  • 8/10/2019 Ledpod Instructions NEW

    1/2

    Wagner LumenrailLedpod

    INSTALLATION AND WIRING INSTRUCTIONS:

    1. Installation must be performed by a licensed electrician and allwiring must conform to local electrical code. Read all instructionsbefore beginning installation. Contact R&B Wagner, Inc. with anyquestions at 888-243-6914 or [email protected].

    2. Turn off the power before terminating the Driver or fixtures. Neverperform electrical work on a live circuit.

    3. Ensure all Ledpod holes are de-bured inside and out.

    4. Install 24 VDC positive (+) and negative (-) wires down hand rail(fig. 1). Refer to driver spec sheet for wire gauge recommendations.

    5. Pull a loop of the 24 VDC wires out of the 25mm Ledpod hole (fig.2).

    6. Install the retaining spring (fig. 3).

    7. Install the Scotchlocs to the 24 VDC main wires and the stepdown transformer (fig. 4). Ensure that the polarity of wires fromthe step-down transformer (+ = red, - = black) connect to thecorrect polarity main 24 VDC wires.

    8. Carefully push wires, Scotchlocs, and step down transformerinto the hole (fig. 5).

    9. Plug the Ledpod into the step-down transformer.

    fig. 3

    fig. 5

    fig. 2

    fig. 4 fig. 6

    Spring Clip

    Step-downtransformer

    Scotchlocs

    fig. 1

    24 VDC wires

    10. Carefully push the remaining wire into the hole. Push the Ledpodinto the hole. The witness mark on the Ledpod should be pointed

    towards the pathway. If the Ledpod does not push in, remove andcheck spring alignment (fig. 6).

    11. Mount driver in a suitable NEMA rated enclosure. Ledpods may beused in wet location if driver is mounted in suitable rated enclosureand wire connections are made with listed wet location terminationsNote: Driver must be a Listed Component, Class 2, and 24 VDC.

    12. Connect the driver to the AC power mains using location appropri-ate electrical terminations. Ground the driver and enclosure usingthe mounting studs inside the enclosure.

    WAGNER ARCHITECTURAL | (414) 716 8401 | [email protected] | WAGNERARCHITECTURAL.COM 2013

  • 8/10/2019 Ledpod Instructions NEW

    2/2

    Wagner LumenrailLedpod

    WAGNER ARCHITECTURAL | (414) 716 8401 | [email protected] | WAGNERARCHITECTURAL.COM 2013

    Driver with Enclosure

    120 - 277 Volt Input

    (Conduit Entry)Secondary Feed Routed

    Through Stainless Bracket

    120 - 277 Volt Input

    (Conduit Entry)

    3M Scotchlock wire connectorsLedpod assembly

    Soft Start

    Relay Soft Start

    Relay

    Driver with Enclosure

    Soft Start

    Relay

    120 - 277 Volt Input

    (Conduit Entry)Secondary Feed Routed

    Through Stainless Bracket

    120 - 277 Volt Input

    (Conduit Entry)

    3M Scotchlock wire connectorsLedpod assembly

    Soft Start

    Relay

    Wall Mount Wiring Diagram

    Post Mount Wiring Diagram

    24 VDC

    100WDriver

    18'

    MAXIMUM DISTANCE FROM DRIVER TO FIRST LED

    WIRE SIZE

    DISTANCE

    10AWG

    120' 71' 46' 29'

    12AWG

    14AWG

    16AWG

    18AWG

    Remote Distance Chart

    NOTE: Wire to be supplied by installer, appropriately sized, and meeting localelectical code.

    Concrete

    EMBEDDED

    Cover FlangeWith or Without

    Set Screw

    Rockite

    or Kwixset

    or

    conduit

    SURFACE MOUNT

    1"

    Anchor PlateWith Cover Flange

    Concrete

    41/2"13/16"