was more than a speculative chance that the third party
in question would have acted in a way that would have avoided the claimant’s
loss but cannot go so far as to prove this on the balance of probabilities, the
court may assess as a percentage the likelihood or chance that this would have
happened and award as damages that percentage of the loss (such damages
are sometimes referred to as loss of a chance damages) .
There seems to be no authority on the question of whether this percentage
chance approach can be followed in the case of a claim by a disappointed
beneficiary under the principle in White v Jones . Is the testator, although
the solicitor’s client, to be treated as a third party for this purpose? The
hypothetical question in this particular case involved the conduct of the 90-year
old lady: what would she have done if the solicitor had responded promptly
to her instructions? Would she have stuck with her intention to leave the
bulk of her estate to the new beneficiary? In order to recover her full loss, the
claimant would have to satisfy the court that, on the balance of probabilities,
she would have done . But if she could not do this, could the percentage chance
assessment be applied to enable her to recover a percentage of her loss?
“ If it fails to discharge this burden, the claim will fail
”
Professional liability: solicitors, accountants and financial advisers continued
in recent years . It seems clear that the solicitor’s conduct of the transaction
does not necessarily have to have achieved an especially high standard in order
for the solicitor to obtain relief under this section . Minor or one-off instances of
poor practice, for example, even if negligent, may not prevent the solicitor from
obtaining relief, particularly if they have not caused the loss that has occurred .
The importance of this last point was illustrated a few months later in the case
of Ikbal v Sterling Law (30 October) . This was another case of an imposter
selling a property that he did not own and of the purchaser’s solicitors parting
with the funds for a purchase that was not completed . It was held, following
the earlier authorities, that the solicitors had therefore parted with their client’s
funds in breach of trust, which again raised the question – would the court
grant relief to the solicitors under section 61 of the Trustee Act?
In this case, the conduct of the solicitors did seem to be open to criticism . The
judge came to the conclusion that, from start to finish, the work of the solicitors
was conducted casually, and that they were in serious breach of duty following the
purported completion in failing to warn their client for some time that the transfer
document had not been received, during which time the client incurred expenses
on the house that he thought he had purchased . However, because there was no
causal connection between the solicitors’ conduct and the loss of the funds, the
judge granted relief under section 61 . (The client was awarded damages flowing
from the solicitors’ breach of duty following the purported completion) .
The judge rejected an argument that there were signs that should have made
the solicitors suspicious . However, he pointed out that the events in question
had occurred prior to the issue by the Law Society in October 2010 of a
practice note about “Property and registration fraud”, since when it could be
argued that solicitors should be more alert to any possible signs of fraud .
The White v Jones principle
The well-known case of White v Jones established some years ago that a
disappointed beneficiary could make a claim against a solicitor who had been
negligent in the preparation of a will . The reason that a special rule was needed
was because the solicitor’s client was the testator and so normally only the
testator or, following the testator’s death, the testator’s estate could bring a
claim against the solicitor for negligence . However, the negligence may not have
resulted in any loss to the estate: for example, if, as a result of the solicitor’s
negligence, person A receives a legacy which the testator had intended to go
to person B, the estate itself will have suffered no loss . Hence the need for a
special rule allowing person B to sue the solicitor .
A situation of this kind arose in Feltham v Freer Bouskell (15 July), where a
90-year old lady in a nursing home instructed her solicitor to make changes to
her will, leaving the bulk of her estate to a relative not mentioned in her existing
will . The solicitor failed negligently, as the judge later held, to act promptly in
response to these instructions before the lady died . (She did in fact make a new
will before she died, but the validity of this will was open to challenge) .
“ The judge came to the conclusion that, from start to finish, the work of the solicitors was conducted casually, and that they were in serious breach of duty
”
www.beale-law.comLondon | Bristol | Dublin 15www.beale-law.comLondon | Bristol | Dublin 14
Professional liability: solicitors, accountants and financial advisers continued
It was accepted that the solicitors had not been engaged to advise their client
on the commercial wisdom of making the loan . However, before the loan was
made, it came to the attention of the solicitors that the loan would in fact be
used to purchase the property in question and discharge a mortgage on it,
which the client claimed he had not realised . The solicitors were held to have
been under a duty to inform their client of this and were therefore in breach of
duty when they failed to do so .
What damages were claimable from the solicitors? The solicitors relied on what
has come to be known as the SAAMCO principle (called after the well-known
valuers case in 1996 of South Australia Asset Management Corporation v York
Montague Ltd) .
Application of the SAAMCO principle
This principle is now a cornerstone of the law relating to professional liability .
Briefly, it is that the extent of a professional person’s liability for any particular
loss is conditioned by the scope of the professional person’s duty . However,
stating the principle is sometimes easier than applying it in practice .
The first question addressed by the court in the Gabriel case was – what actual
loss (if any) was incurred by the client as a result of making the loan? In reply
to this, in view of the findings of the judge in the court below, the court of
appeal accepted (not without some hesitation) that the client did not know
how the loan was going to be used and that, if he had known this, he would not
have proceeded with it . Therefore, the loss incurred was the full amount of the
client’s loss on the transaction .
The next question addressed by the court was whether, having regard to the
scope of the solicitors’ duty, the solicitors were liable for the whole of this loss
or only some (and if so what) part of it . The court held that the duty of which
the solicitors were in breach was a duty to provide information to the client,
not to advise the client on the course of action that he should take . It followed
that the full loss incurred by the client as a result of making the loan did not fall
within the solicitors’ duty of care and so the solicitors were not liable for the
whole of the loss .
The court then asked – what were the consequences of the duty that the
solicitors did owe (to provide the information) being breached? This is not the
same question as “what would have been the consequences if the duty of care
had been fulfilled?” (the answer to which, on the facts accepted by the Court of
Appeal, would have been that the full loss would have been avoided) . The court
concluded that none of the loss was attributable to the solicitors’ breach of
duty: the whole loss was the foreseeable consequence of obvious commercial
risks that the client chose to take .
In short, the application of the SAAMCO principle in this case led to the
conclusion that the solicitors were not liable for any part of the client’s loss .
“ The first question addressed by the court in the Gabriel case was – what actual loss (if any) was incurred by the client as a result of making the loan?
”
Professional liability: solicitors, accountants and financial advisers continued
The judge was of the view that it could but that the point remains to be
decided by an appellate court . As it was, the judge held that the claimant in
fact succeeded on the balance of probabilities and so was able to recover her
full loss .
Duty to explain unusual clauses
There is a principle established in past cases that a solicitor owes a duty to his
or her client to explain unusual clauses in an agreement into which the client is
contemplating entering . It has also been said that, especially where the client is
unsophisticated, it is incumbent on the solicitor to confirm the advice in writing .
This principle was considered in the case of Mathiesen v Clintons (11 October),
which concerned a complicated clause in a share agreement between a
husband and wife to make financial provision for the wife . (The marriage was in
difficulties but neither at this stage wanted a divorce) .
Arguably, the solicitors acting for the wife were remiss in failing to obtain
details of the husband’s salary and of a scheme by which it could be increased
but the judge held that these failings did not, in the circumstances, amount to
negligence . However, the judge held that the solicitors had been negligent in
failing to advise their client on the workings of the clause, prior to execution of
the agreement . This was notwithstanding the fact that, as he held, the client
was far from being unsophisticated and had been involved in the negotiations
(but had not entered into such an arrangement before) . He held that it would
have been prudent but not essential to have put the advice in writing .
The claim against the solicitors in fact failed because it was out of time – an
argument that there had been deliberate concealment was rejected – and
the judge also held that the client would not have sought to renegotiate the
agreement in any event .
A duty to warn
The scope of a professional person’s duty should be determined by the
retainer . However, it is always possible that a particular duty may be triggered
by circumstances that arise during the commission . An example is where
a professional person, in the course of doing that for which he is retained,
becomes aware of a risk or potential risk to the client . The professional may
thereby become under a duty to warn (or at least inform) the client of the risk,
even if the risk may concern matters that are outside the retainer .
This is what happened in the case of Gabriel v Little (22 November), which
concerned solicitors who acted for a businessman making a loan to be used for
the development of a property . The loan was never repaid and, although the
loan was secured on the property, the property itself was never developed and
was eventually sold in a derelict state for a pittance .
“ Arguably, the solicitors acting for the wife were remiss in failing to obtain details of the husband’s salary
”
www.beale-law.comLondon | Bristol | Dublin 17www.beale-law.comLondon | Bristol | Dublin 16
Professional liability: solicitors, accountants and financial advisers continued
Could such an order be made against solicitors who act for a party in litigation
but are not, of course, parties to the litigation themselves?
Solicitors acting under CFAs
Many solicitors regularly conduct litigation under a conditional fee agreement
(CFA) (a matter that was a particular focus of the reforms to civil litigation
that came into effect on 1 April) . Broadly, the solicitor acts for the claimant on
terms that the claimant will only have to pay the solicitor’s fees if it wins the
case . The claimant can also protect itself against liability for the defendant’s
costs by taking out after-the-event (ATE) insurance, which of course protects
the defendant too (or, more commonly, the defendant’s insurers) if the claimant
would otherwise be unable to pay its costs .
However, if the claimant does not take out ATE insurance (it may not be able
to afford the premium), the successful defendant or its insurers may not be
able to recover any of its costs – unless perhaps it can recover them from the
claimant’s solicitors, on the basis that, by enabling the claimant to pursue the
claim, they have in effect funded the claim . The extent to which solicitors acting
on behalf of claimants can fund or “prime pump” litigation for those of limited
means, without thereby exposing themselves to adverse orders for costs should
the claims fail, was the issue before the Court of Appeal in two cases, Flatman v Germany and Weddell v Barchester Health Care Ltd (10 April) .
Such an order would not be made against a solicitor unless the solicitor had
acted outside the normal role of a solicitor . Therefore, since solicitors are
permitted to act under a CFA, a third party costs order would not be made
against a solicitor who has acted for an unsuccessful party merely on the basis
that the solicitor had agreed that the party would not have to pay the solicitor’s
costs if it lost the case . The point of principle in the Flatman and Weddell
cases was whether the same applies where the solicitor has also paid the
disbursements of the unsuccessful party (for example, court fees and expert
witness fees) without requiring them to be repaid to the solicitor in the event of
the party being unsuccessful .
The Court of Appeal considered whether the legislation that permitted
solicitors to act under a CFA covered disbursements as well as normal costs .
The court ruled that it did . The effect of the court’s ruling, therefore, is that a
solicitor acting under a CFA who pays the client’s disbursements in litigation
will not, without more, be at risk of incurring an order to pay the other
party’s costs .
Further factors
However, further factors could justify the making of such an order against
solicitors acting in litigation, of which one of the two cases may provide an
example . There was evidence before the court that the solicitors may have
“Such an order would not be made against a solicitor unless the solicitor had acted outside the normal role of a solicitor
”
Professional liability: solicitors, accountants and financial advisers continued
Drafting the chief executive’s service contract
When solicitors are retained by a company to draft a service contract for its
chief executive, should they take instructions from the chief executive, or would
that involve a conflict of interest?
The point arose in Newcastle International Airport Ltd v Eversheds LLP (28
November) . The case arose out of events of some notoriety in the north east,
when it transpired that variations to the contracts of the chief executive officer
and the finance director of Newcastle International Airport Limited (of which
various local authorities were shareholders) entitled them, upon completion of
the refinancing of the company’s debt, to bonuses totalling some £8m .
The solicitors, who were engaged by the company to draft the new contracts
and, in doing so, took instructions from the chief executive himself, maintained
that, in their experience, their instructions in relation to the drafting of such
contracts invariably come from the executive directors, with the resultant draft
then being reviewed by the company’s remuneration committee . The Court of
Appeal accepted that the solicitors were entitled to regard the chief executive
as having the authority of the company when giving instructions, but did not
agree that advice given by the solicitors to the executives on the effect of the
drafts could therefore be treated as advice to the company .
The court held that the solicitors were under a duty, having completed the
drafts, to give separate advice to the remuneration committee on the effect of
the drafts, explaining in user-friendly language a summary of the scheme and
the workings of each material change to the original contracts and identifying
where in the drafts the changes could be found .
What would have happened if they had done this? In the very unusual
circumstances of this case, the court held that the chairwoman of the
remuneration committee, who, among other things, seems to have had an
aversion to reading legal documents, would not in fact have read and ensured
that she understood the advice that should have been given . The case against
the solicitors failed, therefore, on causation .
Although the court did not suggest that the solicitors should not have taken
instructions from the executives, it did remark that it was less than ideal that
they should have done so, whatever may be the current practice .
Solicitors liable for litigation costs?
A court may order a person who is not a party to the litigation to pay the
costs of the successful party in the litigation if the non-party has funded the
unsuccessful party and the unsuccessful party is unable to pay the costs itself .
However, such an order would not normally be made against a mere funder: the
funder must have had an interest in the proceedings and have stood to benefit
from them (had the unsuccessful party been successful) or have sought to
control the conduct of the proceedings on behalf of the unsuccessful party, so
that the funder could be said to be the “real” party to the action .
“ The Court of Appeal accepted that the solicitors were entitled to regard the chief executive as having the authority of the company…
”
www.beale-law.comLondon | Bristol | Dublin 19www.beale-law.comLondon | Bristol | Dublin 18
Professional liability: solicitors, accountants and financial advisers continued
Much of the judgment was then concerned with what would then have
happened if they had done that: whether the claimant would in fact have been
advised by a specialist to follow the bearer warrant scheme, whether he would
have taken that advice and done so in time and whether it would in fact have
worked to his advantage . These points were resolved in the claimant’s favour
(the answer to each question was held to be yes) and the accountants were
therefore ordered to pay damages comprising the amount of capital gains tax
that the claimant had had to pay and the costs of another scheme that the
claimant had tried but had proved abortive .
Another, more fundamental, issue in the case was whether the accountants
were under a duty to the claimant to advise him on tax planning at all,
given that he had not requested such advice and it was not covered in the
accountants’ retainer letter . The judge held that such a duty was owed because
such advice had in fact regularly been given by the accountants without being
requested, and was in fact given by them in relation to capital gains tax on the
proposed sale . In short, it was a case of a duty arising as a result of what was
actually done .
Professional negligence: expert opinion
Professional negligence is falling below the standards properly to be expected of a
person of the relevant profession . In order to prove that there has been professional
negligence, expert evidence of the relevant standards from those within the
same profession is normally crucial (save in the case of claims against solicitors
and barristers, where the judge is presumed to have the relevant expertise) . If
a properly qualified and reputable independent expert expresses a reasoned
opinion that the work carried out by the professional met the required professional
standard, it is for the claimant to establish why that view should be rejected .
So said the Privy Council on an appeal from the Court of Appeal of Jamaica
in the case of Caribbean Steel Co Ltd v Price Waterhouse (9 July), where the
work in question concerned a valuation prepared by accountants of the shares
of a company prior to its acquisition by another company . The criticism of the
accountants’ valuation centred upon their treatment in the report of a surplus
in the company’s pension fund . The view of the accountants’ expert witness
was that the accountants’ estimate of the value of the company was reasonable
and had been properly carried out and that the pension fund surplus could be
considered an asset of the company . The judge at first instance rejected this
evidence: the Court of Appeal said that he was wrong to have done so .
The fact that the accountants had called an independent expert to testify that
in his opinion there was no negligence did not, of course, preclude the court
from rejecting the expert’s view . But it was essential that the reasons given
by the expert for reaching his opinion were carefully scrutinised; for unless
there was sound reason for rejecting it, a judge could not properly find that
professional negligence had been established .
“ The judge held that such a duty was owed because such advice had in fact regularly been given by the accountants…
”
Professional liability: solicitors, accountants and financial advisers continued
proceeded with the case despite instructions from their client (the claimant)
not to do so without ATE insurance in place . Despite the solicitors having
succeeded on the point of principle concerning disbursements, the court
upheld (both in this case and in the other case where the same solicitors
were acting) an order for disclosure of documents relating to the funding
arrangements for the claimant, to enable the defendant’s insurers to consider
whether there were still grounds for seeking an order for costs against the
solicitors .
A negligent failure on the part of the solicitors to obtain ATE insurance for
their client and to inform their client of this was in fact the background to
Heron v TNT(UK) Ltd (2 May), another case before the Court of Appeal . It
was argued that the solicitors’ negligence had created a conflict of interest
between the solicitors and their client, as the solicitors had an interest of
their own in endeavouring to resolve the case in a way that avoided any cost
liability for their client that should have been covered by ATE . However, there
was no evidence that the failure to obtain ATE insurance had caused costs
to be incurred that would not have been incurred anyway and the judge in
the court below had rejected a claim of conscious impropriety on the part of
the solicitors .
In these circumstances, the Court of Appeal rejected the claim for an order
making the solicitors liable for the costs of the other side . Otherwise, any act
of negligence by a solicitor in the conduct of litigation (thereby giving rise to
a conflict) would be sufficient to make such an order, and the court did not
accept that the law goes that far .
Tax advice
Despite the political unpopularity of tax avoidance schemes, the judgment
in Mehjoo v Harben Barker (5 June) is a reminder that an accountant may
nonetheless be in breach of duty to its client if it fails to advise on legal ways of
avoiding (or mitigating or saving) tax . The case concerned a scheme known as a
Bearer Warrant Scheme which was available to people not domiciled in the UK as
means of avoiding capital gains tax on the sale of shares in a company . It involved
the conversion of registered shares in the company into bearer shares, the shares
being moved into an offshore jurisdiction (such as Jersey) and gifted to an
offshore trust set up for this purpose . The sale of the shares by the trust would be
outside the scope of UK tax . The scheme has since been blocked by legislation
but would have been available at the time to the claimant in this case .
The case against the claimant’s accountants, who were generalist accountants,
was not that they should have known or advised the claimant about this
scheme but that they should have realised that the claimant, who had been
born in Iran, was likely to have non-domiciliary status and that this would have
potential tax advantages; and so, when it was clear that the claimant would
face a large claim for capital gains tax on the sale of his shares, they should
have advised the claimant to seek advice from non-dom specialists .
“ It was argued that the solicitors’ negligence had created a conflict of interest…
”
www.beale-law.comLondon | Bristol | Dublin 21www.beale-law.comLondon | Bristol | Dublin 20
Professional liability: solicitors, accountants and financial advisers continued
Did the limitation period for the claimant’s subsequent action against the
solicitors start to run only from the date when she settled the original action? If
the action had actually been struck out, would the limitation period have only
started to run from the date when it was struck out?
On these (essentially the same) questions, the leading authorities may not be
entirely consistent, but it seems that in most situations it is likely that damage
will be held to have been sustained – and the limitation period to have started
to run – before the original action was settled or struck out (or permitted to
continue only on a restricted basis) as the case may be . This is because, once
there was a material risk of the action being struck out, which is likely to have
happened before it actually was struck out, the value of the claim in the action
would have been diminished, and this would constitute damage .
In St Anselm Development Co Ltd v Slaughter & May (1 February), the issue
was whether a single act of negligence could give rise to two causes of action,
each with its own limitation period . Solicitors were alleged to have advised
negligently on extensions to the leases of two flats, causing a disadvantage
to their client (the lessor) . The extended lease for each flat was completed at
different times . The claim against the solicitors was started more than six years
after completion in respect of the first flat but before the end of the six years in
respect of the second . Was the claim in respect of the second flat doomed as
well? This depended on whether there was a separate cause of action in respect
of each flat . The judge held that there was, as the solicitors owed a separate
duty to advise on each underlease, even though the advice was the same in
both cases . The claim in respect of the second flat was, therefore, in time .
“ Was the claim in respect of the second flat doomed as well?
”
Professional liability: solicitors, accountants and financial advisers continued
Statutory and common law duties
Breach of a statutory duty may in some cases give rise to a right of action in
private law for a person who suffers loss as a result of the breach but it does
not follow that the existence of the statutory duty gives rise to a co-extensive
duty of care at common law . So it was held by the Court of Appeal in Green v Royal Bank of Scotland (9 October) .
The case concerned the sale of an interest rate swap by the bank to two of
their customers . The Bank did not give the customers any recommendation or
advice in relation to the swap but it was alleged that the bank was in breach of
the then current Conduct of Business Rules in failing to take reasonable steps to
ensure that they understood the nature of the risks involved .
It was too late for the customers to bring an action for this alleged breach of
statutory duty (as would have been possible) but an action for breach of a
common law duty of care would still have been in time, if there was any such
duty (one of the potential advantages of an action for breach of a common law
duty of care is a longer limitation period) .
The Bank did not assume any advisory duty of care to the customers nor did
any such duty arise . The common law duty of care established in the well-
known case of Hedley Byrne and Co Ltd v Heller and Partners Ltd is a duty
to take care in making a statement but does not comprise a duty to give any
particular information or advice, unless the lack of such information or advice
itself renders a statement misleading .
The performance of a statutory duty by (typically) a public body may bring
about a relationship between itself and another person, which could give rise
to a duty of care owed to that person . But such a duty would arise out of the
relationship so created, not by reason of the imposition of the statutory duty .
In short, no common law duty of care in this case was owed by the bank to its
customers . However, the Court did say that the existence of a statutory duty
may give rise to a common law duty of care in circumstances where breach of
the statutory duty is not actionable in private law .
Limitation
A perennial issue in professional negligence claims is the question of when
damage is first sustained by the claimant, because this is when the six-year
period for starting an action in tort is triggered . In the case of Berney v Saul (5 June), the Court of Appeal had to consider this issue in relation to a claim
against solicitors who were alleged to have negligently delayed in prosecuting
an action, such that there was a risk of the action being struck out, or of only
being allowed to continue with a restriction on the amount that could be
claimed . It was not known whether either risk would have materialised, because
the claimant, in the face of this situation, had settled the action for what, she
claimed, was a considerable undervalue .
“ The Bank did not assume any advisory duty of care to the customers nor did any such duty arise
”
www.beale-law.comLondon | Bristol | Dublin 23www.beale-law.comLondon | Bristol | Dublin 22
in the net contribution clause to other…..contractors was only to those other
contractors .
Consultants seeking to include a net contribution clause in their contracts
may be well-advised, therefore, to ensure that it expressly covers the main
contractor .
This being a contract with a residential house owner, the Unfair Terms in
Consumer Contracts Regulations 1999 applied, and the judge also pointed out
that where there is doubt about the meaning of a contractual term, it should
be construed in the consumer’s favour . The judge did not, though, rule that
the clause itself was void as unfair under the Regulations .
Some architect duties
On the scope of an architect’s duty of inspection, the judge made the
following comments:
… an architect probably should be present when this type of operation [the pouring of a floor slab in a domestic project] is being carried out if that is reasonably possible….an architect would not be expected to check the precise depth of the excavation or the mix of the concrete, unless he was put on notice that something was obviously wrong….an architect would be looking to see that the work appeared to be in accordance with the specification. For example, if the design of a strip foundation specified that it was to be 750mm deep, I would expect an architect to notice if the trench for it was only some 300-400mm deep….I would not necessarily expect an architect to notice if the trench was only 600-650mm deep….That might not be immediately obvious…..one would not ordinarily expect an architect to be carrying a ruler and measuring every dimension, unless he or she had some particular reason for concern about some particular aspect of the work.
(The judge concluded that the architect was not in breach of duty in failing to
notice defects in the floor slab) .
The specification for the M&E services was essentially a performance
specification, so it required the contractor to produce the detailed design
of the M&E installation . The judge did not consider that the architect was
negligent in failing to specify a form of contract that provided for contractor’s
design (though if this had been done, the contractor would probably have
been required to have professional indemnity insurance in relation to its
design duties) .
Professional conduct
People who wish to practice as architects must be entered on the Register
of Architects maintained by the Architects Registration Board under the
Architects Act 1997 . Appropriate qualifications and practical experience
or a sufficient standard of competence are required to be entered on the
Professional liability: construction professionals continued
“ …an architect probably should be present when this type of operation [the pouring of a floor slab in a domestic project] is being carried out if that is reasonably possible…
”
Professional liability: construction professionals
Net contribution
West v Ian Finlay & Associates, on 16 April, involved a successful claim for professional negligence against architects. The case involved renovation work to a residential property. The project, in the words of the judge, proved to be a disaster. One feature of the disaster is that the main contractor became insolvent, so the claim lay solely against the architects.
This is the sort of nightmare that professional consultants and their
professional indemnity insurers dread – the consultant being left to carry the
whole of the can because the contractor, who might well have been primarily
responsible for the damage, turns out to be insolvent . The allegations upheld
against the architects in this case concerned both design and inspection; but,
in relation to the latter at least, the architects might well have expected the
main share of liability to be apportioned to the contractor .
To deal with just this sort of situation, professional engagements frequently
contain a net contribution clause, the purpose of which is, in effect, to limit
liability to what the consultant would have had to pay had all other parties
to blame actually paid the amount that was or would have been apportioned
to them . Such a clause was included in the contract of engagement of the
architects in this case, in the following terms:
Our liability for loss or damage will be limited to the amount that it is reasonable for us to pay in relation to the contractual responsibilities of other consultants, contractors and specialists appointed by you.
Unfortunately for the architects, interpreting the contract in its context, the
judge did not consider that the term contractors in this clause included the
main contractor . The relevant context was that the house owners decided to
appoint directly various other contractors to supply certain elements of the
works, which saved them from having to pay the main contractor’s overhead
and profit in relation to those items . The judge concluded that the reference
“ One feature of the disaster is that the main contractor became insolvent, so the claim lay solely against the architects
”
www.beale-law.comLondon | Bristol | Dublin 25www.beale-law.comLondon | Bristol | Dublin 24
2008 and the value of the development fell over the period of delay by a
substantial amount . The question for the Court of Appeal was whether the
engineer could, in principle, be liable for loss suffered by the developer as a
result of this fall in market value .
The Court said the appeal raised an issue of some importance about the law
on remoteness of damage in cases of breach of contract . Was the damage in
question too remote?
The legal test of remoteness stems from the nineteenth century case of
Hadley v Baxendale . The standard exposition of the test in modern times
is that a type of loss is not too remote if the party in breach ought to have
realised at the time of making the contract that it (i .e . the type of loss in
question) was not unlikely to result from the breach .
A fall in the property market could be said to be something not unlikely to
occur: it is well known that properties go up and down in value .
It was argued on behalf of the engineer that, applying the SAAMCO principle,
the first step should be to establish the scope and nature of the duties
owed by the engineer under the contract and whether the loss for which
compensation is sought is of a kind or type for which the engineer ought fairly
to be taken to have accepted responsibility . Approaching the matter in this
way, it would be seen that there was no duty on the engineer to protect the
developer against losses due to falls in the market .
The facts of this case were not dissimilar from that of the SAAMCO case itself,
where it was held that valuers advising lenders on the value of properties to
be taken as security for a loan who negligently overvalue the property should
not be liable for losses attributable solely to a fall in the property market,
notwithstanding that such losses were foreseeable in the sense of being not unlikely . Such liability was excluded on the ground that it was outside the
scope of the liability which the parties would reasonably have considered that
the valuer was undertaking .
However, perhaps rather surprisingly, the Court of Appeal held in the John
Grimes Partnership case that the SAAMCO principle does not and is not
intended to alter the standard approach based on reasonable foreseeability
derived from Hadley v Baxendale . It merely shows that in some situations the
standard approach will not apply, because it will not reflect the expectation or intention reasonably to be imputed to the parties . However, the Court said that
such situations are unusual and that Hadley v Baxendale remains a standard
rule, which has been rationalised on the basis that it reflects the expectation
to be imputed to the parties in the ordinary case:
Normally, there is an implied term accepting responsibility for the types of losses which can reasonably be foreseen at the time of contract to be not unlikely to result if the contract is broken.
On behalf of the engineer, it was argued that acceptance of such
responsibility for losses due to the fall in property market should not be
imputed to the engineer: the contrast between the modest fee payable to
Professional liability: construction professionals continued
“ Approaching the matter in this way, it would be seen that there was no duty on the engineer to protect the developer against losses due to falls in the market
”
Professional liability: construction professionals continued
Register . However, the Act also requires the Board to issue a Code laying down standards of professional conduct and practice expected of registered persons. Under the Code that has been issued in accordance with this
requirement, architects are required to ensure that their personal and
professional finances are managed prudently . An order of bankruptcy or
failure to pay a judgment debt are examples of matters that may be examined
by the Board .
John Dowland v The Architects Registration Board (19 April) concerned an
architect who was struck off the Register after being made bankrupt and
whose application for re-admission after two years was refused by the Board .
The architect (or former architect, as he now was) appealed to the court,
arguing that the Board’s decision not to re-admit him was flawed on various
grounds . The judge dismissed the architect’s arguments . One argument raised
by the architect, based on an interpretation of the Act, was that under the Act
only matters of competence could be considered on an application for re-
admission; however, the judge held that the Board’s considerations were not
so confined .
The judge also ruled that it was not open to the former architect to appeal
under the Act against the Board’s refusal to reinstate him on grounds
concerning professional conduct (as opposed to professional competence)
but that he could have applied to the court for judicial review: the outcome,
though, would have been the same .
Whatever the circumstances of this particular case, some might argue that
matters of conduct which have no bearing on an architect’s competence
should not cause an architect to be struck off the register or prevent him or
her being re-admitted .
The SAAMCO principle not applied
We have referred above to a solicitors case where the SAAMCO principle
(called after the well-known valuers case in 1996 of South Australia Asset
Management Corporation v York Montague Ltd) was applied . The principle
was not applied, however, in a case against engineers, John Grimes Partnership Ltd v Gubbins (5 February) . Instead, the Court of Appeal
considered the issue of liability for the loss in question through the narrower
prism of whether the loss was too remote .
The engineer had been engaged to design the road and drainage for a
residential development . The judge found that it was an express oral term of
the contract that the agreed work would be completed by a particular date,
and he also held that that was a reasonable time for the work to be done . The
work was not completed by the agreed date and the judge found that, due
to this breach of contract on the part of the engineer, the development was
delayed by 15 months .
Unfortunately, this delay occurred in the aftermath of the financial crisis of
“The architect (or former architect, as he now was) appealed to the court, arguing that the Board’s decision not to re-admit him was flawed…
”
www.beale-law.comLondon | Bristol | Dublin 27www.beale-law.comLondon | Bristol | Dublin 26
Professional liability: construction professionals continued
the loss in question is economic than where physical injury is concerned .
However, in the case of Harrison v Technical Sign Co Ltd & Ors (4 December),
which concerned serious injuries to passers-by caused by the fascia of a shop
becoming detached and falling to the pavement, the Court of Appeal held
that the judge below had been wrong to hold that a firm of surveyors owed a
duty of care owed to the passers-by .
The surveyors in question had a few months before inspected the awning
beneath the fascia and, in the view of the judge, should have noticed that the
fascia had dropped . The judge applied the three-fold test and held that it was
satisfied . However, the Court of Appeal held that the judge had placed too
much emphasis on foreseeability of harm, almost to the point of treating it as
sufficient to create a relationship of proximity between the surveyors and the
passers-by: on its own, said the court, foreseeability of harm is not enough .
The proprietor of the shop was concerned that the awning may have been
damaged during building work carried out by the proprietor’s landlord which
the surveyors had managed and supervised and the proprietor had asked the
surveyors to inspect the awning in their capacity as the landlord’s agents . This
limited role of the surveyors in inspecting the awning meant that there was an
insufficient degree of proximity between them and the passers-by to give rise
to a duty of care on their part .
Common law duty of care (economic loss)
The case of Finesse Group Ltd v Bryson Products and another (29 October)
concerned exhibition stands and the adhesive which was supposed to stick
colour laminated panels to the structure of the stands . However, this was
not a case where the panels fell off and injured people . The complaint was
that some of the panels began to delaminate from the structure of the stand
and displayed a bubbling or bulging effect . Any damage complained of
here, therefore, appeared to be economic loss . Only rarely will a common
law duty of care be owed in respect of economic loss, and if there is no prior
relationship between the parties, hardly ever . A claim in tort, therefore, by the
makers of the exhibition stands against the manufacturers of the adhesive
(by whom they had not been supplied directly, so they had no contract with
them) seemed hopeless and it was struck out at the first case management
conference .
Most cases in which a common law duty of care to prevent economic loss
have been held to exist refer back to the landmark case of Hedley Byrne v Heller & Partners . The duty derived from that case and as refined in
subsequent cases arises broadly out of an assumption of responsibility by
one party professing a particular skill and reliance on that assumption by the
other party, in circumstances that are equivalent to contract . In Hunt v Optima (Cambridge) Ltd (29 April), consultants were retained by the developer of
a block of flats to carry out periodic inspections during construction with
a view to producing certificates for purchasers of the flats, certifying that,
“ However, the Court of Appeal held that the judge had placed too much emphasis on foreseeability of harm…
”
Professional liability: construction professionals continued
the engineer under the contract and the potential scale of the losses through
market movement was emphasised, as was the fact that the engineer had no
control over the market movement .
The court was dismissive of the first point:
It may not infrequently be the case that the breach of a contract of modest size gives rise to a substantial claim in damages. Moreover, any such contrast is merely one possible pointer towards a contracting party not having undertaken a potential liability which is reasonably foreseeable and by itself would not normally suffice to establish such an absence of responsibility. It does not do so here.
As for the argument that the engineer had no control over the property
market, the court pointed out that there are many decided cases where delay
in delivery of goods has been held to give rise to damages for loss suffered
through a change in the market price .
This was a disappointing decision not just for the engineers in the case but for
professional people and professional indemnity insurers generally . The Court
seemed concerned to confine the SAAMCO principle within narrow bounds,
as only arising in exceptional cases . This approach does not, though, seem
consistent with the approach in other cases .
The same issue was the subject of a procedural judgment a few days earlier
in the Technology and Construction Court in the case of Aldersgate Estates Ltd v Ham Construction Ltd (In Liquidation) & another (31 January), also
involving a claim against an engineer (and also a contractor) . The case
concerned a property development, during which the façade of the property
(which was to be retained) started to subside and was damaged . As well as
the costs of rebuilding the façade, the claim also included damages for delay
in practical completion of the works, and in particular for diminution in value
due to market changes during the period of delay . The total claim, as of 31
January, came to £4,418,224, of which no less than £3,441,328 was said to be
the result of the diminution in value due to market changes .
The judge refused an application for the issue (of whether the defendants
could be liable for this diminution in value) to be tried as a preliminary issue .
Common law duty of care (physical injury)
There are various legal tests for determining whether, in any particular
situation, a common law duty of care is owed . One is the three-fold test
approved in the well-known case of Caparo Industries Plc v Dickman: foreseeability (whether it was foreseeable that negligence by the defendant
might cause the injury or loss that has occurred), proximity (whether there
was a sufficient relationship of proximity between the defendant and the
claimant who suffers injury or loss) and fairness (whether it would be fair just
and reasonable to impose on the defendant a duty of care to the claimant) .
The courts are likely to be more cautious in imposing a duty of care where
“ The Court seemed concerned to confine the SAAMCO principle within narrow bounds, as only arising in exceptional cases
”
www.beale-law.comLondon | Bristol | Dublin 29www.beale-law.comLondon | Bristol | Dublin 28
Construction
Building contracts
There have been a number of well-known cases in recent years about contractual interpretation, at least some of which are almost always referred to in any judgment now where interpretation of a contract is an issue. In one case in 2013 (RWE Npower Renewables Ltd v J N Bentley Ltd, which is referred to below), the effect of these cases was summarised by the judge in the following way:
One needs to determine objectively what a reasonable person with all the background knowledge reasonably available to the parties at the time of the contract would have understood the parties to have meant and one is looking to adopt the more rather than less commercial construction .
Meaning of the words used
Some fundamental principles of contract construction were considered in
AJ Building & Plastering Ltd v Turner (11 March) . The case concerned insurance
claims for damage to houses . The contractors who carried out the remedial
work had not been instructed directly by the household insurers; the insurers
had instructed another company, which had subcontracted the work to the
contractors . Unfortunately, this company had gone into administration leaving
the contractors unpaid, with no right of recourse against the insurers . The
contractors therefore looked for payment from the householders themselves .
The contractors’ claim against the householders was based on a mandate
that they had procured from the householders . Under this mandate, as well as
agreeing to employ the contractors to carry out the work, the householders
stated that they would remain responsible for payment of any policy excess or any monies due for work authorised by me/us, which is not paid by my/our insurer . Did this mean that the householders had to pay for the work which
they had assumed would be paid for by their insurers?
“ …a reasonable person with all the background knowledge reasonably available to the parties at the time of the contract
”
Professional liability: construction professionals continued
based on those inspections, the work had been constructed to a satisfactory
standard and in general compliance with approved drawings and the Building
Regulations . They were held to owe a duty of care to the purchasers of the
kind derived from Hedley Byrne v Heller, and that the duty of care extended
not only to the making of the statements in the certificates but also to the
performance of the services which were necessary to enable the certificates
to be issued .
The judge also held that the certificates constituted contractual warranties .
The purchase price paid by the purchasers for the flat, although not, of
course, paid to the consultants, was valid consideration for this purpose: while
consideration, in order to create a contract, must move from the promisee
(the purchasers), it need not move to the promisor (the consultants) .
“ The judge also held that the certificates constituted contractual warranties
”
www.beale-law.comLondon | Bristol | Dublin 31www.beale-law.comLondon | Bristol | Dublin 30
see if there is an ambiguity. If it is possible to identify a clear and sensible commercial interpretation from reviewing all the contract documents which does not produce an ambiguity, that interpretation is likely to be the right one; in those circumstances, one does not need the “order of precedence” to resolve an ambiguity which does not actually on a proper construction arise at all.
The judge ruled in this case (deciding against the contractors and disagreeing
with the adjudicator) that, despite some verbal differences between the
documents, there was no material ambiguity between the descriptions of the
work comprised in the section in question .
Variation omitting work
The case of MT Hojgaard A/S v E.ON Climate & Renewables UK Robin Rigg East Ltd (23 April) raised the question of how a variation constituting the
omission of work was to be valued . The contract involved the installation of
the foundations for wind turbine generators offshore . A jack-up barge was to
be used for this purpose but the particular barge provided by the contractors
turned out to be inadequate for the job . The engineer issued variation orders
requiring the substitution of a different vessel . The new vessel was hired
directly by the employer and provided on a free-issue basis to the contractor .
The contract was bespoke but contained not unusual provisions for variations
to be valued by the engineer applying a specified schedule of rates if those
rates are directly applicable to the relevant work; if not, that the engineer
should apply suitable rates that reflect the level of pricing in the schedule;
or if there is no rate in the schedule that could be reflected in a suitable
rate, the engineer shall determine an amount that is in all the circumstances
reasonable .
These provisions are clear in identifying how rates are to be established, where
this is possible . What they do not say is how such rates are to be treated so as
to reach an appropriate adjustment of the contract price, or how a reasonable
amount is to be determined where no rates can be established . This is not a
problem when valuing additional work, where the work in question has been
or will be actually carried out; but the position is different with omissions .
The choice here, for determining how the contract price should be adjusted
(i .e . reduced), was between adopting the contractor’s original projected price
for the work to be carried out using the contractor’s barge (which was later
replaced) or a hypothetical calculation of what would have been a reasonable
price if the work using that barge had in fact been carried out .
In the circumstances of this case, the judge accepted the contractor’s
argument that the former approach was correct . The employer argued for the
latter approach, but the cost of carrying out the work using the inadequate
barge would, of course, have been very substantial . This approach would in
effect have entailed an award of damages against the contractor for failure
to perform the works using its own barge; however, the employer had chosen
Construction continued
“ A jack-up barge was to be used for this purpose but the particular barge provided by the contractors turned out to be inadequate for the job
”
The judge held that, properly construed against the relevant factual
background, the requirement in the mandate referred only to work that
was not covered by the insurance, for example, any additional work that a
householder may have asked the contractors to do . If that construction was
wrong, the judge held that the reference in the mandate to payment which is not paid by my/our insurer should not be read as being limited to payment
made directly to the contractor but could also cover monies paid by the
insurer to the company that went insolvent .
The judge referred to recent Supreme Court authority that, where a contract
is capable of more than one meaning, the court is entitled to prefer the
construction that best accords with commercial common sense even though
another construction would not produce an absurd or irrational result .
Another issue concerned the effect of the Unfair Terms in Consumer
Contracts Regulations, which applied to the contract (as created by the
mandate) between the householders and the contractors . These Regulations
provide that:
If there is doubt about the meaning of a written term, the interpretation which is most favourable to the consumer shall prevail…
The judge held that, if the normal principles of construction yield a clear
preference for one interpretation over another, this regulation does not
apply . The regulation will only operate as a “tie-breaker” where the process
of construction does not clearly favour one interpretation over another . This
regulation did not, therefore, influence the outcome in the householders’ favour .
Precedence of contract documents
The same point was made, albeit in a rather different context, in the judgment
in RWE Npower Renewables Ltd v J N Bentley Ltd (22 April) . The case here
concerned large civil engineering works divided into sections and the dispute
was over what constituted the work to be carried out in one particular section,
so as to decide whether or not completion of that section had taken place
in time in order to determine whether liquidated damages in relation to that
section were payable .
There were a number of different contract documents which were given
an order of precedence by the contract . However, the judge said that this
order of precedence should only be resorted to as an aid to interpretation
if the normal process of construing the contract, reading contract
documents together against the relevant background to the contract, had
led to the conclusion that there was an irreconcilable ambiguity between
the documents . However, as the judge said, often, on analysis, apparent
ambiguities are not ambiguities at all:
What one cannot and should not do is to carry out an initial contractual construction exercise on each of the material contract documents on any given topic and then, so to speak, compare the results of that exercise to
Construction continued
“ If there is doubt about the meaning of a written term, the interpretation which is most favourable to the consumer shall prevail…
”
www.beale-law.comLondon | Bristol | Dublin 33www.beale-law.comLondon | Bristol | Dublin 32
contractor would not comply with a (revised) completion date . Eventually the
contract was terminated .
The judge accepted that the slippage in the timetable did not in itself mean
that the contractor was not proceeding with due diligence . The absolute
contractual obligation to complete by a certain date and the due diligence
obligation were two separate obligations . Nonetheless, other cases in which
the issue has been considered suggest that the obligation of diligence will
be linked to the parties’ contractual obligations, and in this contract the
obligation was directed to the discharging of the contractual obligations
relating to the carrying out and completion of the works . The mere fact that
the obligation to complete on time may have been or become impossible
for the contractor to achieve does not render that obligation irrelevant when
considering the separate obligation to exercise due diligence .
On behalf of the contractor, it was submitted that the obligation of due
diligence does not require the contractor to achieve the impossible; rather,
at any given moment, the obligation should be assessed with regard to what
is feasible at the time . In particular, it was argued that the obligation did not
impose on the contractor an obligation to take accelerative measures to
ensure that it complied with the completion date, at least to the extent that
the delays were not in fact retrievable .
The judge disagreed . If an absolute contractual requirement (such as
achievement of the completion date) becomes impossible, the obligation
to exercise due diligence would then normally attach to the objective of
minimising the ongoing breach; or, in other words, it would attach to the
nearest possible approximation to proper contractual performance of
the absolute obligation . The due diligence obligation is also flexible: its
performance will depend on what is required from time to time to achieve
the contractual objects in hand . This may in some circumstances include
the taking of measures not originally contemplated, such as accelerative
measures .
After close consideration of the contractor’s conduct and progress on various
elements of the works, the judge concluded that the contractor had failed
to exercise due diligence in certain key areas . The termination was therefore
justified . The judge held that the contractor was not in repudiatory breach of
contract, although this issue was no longer relevant .
Adjudication
There were the usual crop of court cases concerning adjudication, usually
consisting of an application to the court by the claimant to enforce an
adjudicator’s decision, where the respondent considered that there were
grounds for resisting enforcement . Some broader points concerning the
adjudication process were also the subject of judicial consideration .
Construction continued
“ …the judge concluded that the contractor had failed to exercise due diligence in certain key areas…
”
Construction continued
to pursue the variation route rather treat the contractor as being in breach of
contract .
Lump sum
When is a lump sum contract not a lump sum contract? In Atkins Ltd v Secretary of State for Transport (1 February), the contractor was engaged
to maintain part of the highways network . Its obligations included the repair
of minor defects, including potholes . It was to be paid a lump sum over the
period of the contract . The contract contained a modified version of the NEC3
Conditions, which the judge said:
are used throughout the construction and engineering industries and are highly regarded in the sense that they are perceived by many as providing material support to assist the parties in avoiding disputes and ultimately in resolving any disputes which do arise.
The contractor claimed that the prevalence of potholes on the network
was significantly greater than it had anticipated and argued that, where the
number of potholes exceeded the amount that it would have been reasonable
for an experienced contractor or consultant to have allowed for, this
constituted a defect within the meaning of clause 60 .1(11) of the conditions,
giving rise to a compensation event .
The judge rejected the contractor’s argument . As well as ruling that the
language of the contract did not permit this interpretation, the judge pointed
out that this interpretation of the contract would remove the commercial risk
on the contractor of the number of potholes being more than anticipated
while being able still to recover the full lump sum if the number turned out to
be less .
The judge held that the question was one of general public importance,
because the NEC contract is widely used throughout the country and
potholes are an increasingly widespread problem!
Due diligence
The meaning of due diligence in a construction contract was given particular
attention in the long judgment in the case of Sabic UK Petrochemicals Ltd v Punj Lloyd Ltd (10 October) . As well the obligation to complete on time, with
liability for liquidated damages in the event of failure to do so, the contract
provided that:
the Contractor shall, with due diligence, carry out and complete the Engineering Works in accordance with the Contract and the Regulations and to the reasonable satisfaction of the Project Director .
There was a right to terminate the contractor’s employment if (among other
things) the Contractor is failing to proceed with the Engineering Works with due diligence . The contract fell into delay and it became clear that the
“ …the judge pointed out that this interpretation of the contract would remove the commercial risk on the contractor…
”
www.beale-law.comLondon | Bristol | Dublin 35www.beale-law.comLondon | Bristol | Dublin 34
was not time for this and the other exceptions to statutory adjudication to be
done away with, so that all parties to a construction contract can enjoy the
benefits of adjudication .
Is a collateral warranty a construction contract?
A question that has been the subject of some uncertainty is whether a
collateral warranty is a construction contract within the meaning of the Act
and whether, therefore, a claim under a collateral warranty can be referred to
adjudication under the Act . The question arose for consideration in Parkwood Leisure Ltd v Laing O’Rourke Wales & West Ltd (29 August), where the
claimant making a claim under a collateral warranty sought from the Court a
declaration that it could institute adjudication .
The case concerned the construction of a swimming and leisure facility .
The contractor was engaged under a standard JCT design and build
contract and gave a collateral warranty to the operator of the facility . The
warranty contained familiar provisions . In clause 1, the contractor warranted, acknowledged and undertook that:-
it has carried out and shall carry out and complete the Works in accordance with the Contract
There was nothing unusual in the warranty, although it was not in one of
the standard forms, and it was to these opening words that the judge paid
particular attention . The judge had no doubt that this collateral warranty
was a construction contract for the purposes of the Act and to be treated as
such . The judge particularly stressed the point that under the warranty the
contractor was undertaking to carry out at least some work that had not yet
been completed .
The judge said that it does not follow that all collateral warranties given in
connection with construction developments will be construction contracts
under the Act . For example, this may not be the case where all the works
are completed and the contractor (or whoever) is simply warrantying a past
state of affairs as reaching a certain level, quality or standard . This is despite
the fact that an ordinary contract (i .e . not one that is a collateral warranty)
is not prevented from being a construction contract by the fact that it is
retrospective in effect . As the judge said, it is common for contracts to be
finalised after the works have started and to be retrospective in effect back
to the date of commencement; a construction contract does not have to be
wholly or even partly prospective . However, it seems that this may not be so
in the case of a collateral warranty .
So the question seems to be open as regards warranties in respect of past
work . But for warranties that relate to the carrying out of work still to be done,
the position seems reasonably clear, unless and until the matter falls to be
reconsidered by a higher court .
Construction continued
“ …it has carried out and shall carry out and complete the Works in accordance with the Contract
”
Construction continued
Compliance with the Act
The adjudication provisions in a contract must comply with the Act that
originally required such provisions to be included in a construction contract
(i .e . the Housing Grants Construction and Regeneration Act 1996) .
The contract in Pioneer Cladding Ltd v John Graham Construction Ltd (4
October), which was a sub-contract, provided that, if a monetary award in
an adjudication was made in favour of the sub-contractor, the amount would
be placed in an account in the joint names of the solicitors for the parties
(as opposed to being paid straight to the sub-contractor) . The judge had no
doubt that this term was in breach of both the policy behind the Act and of
the Act itself and could not be enforced . The same went for another term that
made the party referring a dispute to adjudication responsible for payment of
the adjudicator’s fees .
The sub-contractor thus obtained judgment from the court to enforce a
monetary award from the adjudicator in its favour; however, the judge held
that this was one of those rare cases where, due to the financial circumstances
of the sub-contractor, execution of the judgment should be stayed, pending
the outcome of arbitration between the parties .
The residential occupier exception
The statutory right to refer disputes to adjudication does not apply to
contracts for work on a dwelling which one of the parties occupies, or intends to occupy, as his residence . This is often referred to as the residential occupier exception . It does not often apply because most construction contracts
now contain terms providing for adjudication anyway . The intention of the
exception was to protect ordinary householders from what was, originally, a
new and untried system of dispute resolution .
There were no terms providing for adjudication in the case of Westfields Construction Ltd v Lewis (27 February), which concerned refurbishment
works to a dwelling house . However, the judge held that the intention of the
owner of the house was to let out the property once the works had been
completed . In these circumstances, the judge held that the owner of the
house was not a residential occupier within the meaning of the Act . The
judge rejected the argument that one could be a residential occupier merely
by virtue of living in the dwelling at the time the contract is entered into;
although that may be an important consideration, residential occupation has
to be ongoing and cannot be determined by reference to a single snapshot
in time . The dispute therefore that had arisen in this case had been properly
referred to adjudication and the adjudicator’s decision was enforceable .
The judge suggested that the residential occupier exception is now difficult
to justify as adjudication in construction contracts is generally thought to have
worked well and has certainly reduced costs . He asked rhetorically whether it
“ …which one of the parties occupies, or intends to occupy, as his residence…
”
www.beale-law.comLondon | Bristol | Dublin 37www.beale-law.comLondon | Bristol | Dublin 36
should not be put before an adjudicator or why the second adjudicator should
not have regard to the earlier decision .
The second adjudicator did not consider himself to be bound by the earlier
decision, so the argument that he took an unduly restrictive view of his
jurisdiction did not arise .
Crystallisation of a dispute
Enforcement of an adjudicator’s award can be resisted on the ground that
no dispute had crystallised at the date of the notice of adjudication (so the
adjudicator had no jurisdiction) .
A dispute does not arise simply by virtue of one party (the claimant) making
a claim . On the other hand, the other party (the respondent) does not have to
have expressly rejected the claim before it can be said that there is a dispute . A
dispute does not arise unless and until it emerges that the claim is not admitted .
Non-admission of the claim may be inferred from various circumstances, for
example, the nature of any discussions that may ensue between the parties,
or the respondent prevaricating or remaining silent for a longer period of
time than in all the circumstances would be reasonable for responding to the
claim . (A deadline imposed by the claimant for this purpose would not in
itself be effective, unless it would otherwise be a reasonable period of time for
responding) .
Fermanagh DC v Gibson (Banbridge) Ltd (4 February) concerned a
contractor’s interim application for payment made following completion of the
works . The application effectively comprised the contractor’s final account .
The employer’s project manager had requested further information to enable
them to assess the claim and contended that sufficient information had not
been received prior to adjudication being commenced by the contractor .
The judge was satisfied that the project manager had had a reasonable time
to make the assessment prior to issue of the notice of adjudication: if the
supporting documentation was not sufficient to support the application, that
would have been reflected in the assessment . It followed that there was a
dispute over the contractor’s claim at the time of the notice of adjudication
and so the adjudicator had jurisdiction .
Completion of construction work is not uncommonly followed by a lengthy
process of negotiation over the contractor’s final account . Detailed scrutiny
will be part of this process, much of which may simply involve verifying the
details of the contractor’s claim . The case illustrates that a contractor can in
the meantime, through adjudication, obtain a provisional payment based on a
more broad brush assessment .
Procedural unfairness?
Another ground on which the employer resisted enforcement of the
adjudicator’s award was procedural unfairness on the part of the adjudicator .
Construction continued
“ The judge was satisfied that the project manager had had a reasonable time to make the assessment
”
Applying for final resolution
An adjudicator’s decision is binding pending final resolution of the dispute by
legal proceedings, arbitration or agreement between the parties . So the losing
party in an adjudication can still apply to court (or arbitration, if the contract so
provides) for final resolution of the dispute and if the court (or arbitrator) finds
in its favour, it can recover from the other party any money that it was ordered
to pay by the adjudicator . However, this will not be possible if the relevant
limitation period for commencing legal proceedings or arbitration has expired .
When does the limitation period (which for a claim under a contract is 6 years,
or 12 where the contract is under seal) in such a case commence running?
This question has arisen in two recent reported cases, and raises the wider
question of the nature of the proceedings to recover sums paid following an
adjudication, a point on which the Act is somewhat opaque .
In the first case, which was in 2009, the court held that the right of a party to
refer a dispute to court or arbitration (as the case may be) for final resolution
following an adjudicator’s decision is an implied term of the contract, so that
the limitation period for commencing the necessary proceedings does not
commence until that right accrues – i .e . until the adjudicator’s decision has
been given .
In 2013, in the case of Aspect Contracts (Asbestos) Ltd v Higgins Construction Plc (23 May), the judge disagreed with the decision in 2009 .
He held that there was no need to imply a term of the kind decided in that
case because a party anticipating having to go to court or arbitration to
seek repayment of a sum paid in compliance with an adjudicator’s decision
can protect its position against the running of the limitation period by
commencing proceedings for negative declaratory relief, i .e . for a declaration
that it is not liable for the sum in question . It would not have to wait first
for the adjudicator’s decision . In the view of the judge, the limitation period
commenced to run at the same time as it did for the actual claim .
On 29 November, the Court of Appeal allowed the appeal . As an adjudicator’s
decision is binding pending final resolution of the dispute by legal
proceedings, arbitration or agreement between the parties, the court held
that there is plainly an implicit right for a party who makes a payment in
compliance with an adjudicator’s decision to seek repayment of that amount
in legal proceedings or arbitration (as the case may be) . That being the case,
the period of limitation for seeking repayment only starts running when the
payment is made .
The Court of Appeal was doubtful about the appropriateness of an action for
negative declaratory relief .
An earlier adjudication
In Arcadis UK Ltd v May & Baker Ltd (29 January), the judge ruled that there
was no reason why the decision in an earlier adjudication on similar issues
Construction continued
“ The Court of Appeal was doubtful about the appropriateness of an action for negative declaratory relief
”
www.beale-law.comLondon | Bristol | Dublin 39www.beale-law.comLondon | Bristol | Dublin 38
decision . An example of a breach of the rules of natural justice is where an
adjudicator, in making his or her decision, relies on a point that had not been
made by either party and on which the parties had not had an opportunity to
comment (what has been called an adjudicator going off on a frolic of his own);
however, such a breach would only render the decision unenforceable if the
point is or is likely to have been of decisive or considerable importance to the
adjudicator’s decision .
ABB Ltd v BAM Nuttall Ltd (12 July) was, in the words of the judge, one of those relatively rare cases where there was a breach of this nature . The dispute
arose out of a sub-contract substantially in the NEC (Option A) form and
concerned the scope of an agreement that the parties reached over payment
for a compensation event, an agreement that had not been recorded in writing .
The adjudicator concluded that there had been no agreement over the scope of
the agreement (i .e . over what work the agreed payment covered), a conclusion
which led the adjudicator to award a substantial further payment to the sub-
contractor .
In reaching this conclusion, the adjudicator relied heavily on clause 11 .1A of the
contract, which states:
No alterations or amendment may be made to this subcontract except where expressly recorded in writing by a document expressed to be supplemental to this subcontract and signed by the parties.
Unfortunately, this clause had never been mentioned during the course of the
adjudication, by either of the parties or the adjudicator himself . The contractor,
therefore, had not had an opportunity to argue, as it might have done, that
the agreement in question did not constitute an alteration or amendment to
the sub-contract as such and that clause 11 .1A was, therefore, irrelevant . It was
not possible to speculate on what the adjudicator might have decided without
having regard to clause 11 .1A . The adjudicator’s breach of the rules of natural
justice was, therefore, material and his decision could not be enforced .
Human rights
A major challenge in Scotland to the enforcement of an adjudicator’s decision
was made under the European Convention on Human Rights and Fundamental
Freedoms in the case of Whyte & Mackay Ltd v Blyth & Blyth Consulting Engineers (9 April) .
The dispute arose out of a claim of professional negligence against consulting
engineers involving allegations of defective foundations and settlement to a
commercial building . The claim was intimated some five years after the work
was completed . The adjudicator’s decision required the engineers to pay almost
£3m . The major head of claim would not be incurred until the end of the lease
of the building in 2035/6 . In the meantime, the cost saving enjoyed by the
pursuer (as the claimant is called in Scotland) in not having incurred additional
piling work will mean that the pursuer will not be out of pocket and so will
suffer no loss .
Construction continued
“ The adjudicator’s breach of the rules of natural justice was, therefore, material and his decision could not be enforced
”
Construction continued
The contractor’s claim was contained in 63 lever arch files . The adjudicator
refused a request by the employer for a longer period than 7 days in which
to respond . The judge said that a breach of the rules of natural justice or
procedural unfairness would be material where an adjudicator had failed
to afford to a party a reasonable opportunity to respond to the case being
made by the other party . However, the judge held that the employer had been
given a reasonable time to respond given the opportunity that had existed
prior to the commencement of adjudication for the employer to address the
application for payment .
The judge emphasised that one can only expect a summary and objective
view of a dispute to be taken through adjudication, however substantial the
claim .
Procedural irregularities?
Procedural irregularities in the adjudication process may also invalidate the
process, but in order to have this effect the irregularity would have to involve
non-compliance with a provision that could be described as fundamental . The
requirement on a claimant to refer the dispute to the adjudicator within 7 days
of the notice of adjudication is a fundamental provision, in view of the clear
intention of the Act in this respect, and so late service of the referral would
invalidate the adjudication; however, a more minor breach, such as late service
of a particular referral document or failure to comply in some particular way
with the prescribed manner of referral, may not have this effect . Such was
said to be the case in Willmott Dixon Housing Ltd v Newlon Housing Trust (9
April) .
Another rule, considered to be well established by the authorities, is that no
more than one dispute can be referred in the same adjudication . However,
also in the Willmott Dixon case, the judge held that this did not mean that
two disputes could not be referred to the same adjudicator by way of two
separate adjudications .
The judge also cast doubt on whether it is in fact correct that more than
one dispute cannot be heard in one adjudication, without the consent of the
parties, although a different judge commented later in another case - TSG Building Services v South Anglia Housing (8 May) – that the authorities
on this point are sufficiently well established, albeit that the courts adopt a
sensible and commercial approach in determining the relative width of any
given dispute .
The rules of natural justice
Although adjudicators should observe the rules of natural justice in
conducting adjudications and making decisions, a breach of these rules by
an adjudicator will cause his or her decision to be unenforceable only if the
breach in question was material – i .e . if it had an important effect on the
“ The judge also cast doubt on whether it is in fact correct that more than one dispute cannot be heard in one adjudication
”
www.beale-law.comLondon | Bristol | Dublin 41www.beale-law.comLondon | Bristol | Dublin 40
Litigation
Jackson reforms: compliance with the Civil Procedure Rules
There is little doubt that a more robust approach to observance of the Civil Procedure Rules was intended to be and, so far, has been achieved by the changes to the rules that came into effect on 1 April, notably the changes to rule 1.1, which makes enforcing the rules part of the overriding objective of achieving justice, and rule 3.9, which makes enforcement of the rules one of two specific factors to be taken into account in dealing with applications for relief from penalties for default.
One new rule is that costs budgets must be filed at least 7 days before a case
management conference . In the event of a party failing to do this, it will be
treated as having filed a budget comprising only the applicable court fees – i .e .
it will only be entitled to recover the court fees that it has incurred; no solicitors’
or counsel’s fees or anything else .
This rather draconian sanction was applied in Mitchell v News Group Newspapers (18 June, 1 August and 27 November), where the claimant, Andrew
Mitchell MP, had failed to file a budget in time: it was filed one day before
the case management conference . The budget was in the sum of £506,425 .
Although the new rules did not apply at the relevant time, they were treated as
a guide to the way the court should approach the matter . The court accordingly
ordered that the claimant be treated as having filed a budget comprising only
the applicable court fees .
A court may grant relief from a penalty of this nature . The critical question in
the post-Jackson regime is how willing will the courts be to grant such relief .
The court in this case felt that, in the light of the stricter approach to complying
with the rules, it should not do so . Permission to appeal was granted in case too
strict an approach had been adopted in this particular case .
On 27 November, the Court of Appeal gave its judgment: the order of the court
below was upheld .
“ One new rule is that costs budgets must be filed at least 7 days before a case management conference
”
Construction continued
The judge accepted the engineers’ argument that enforcement of the award would
infringe their right under the Convention to their possessions . The judge stressed
the unusual features of the case and emphasised that the challenge was not to
the legislative scheme for adjudication itself and the decision not to enforce the
award should not undermine the scheme . Doubt has been expressed before as
to whether the scheme for adjudication was ever intended to deal with a claim of
this nature, some years after work on site had been completed . What the judge
referred to as the well-known problems, disadvantages and potential injustices
of an adjudication were not, in the particular circumstances of this case, counter-
balanced, let alone outweighed, by any of the aims and purposes lying behind the
1996 Act .
A point left for further consideration was whether the fact that the engineers had
professional indemnity insurance meant that there could not be an interference
with their Convention right to their possessions but the judge seemed doubtful
that this was a relevant consideration .
Whether a court in England would be prepared to take a similar view of the
potential applicability of Convention rights to enforcement of an adjudicator’s
award remains (perhaps) to be seen .
The Defective Premises Act
Under the Defective Premises Act 1972, a person who builds a dwelling house owes
a duty to see that the work is done in a workmanlike or professional manner, with
proper materials and so that, when completed, the dwelling will be fit for human
habitation . A person who arranges for someone else to build the house (typically,
a developer or house owner who engages a builder) will owe the same duties if
doing so in the course of a business involving the provision of dwellings .
In the case of Zennstrom v Fagot (21 February), a couple bought a house, which
they later decided to demolish and rebuild, and engaged builders and architects for
this purpose . Their intention was to live in the new house as their home, but after
completion, their plans changed and they sold the house . Unfortunately, serious
defects were later discovered in the house . The builders were insolvent and the
architects had no insurance, which perhaps explains why the new owners sought
to argue that the couple owed the duties imposed by the Defective Premises Act;
but this meant that they had to prove that the couple had arranged for the building
of the house in the course of a business involving the provision of dwellings .
The new owners might have been able to prove their case if they could show
that the couple had always intended to sell the house on completion and not live
there themselves or only live there for a minimal period . That could have entailed
acting in the course of a business and it would not have mattered if it had been the
first time they had done this or that they were not providing any other dwellings .
However, the judge held that the couple had to have formed the intention to sell
the house on or soon after completion prior to entering into the contract with the
builder, contrary to what they were saying . In the event, the judge had no hesitation
in accepting their evidence that they had no such intention at that stage, and the
claim against them failed .
“ Their intention was to live in the new house as their home, but after completion, their plans changed…
”
www.beale-law.comLondon | Bristol | Dublin 43www.beale-law.comLondon | Bristol | Dublin 42
One suspects that, had this case been heard following the judgment in the
Mitchell appeal, the stricter approach would have been enough on its own to
refuse permission, without reference to the particular factors mentioned by the
judge . It seems that it would be enough that there was simply no good reason
for service of the particulars being late .
One consequence of the new strict approach may almost inevitably be an
increase in claims for negligence against solicitors who miss deadlines or
fail otherwise to comply with the rules, until the culture of delay and non-compliance identified by Sir Rupert Jackson has become a thing of the past .
Costs budgeting
Costs budgeting as a way of controlling the costs of litigation is an important
part of the reforms that came into effect on 1 April . Various pilot schemes
had already been in effect, including a scheme for defamation proceedings .
This required each party to prepare a costs budget for approval by the court
at the first case management conference following the start of proceedings
and a revised cost budget for approval at various stages of the proceedings
thereafter . The solicitors were also to liaise monthly to check that their
respective budgets were not being exceeded .
The question that arose for the Court of Appeal in Sylvia Henry v News Group Newspapers Ltd (28 January) and may well arise in other cases is whether a
party entitled to recovery of its costs from another party can recover more
than its latest approved budget . The rules of the scheme provide that this can
only happen if good reasons can be shown . The judge assessing the costs
in this case had felt constrained to rule that the costs recoverable by the
claimant from the defendant could not exceed the claimant’s initial budget
because, although the costs that exceeded that budget seemed reasonable
and proportionate, no revised budget had been approved following her initial
budget and the defendant was consequently unaware that the initial budget
was being exceeded .
The Court of Appeal stated that the objectives of the scheme were to manage
the costs so that they were reasonable and, most importantly, proportionate
to what was at stake in the case, and to ensure that the parties were on an
equal footing . The purpose of the latter objective was to protect a party in any
particular case against the superior financial resources of the other party . The
Court of Appeal held that the claimant’s failure to comply with the rules of the
scheme had not undermined these objectives . In these circumstances, the court
was entitled to take all circumstances into account, so that failure to follow the
rules in liaising regularly with the other defendant over costs and obtaining
approval to revised budgets was just one factor among others that could be
considered . Taking this and other factors into account, the Court allowed the
appeal, thus enabling the claimant in this case to recover more than her budget
(subject to detailed assessment of the costs) .
However, the Court of Appeal did say that the starting point must be that
Litigation continued
“ The rules of the scheme provide that this can only happen if good reasons can be shown
”
The Court of Appeal quoted from Sir Rupert Jackson’s Final Report: the courts
have become too tolerant of delays and non-compliance with orders and lost
sight of the damage which the culture of delay and non-compliance is inflicting
upon the civil justice system . They also quoted from a lecture earlier in the
year by the Master of the Rolls, in which he said, in relation to applications for
relief from penalties for default, that there is to be a shift away from exclusively
focusing on doing justice in the individual case . Parties’ procedural obligations
serve the wider public interest of ensuring that other litigants can obtain justice
efficiently and proportionately . Parties can no longer expect indulgence if they
fail to comply with these obligations .
Giving some guidance of the new approach, the Court said that the relief from
penalties for default would now usually be granted only in two situations: where
the breach is trivial and application for relief made promptly, or where there is a
good reason for the default . Merely overlooking a deadline, whether on account
of overwork or otherwise, is unlikely to be a good reason . Overwork and staff
shortages were said to be reasons for the default in this case . Good reasons
are only likely to arise from circumstances outside the control of the party in
default .
The Court was very conscious of the significance of their decision . We believe that the wide publicity that is likely to be given to this judgment should ensure that the necessary changes will take place before long… . .we hope that our decision will send out a clear message. If it does, we are confident that, in time, legal representatives will become more efficient and will routinely comply with rules, practice directions and orders.
Testament to the significance of this case is that it has already been referred to
in at least eight reported cases in the few weeks since the judgment was given .
The judgment is not only, of course, relevant to the particular default in the
Mitchell case – the failure to file a costs budget in time – but to any non-
compliance with the rules of civil procedure . A common example is failure to
serve particulars of claim within the stipulated time limit following the claim
being issued . In Venulum Property Investments Ltd v Space Architecture Ltd (22 May), the claimant’s solicitors had served the claim form within
the four months allowed for service but had mistakenly thought, due to a
misunderstanding of the rule, that they had a further 14 days for service of the
particulars of claim . The limitation period applicable to the claim had expired
since the claim had been issued, so it would not be possible to start another
action if permission to extend time was not granted .
The judge said that, if all other things were equal, he would have difficulty in
seeing how it would be either just or proportionate to visit a few days delay in
the service of the particulars by the sanction of preventing the claimant from
pursuing its claim against the defendants in question for all time . Other things
were not equal, however, in the view of the judge . He referred to three factors in
particular and added that all the circumstances also had to be considered in the
light of the stricter approach . Permission to extend time was therefore refused
and the claim effectively struck out .
Litigation continued
“ We believe that the wide publicity that is likely to be given to this judgment should ensure that the necessary changes will take place before long…
”
www.beale-law.comLondon | Bristol | Dublin 45www.beale-law.comLondon | Bristol | Dublin 44
showed an increase over the approved budget, stated that he did not think
that good reasons had been shown to explain the increases, save in one case .
The main reason for the overall increase seemed to be a mistake in the original
budget .
The costs management order is stated to be relevant to costs assessed on
the standard basis . What if the costs are to be assessed on the indemnity
basis? The question did not have to be decided because the judge rejected
the defendant’s application for costs on the indemnity basis; however, the
judge expressed the view that, in principle, there is no reason why the costs
management order should not be taken into account as the starting point when
assessing costs on the indemnity basis . It may be easier in such a case to show
good reason for departing from the budgeted amount; in some cases, an award
of indemnity costs may itself constitute a good reason .
In an earlier case, Murray v Neil Dowlman Architecture Ltd (16 April), the same
judge said that a mistake in a costs budget which is then approved by the
court would not normally be justification for the budget later being rectified; in
short, one must get it right the first time . Likewise, the absence of prejudice to
the other party would not normally alone be sufficient to justify a revision . The whole basis of the recent amendments to the CPR is the emphasis on the need for parties to comply with the CPR, and the court orders made under it.
Mediation
The Court of Appeal continued to try and encourage parties to endeavour to
settle disputes through mediation .
Some years ago, the Court of Appeal held in the case of Halsey v Milton Keynes General NHS Trust (11 May 2004) that an unreasonable refusal to
engage in mediation could be penalised in costs, even though the party which
had so refused had been successful in the litigation . That principle has since
been applied in many cases . What often happens is that the successful party
which had unreasonably refused to engage in mediation is not allowed to
recover all of its costs from the unsuccessful party .
In the case of PGF II SA v OMFS Ltd (23 October), the Court of Appeal
extended the principle to cover a situation where a party simply fails to respond
at all to an invitation to engage in mediation or some other form of alternative
dispute resolution (ADR) . In fact, the Court held that failure to respond at all
to such an invitation (as opposed to responding but refusing the invitation, for
whatever reason) is generally in itself unreasonable . The defendant in this case
made a Part 36 offer which the claimant eventually accepted but long after
the end of the relevant period specified in the offer . During that further period,
the defendant had incurred further costs amounting to some £250,000, which
it would normally have been entitled to recover from the claimant . However,
because it had failed to respond to an invitation to mediate, the judge had
declined to make an order allowing it to recover these costs, and the Court of
Appeal upheld the judge’s order .
Litigation continued
“ It may be easier in such a case to show good reason for departing from the budgeted amount…
”
Litigation continued
the approved budget is intended to provide the financial limits within which
the proceedings are to be conducted and that the court will not allow costs
in excess of the budget unless something unusual has occurred . Further, the
rules of the pilot scheme that applied to this particular case have now been
superseded by the rules that came into general effect on 1 April and these rules,
read as a whole, lay greater emphasis on the importance of the approved or
agreed budget as providing a prima facie limit on the amount of recoverable
costs . A court is unlikely to be persuaded that costs incurred in excess of the
budget are reasonable and proportionate to what is at stake .
The case of Elvanite Full Circle Ltd v AMEC Earth & Environmental (UK) Ltd (14 June) concerned another, similar pilot scheme, for proceedings in the
Technology and Construction Court . This scheme too required detailed budgets
setting out estimated costs for the entire proceedings to be filed at court for
approval by the court . The court will then make a costs management order
recording its approval of the budgeted amount . A party may later file and serve
a revised budget if the original budget is no longer accurate . When assessing
costs on the standard basis, the court will not depart from the last approved
budget unless satisfied that there is good reason to do so . In other words, the
amount of the latest court-approved budget will normally constitute a limit on
the costs that a successful party in the litigation can recover from another party .
In this case, the approved budget costs of the successful party (who was the
defendant in the action) were £268,488 . However, the total costs which the
defendant sought to recover from the unsuccessful claimant at the conclusion
of the litigation came to £497,593 .
The defendant had in fact sent a revised estimate, which was double the
previous estimate, to the claimant shortly before the trial . However, this revised
estimate had not been brought to the attention of the judge nor had a revised
costs management order been sought or obtained . The question was whether
a revised costs management order could be made now, after the end of the
trial, when the recoverable costs were due to be assessed . The real question, of
course, was whether the defendant could recover more than the amount of its
last approved budget of £268,488 .
The judge had little hesitation in rejecting the application for a revised
costs management order at this stage . Such an application should be made
immediately it becomes apparent that the original budget costs have been
exceeded by more than a minimal amount . The application in this case should
have been made before the trial, and such an application should never be made
after judgment, when it can no longer be a budgeting exercise but based on
actual costs that have been incurred . It would make a nonsense of the costs
management regime if a party could apply to double the amount of its costs
budget at the end of the trial .
That still left open the question of whether, on assessment of costs, the
defendant would be able to show that there was good reason to depart from
the last costs management order . That would ultimately be a matter for the
costs judge but the trial judge, having considered the various items of cost that
“ When assessing costs on the standard basis, the court will not depart from the last approved budget unless satisfied that there is good reason to do so
”
www.beale-law.comLondon | Bristol | Dublin 47www.beale-law.comLondon | Bristol | Dublin 46
defendant) . The order for costs on discontinuance could not pre-empt what
would have been decided at trial . If the claimants had felt very confident about
winning the case, they could have applied for summary judgment or to have the
defence struck out .
The only basis for a different order on costs could be on the grounds of
the defendant’s conduct . The Court of Appeal, allowing their appeal, held
that the defendant’s failure to respond to any of the four letters prior to the
action amounted to conduct justifying a departure from the normal rule . The
defendant was ordered to pay the costs of the claimants up until service of the
defendant’s defence . After that, there was to be no order as to costs .
Costs: who is the successful party?
In a case where there has been a trial and judgment, the normal rule (or, at least,
the starting point) is that the successful party is entitled to be paid its costs
by the unsuccessful party . Sometimes, however, it may not be clear who has
been the successful party; for example, in a case where a claimant is awarded a
sum which is trivial in relation to the full amount that it had been claiming . The
prevailing view in recent cases in the Court of Appeal is that in such a case the
defendant would normally be regarded as the successful party .
There seems to be some difference of opinion on this . In one recent case with
an outcome of this nature, Lord Justice Jackson, dissenting from the majority
view, argued that the claimant should be regarded as the successful party
because the defendant did not make a Part 36 offer in relation to the small
amount for which it was held liable .
In Magical Marking Ltd v Ware & Kay LLP (20 March), at the end of the trial
of a professional negligence claim against solicitors, the claimant was awarded
£28,000, having been claiming damages in excess of £10 million . Following the
prevailing view in the Court of Appeal, the judge held that the defendants were
the successful party . He reduced the costs payable by the claimant by 15% to
reflect the issue on which it had been successful .
This issue had only been raised by the claimant, by an amendment to its case,
on the last day of the trial . A Part 36 offer made at that stage by the defendants
to cover their liability on this issue would have been inappropriate because
it would have carried with it liability for all the costs to date . Lord Justice
Jackson’s point would seem to apply more readily where the potential liability
of the defendant on a small matter, relative to the rest of the claim, was clear
from the outset of the case .
Costs and Part 36 offers
An important change, or addition, to Part 36 of the Civil Procedure Rules
came into effect during the year as part of the Jackson reforms . If a claimant
succeeds in beating its own Part 36 offer, in addition to the consequences that
already existed (enhanced interest and indemnity costs), the claimant will now
Litigation continued
“ The prevailing view in recent cases in the Court of Appeal is that in such a case the defendant would normally be regarded as the successful party
”
Litigation continued
The Court of Appeal did in fact say that it might itself have allowed the
defendant to recover some of these costs; however, the precise order was in the
discretion of the judge and the Court was content anyway to allow the judge’s
order, even if a little harsh, to stand, pour encourager les autres . The case, said
the Court, sends out an important message to civil litigants, requiring them to
engage with a serious invitation to participate in ADR .
The Court referred also to the ADR handbook which has been prepared and
published in response to Sir Rupert Jackson’s report on civil litigation costs .
It may, of course, in some circumstances, not be unreasonable to refuse an
invitation to participate in ADR . However, a party that takes this view should
state its reasons there and then in response to the invitation and not at some
later date, for example, when the question of the costs of the action arises .
In Halsey v Milton Keynes, the Court of Appeal took the view that unwilling
parties could not actually be obliged to refer their disputes to mediation,
because that would impose an unacceptable obstruction on their right of
access to the court . However, in Wright v Michael Wright (Supplies) Ltd
(27 March), a case in which the parties had resisted judicial entreaties to
refer the dispute to mediation, the Court of Appeal suggested that it was
time nonetheless to consider whether a court could at least direct a stay for
mediation to be attempted, even if neither party was requesting it .
Costs on discontinuance
Arguments about costs typically arise where there may be grounds for
departing from the normal rule . For example, where a claimant discontinues
its claim, the normal rule is that it pays the defendant’s costs . This rule was not
followed, however, in the case of Nelson’s Yard Management Co v Eziefula (21
March), which sprang from concern of the claimants about work being carried
out on a neighbouring property . They sent four letters to the owner of that
property, pointing out, among other things, that he had not served Party Wall
Notices or permitted their surveyor to have access to the site . They received no
reply at all to any of these letters and felt constrained to start proceedings .
Eventually, before the proceedings had progressed very far, they achieved
much of what they had been seeking: their expert was permitted to inspect the
excavation work, trial holes were drilled under the supervision of the claimants’
Party Wall surveyor and it was agreed with the local authority’s building control
officer that no damage could have occurred to the foundations and that the
construction of a retaining wall would be acceptable . A Party Wall Notice was
served and a Party Wall Award agreed (though the defendant maintained that
these were in relation to work that he had only later decided to carry out) .
In the light of all this, the claimants served notice to discontinue the
proceedings but sought a different order on costs than the one that would
normally apply (i .e . that they should pay) . They could not rely on the fact they
would have won if the case had gone to trial, even if this had been reasonably
certain (but especially as there were matters that were in fact disputed by the
“ However, a party that takes this view should state its reasons there and then in response to the invitation…
”
www.beale-law.comLondon | Bristol | Dublin 49www.beale-law.comLondon | Bristol | Dublin 48
Interest
Can the Late Payment of Commercial Debts (Interest) Act 1998 apply to an
award of common law damages for breach of contract? An interesting but
previously undecided issue, said the judge at the end of National Museums and Galleries on Merseyside Board of Trustees v AEW Architects and Designers Ltd (11 October), a case in which the claimant was awarded damages of over £2
million against its architects
The claimant was entitled to interest on those part of the judgment sums that
relate to historical costs - for instance, costs and expenses incurred by the
claimant in relation to dealing with collapsed ceilings in 2011 - but at what rate?
The usual discretionary rate is Bank of England base rate plus 2% (i .e . 2 .5%,
currently) but the 1998 Act allows for interest of 8% .
The 1998 Act applies to debts of the kind identified in the Act . In the case of
a contract, an obligation to pay the whole or any part of the contract price is
a debt covered by the Act . The judge said that there is a very clear distinction
between the payment of the contract price and any liability for damages for
breach of contract and held that the latter is not a debt as such . The Act,
therefore, does not apply to an award of damages for breach of contract .
Liability for damages could be said to be converted into a debt as a result
of a judgment or arbitration award but at that stage it attracts the specified
judgment rate of interest for late payment of a judgment sum .
New claims
Complex building disputes seldom end exactly as they began . The claimant
may make new allegations as the dispute progresses or the other party may
raise new grounds of defence . Where design or construction defects are the
subject of the dispute, the existence of further defects may be alleged . When a
claimant seeks to make a new allegation, the question may arise – is this a new
cause of action? If it is, and the period of limitation for bringing a claim of this
nature has or may have expired, the court should not permit it to be raised in
the existing action, by way of an amendment to the pleaded case, unless the
new claim arises out of the same or substantially the same facts as are already
in issue on any claim already made in the existing action .
The new claim must be compared with the existing claim or claims . If the
new claim asserts a breach of a new duty, this would normally constitute a
new cause of action . If, however, the new claim asserts a further breach of a
duty that is already pleaded, the courts have had more difficulty in deciding
whether a new cause of action is involved, particularly in construction cases:
it is a question of fact and degree . In a case involving damage to a building, it
will generally amount to a new cause of action if the new breach is said to have
caused damage to a different element of the building .
Litigation continued
“ Liability for damages could be said to be converted into a debt as a result of a judgment or arbitration award…
”
be entitled to an additional lump sum, not to exceed an amount calculated in
accordance with the tables set out in the rule, unless it is unjust to do so .
Feltham v Freer Bouskell (15 July), a case of solicitors’ negligence which is
referred to in the professional liability section above, was the first case in which
this new costs sanction was considered . The maximum amount which could
have been ordered was slightly less than £75,000 . In fact, the judge decided
that it would not be just in the circumstances of this case to make any such
order . The circumstances in question were an important point first being raised
by the claimant only at the opening of the trial, late disclosure by the claimant
of some important documents and the lateness of the claimant’s Part 36 offer
itself . The judge observed that the last point is bound to be relevant in relation
to the award of a lump sum, whereas the other sanctions (enhanced interest
and indemnity costs) only take effect from the date of the offer anyway .
There was a sting in the tail for the defendants though, because the judge then
ruled that he would not make any deduction in the costs to which the claimant
was entitled, which, if he had ordered payment of an additional lump sum in
accordance with the new rule, he would have done .
Near miss offers
Some years ago, the Court of Appeal ruled that a Part 36 offer which
comes very close to beating the amount eventually awarded could have the
consequences of a successful Part 36 offer, on the basis that the narrowness
of the margin means that the other party would in fact have been better off
accepting the offer, taking into account time, cost and effort since incurred
in order to achieve such a small increase . This could perhaps be seen as part
of the more flexible approach to costs that the courts have shown in recent
times but Lord Justice Jackson in his report expressed concern about the
uncertainty that this case introduced into the workings of Part 36 and the rule
was amended to make it clear that the success or failure of a Part 36 offer must
be judged in money terms only, however small .
Subject to the consequences of any successful Part 36 offer, which should
normally be applied, the courts still have considerable discretion when making
orders for costs under the general rules on costs, which are set out in Part 44 .
However, in the case of Hammersmatch Properties (Welwyn) Ltd v Saint-Gobain Ceramics & Plastics Ltd (24 July), where a Part 36 offer had narrowly
failed to beat the amount awarded, the judge said that a near miss offer such
as this should not be rewarded under Part 44 with the consequences which it
cannot now achieve under Part 36 . The judge referred to a principle set out in
the case of Multiplex Construction (UK) Ltd v Cleveland Bridge UK in 2008 that
if one party makes an offer under Part 36 or under Part 44 which is nearly but
not quite sufficient and the other party rejects that offer outright without any
attempt to negotiate, then it might be appropriate to penalise the second party
in costs . The judge held that this was no longer a principle that applied to Part
36 and should not be applied as a special near miss rule through Part 44 .
Litigation continued
“ There was a sting in the tail for the defendants though, because the judge then ruled that he would not make any deduction in the costs…
”
www.beale-law.comLondon | Bristol | Dublin 51www.beale-law.comLondon | Bristol | Dublin 50
There may sometimes be problems over litigating all issues arising in a complex
dispute in one action . A few years ago, in the case of Aldi Stores Ltd v WSP (28
November 2007) Group PLC, it was said that a party involved in litigation who
was faced with the issue of wishing to pursue other proceedings should raise
the matter at a case management conference in the existing action so that any
appropriate directions could be given . The Court of Appeal made it clear that
this must be done and that there could be no excuse for failure to do so . In a
later action, the Court of Appeal warned that parties who keep future claims
secret risk having them held to be an abuse .
The Court of Appeal confirmed in the present case that failure to follow the Aldi guidelines could be a relevant factor pointing towards a second action being an
abuse .
Privilege
On 23 January, the Supreme Court gave its judgment in R (on the application of Prudential plc and another) v Special Commissioner of Income Tax and another on the issue of whether legal advice privilege covered legal advice on
tax matters given by accountants . By a majority of 5 to 2, the court held that
the privilege is confined to legal advice given by qualified lawyers, save where it
has been extended by legislation (for example, to patent and trade mark agents
and licensed conveyancers) .
Legal advice privilege is a common law right developed over several hundred
years . Its object is to encourage candour and completeness in communications
seeking and providing professional legal advice by ensuring that such
communications need never be disclosed to any other party (including
government or state authorities) . The privilege belongs to the client, not to the
adviser . The majority of the court accepted that there was no principled reason
for confining the privilege to legal advice given by qualified lawyers, especially
as such advice is increasingly given by non-lawyers, such as accountants giving
specialist tax advice .
However, whatever the logic of the matter, the fact is that it has long been
assumed that the privilege is confined to advice given by qualified lawyers . The life of the common law has not been logic (as was said in a nineteenth century
text book on the common law) . Some common law rules may have limitations
or other aspects which are only explicable by reference to historical practices
or beliefs . Given the belief that legal advice privilege is confined to advice given
by qualified lawyers, it would in practice be extending its ambit to declare that
it also covers legal advice given by accountants or anyone else . The majority of
the court considered that any such extension should only be effected (if at all)
through legislation by Parliament .
Litigation continued
“ Legal advice privilege is a common law right developed over several hundred years
”
The case of Birse Developments Ltd v Co-operative Group Ltd (1 May)
involved alleged defects to a warehouse floor . The original allegations were that
the floor suffered severe cracking and other defects caused by the breaches of
duty of the defendants and that it was necessary to carry out repairs at a cost
of some £381,000 . The new allegation which the claimant was seeking to make
was that it had been discovered that the steel fibre content of the concrete
used for the construction of the floor was insufficient and that the entire floor
needed to be replaced at a cost of some £2 .5 million .
The Court of Appeal had no doubt that this amounted to a new cause of action,
and that it did not arise out of the same or substantially the same facts as were
already in issue . The action had been started within the limitation period, but
the limitation period had now expired and so this new claim could not now be
raised .
Re-litigating old issues
Courts have long been wary about claims being re-litigated in subsequent
actions and a subsequent action may be struck out as an abuse . The absence
of overlap between defendants - for example, where a claimant brings an action
against a person and then, when that action is over, starts a new action for the
same thing against another person - is traditionally a powerful factor against
finding abuse but not a bar, and it did not prevent a second action of this
nature being held to be an abuse in Gladman Commercial Properties v Fisher Hargreaves Proctor (18 January) .
Both actions arose out of a contract for the sale of land to the claimant (in the
second action), which the claimant alleged had been induced by fraudulent
or negligent misrepresentation . The first action was between the claimant,
the vendor of the land and the local authority and was settled mid-trial on
terms that seemed quite favourable to the claimant . Notwithstanding that
apparent success, the claimant then started an action against the surveyors
who, as agents for the vendor and for the local authority, had made the alleged
misrepresentations .
The action was struck out anyway, because the settlement of the first action
was held, as a matter of law, to have released the surveyors from liability, as
joint tortfeasors . There is still a common law rule that, where there are joint
tortfeasors, the release of one will have the effect of releasing the other or
others (subject always to the terms of the release) . This has been described as
a trap for the unwary .
However, both the judge at first instance and the Court of Appeal also held that
the second action should be struck out as an abuse . Although the defendants
were different, the issues were the same and personnel from the surveyors, who
had faced hostile cross-examination as witnesses in the first action, would have
to endure that ordeal again .
Litigation continued
“ Notwithstanding that apparent success, the claimant then started an action against the surveyors…
”
www.beale-law.comLondon | Bristol | Dublin 53www.beale-law.comLondon | Bristol | Dublin 52
relational contracts as they are sometimes called . Such contracts may, in the
words of the judge, require a high degree of communication, co-operation and
predictable performance based on mutual trust and confidence and involve
expectations of loyalty which are not legislated for in the express terms of the
contract but are implicit in the parties’ understanding and necessary to give
business efficacy to the arrangements .
The judge concluded that the traditional English hostility towards a doctrine of
good faith in the performance of contracts, to the extent that it still persists, is
misplaced . He could see no objection, and some advantage, in describing the
duty as one of good faith and fair dealing .
Most construction contracts and certainly those involving the maintenance
of facilities and provision of other services over a period of time could be
described as relational contracts and might therefore be assumed to include a
duty of good faith and fair dealing .
However, on 15 March, the Court of Appeal allowed the appeal of the NHS Trust
in Mid-Essex Hospital Services NHS Trust v Compass Group UK & Ireland Ltd . The Court referred to the judgment in Yam Seng case but evinced a much
narrower approach to the question of good faith .
The Compass Group case (which featured in our report of 2012) concerned a
contract for the provision of catering and cleaning services to two hospitals . In
the court below, the NHS trust was held to be in breach of contract in making
unreasonable deductions from payments to the service providers and in
awarding excessive service failure points, entitling the latter to terminate the
contract . Assessments made by the Trust of the service provider’s performance
were said to have been made on an extremely harsh basis and some of them
were plainly absurd . The judge found that such conduct had led to a poisoning
of the relationship between the parties .
The judge in the court below held that the Trust was in breach of an implied
term not to exercise its right to make deductions and award service failure
points arbitrarily, capriciously or irrationally . The Trust was also held to be in
breach of an express contractual term to co-operate in good faith .
The Court of Appeal, however, ruled that there was no implied term not to
act arbitrarily, capriciously or irrationally in deciding to award service failure
points or make deductions: there was no need to imply such a term because
the contract itself contained precise rules for determining such matters . The
court also interpreted narrowly the express duty to co-operate in good faith,
ruling that it applied only to the two specific matters mentioned in the same
clause – the efficient transmission of information and instructions and enabling
the Trust to derive the full benefit of the contract . Co-operation on such
matters was irrelevant to the levying of deductions . The duty to co-operate
in good faith meant only to work together honestly . The Trust’s conduct
(The Trust’s managers were aggressive in meetings and intemperate in their correspondence) did not, it seems, trouble the Court of Appeal, because it did
not affect the provision of the services .
Contracts continued
“ He could see no objection, and some advantage, in describing the duty as one of good faith and fair dealing
”
Contracts
Duty of good faith
Some contracts contain a term expressly imposing a duty to act in good faith. In the case of Yam Seng PTE Ltd v International Trade Corp Ltd (1 February), the judge considered whether such a duty may now govern all contractual relationships, even if it is not expressly stated.
The judge referred to an apparent view among commentators that there is
no legal principle of good faith of general application in English contract law .
English law is said to embody an ethos of individualism, whereby the parties
are free to pursue their own self-interest not only in negotiating but also in
performing contracts provided they do not act in breach of a term of the
contract .
However, in this respect, English law appears to be swimming against the
tide . A general principle of good faith is not only recognised in most civil
law jurisdictions (including those of France, Germany and Italy) but in other
common law countries, including the United States and Australia . But while
there may be no such general principle in England, a duty of good faith may
be implied in any ordinary commercial contract, following the established
methodology of English law for the implication of terms .
The approach to the interpretation of contracts has undoubtedly changed
in recent times . It is now emphasised that contracts are made against a
background of unstated shared understandings which inform their meaning .
The relevant background includes not only matters of fact known to the parties
but also shared values and norms of behaviour . It is not therefore difficult
to imply into any commercial contract a term that the parties will abide by
standards of commercial dealing which are so generally accepted that they
would reasonably be understood to take them as read .
Duties of good faith are likely to be of particular significance in contracts
involving a longer term relationship (as opposed to a simple exchange), or
“ The judge referred to an apparent view among commentators that there is no legal principle of good faith of general application in English contract law
”
www.beale-law.comLondon | Bristol | Dublin 55www.beale-law.comLondon | Bristol | Dublin 54
aside the effect of the purported termination, the target date for the part of
the development which had been suspended would have been exceeded by 15
months .
It was no longer disputed in the Court of Appeal that the developer was in
breach of its obligation to carry out the works with due diligence and to use
reasonable endeavours to procure completion by the target date . But was
either breach repudiatory? The trial judge’s view was that the developer’s
ongoing breach of its due diligence obligation had become repudiatory at least
by the time that work had been halted for over 5 months and the developer
could not say when it would resume .
The Court of Appeal said that the test for repudiatory breach is whether the
breach has deprived the injured party of substantially the whole benefit of the
contract or, possibly, a substantial part of the benefit . The first test, in particular,
sets the bar high .
The claimant was intended to obtain, first and foremost, a leasehold interest of
999 years duration in the commercial units comprised in the development . The
claimant was not in a position where it was never going to obtain that interest .
If (hypothetically) it had received all the commercial units one year late, it would
still have got what it had contracted for, and getting it one year late would not,
on the face of it, have deprived the claimant of a substantial part of the benefit
it was intended to receive, let alone substantially the whole benefit .
The next thing to consider was what loss the claimant had or might have
suffered as a result of the breach . At the time it purported to terminate the
contract, it had suffered no actual loss . It was concerned that the delay would
interfere with its marketing programme (it planned to sublet the various units
to business tenants) . It might also have to bear for longer the cost of funding
its original deposit and the balance of the purchase price for the units on which
work had not been halted . Such matters, which could be compensated by
payment of damages, were not sufficient to establish a repudiatory breach .
The court also held that the question of whether a breach is repudiatory
must be judged at the date when the injured party purports to terminate the
contract . The circumstances that determine whether a breach is repudiatory
may change: a breach that is not repudiatory initially may become so as the
consequences of that breach worsen and the reverse may also be true . Here,
the uncertainty at the end of 2009 to which the judge attached significance
had diminished in October 2010, when the claimant purported to terminate,
because the work that had been halted had by then resumed . In a changing
situation, an injured party wishing to terminate the contract must be careful
neither to strike too soon nor leave it too late . In this case, however, the court
was doubtful whether at any stage a repudiatory breach had been established .
These issues need not arise, of course, if the contract sets out expressly the
circumstances in which a party may terminate the contract, as most building
contracts do .
Contracts continued
“ At the time it purported to terminate the contract, it had suffered no actual loss
”
A similarly restrictive view of an obligation to work together and individually in the spirit of trust, fairness and mutual co-operation was followed by the judge
(disagreeing with the adjudicator) in the case of TSG Building Services Plc v South Anglia Housing Ltd (8 May) . The contract was for the provision for a
Housing Association of a programme of gas servicing and associated works for
some 5,500 individual properties, with each party having the right to terminate
the contract at any time for any (or no) reason . The parties were referred to
as partnering team members, and they were required to establish, develop and implement their partnering relationships…with the objective of achieving…trust, fairness, mutual co-operation, dedication to agreed common goals and an understanding of each other’s expectations and values.
The judge held that these provisions did not require the Housing Association
to act reasonably in exercising (or in choosing to exercise) its right under the
contract to terminate the contract early, as it decided to do . The judge also
ruled that there was no implied duty of good faith, and that, even if there was, it
would not or could not circumscribe or restrict what the parties had expressly
agreed about the right to terminate .
The requirements of good faith are clearly sensitive to context . However,
where a duty to act with good faith – whether express or implied – means no
more than to act honestly, it is hard to see that it adds anything much . Under
English law, any contractual obligation must be interpreted in context, but the
contextual approach need not be restrictive – it may well be the opposite . The
starting point of the Court of Appeal was that there is no general doctrine of
good faith in English law, the very point that was effectively challenged by
the judge in the Yam Seng case . It would not be surprising, therefore, if two
broadly diverging strands of judicial opinion are emerging on the question of
good faith, a conflict which will no doubt be addressed in due course by the
Supreme Court .
Repudiatory breach
Last year’s report (on 2012) included the case of Ampurius NU Homes Holdings Limited v Telford Homes (Creekside) Limited, which concerned the question
of repudiatory breach of contract, i .e . the sort of breach that entitles the injured
party to bring the contract to an end .
Care has to be taken in treating a breach of contract as repudiatory, in case it
is later decided by the court that the breach was not repudiatory . This is what
happened in this case, in which a high court judge ruled in 2012 that the breach
was repudiatory but, on 23 May 2013, the Court of Appeal ruled otherwise .
The case involved a contract for the development of a property to be
purchased by the claimant on completion . While the works were proceeding,
the developer had funding problems as a result of the credit crunch and halted
work on part of the development . This work was resumed 15 months later
but shortly afterwards the claimant purported to terminate the contract . The
developer continued with the development . The trial judge held that, leaving
Contracts continued
“ Under English law, any contractual obligation must be interpreted in context…
”
www.beale-law.comLondon | Bristol | Dublin 57www.beale-law.comLondon | Bristol | Dublin 56
not cover a failure to perform the contract at all . Thus the expression in the
sub-clause in relation to this Agreement should be understood as meaning in relation to the performance of this Agreement .
The case could be regarded as a paradigm of modern construction of an
agreement . One starts with a clause the meaning of which seems quite clear
(as the judge at first instance thought) but which does not seem to accord
with commercial sense . One therefore resorts to a wider context to produce an
interpretation that yields to business common sense . The context in this case
was found mainly within the agreement itself but of course a much broader
context can also be taken into account .
The judge at first instance seems to have thought erroneously that the issue of
construction only arises if there at least two alternative interpretations of the
form of words used .
Contracts continued
“ Agreement should be understood as meaning in relation to the performance of this Agreement
”
Contracts continued
Limitation of liability
The case of Kudos Catering (UK) Ltd v Manchester Central Convention Complex Ltd (7 February) concerned the following clause in a contract for the
supply of catering services:
The Contractor hereby acknowledges and agrees that the Company shall have no liability whatsoever in contract, tort (including negligence) or otherwise for any loss of goodwill, business, revenue or profits…..suffered by the Contractor or any third party in relation to this Agreement…..
When the company purported to terminate the contract before the end of its
five-year term, the contractor alleged that this was a repudiatory breach of
the contract and claimed damages, including loss of the profits that it would
have earned during the remaining twenty months of the contract . Perhaps
not surprisingly, the company said that the claim was excluded by the above
clause . The point was tried as a preliminary issue (therefore assuming, for this
purpose only, that the company’s purported termination of the contract was
a repudiatory breach) . The judge agreed with the company, but the Court of
Appeal allowed the contractor’s appeal .
The Court of Appeal observed that the company’s interpretation of the clause
would effectively deprive the agreement of contractual content, because there
would be no sanction for non-performance of the agreement by the company
(the court was not impressed by the argument that the contractor could seek
injunctive relief from the courts) . The court said that the judge had failed to
consider the words of the clause in their wider context . The main relevant
context in this case was the head clause in which this clause appeared as a sub-
clause .
The head clause was headed “Indemnity and Insurance” and contained (not
unusual) sub-clauses requiring the contractor to indemnify the company
against claims for personal injury and damage to property and to effect the
usual insurances covering such matters . Then followed a sub-clause requiring
the company to indemnify the contractor against claims arising out of the
provision of or damage to property caused by the negligence of the company .
The next sub-clause reverted to a point about insurance and seems to have
been inserted in the wrong place . The sub-clause after that (which should have
immediately followed the company’s indemnity) contained the exclusion of
liability with which the case was concerned .
The Court of Appeal concluded that the sub-clause was basically intended to
qualify the company’s indemnity that preceded it . However, the court accepted
that, in view of its wide wording, it must have been intended to do more that .
The key was the reference in the sub-clause to loss suffered by any third party .
Liability of the company for any such loss would only arise, under the indemnity,
as a result of negligence by the company . The court, therefore, concluded
that the exclusion of liability in the sub-clause was concerned only with liability
arising out of the company’s negligent performance of the contract and did
“ The Court of Appeal observed that the company’s interpretation of the clause would effectively deprive the agreement of contractual content…
”
www.beale-law.comLondon | Bristol | Dublin 59www.beale-law.comLondon | Bristol | Dublin 58
The conclusion [we] come to, which is the inevitable conclusion one must come to, is that every file conducted by [the conveyancing firm taken over]……contains or is more likely than not to contain examples of malpractice negligence and breach of contract and so each and every file………..should properly be notified to you as individually containing shortcomings on which claimants will rely for the purposes of bringing claims against [us] as successor practice.
The insurers rejected the notification, save in respect of the 33 files where
defects had been specifically identified . Regarding all the rest of the files, the
solicitors had not identified a specific incident, occurrence, fact, matter, act or
omission which would give rise to a claim on each individual file, and so the
notifications were firmly rejected in their entirety and without question .
The insurers also refused to renew the policy and the solicitors were unable
to obtain cover from another qualifying insurer and had to enter the Assigned
Risks Pool . The solicitors applied to court for a declaration that their notification
was valid .
Blanket notifications by solicitors have been the subject of earlier court cases,
which have been decided in favour of the solicitors in question, though the
issue there was whether a claim made later was covered by the notification . The
notifications in those cases were held to be valid in relation to the later claim,
even though the notification had not even referred to the transaction from
which the claim arose, let alone identified a defect in relation to the handling of
that particular client as likely to give rise to a claim .
The judge therefore held that the stance taken by the insurers in the present
case was clearly wrong and their contention that their liability was limited to
identified files was misconceived and at odds with case law .
The judge, however, did not feel able to grant a declaration concerning the
validity of the notification, not least because of the difficulty in deciding exactly
what the declaration should say . If and when a claim arose, it would have to be
considered at that stage whether it was covered by the notification . This issue
concerning a declaration was later (on 2 December) considered by the Court
of Appeal and the judge’s ruling upheld . The judge’s comments on the insurers’
rejection of the notification were not challenged (and in the meantime the
solicitors had been able to obtain insurance from a qualifying insurer, though at
a rather higher premium) .
Public liability insurance
Public liability insurance policies sometimes contain extensions that seem to
take it outside the field of public liability as generally understood . M J Gleeson Group Plc v AXA Corporate Solutions Assurance SA (4 June) concerned
a building contractor’s policy that extended to indemnify the contractor
in respect of legal liability arising from the defective workmanship of their
subcontractors including the cost of making good defective workmanship .
Insurers continued
“ The insurers also refused to renew the policy and the solicitors were unable to obtain cover from another qualifying insurer…
”
Insurers
Blanket notifications
Professional indemnity insurance is almost invariably written on a claims made basis, which in principle means that liability for a claim is covered under the policy in force at the time the claim is made and by the insurers who have issued that policy, as opposed to the policy at the time that the negligence or other event giving rise to liability occurred.
However, the assured is under a duty to notify the insurer of any circumstances
of which it is aware that may give rise to a claim; and in practice it is the policy
in force at the time of that notification that has to respond to any claim arising
out of the circumstances so notified, even though the claim itself may only be
made at a time when that policy is no longer in force .
This situation has given rise to disputes over whether a particular claim is or is
not covered by an earlier notification, a matter that may decide which policy
and which insurer cover the claim or whether indeed the claim is covered at all .
An unusual (and possibly unprecedented) feature of the case of McManus and others v European Risk Insurance Co HF (17 January) is that it concerned a
dispute over the scope of a notification without any claim having actually been
made .
The case concerned a firm of solicitors with an exemplary claims record who
took over a conveyancing practice . As the solicitors were later constrained
to accept, their due diligence in relation to the take-over seems to have been
deficient . Within a few weeks, 17 claims were received in connection with the
files of the firm taken over . Investigations indicated patterns of bad practice,
another 33 files were identified where there could well be a problem and there
were inevitably doubts about all the hundreds of files of this conveyancing
practice of which the solicitors were deemed to be the successor practice .
In the notification which the solicitors sent to their insurers, the solicitors listed
a number of specific recurring problems in the files that had been reviewed, and
said:
“ This situation has given rise to disputes over whether a particular claim is or is not covered by an earlier notification…
”
www.beale-law.comLondon | Bristol | Dublin 61www.beale-law.comLondon | Bristol | Dublin 60
Insurers continued
Basis of contract clauses
Genesis Housing Association Ltd v Liberty Syndicate Management Ltd (for and on behalf of Syndicate 4472 at Lloyds) (4 October) concerned insurance
taken out by a housing association in relation to a building project . The
insurance included cover for the risk of the builder becoming insolvent during
the construction period .
Unfortunately, the wrong builder was inadvertently named on the proposal
form . The builder contracted to carry out the works was formed as a special
purpose vehicle for this development; the builder named on the proposal form
was another, more substantial company in the same group . After the project
had been running for about 18 months, the builder went into administration but,
because of the error in the proposal form, the insurers denied liability under the
policy .
The main problem for the Housing Association was that, in the declaration on
the proposal form, it was agreed that the proposal form and the statements in
it would form the basis of the contract between the parties (i .e . the contract
between insurer and insured) . Under a line of authorities stretching back
for more than a century, the effect of a basis of contract clause is that the
statements in the proposal form become contractual warranties . This remains
the case even if the policy itself contains no reference to the proposal form .
The fact that the statements in the declaration were expressed to be to the best of our knowledge and belief would not help; in any event, although the error
was inadvertent, it was known who the builder was to be .
The Court of Appeal observed that the principle has been the subject of some
criticism and its juristic basis has been said to be unclear . There is now statutory
reform to exclude the principle in relation to consumer contracts but that could
not affect this case .
The Court of Appeal, therefore, dismissed the Housing Association’s appeal,
thus upholding the right of the insurers to reject the claim .
Rights of subrogation
It is well established that insurers, after indemnifying an insured against a
particular loss, cannot exercise rights of subrogation against a co-insured where
the co-insured is insured in respect of the same loss . In such a situation, there is
considered to be a policy waiver . However, it does not seem that an insurer can
never pursue a subrogated claim against another party insured under the policy
in question .
Rathbone Brothers Plc and another v Novae Corporate Underwriting & Ors (8
November) concerned a professional liability policy taken out by an investment
company which also covered its subsidiaries and employees . The court held
that the policy covers an individual, who was engaged as a consultant by a
“ The Court of Appeal observed that the principle has been the subject of some criticism…
”
Insurers continued
The judge referred to the importance of the factual background in interpreting
contracts . The relevant background included here the general nature of the
policy . The judge commented that it could not be the case that this policy was
intended to provide what in effect would be a contractual guarantee of the
workmanship of the subcontractors . The judge concluded that the extension
only applied where damage to property (i .e . the sort of damage caused by
tortious acts that public liability insurance is intended to cover) has been
caused by the defective workmanship in question .
This approach was similar to that in a case a few years ago Tesco Stores v Constable (16 April 2008) where it was held that the policy did not cover
contractual liability for the losses of third parties caused by damage to property
The order in which multiple claims should be met
Teal Assurance Co Ltd v W R Berkley Insurance (Europe) Ltd (31 July) was
a judgment of the Supreme Court concerning the top layer of a professional
liability insurance programme taken out by an engineering company . The first
or primary layer was placed with an insurance company; the three successive
excess layers and the top layer itself were placed with a captive insurer
of the engineer which reinsured the risks under these layers with various
retrocessionaires . Each level contained a limit of cover for each and every claim
and a limit in the aggregate, and each would drop down as and when the layer
below it became exhausted .
The top and drop policy which constituted the top layer excluded any claims
emanating from or brought in the USA and Canada . The engineer faced a
number of claims, some emanating from the USA, some not . The engineer,
through its captive insurer, wished to ensure that there was cover available in
the lower layers to meet the USA claims, i .e . that they were not exhausted by
non-USA claims, for which there would be cover in the top layer . This meant
choosing which claims to meet from the lower layers and therefore meant
choosing the order in which claims would be met . The reinsurers of the top
layer, not surprisingly, objected, and argued that they were not entitled to do
this . The Supreme Court, and the courts below, agreed with the reinsurers .
The basis of the court’s judgment is that the insurance cover in relation to a
particular claim becomes exhausted through that claim being ascertained
(whether by judgment or settlement or however) and at the same time: that
is the moment when the insurers become liable to meet the claim . The captive
insurers, on behalf of the engineers, argued that, under the policy wording, a
particular layer is only obliged to respond to a claim when the amount due from
the layer below has been paid . Following an earlier case, the Supreme Court
held that this meant when the claim has been ascertained, but even if the word
paid were interpreted literally, it would not entitle the insured to alter the order
in which claims fall become due to be paid .
It seems clear that the order, for the purpose of policies with aggregate limits, is
determined by the order in which claims are ascertained .
“ The engineer, through its captive insurer, wished to ensure that there was cover available in the lower layers to meet the USA claims…
”
www.beale-law.comLondon | Bristol | Dublin 63www.beale-law.comLondon | Bristol | Dublin 62
Health and Safety and public liability
The role of reasonable foreseeability
The obligations and potential liability of employers under health and safety legislation may not, for most part, be strict, but the extent to which the common law concept of reasonable foreseeability is relevant has long been debatable. Under the Provision and Use of Work Equipment Regulations, every employer shall ensure that work equipment is so constructed or adapted so as to be suitable for the purpose for which it is used or provided. The term suitable is defined as meaning suitable in any respect which it is reasonably foreseeable will affect the health or safety of any person. Thus through this definition the concept of reasonable foreseeability is brought into play, but to what effect?
This question was considered by the Court of Appeal in Hide v Steeplechase Co (Cheltenham) Ltd (22 May) . The court held that the concept of reasonable
foreseeability in the regulations had to be construed so as to be consistent
with the European Directives under which the regulations were made . The main
directive provides that employers’ responsibility may be excluded or limited
where occurrences are due to unusual and unforeseeable circumstances,
beyond the employers’ control, or to exceptional events, the consequences of
which could not have been avoided despite the exercise of all due care .
This implies a much more limited concept of foreseeability . However, the
significance of this judgment is clearly affected by the coming into force on 1
October of section 69 of the Enterprise and Regulatory Reform Act 2013 .
This amends section 47 of the Health and Safety at Work etc Act to provide,
in general terms, that breach of health and safety regulations will no longer
be civilly actionable save insofar as further regulations provide . The aim is to
address the problem of a perceived compensation culture and the effect is that
it will usually only be possible to bring civil claims arising out of such breaches
as a common law action for negligence . This would obviously bring the
common law concept of reasonable foreseeability back into play .
“ The term suitable is defined as meaning suitable in any respect…
”
Insurers continued
subsidiary, against proceedings that have been brought against him . However,
the consultant also has the benefit of a contractual indemnity from the parent
company and the court held that the insurers could pursue a subrogated claim
against the parent company (i .e . the policyholder) under this indemnity .
Disclosure of insurance details
A few years ago, a judge held that the civil procedure rules enabled a court to
order a defendant to disclose details of its insurance in respect of the claim
against it . Some months later, a different judge held that the rules gave the
court no power to make such an order and so felt constrained to disagree with
the earlier decision .
In XYZ v Various sub nom Re PIP Breast Implant Litigation (22 November), the
judge agreed that the court had no power to make such an order under the rule
concerning disclosure of documents (the only rule that had been considered
in the earlier cases) . However, she considered the matter under the rule
concerning case management and held that under that rule she could order
the defendant, whose financial solvency was doubtful but who seemed to have
insurance in respect of the claim, to disclose whether or not its insurance was
sufficient to fund its participation in the proceedings . An order to this effect
could be justified on the basis that it would affect the court’s management of a
highly complex piece of litigation .
She did not, however, consider that there was authority under the rule to order
a party to disclose information that would show whether its insurance would be
sufficient to meet any orders for damages or costs . The ruling was rather less,
therefore, than the claimants had presumably been hoping for .
“ An order to this effect could be justified on the basis that it would affect the court’s management of a highly complex piece of litigation
”
www.beale-law.com www.beale-law.comLondon | Bristol | Dublin London | Bristol | Dublin64 65
There has been some debate over the extent to which this case extends the law
and, in particular, may increase the burden on local authorities and their insurers .
The case does not expand the categories of negligence as such . Nonetheless, it
does mean that local authorities which outsource functions of the kind covered
by the case may be liable for the negligent performance of those functions
without any fault on their own part . Where the party to whom the function is
outsourced is a substantial organisation, this may not matter: the party that has
actually been negligent will always be primarily liable, and one can expect that in
many cases it will have indemnified the authority . The case is likely to be of more
practical relevance where functions are outsourced to poorer or uninsured or
underinsured contractors .
Causation
Establishing liability for damages due to negligence or any other breach of duty
involves proving not only that there was a breach of duty but that the breach
caused the loss in question . As we have mentioned above in connection with
professional liability, this may mean venturing into the realm of hypothesis:
what would have happened if the duty in question had been fulfilled rather than
breached? Would the loss have been prevented?
If the duty was to take a specific step or give some particular advice, and the
breach of duty was a failure to take that step or give that advice, the hypothetical
question will normally be – what would have happened if this had been done and,
in particular, would the loss have been avoided as a result? In the case of advice,
for example, would the advice have been acted on?
However, the duty in question may be of a kind that could have been fulfilled by
one or more of a range of possible actions, and the breach of duty a failure to do
anything . In such a case, the answer to the hypothetical question may vary with
each possible action . One such action may not have avoided the loss but it may
nonetheless have been perfectly reasonable (and therefore not negligent) to
have taken that action; another action may have avoided the loss but may have
involved going beyond the call of duty .
Does one have to ask what the person in breach of duty should have done, or (if
this is different) what that person would in fact have done? The answer is: the
latter .
The point arose in Robbins v Bexley London Borough Council (17 October),
where the Council was held liable to a house owner for tree root damage caused
by trees for which the Council was responsible . The duty of which the Council
was held to have been in breach was to take reasonable steps to prevent such
damage being caused by the trees . The judge was of the view that a reasonable
programme of maintenance would have been to reduce the height of the trees
every few years by 25% but that such a programme would not have prevented
the damage . However, the judge held that if the Council had taken steps to
perform its duty, more severe pruning would in fact have taken place, which
would have prevented the damage . The Court of Appeal upheld the judgment .
Health and Safety and public liability continued
“ …what would have happened if the duty in question had been fulfilled rather than breached?
”
The amendment does not apply to breaches that occurred before it came into
effect, so it will be a while before its impact is felt . On the face of it, though,
and subject to arguments over interpretation and a possible challenge by the
European Commission, the change is favourable to employers and their insurers
Non-delegable duties
The judgment of the Supreme Court in Woodland v Essex County Council (23
October), arising from a tragic injury to a school girl during a swimming lesson,
attracted some attention in the media . In short, the education authority was held
potentially liable for the incident (subject to proof of negligence and causation) .
The courts below had held that the authority could not be liable because the
conduct of the swimming lesson had been contracted out by the school .
The general rule is that a person (whether a corporation or an individual) is not
liable for the negligence of an independent contractor engaged by it, unless that
person is itself at fault . This contrasts with the vicarious liability of an employer
for the negligence of its employee, which exists regardless of any fault on the
part of the employer . However, there is an exception to the rule concerning
independent contractors, where the person who employs the contractor can
be said to owe a non-delegable duty for the performance of the work that it
employs the contractor to carry out . This does not mean that it cannot delegate
the work to another person at all but that it cannot delegate its own legal duty
for the proper performance of that work: if, therefore, the contractor does not
perform the work properly, the person who engaged the contractor will be liable,
without any fault on its own part . (The contractor will, of course, also be liable,
being the party at fault) .
It has long been held that there may be a non-delegable duty where the work in
question is of a hazardous nature . This would not apply to teaching children to
swim . However, another category of case where there may be a non-delegable
duty is (1) where there is an antecedent relationship between defendant and
claimant, (2) the duty is to protect a particular class of persons against a
particular class of risks and (3) the duty is personal to the defendant . This would,
on the face of it, cover a situation as between a school and its pupils, so that
if the school delegates a particular function, such as the taking of swimming
lessons, to a third party, the school (and hence the local education authority) will
remain responsible for the non-negligent performance of that function .
The Supreme Court reviewed the cases in this latter category and held that the
time had come to recognise that a non-delegable duty does indeed arise in such
situations, where the claimant is a patient or a child, or for some other reason is
especially vulnerable or dependent on the protection of the defendant against
risk of injury, and the claimant has been placed in the custody, charge or care of
the defendant .
The boundaries of this category of case cannot be defined with precision and
each situation that may fall within it will have to be considered on its own facts .
Health and Safety and public liability continued
“ This does not mean that it cannot delegate the work to another person at all but that it cannot delegate its own legal duty…
”
www.beale-law.comLondon | Bristol | Dublin 67www.beale-law.comLondon | Bristol | Dublin 66
London Antony Smith Senior Partner
T: +44 (0) 20 7420 8704
E: a .smith@beale-law .com
It is important to identify the content of the duty breached – it was not a
duty to implement a programme of regular 25% reductions but a duty to take
reasonable steps to prevent tree root damage to the claimant’s house . From
that point one asks the hypothetical question of what would have happened
had the duty been fulfilled, and on the facts one reaches the answer that the
damage would have been prevented .
Ascertaining the cause
Sherlock Holmes famously said that when you have eliminated the impossible,
whatever remains, however improbable, must be the truth . Holmes’ dictum
is not, however, good law . Michael Nulty (dec’d) and others v Milton Keynes Borough Council (24 Jan) concerned a fire in a warehouse, each possible cause
of which seemed inherently unlikely . The judge had concluded that the most
likely cause of the fire was one that was the least unlikely . The Court of Appeal
said that this did not follow as a matter of law but that it was a valid factual
finding for the judge to make in all the circumstances . There may be situations
where a court concludes that no cause of a particular event has been proved
on the balance of probabilities, which could mean that a claim arising out of the
event in question is bound to fail .
The Court of Appeal also said that one cannot apply a percentage chance to
the question of whether something has already occurred; one cannot say, for
example, that there is a 25% chance that something has happened: either it
has happened or it has not, and the court has to decide that question on the
balance of probabilities .
Health and Safety and public liability continued
“ There may be situations where a court concludes that no cause of a particular event has been proved…
”
Antony Smith Senior Partner
Rhian Howell Partner
Tara Cosgrove Partner
For further information about any case or issue covered in this Legal Review please contact … .
Bristol Rhian Howell Partner
T: +44 (0 117 311 7471
E: r .howell@beale-law .com
Dublin Tara Cosgrove Partner
T: +353 (0) 1 775 9546
E: t .cosgrove@beale-law .com
www.beale-law.comLondon | Bristol | Dublin 69
LondonBeale and Company Solicitors LLPGarrick House27-32 King StreetCovent GardenLondonWC2E 8JB
DX No . 51632 Covent Garden
T: +44 (0) 20 7240 3474F: +44 (0) 20 7240 9111
Beale and Company Solicitors LLP34 Lime StreetLondonEC3M 7AT
DX No . 517 London/City
T: +44 (0) 20 3544 5060F: +44 (0) 20 3544 5061
BristolBeale and Company Solicitors LLPRoyal Talbot House2 Victoria StreetBristolBS1 6BN DX No . 7809 Bristol
T: +44 (0) 117 311 7474F: +44 (0) 117 311 7475
DublinBeale and CompanyHamilton House28 Fitzwilliam PlaceDublin 2
DX No . 109048 Fitzwilliam
T: +353 (0) 1 775 9505F: +353 (0) 1 775 9506
DubaiAnjarwalla Collins & HaidermotaBoulevard Plaza, Tower 1 Level 29, Unit 2902, P .O .Box 58553, Dubai . United Arab Emirates T: +971 4 4529091 F: +971 4 4529078
T: +353 (0) 1 775 9505F: +353 (0) 1 775 9506