lecture #5 highway construction

Upload: fatmah-el-wardagy

Post on 02-Jun-2018

230 views

Category:

Documents


8 download

TRANSCRIPT

  • 8/10/2019 Lecture #5 Highway Construction

    1/41

    H22 IS3 : Transport Infrastructure

    Topic #5 :Highway Construction (Road Pavement)

  • 8/10/2019 Lecture #5 Highway Construction

    2/41

    Introduction

    Unbound Layers

    Asphalt Production

    Batch Plant / Batch Type Mixer

    Drum Mix Plant

    Laying Asphalt Associated Processes

    Concrete Paving

    Modern Equipments & Procedures

    Highway Construction (Road Pavement)

    Contents

  • 8/10/2019 Lecture #5 Highway Construction

    3/41

    Introduction

    Theheart of the highway construction process is the building ofthe road pavement itself.

    This lecture outlines some of the most important processesinvolved.

    Highway Construction (Road Pavement)

  • 8/10/2019 Lecture #5 Highway Construction

    4/41

    Unbound Layers

    The technology involved in placing the lower layers of apavement is much the same as that involved in earthworks.

    The materials are better controlled than would be the case foran embankment fill material for instance.

    The grading is carefully controlled, sometimes by blendingvarious sizes together at the quarry, often by sieving out someof the finest particles created during the quarrying process.

    On site material is tipped from wagons, spread by means ofdozers & graders, & then compacted.

    Moisture content controlis important for many materials as thiscan affect the compactibility of the material.

    Highway Construction (Road Pavement)

  • 8/10/2019 Lecture #5 Highway Construction

    5/41

    Asphalt Production

    Asphalt is the generic name given to stone / bitumen mixtures.

    The commonly used term tarmac is actually short for tar

    macadam, the standard tar bound material which to be usedbefore bitumen took over as the dominant binder.

    The basic purpose of an HMA plant is to properly proportion,blend, & heat aggregate & asphalt to produce an Hot MixAsphalt (HMA) that meets the requirements of the Job MixFormula (JMF).

    There are 2 basic types ofHMA plantscommonly in use today:

    1) Batch plant

    2)Drum mix plant(most popular)

    Batch plants produce HMA in individual batches while drumplants produce HMA in a continuous operation.

    Highway Construction (Road Pavement)

  • 8/10/2019 Lecture #5 Highway Construction

    6/41

    Asphalt Production

    Highway Construction (Road Pavement)

    Figure 5.1 : Batch Plant Figure 5.2 : Drum Plant

  • 8/10/2019 Lecture #5 Highway Construction

    7/41

    Asphalt Production

    Batch plants, which produce HMA in individual batches, are theolder of the 2 types of HMA production facilities.

    HMA was originally made in batches; it was not until the 1970sthat drum plants became a popular HMA production option.

    The older batch plants are likely to be replaced by new drumplants, which can provide greater mobility & production capacity.

    Typical batch quantities range from 1.5 to 5 tons of HMA.

    Highway Construction (Road Pavement)

  • 8/10/2019 Lecture #5 Highway Construction

    8/41

    Batch Plant / Batch Type Mixer

    Highway Construction (Road Pavement)

  • 8/10/2019 Lecture #5 Highway Construction

    9/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

  • 8/10/2019 Lecture #5 Highway Construction

    10/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

    Drum Mix Plant

  • 8/10/2019 Lecture #5 Highway Construction

    11/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

    Control Center

    The control center controls plantoperations from 1 central location.

    Asphalt Cement Storage TanksAsphalt cement is stored in tanks

    while awaiting delivery into thepugmill.

    Asphalt cement in the tanks iskept heated between 150C

    (300F) to 180

    C (350

    F)depending upon the grade & type

    of asphalt.Asphalt is delivered from the

    tanks to the pugmill for mixing

    with aggregate.

    Figure 5.5 : Control Center

    Figure 5.6 : AC Storage Tanks

  • 8/10/2019 Lecture #5 Highway Construction

    12/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

    Fines / Additive SiloSome plants may have one or more silos for storing mineral filler,

    fines from the baghouse (secondary collector) or special

    additives that are added to the mix.

    Figure 5.7 : Fines / Additive Silo

  • 8/10/2019 Lecture #5 Highway Construction

    13/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

    Cold Feed BinsStockpiled aggregate is

    located into the cold feed

    bins for delivery to theaggregate dryer.

    Each bin usually holds aseparate aggregate sizeor gradation & has anadjustable gate thatmeters aggregate onto amoving conveyor belt.

    The degree to which

    these gates open & theconveyor belt speedcontrol the amount ofaggregate introduced intothe plant & thus, controls

    mix gradation.

    Figure 5.8 : Cold Feed Bins

  • 8/10/2019 Lecture #5 Highway Construction

    14/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

    Cold Feed for Reclaimed Asphalt Pavement (RAP)Reclaimed asphalt pavement (RAP) can be used in hot mix at

    ratios up to about 50%.

    RAP is generally loaded into its own cold feed bin then typicallymoved by conveyor belt to be discharged directly into thepugmill or hot elevator where its heated by the already hotaggregate.

    Figure 5.9 :RAP

  • 8/10/2019 Lecture #5 Highway Construction

    15/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

    DrumThe rotating drum heats the aggregate then mixes the hot

    aggregate with asphalt cement.

    There are 2 basic types of drum mixes :(1) Parallel flow (where the aggregate enters the drum at the

    same end as the burner & travels parallel to the hot air stream)(2) Counterflow (where the aggregate enters the drum at the

    opposite end from the burner & travels counter to the hot airstream).

    Asphalt is added to, & mixed with, the hot aggregate in thedrum at different location depending upon the design of thedrum mixer.

  • 8/10/2019 Lecture #5 Highway Construction

    16/41

  • 8/10/2019 Lecture #5 Highway Construction

    17/41

  • 8/10/2019 Lecture #5 Highway Construction

    18/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

    Secondary Collector (Baghouse)The baghouse removes fine particulate matter from the dryer

    exhaust gasses before the exhaust gasses are released to the

    atmosphere.Its basically a series of cylindrical filter fabric bags through

    which the exhaust gas travels.Some plants may use a wet scrubber as a secondary collector.This device sprays water on the exhaust gases & reduces the

    velocity of the air flow to precipitate the fine particles form theexhaust gases.

    Particulate laden water from the scrubber flows to a setting basinwhere the particles settle out so that the water can then be

    reused.

  • 8/10/2019 Lecture #5 Highway Construction

    19/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

    Figure 5.12 : Secondary Collector

  • 8/10/2019 Lecture #5 Highway Construction

    20/41

  • 8/10/2019 Lecture #5 Highway Construction

    21/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

    Storage SilosAfter the aggregate & asphalt cement are mixed in the pugmill

    the resulting hot mix is either discharged directly to trucks for

    transport or stored in silos for later delivery.Generally there are two type of silos: surge & storage.Surge silos are usually insulated but unheated & are designed to

    hold hot mix for short periods of time (several hours) betweentruck arrivals.

    Storage silos are well insulated, heated, near air-tight & aredesigned to hold mix for long periods of time (up to a week).

    Coarse-graded mixes (e.g., friction course & stone matrix asphalt)should not be stored for long periods of time because the asphaltcement will tend to flow off the aggregate (drain down) & collectat the bottom of the silo.

  • 8/10/2019 Lecture #5 Highway Construction

    22/41

    Drum Mix Plant

    Highway Construction (Road Pavement)

    Figure 5.14 : Storage Silos

  • 8/10/2019 Lecture #5 Highway Construction

    23/41

    Batch Plant / Batch Type Mixer

    Highway Construction (Road Pavement)

    Aggregate DryerIn the aggregate dryer, aggregate is heated by tumbling

    aggregates through a hot gas stream.

    The type of dryer is referred to as a counter flow dryer sincethe aggregate moves in a direction opposite that of the hot gasstream.

    Aggregates enter the dryer at the upper end & tumble down therotating drum toward the burner at the opposite end of the dryer.

    Hot ElevatorThe hot elevator takes the heated aggregate from the aggregatedryer & delivers it to the screen deck.

  • 8/10/2019 Lecture #5 Highway Construction

    24/41

    Batch Plant / Batch Type Mixer

    Highway Construction (Road Pavement)

    Screen Deck & Hot BinsHot aggregate is discharged from the hot elevator over a series

    of vibrating screens used to separate it into various sizes (the

    screen deck).The various sizes are then temporarily stored in hot bins until

    the predetermined amount of each aggregate size isaccumulated for a batch.

    Once this occurs, the correctly proportioned aggregate from eachhot bin is discharged into the pugmill.

    PugmillThe aggregate & asphalt cement are blended together in the

    pugmill.Blending is done in batches, thus the name Batch Plant.Pugmills typically have a capacity of 2 to 5 tons per batch.Blending is typically quite short (e.g. short as 35 seconds per

    batch).

  • 8/10/2019 Lecture #5 Highway Construction

    25/41

    Laying Asphalt

    Highway Construction (Road Pavement)

    Asphalt is a much more expensive material than the unboundlayers. It forms the upper part of the pavement & has to be laidto quite tight tolerances.

    To achieve this, it has normally to be laid by a purpose builtpaving machine.

    Figure 5.15 : Truck & Paver

  • 8/10/2019 Lecture #5 Highway Construction

    26/41

    Laying Asphalt

    Highway Construction (Road Pavement)

    Paving takes place continuously. The machine takes asphalt fromthe delivery wagons & feeds is at a controlled rate to the back ofthe paver, where it is spread mechanically to form an even mat

    beneath the paving screed.

    Figure 5.16 : Paver Schematic

  • 8/10/2019 Lecture #5 Highway Construction

    27/41

    Laying Asphalt

    Highway Construction (Road Pavement)

    The paving screed itself vibrates, helping to compact the asphaltmat but does not otherwise control the layer thickness.

    This is done by the operator ensuring the feed of asphalt to the

    back of the paver & the forward movement of the machine aresuch that the correct volume of material is fed onto thepavement.

    Figure 5.17 : Asphalt Paving Machines

  • 8/10/2019 Lecture #5 Highway Construction

    28/41

    Laying Asphalt

    Highway Construction (Road Pavement)

    When it leaves the paver, theasphalt will probably be littleover 100C & will be partially

    compacted. Final compaction is carried out

    by rollers. There are 3 maintypes:Dead weight steel wheel -

    traditional type, good atachieving a smooth surface;

    Vibrating steel roller -achieves better compaction;

    Dead weight pneumatic tired- gives a kneading action,excellent compaction.

    Figure 5.19 : Pneumatic Tire Roller

    Figure 5.18 : Steel Wheeled Roller

  • 8/10/2019 Lecture #5 Highway Construction

    29/41

    Laying Asphalt

    Highway Construction (Road Pavement)

    The asphalt has to be over about 80C in order to allow goodcompactionto be achieved.

    This means that compaction has to be carried out within about8

    minutes from the time it is laid. However, if it is too hot, it willmove around too much rather than densifying properly.

    Thus it should be appreciatedthat control of temperatureis criticalto achieving a good final product.

    The weather of course has a part to play here & very cold or windy

    weather is not suitable for laying asphalt.

  • 8/10/2019 Lecture #5 Highway Construction

    30/41

  • 8/10/2019 Lecture #5 Highway Construction

    31/41

    Associated Processes

    Highway Construction (Road Pavement)

    Figure 5.20 : AC Paving Process

    Surface textureis one of the important safety requirements for aroad surface.

    One of the ways of achieving this is byspreading coated chippings,

    that is single sized pieces of stone coated with bitumen, over thesurface of the road.

    This has to be carried out during the 8 minutes before the asphaltis too cold to compact.

  • 8/10/2019 Lecture #5 Highway Construction

    32/41

    Associated Processes

    Highway Construction (Road Pavement)

    In many cases it is necessaryto spray a film of bitumen onto asurface in order to ensure that the next layer of asphalt sticksproperly.

    This is a tack coat & the form of bitumen used is an emulsionasphalt. In this form (rather like an emulsion paint) the bitumen isworkable & can be sprayed through a nozzle.

    An emulsion sprayed onto the surface combined with a layer ofcoated chippings forms a very useful means of restoring the

    texture of the surface without the need for a full asphalt layer. Thisprocess is surface dressing.

    Often a new layer of asphalt has to be applied to an existingsurface. In this case the existing surface will probably requireshaping in some way &the top surface will have to be planned outto leave a rough texture for the new asphalt to adhere to.

  • 8/10/2019 Lecture #5 Highway Construction

    33/41

    Concrete Paving

    Highway Construction (Road Pavement)

    Concrete paving is a specialised activity requiring a number ofpurpose built pieces of equipment.

    Together, these pieces of equipment are referred to as a paving

    train. The traditional paving train runs on fixed rails either side ofthe pavement, the rails also forming the side shutters to theconcrete.

    1) Fix tie bars for longitudinal joint2) Spread first layer of concrete

    3) Place dowel bars for transverse joints4) Spread second layer of concrete5) Form longitudinal joint recess6) Form transverse joint recess7) Diagonal finisher gives even surface8) Texture surface using brush9) Spray on curing compound10)Cover during early stages of curing

  • 8/10/2019 Lecture #5 Highway Construction

    34/41

  • 8/10/2019 Lecture #5 Highway Construction

    35/41

    Concrete Paving

    Highway Construction (Road Pavement)

    In modern concrete paving,slipform pavingis used & its mostappropriate for larger jobs that require high production rates.

    Slipform paving is defined as a process used to consolidate, form

    into geometric shape & surface finish a PCC mass by pulling theforms continuously through & surrounding the plastic concretemass.

    Slipform paving is most appropriate for larger jobs that requirehigh production rates.

  • 8/10/2019 Lecture #5 Highway Construction

    36/41

    Concrete Paving :Modern Equipments & Procedures

    Highway Construction (Road Pavement)

    1) Placer / SpreadersAlthough not always used,

    placer/spreaders are quitecommon.

    They place a metered supply ofPCC in front of the slipform

    paver using a series of conveyor belts, augers, plows &strikeoff device.

    Using a placer/spreader allowsthe contractor to receive

    material from transportvehicles & place a uniformamount of PCC in front of theentire paver width, whileminimizing segregation.

    Figure 5.21 : Smaller Placer/Spreaders

    Figure 5.22 : Large Placer/Spreader

  • 8/10/2019 Lecture #5 Highway Construction

    37/41

  • 8/10/2019 Lecture #5 Highway Construction

    38/41

    Concrete Paving :Modern Equipments & Procedures

    Highway Construction (Road Pavement)

    1) An auger spreads the PCC in front of the strike off plate.2) The strike off plate (screed) removes excess portions of the auger-placed

    PCC & brings the slab near its final elevation.3) The PCC is consolidated by a group of vibrators.4) A tamper (if present), pushes large aggregate particles below the slab

    surface.5) The profile pans level off the slab at the right elevation & provide initial

    finishing.

    Figure 5.24 : Basic Slipform Paving process as it occurs underneath the Paver

  • 8/10/2019 Lecture #5 Highway Construction

    39/41

    Concrete Paving :Modern Equipment & Procedures

    Highway Construction (Road Pavement)

    Figure 5.25 : PCC Vibrators on theUnderside of a Paving Machine

    Figure 5.26 : Sideforms & Profile Pan

  • 8/10/2019 Lecture #5 Highway Construction

    40/41

    Concrete Paving :Modern Equipments & Procedures

    Highway Construction (Road Pavement)

    3) Texturing & Curing MachineThis machine follows the paver & is used to impart

    macrotexture (usually by dragging a tined instrumentacross the fresh pavement) & apply a curing membraneover the pavement.

    Sometimes the paver is equipped with a tining machine,while a separate machine is used for applying the curing

    membrane.Curing is typically done once finishing of an area is

    complete & the original wet sheen has nearly disappeared.On tined pavements, curing is usually specified to occur

    in 2 passes, 1 forward & 1 in reverse, to ensure both

    sides of the texture ridges are coated with curingmembrane.

  • 8/10/2019 Lecture #5 Highway Construction

    41/41