las colonias subdivision september 2010 flood study · •programmed for fy12-13 design •$17.5m...

23
Las Colonias Subdivision September 2010 Flood Study Curtis Beitel, P.E., CFM Scott Muchard, P.E. – Project Engineer William Badini, CFM – Senior Meteorologist

Upload: others

Post on 03-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Las Colonias Subdivision

September 2010 Flood Study

Curtis Beitel, P.E., CFM

Scott Muchard, P.E. – Project Engineer

William Badini, CFM – Senior Meteorologist

Page 2: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Location Map

Page 3: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Background

• Los Colonias Subdivision

– Constructed in 1986

– Construction Standards for Floodplain Management essentially unchanged

• Build finish floor at the Base Flood Elevation

– Subdivision is currently located partially in FEMA Zone A & B flood zones

• Zone A is 1% chance (100 year) floodplain

• Zone B is 0.2% chance (500 year) floodplain

Page 4: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Background

• Effective FIRM = July 18, 1985

• Zone A4 BFEs

22 to 24

Page 5: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

La Volla Creek Watershed

Las Colonias Subdivision

Margaret Kelly Ditch

Saratoga Downs Ditch

Airport Ditch

Tot

Total Contributing Drainage Area Approximately 17,172 Acres

Page 6: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

September 2010 Event Summary

• Monthly Precipitation reached record levels: – Continued rainfall recharged reservoirs and saturated ground surfaces

– Subjected the City to extreme flooding during rain events the weekend of September 18th, 2010

• Two Tropical Depressions – Sept. 6 thru 8th, Tropical Storm Hermine

– Sept. 14 thru 18, Tropical Storm Karl

• September 18, 2010 - Water Surface Elevations (WSE) – Los Colonias Subdivision – El. 27.8’ (at high point)

– Greenwood WWTP – El. 27.x

– Saratoga Bridge – El. 28’

– La Volla Creek / Oso Creek Convergence – El. 25’

Page 7: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

September 2010 Event Summary

Greenwood Waste Water Treatment Plant

Page 8: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Saratoga Bridge – Downstream Face

September 2010 Event Summary

Page 9: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Looking North from the Saratoga Bridge

September 2010 Event Summary

Page 10: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Las Colinas Subdivision

September 2010 Event Summary

Page 11: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

• Utilized both Corpus Christi and Brownsville radars

• Corpus Christi NEXRAD site is in watershed

NEXRAD Radar Rainfall Analysis

Page 12: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

• Reviewed Atmospheric Conditions

• Estimated Maximum Precipitation Rates

• Related to Reflectivity to Develop Grid

NEXRAD Radar Rainfall Analysis

Page 13: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

• GIS polygons

• Basin Average 15-minute Rainfall Depths

• Compared to Drainage Criteria Manual Rainfall Depths

NEXRAD Radar Rainfall Analysis

Page 14: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Rainfall Frequency Analysis

Duration

Las Colonias

(OCB-200)

(inches)

Oso Creek

U/S of La Volla Creek

(inches)

Oso Creek

D/S of La Volla Creek

(inches)

15 Minute 0.72 0.60 0.64

30 Minute 1.29 1.14 1.28

60 Minute 2.30 2.09 2.47

2 Hour 4.41 3.75 4.50

3 Hour 5.92 4.97 5.92

6 Hour 7.65 6.68 7.90

12 Hour 8.04 7.07 8.29

Duration

Return Frequency (years)

Las Colonias

(OCB-200)

(inches)

Oso Creek

U/S of La Volla

Creek

(inches)

Oso Creek

D/S of La Volla

Creek

(inches)

15 Minute < 5 < 5 < 5

60 Minute < 5 < 5 < 5

2 Hour 30 14 33

3 Hour 68 29 68

6 Hour 79 43 90

12 Hour 40 23 45

• 6 hour duration

• Oso Creek above La Volla

– 40-year frequency

• La Volla Creek

– 80-year frequency

• Oso Creek below La Volla

– 90-year frequency

Page 15: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Hydrology

• Basin Hydrology – Oso Creek

HEC-HMS model from Draft Storm Water Master Plan

– New rainfall gauge for each 15-minute Basin Average Rainfall

– Same loss rates

– Same unit hydrograph parameters

Page 16: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Hydrology

• Resulting Peak Flows

– 5,435 cfs in La Volla Creek at Saratoga

– FEMA 1992 Flood Insurance Study Peak Discharges

• 4,359 cfs = 100-year at Saratoga

• 6,150 cfs = 500-year at Saratoga

Page 17: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Hydraulics

• Draft SWMP HEC-RAS model of La Volla Creek

• Included 2004 TxDOT bridge configuration at Saratoga Boulevard

• Adjusted roughness coefficients

Page 18: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Hydraulics

• Resulting Water Surface Elevations

– 28.1 at Greenwood WWTP pump house

– 28.5 upstream of Saratoga bridge

– 28.5 to 28.7 in Las Colonias subdivision

– Natural ground at 23 to 24

Page 19: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Impact of Proposed CIP Projects

1. Channel Clearing and Stabilization Project

• Upstream of Saratoga to Airport Ditch

• Vegetation clearing only

• If in place in September 2010

– 28.1 at Greenwood WWTP pump house (0.0 ft reduction)

– 28.3 upstream of Saratoga bridge (0.2 ft reduction)

– 28.3 in Las Colonias subdivision (0.4 ft reduction)

• Future Overbank / floodplain excavation (100 ft bottom width)

Page 20: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

2. Drainage Channel Excavation – La Volla Creek

• Airport Ditch down to Oso Creek (150 ft bottom width)

• Programmed for FY12-13 Design

• $17.5M Project Construction Estimate

• If in place in September 2010

– 23.9 at Greenwood WWTP pump house (4.2 ft reduction)

– 23.9 upstream of Saratoga bridge (4.6 ft reduction)

– 23.9 to 24.0 in Las Colonias subdivision (4.7 ft reduction)

Impact of Proposed CIP Projects

Page 21: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Status & Future Actions

• Presented at December 14, 2010 City Council meeting – Subdivision Ideas Committee

• Citizens, City staff, City Council member

– Recognized community relief contributions

– Event Summary

– Engineering Analysis

• Less than 3 months after flood event occurred

Future Actions:

• Storm Water Master Plan and Drainage Criteria Adoption

• Storm Water Operation and Capital Improvement Revenue

• Floodplain Management and Drainage Design Review

Page 22: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

• La Volla Creek Detention Improvements – HMGP Grant Application pending

• La Volla Creek Drainage Channel Excavation project (Saratoga Bridge to Oso Creek) – Currently in preliminary design

• Oso Creek Basin Drainage Enhancement Study – Alternatives to relieve several hydraulic choke points

– Study is underway

• TxDOT Bridge Replacement

Current & Future Actions

Page 23: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood

Questions

Curtis Beitel, PE, CFM HDR Engineering, Inc. [email protected] 817-333-2817