lecture 7 risk

Upload: sidra-majeed

Post on 03-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Lecture 7 Risk

    1/59

  • 7/28/2019 Lecture 7 Risk

    2/59

  • 7/28/2019 Lecture 7 Risk

    3/59

  • 7/28/2019 Lecture 7 Risk

    4/59

  • 7/28/2019 Lecture 7 Risk

    5/59

  • 7/28/2019 Lecture 7 Risk

    6/59

    http://www.funnytimes.com/
  • 7/28/2019 Lecture 7 Risk

    7/59

    http://www.funnytimes.com/http://www.funnytimes.com/
  • 7/28/2019 Lecture 7 Risk

    8/59

  • 7/28/2019 Lecture 7 Risk

    9/59

    First Solar Plane Flight 19/04/2013

  • 7/28/2019 Lecture 7 Risk

    10/59

    What is Project Risk?

    Project Risk is an uncertain event or condition that, if occurs, has a

    positive or negative effect on one or more project objectives such as

    scope, schedule, cost and quality.

  • 7/28/2019 Lecture 7 Risk

    11/59

    PMBOK Perspective1 Plan Risk Management: The process of defining how to conduct risk management activities for a

    project

    2 Identify Risks: The process of determining which risks may affect the project and documenting their

    characteristics.

    3 Perform Qualitative Risk Analysis: The process of prioritizing risks for further analysis or action by

    assessing and combining their probability of occurrence and impact.

    4 Perform Quantitative Risk Analysis: The process of numerically analyzing the effect of identified

    risks on overall project objectives.

    5 Plan Risk Responses: The process of developing options and actions to enhance opportunities and

    to reduce threats to project objectives.

    6 Control Risks: The process of implementing risks response plans, tracking identified risks,

    monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the

    project.

  • 7/28/2019 Lecture 7 Risk

    12/59

    Some Risk Conditions Risk conditions may include aspects of the projects or

    organizations environment that contributes to projectrisk:

    Immature project management practices

    Lack of integrated management systems Concurrent multiple projects

    Dependency on external participants who are outsidethe direct project control

    Project manager is too optimist

  • 7/28/2019 Lecture 7 Risk

    13/59

    Risk Attitude Depends Upon

    Risk Appetite The degree of uncertainty an entity is willing to take on

    in anticipation of a reward.

    Risk Tolerance

    The degree, amount or volume of risk that anorganization or stakeholder will withstand

    Risk Threshold

    Below this threshold, the company will accept the risk

    and above it, the organization will not tolerate the risk.

  • 7/28/2019 Lecture 7 Risk

    14/59

    Positive Risks

    What are positive Risks?

    Why they are called opportunities?

    Are they considered good ?

  • 7/28/2019 Lecture 7 Risk

    15/59

    Positive Risk

    Definition: Positive RiskPositive risk is the chance that your objectives will produce too much ofa good thing. Positive risks are deemed as undesirable despite beingpositive at face value

    Positive Risk As An Opportunity :Risk-taking is the process of accepting risk. Examples of risk-takinginclude investing, developing new products and changing businessprocesses. Risk-taking is the basis of economic progress. It's oftenpositive.

    Positive risk is different it's something you're trying to avoid.

  • 7/28/2019 Lecture 7 Risk

    16/59

    Positive Risks Being under budget is a good thing because the company saves money.

    However, in the context of project management it's considered a

    planning error. You didn't really save money

    the project manageroverestimated the project.

    A bridge is constructed to last 50 years. The project management teamcarefully monitors quality risks (the risk it won't last to the 50 yeartarget). They also manage the positive risk that the bridge will last too

    long. If they discover that the bridge will last 100 years

    it was likelyover-engineered.

    Your accountant points out the positive risk that if your income risespast a certain mark then tax rules will apply that will reduce your netincome.

    An ambitious manager seeks important responsibilities. She managesthe risk that she won't take on enough work to achieve recognition. Shealso manages the positive risk that the firm will trust her with so manyresponsibilities that she'll be unable to deliver.

  • 7/28/2019 Lecture 7 Risk

    17/59

    Plan Risk Management

    InputsAll approved plans and baselines;scope, schedule & cost

    2.Project Charter: contains highlevel risks

    3. Stakeholder Register forCommunications managementplan

    4.Enterprise environmental

    factors Risk attitude, threshold,tolerances

    5.Organizational process assets:Risk categories, Roles &responsibilities

    Tools & Techniques

    Analytical TechniquesExpert JudgmentMeetings

    Participants:Project Manager, Selected Project TeamMembers, Stakeholders, thoseresponsible to manage risk planningand execution activities

    Risk Management Plan

    See Next Page

  • 7/28/2019 Lecture 7 Risk

    18/59

    Risk Management Plan

    Include: Methodology: Approaches to perform Risk Management Roles and responsibilities: Defines the lead, support and

    risk management team members & their responsibilities Budgeting: Estimated Funds needed for inclusion in cost

    baseline and establishes protocols for application of

    contingency and management reserves. Timing: How often the risk process will be performed

    throughout the project life cycle Risk Categories: Categories a-z depending on the severity Probability & Impact: a method to determine which risks

    will and will not be acted upon Reporting formats: Documentation, analysis and reportingof risk whenever it will happen.

    Tracking: How recording of the risk will be documented forauditing and future reporting

  • 7/28/2019 Lecture 7 Risk

    19/59

  • 7/28/2019 Lecture 7 Risk

    20/59

    Identify RisksInputs

    1.Risk management plan

    2.Cost management plan

    3.Schedule management plan

    4.Quality management plan

    5. Human Resource Mgt. Plan

    6.Scope baseline

    7.Activity costs estimates

    8.Activity duration estimates

    9.Stakeholder register

    10. Procurement Document11.Project documents

    12.Enterprise environmentalfactors

    13.Organzational process assets

    Tools & Techniques1. Documentation reviews2. Information gathering techniques

    BrainstormingDelphi TechniqueInterviewingRoot cause analysis

    3. Checklist analysis4. Assumptions analysis5. Diagramming techniques

    FlowchartingCause and effect diagram

    6. SWOT Analysis7. Expert judgment

    Risk registerList of Identified RisksList of potential Responses

  • 7/28/2019 Lecture 7 Risk

    21/59

    Perform Qualitative Risk Analysis

    Tools & Techniques1. Risk probability and impact assessment2. Probability and impact matrix

    3. Risk data quality, reliability assessment4. Risk categorization (RBS) and area of the

    project affected5. Risk urgency assessment (near term)6. Expert judgment

    Risk register updatesAssumptions Log Update

    Inputs1.Risk register

    2.Risk management plan

    3.Project scope baseline4.Organizational processassets

  • 7/28/2019 Lecture 7 Risk

    22/59

  • 7/28/2019 Lecture 7 Risk

    23/59

    Perform Quantitative Risk AnalysisTools & Techniques

    1. Data gathering and representationtechniquesInterviewing (3-point estimates)Probability Distribution

    2. Quantitative risk analysis and

    modeling techniquesSensitivity Analysis (potentialimpact)

    3. Expert judgment

    Risk register updatesProbabilistic analysis of the projectProbability of achieving cost and time objectivesPrioritized list of quantified risks

    Inputs1. Risk register

    2. Risk management plan

    3. Scope Baseline

    4. EEF

    5. OPA

  • 7/28/2019 Lecture 7 Risk

    24/59

    Exercise

    A company is trying to determine if prototyping is worthwhile onthe project. They have come up with the following consequences ofwhether the equipment works or fails when it is used. Based on theinformation provided below, what is the expected value of yourdecision?

    24

  • 7/28/2019 Lecture 7 Risk

    25/59

    SolutionPROTOTYPE 35% x $120,000 plus US$200,000

    =US$242,000

    Do not

    Prototype

    70% x $450,000 = US$315,000

  • 7/28/2019 Lecture 7 Risk

    26/59

  • 7/28/2019 Lecture 7 Risk

    27/59

  • 7/28/2019 Lecture 7 Risk

    28/59

  • 7/28/2019 Lecture 7 Risk

    29/59

  • 7/28/2019 Lecture 7 Risk

    30/59

    QUANTITATIVE RISK ANALYSISIs a numericalanalysis of the probability and

    consequences (amount at stake or impacts)of the highest risks on the project to:

    Determine which risk events warrant a response Determine overall project risk (risk exposure) Determine the quantified probability of meeting

    project objectives - e.g., "We only have an 80%chance of completing the project within the sixmonths required by the customer," or "We only havea 75% chance of completing the project within the

    $80,000 budget." Determine cost and schedule reserves Identify risks requiring the most attention Create realistic and achievable cost, schedule or

    scope targets

  • 7/28/2019 Lecture 7 Risk

    31/59

    QUANTITATIVE RISK ANALYSIS

    Risk quantification involves the following activities:

    Further investigation into the highest risks on theproject

    Determination of the type of probability distribution

    that will be used - e.g., triangular, normal, beta,uniform or log normal distributions

    Interviewing experts

    Sensitivity analysis - determining which risks have themost impact on the project

    Monte Carlo simulation (simulation) - described later

    Decision tree analysis - described later

  • 7/28/2019 Lecture 7 Risk

    32/59

    DECISION TREE

    A decision tree takes into account future events intrying to make a decision today.

    It calculates the expected value (probability timesconsequences) in more complex situations thanthe expected value previously presented.

    It involves mutual exclusivity (previouslyexplained in the Quality chapter.)

  • 7/28/2019 Lecture 7 Risk

    33/59

    MONTE-CARLO SIMULATION

    Evaluates the project, not the tasks

    Provides the probability of completing theproject on any specific day, or for any

    specific amount of cost Provides the probability of any task actually

    being on the critical path

    Provides a percent probability that each taskwill be on the critical path

  • 7/28/2019 Lecture 7 Risk

    34/59

    MONTE-CARLO SIMULATION Takes into account path convergence (places in the

    network diagram where many paths converge into onetask)

    Translates uncertainties into impacts to the totalproject Can be used to assess cost and schedule impacts Is usually done with a computer-based Monte Carlo

    program because of the intricacies of the calculations Results in a probability distribution

  • 7/28/2019 Lecture 7 Risk

    35/59

  • 7/28/2019 Lecture 7 Risk

    36/59

    RISK RESPONSE PLANNING

    During this step: Strategies are agreed upon in advance by all

    parties

    Primary and backup strategies are selected

    Risks are assigned to individuals or groups totake responsibility

    Strategies are reviewed over the life of theproject for appropriateness as moreinformation about the project becomes known

  • 7/28/2019 Lecture 7 Risk

    37/59

    STRATEGIES FOR Negative Risks and Threats

    The choices include:

    AVOID - Eliminate the threat by eliminating thecause. Changing the Project Plan to eliminate thethreat entirely. Most radical avoidance strategy is toshut the project entirely.

    MITIGATION Project team acts to reduce theprobability of occurrence or impact of a risk and

    bring it down to within threshold limits.

  • 7/28/2019 Lecture 7 Risk

    38/59

    STRATEGIES FOR Negative Risks and Threats

    ACCEPT - Do nothing and say, "If it happens, it happens." Activeacceptance may involve the creation of contingency plans andpassive acceptance may leave actions to be determined asneeded. A decision to accept a risk must be communicated tostakeholders.

    TRANSFER- Make another party responsible for the riskthrough purchasing of insurance, performance bonds,

    warranties, guarantees or outsourcing the work.

  • 7/28/2019 Lecture 7 Risk

    39/59

    Exercise For each strategy described, determine the name of its strategy. Remember to include

    mitigate probability and mitigate impact.

  • 7/28/2019 Lecture 7 Risk

    40/59

    Solution

  • 7/28/2019 Lecture 7 Risk

    41/59

    Sample Exam Questions

    What do you do with non-critical risks? Answer: Document and revisit periodically.

    Would you select only one risk response strategy? Answer: No, you can choose a combination of choices.

    What risk management activities are done during theexecuting phase of the project? Answer: Watching out for non-critical risks that become

    more important.

  • 7/28/2019 Lecture 7 Risk

    42/59

    Sample Exam Questions

    What is the most important item to address in projectteam meetings?

    Answer: Risk.

    How would risks be addressed in project meetings?

    By asking, "What is the status of risks? Any new risks?Any change to the order of importance? "

  • 7/28/2019 Lecture 7 Risk

    43/59

    Strategies for Positive Risks or Opportunities

    Exploit:This is a point where the organization wishes to ensure that the

    opportunity is realized. The strategy seeks to eliminate theuncertainty associated and ensures that opportunity hashappened

    Enhance: Increase the positive impacts of the opportunity

    Share With other teams and projects / portfolios

    Accept Recognition but not pursuing it further

  • 7/28/2019 Lecture 7 Risk

    44/59

    Contingent Response Strategies

    Alternate ways of doing things

    Create sufficient warning to implement plan

  • 7/28/2019 Lecture 7 Risk

    45/59

    RISK MONITORING AND CONTROLThis step involves managing the project according to therisk response plan and may include the following

    activities:

    Keeping track of the identified risks

    Implementing risk responses Looking for the occurrence of risk triggers

    Monitoring residual risks

    Identifying new risks

    Ensuring the execution of risk plans

    Evaluating the effectiveness of risk plans

    Developing new risk responses

  • 7/28/2019 Lecture 7 Risk

    46/59

    Monitor and Control Risks

    Tools & Techniques1. Risk reassessment2. Risk audits

    3. Variance and trend analysis4. Technical performance

    measurement5. Reserve analysis6. Meetings

    Outputs1. Work performance information2. Organizational process asset updates

    3. Change requests4. Project management plan updates

    5. Project document updates

    Inputs1.Risk register

    2.Project management plan

    3.Work performance information

    4.Performance reports

  • 7/28/2019 Lecture 7 Risk

    47/59

    Which is the most important

    tool & technique in Control Riskand why?

    Risk Assessment

    Risk Audit

    Variance & Trend Analysis

    Technical Performance Measurement Reserve Analysis

    Meetings

  • 7/28/2019 Lecture 7 Risk

    48/59

    Change Requests

    Recommended Corrective Actions

    These are activities that realign the performance of theproject work with the project management plan. This

    includes contingency plans and workarounds

    Recommended Preventive Actions

    These are activities that ensure that future performanceof the project work is aligned with the projectmanagement plan.

  • 7/28/2019 Lecture 7 Risk

    49/59

    MCQs

  • 7/28/2019 Lecture 7 Risk

    50/59

    1 The Three attributes of project risk are

    _________, ___________ and ___________.1. What might happen, who it happens to, and how

    much will it cost

    2. Notification, frequency of relevant events,probability of occurrence

    3. Risk cost, quality, control

    4. Quality, risk planning, total number of risk events

    5. Risk event, probability occurrence, the amount atstake

  • 7/28/2019 Lecture 7 Risk

    51/59

    2: A risk is defined as what might happened to the____________ of the project

    1. assessment

    2. detriment

    3. schedule4. cost

    5. scope

  • 7/28/2019 Lecture 7 Risk

    52/59

    3: When is the project's amount at stake the lowest

    1. conceptual

    2. design

    3. close-out4. implementation

  • 7/28/2019 Lecture 7 Risk

    53/59

    4: What is the most accurate method of obtaining

    project information that can reduce the amount of risk?

    1. Observations on the current project

    2. Determining the risk by using brainstormingtechniques

    3. The use of historical data from previous projects thatwere similar in nature

    4. Sensitivity analysis5. Delphi technique.

  • 7/28/2019 Lecture 7 Risk

    54/59

    5: Which of the following fit the category of external

    risks?

    1. Project delays, budget under-runs, movement of cityutilities

    2. Regulatory, currency changes, taxation

    3. Natural disasters, regulatory, design

    4. Inflation, design, social impact

  • 7/28/2019 Lecture 7 Risk

    55/59

    6: Decision trees are best used for

    1. Determining the interaction of the amount at stakeand the expected value

    2. Association of the probabilities with the risk events

    3. An illustration of how to see the interactionsbetween decisions and the associated events

    4. A flow chart which determines the standard

    deviation of the risk event

  • 7/28/2019 Lecture 7 Risk

    56/59

    7: The total amount of risk that is calculated for a

    project is found by

    1. Multiplying the sum of each the risk times theamount at stake

    2. Calculating the cumulative sum of the probability foreach risk and multiplying this value times theconsequence of occurrence of the risk events

    3. Cannot be calculated since all risks are not know

    4. The amount of project reserves available

  • 7/28/2019 Lecture 7 Risk

    57/59

    8: A situation in which one of two or more risk events

    will follow an act, but the precise nature of these events

    may not be known and the probabilities of their

    occurring cannot be objectively assigned, is the

    definition of

    1. certainty

    2. uncertainty3. risk

    4. risk adversity

    5.None of the above.

  • 7/28/2019 Lecture 7 Risk

    58/59

    Answers:

    1: 5

    2: 2

    3: 1

    4: 3

    5: 2

    6: 37: 2

    8: 2

  • 7/28/2019 Lecture 7 Risk

    59/59

    Thank you,

    Any questions?