  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    1/38

    Underbalanced Drilling

    14 May 2015

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    2/38

     Agenda

    • Drilling overview

    • Underbalanced Drilling

     – What is it? – Why to drill UBD?

     – Evaluation Criteria

     – Equipment

     – Well Control

    • Case Study

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    3/38

    Conventional Drilling

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    4/38

    What is Underbalanced Drilling?

    • Low weight DrillingFluid

     – Naturally

     – Induced

    Preservoir 

    > Pbore hole

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    5/38

    Comparison

    Preservoir 

    > Pbore hole

    Preservoir 

    < Pbore hole

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    6/38

    What is Underbalanced Drilling?

    • Low weight DrillingFluid

     – Naturally

     – Induced

    Preservoir 

    > Pbore hole

    • Control

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    7/38

    Why to Drill Underbalanced?

    • To maximize hydrocarbon recovery

     – Reduce formation damage

     – Produce earlier 

     – Increase reservoir knowledge

     – Enhanced oil recovery

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    8/38

    Why to Drill Underbalanced?

    • To minimize P related drilling problems

     – Differential sticking – Minimal fluid losses

     – Improve penetration rate

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    9/38

    Why to Drill Underbalanced?

    “Chip hold down effect”

    • To minimize P related

    drilling problems

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    10/38

    Underbalanced Drilling

    COST

    UBD+30%

    OBD

    PRODUCTION

    OBD

    UBD300%

    UBD is another tool in the box, not a Panacea

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    11/38

    Limitations

    • Technical

     – Wellbore stability

     – Water inflow – Directional drilling

     – Unsuitable reservoir 

    • Economic

     – Equipment

     – Personnel• Expertise

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    12/38

    Evaluation Criteria

    • Determine BHP requirements

    Preservoir - Pdrilling fluid > 200 psi

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    13/38

    Evaluation Criteria

    • Identify the drilling fluid system – Gas-air

     – Gasified Fluid

     – Stable Foam

     – Drilling Fluid

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    14/38

    Evaluation Criteria

    • Identify the drilling fluid system – Gas-air

     – Gasified Fluid

     – Stable Foam

     – Drilling Fluid

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    15/38

    Evaluation Criteria

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    16/38

    Evaluation Criteria• Identify the drilling fluid system

     – Gas-air

     – Gasified Fluid

     – Stable Foam

     – Drilling Fluid

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    17/38

    Evaluation Criteria

    • Determine BHP requirements

    Identify the drilling fluid options• Well design and modelling

     – Fluid (Compressibility)

     – Cuttings removal

     – Formation inflow – Rock integrity

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    18/38

    Evaluation Criteria

    • Determine BHP requirements

    • Identify the drilling fluid system• Well design and modelling

    • Select the surface equipment

     – Productivity -> Capacity at surface

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    19/38

    Case Study

    • On-shore, New Mexico, 20 June 2006

    • Spud date 17 May 2006

    •Overbalanced drilling until @ 9,471 ft

    • Expected formation pressure is 5,000 psi

    • Drilling underbalanced 300 psi

    • Hydrostatic pressure used was 4,700 psi• Mud weight: 9.5 ppg, diesel based

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    20/38

    Case Study

    • Highly permeable formation with large fluid

    losses expected

    • Objective was to avoid economical losses

    due to the loss of drilling fluids and excess

    rig time

    • Objective to prevent differential sticking of

    drill pipe

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    21/38

    Case Study

    • Drilling system: jointed pipe

    • No gas generation equipment because the

    chose liquid system: diesel

    • Rotating head

    • Basic mud gas separation

    • Gas production sent to flair 

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    22/38

    Well site

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    23/38

    Surface Equipment

    • Drilling System

    • Well control equipment• Gas-generation equipment

    • Surface separation equipment

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    24/38

    Drilling System

     – Jointed Pipe drilling

     –Coiled Tubing

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    25/38

    Snubbing Unit

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    26/38

    Rotating Head

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    27/38

    Well site

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    28/38

    Downhole Equipment

    • Pressure-While-Drilling (PWD) sensors

    • eMWD tools• Non return valves

    • Deployment valves

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    29/38

    Downhole Equipment

    • Deployment valves

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    30/38

    Well Control Mechanisms

    Barrier 

    PrimarySecondary

    UBD

    Flow + P*BOP

    PRESSURE CONTROL FLOW CONTROL

    OBD

    Hydrostatic PBOP

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    31/38

    Well Control Mechanisms

    FLOW CONTROL

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    32/38

    Well Control Mechanisms

    PRESSURE CONTROL FLOW CONTROL

    OBD

     – Hydrostatic

    (Dynamic) – Friction

    (Dynamic)

     – BOP

    UBD

     – Hydrostatic (Passive

     – Flow and pressurecontrol Friction

    (Dynamic)

     – Choke Pressure

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    33/38

    Due Diligence

    • Underbalanced

     – “… that method of drilling whereby the terrastatic 

     pressure exceeds the pressure exerted by the

    drilling fluid column in the bore of a well.”• Producing While Drilling

     – “… those methods of drilling whereby the

    formation fluids are deliberately allowed in the

    bore of a Drilling Well and thence removed to the

    surface while … Drilling activities are continued

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    34/38

    Conditions

    I.   “… a blowout preventer configuration

    including one rotating head …”

    II.   “… any sources of ignition are removed

    … from any area … which operations are

    being conducted …”

    III. “all oil/gas separators … will be placed at

    a safe distance from the drilling rig …”

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    35/38

    Case Study

    • On 20 June 2006 at 10,427 feet

    • Well flowing in uncontrolled manner.Expected Pressure: 300 psi

     Actual Pressure: 800 psi• Casing annular shut and killing operation

    began with 10.7 ppg mud.

    Gas bubble came in annular and Pressureincreased to 2400 psi POP

    • Casing burst, Gas leaked at surface

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    36/38

    Case Study

    • Failure on the rotating head caused a gas

    build up in the annular.

    • Well control: increased drilling fluid to 11.2

    ppg

    • 25 June 2006 finally killed the well

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    37/38

    Case Study

    • Remedial measures

     – Located the burst section and squeezed

    • Remedial Casing 7 in and then continued

    with plan UBD section

    • Claim: 3.5 MM

    • Deductible: 250 k

  • 8/19/2019 Lecture 89 Underbalanced Drilling 14 May 2015

    38/38

    Increased Risk?