lead from the front texas nodal 1 eds 4 outage scheduler eds 4.9.2 market call may 30, 2008

13
http://nodal.ercot.com 1 Lead from the front Texas Nodal EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

Upload: aleesha-anderson

Post on 19-Jan-2016

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 1Lead from the front

Texas Nodal

EDS 4 Outage Scheduler

EDS 4.9.2 Market Call

May 30, 2008

Page 2: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 2Lead from the front

Texas Nodal

ERCOT Anti-Trust Admonition

ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws.

Page 3: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 3Lead from the front

Texas Nodal

Agenda

• Outage Scheduler– Release 9.2 update– External Web Services update– Q&A and Roll Call

• Appendix

Page 4: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 4Lead from the front

Texas Nodal

Update on Outage Scheduler

Current Status • OS UI now available

– The URL to access the Outage Scheduler is https://nodaleds.ercot.com/misportal/ Next Weeks Market Test Schedule• Luminant ((6/2) 1 - 3 PM)• LCRA ((6/2) 4 – 6 PM)• CPS ((6/3) 9 – 11 AM)• Topaz Power ((6/3) 4 - 6 PM)• AEP ((6/4) 9 – 11 AM)• Exelon ((6/4) 1 -3 PM)• Austin Energy ((6/5) 9 – 11 AM)• EnergyCo ((6/5) 1 – 3 PM)• Greenville Electric ((6/6) 9 – 11 AM)Completed UI Test LCRA TSP, Fulcrum Power Services LP, IPA Market Inc., ANP Funding LLC, BPTX, BTU (TSP & QSE), FPL, Oncor,

Constellation, Calpine, City of San Antonio, Direct Energy, Centerpoint, Reliant Energy, Coral Power, Tenaska, Suez Energy, Brazos (TSP & QSE), NRG

Future updates• Recurring Planned Outages is now available• Recurring, Grouped and Opportunity Outages through API, available date 6/6, with known issues• Grouped and Opportunity Outages through UI, delayed until 6/30WAN Update• We have completed a capacity study with a few QSE volunteers• Capacity is conducive to allowing a full market test• ERCOT will update the WAN DNS with nodaleds.ercot.com on Monday 6/09/08.• All QSE’s and TSP’s are permitted at that time to begin market submissions over the WAN• ERCOT will continue to evaluate whether large reports and MIS will also be available over the WAN• If issues are found, ERCOT will roll back the DNS entry and notify the market via a market notice• Notifications will remain over the internet only

Page 5: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 5Lead from the front

Texas Nodal

External Interface Spec V 1.14 documentation update

Document update• EIS V 1.14 was published to Nodal Readiness Center on 5/9/08 • Sandbox compliant to EIS V 1.14 as of 5/22/08 • EDS will be compliant to EIS V1.14 evening of 6/5/2008

– Known Issues• Errors not always specific to real issue• Group Opportunity Outages not available at this time

Page 6: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 6Lead from the front

Texas Nodal

Q&A / Open Forum

Roll-Call

Page 7: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 7Lead from the front

Texas Nodal

-Release 9.2 Information-Connectivity information-Links to Key Documentation -Metrics-Data preparation

APPENDICES

Page 8: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 8Lead from the front

Texas Nodal

Outage Scheduler EDS 4.9.2: Objectives

EDS Phase

Description Phase Objectives

9.2.1 Forced Outage Detection •Verify the ability of the EMS to receive outage list from OS•Verify the automation and timing of information from the OS to the EMS•Verify the FOD capability of the EMS

9.2.2 Connectivity / Submission test

•Verify MIS connectivity (if applicable)•Verify EWS connectivity (if applicable)•Verify MP’s ability to enter outages •Verify ERCOT’s ability to approve single and group outages•Verify QSE/TSP ability to receive updates on outage status

9.2.3 Validation of Performance •Verify OS ability to receive a specified quantity of data from multiple sources simultaneously via both the RUI and the EWS•Verify OS data available for real-time reports

9.2.4 Validation of Outage Evaluation in EDS

•Verify OS ability to send outage requests for the time period defined by the EMS user.•Verify OS ability to receive outage status changes from the OE

9.2.5 Validation of Outage Scheduler Interfaces

•Verify outage transfers from the OS into the DA TSA•Verify outage transfers into RUC•Verify outage transfers to all other uses of OS information

9.2.6 Validation of Outage Postings in MIS

•Verify outage transfers from the OS into the MIS•Validate MIS Secure Area access to Market Participants with the appropriate Digital Certificate•Verify performance

Page 9: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 9Lead from the front

Texas Nodal

Appendix - Outage Scheduler 4.9.2 Testing: Basic Communications Test

• Prior to this test QSEs and TSPs using External Web Services will need to have their network and security teams make the following changes:

– QSE’s / TSP’s Outage Scheduler system must be able to access:https://nodaleds.ercot.com:80/2007-08/Nodal/eEDS/EWS/ NOTE: this SSL URL is on port 80

– Market Participants must be able to receive / send transactions to/from the following IP ranges:

• 66.128.16.0/24 • 66.128.17.0/24 • 66.128.18.0/24

Page 10: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 10Lead from the front

Texas Nodal

• QSEs and TSPs using MIS (RUI) will need to have their network and security teams make the following changes:– Ports will be 80 and 443– Market Participants must be able to receive / send transactions

to/from the following IP ranges:• 66.128.16.0/24 • 66.128.17.0/24 • 66.128.18.0/24

Appendix - Outage Scheduler 4.9.2 Testing: Basic Communications Test

Page 11: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 11Lead from the front

Texas Nodal

Key Documentation

Key documents are available at http://nodal.ercot.com/readiness/eds4/documents/index.html

Page 12: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 12Lead from the front

Texas Nodal

Outage Scheduler 4.9.2 Tracking: Readiness Metrics

• TPTF approved MP20 to track MP ability to submit outages to the Nodal Outage Scheduler.

• Execution

– MP’s that have met readiness metric MP20 by 6/13/08 are GREEN

– MP’s that have attempted readiness metric MP20 by 6/13/08 are AMBER

– MP’s that have not yet attempted readiness metric MP20 by 6/13/08 are RED

• ERCOT is calling all MPs that have not signed up for EDS4.9.2

Page 13: Lead from the front Texas Nodal  1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call May 30, 2008

http://nodal.ercot.com 13Lead from the front

Texas Nodal

Appendix- Outage Scheduler 4.9.2 Reference: TSP/QSE Data Preparation

• If QSEs or TSPs need their equipment list to verify xml submissions, please email to [email protected]

• ERCOT is unable to post the information online for all QSEs and TSPs because of the size of the file