las colonias subdivision september 2010 flood study · •programmed for fy12-13 design •$17.5m...
TRANSCRIPT
![Page 1: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/1.jpg)
Las Colonias Subdivision
September 2010 Flood Study
Curtis Beitel, P.E., CFM
Scott Muchard, P.E. – Project Engineer
William Badini, CFM – Senior Meteorologist
![Page 2: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/2.jpg)
Location Map
![Page 3: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/3.jpg)
Background
• Los Colonias Subdivision
– Constructed in 1986
– Construction Standards for Floodplain Management essentially unchanged
• Build finish floor at the Base Flood Elevation
– Subdivision is currently located partially in FEMA Zone A & B flood zones
• Zone A is 1% chance (100 year) floodplain
• Zone B is 0.2% chance (500 year) floodplain
![Page 4: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/4.jpg)
Background
• Effective FIRM = July 18, 1985
• Zone A4 BFEs
22 to 24
![Page 5: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/5.jpg)
La Volla Creek Watershed
Las Colonias Subdivision
Margaret Kelly Ditch
Saratoga Downs Ditch
Airport Ditch
Tot
Total Contributing Drainage Area Approximately 17,172 Acres
![Page 6: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/6.jpg)
September 2010 Event Summary
• Monthly Precipitation reached record levels: – Continued rainfall recharged reservoirs and saturated ground surfaces
– Subjected the City to extreme flooding during rain events the weekend of September 18th, 2010
• Two Tropical Depressions – Sept. 6 thru 8th, Tropical Storm Hermine
– Sept. 14 thru 18, Tropical Storm Karl
• September 18, 2010 - Water Surface Elevations (WSE) – Los Colonias Subdivision – El. 27.8’ (at high point)
– Greenwood WWTP – El. 27.x
– Saratoga Bridge – El. 28’
– La Volla Creek / Oso Creek Convergence – El. 25’
![Page 7: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/7.jpg)
September 2010 Event Summary
Greenwood Waste Water Treatment Plant
![Page 8: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/8.jpg)
Saratoga Bridge – Downstream Face
September 2010 Event Summary
![Page 9: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/9.jpg)
Looking North from the Saratoga Bridge
September 2010 Event Summary
![Page 10: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/10.jpg)
Las Colinas Subdivision
September 2010 Event Summary
![Page 11: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/11.jpg)
• Utilized both Corpus Christi and Brownsville radars
• Corpus Christi NEXRAD site is in watershed
NEXRAD Radar Rainfall Analysis
![Page 12: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/12.jpg)
• Reviewed Atmospheric Conditions
• Estimated Maximum Precipitation Rates
• Related to Reflectivity to Develop Grid
NEXRAD Radar Rainfall Analysis
![Page 13: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/13.jpg)
• GIS polygons
• Basin Average 15-minute Rainfall Depths
• Compared to Drainage Criteria Manual Rainfall Depths
NEXRAD Radar Rainfall Analysis
![Page 14: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/14.jpg)
Rainfall Frequency Analysis
Duration
Las Colonias
(OCB-200)
(inches)
Oso Creek
U/S of La Volla Creek
(inches)
Oso Creek
D/S of La Volla Creek
(inches)
15 Minute 0.72 0.60 0.64
30 Minute 1.29 1.14 1.28
60 Minute 2.30 2.09 2.47
2 Hour 4.41 3.75 4.50
3 Hour 5.92 4.97 5.92
6 Hour 7.65 6.68 7.90
12 Hour 8.04 7.07 8.29
Duration
Return Frequency (years)
Las Colonias
(OCB-200)
(inches)
Oso Creek
U/S of La Volla
Creek
(inches)
Oso Creek
D/S of La Volla
Creek
(inches)
15 Minute < 5 < 5 < 5
60 Minute < 5 < 5 < 5
2 Hour 30 14 33
3 Hour 68 29 68
6 Hour 79 43 90
12 Hour 40 23 45
• 6 hour duration
• Oso Creek above La Volla
– 40-year frequency
• La Volla Creek
– 80-year frequency
• Oso Creek below La Volla
– 90-year frequency
![Page 15: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/15.jpg)
Hydrology
• Basin Hydrology – Oso Creek
HEC-HMS model from Draft Storm Water Master Plan
– New rainfall gauge for each 15-minute Basin Average Rainfall
– Same loss rates
– Same unit hydrograph parameters
![Page 16: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/16.jpg)
Hydrology
• Resulting Peak Flows
– 5,435 cfs in La Volla Creek at Saratoga
– FEMA 1992 Flood Insurance Study Peak Discharges
• 4,359 cfs = 100-year at Saratoga
• 6,150 cfs = 500-year at Saratoga
![Page 17: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/17.jpg)
Hydraulics
• Draft SWMP HEC-RAS model of La Volla Creek
• Included 2004 TxDOT bridge configuration at Saratoga Boulevard
• Adjusted roughness coefficients
![Page 18: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/18.jpg)
Hydraulics
• Resulting Water Surface Elevations
– 28.1 at Greenwood WWTP pump house
– 28.5 upstream of Saratoga bridge
– 28.5 to 28.7 in Las Colonias subdivision
– Natural ground at 23 to 24
![Page 19: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/19.jpg)
Impact of Proposed CIP Projects
1. Channel Clearing and Stabilization Project
• Upstream of Saratoga to Airport Ditch
• Vegetation clearing only
• If in place in September 2010
– 28.1 at Greenwood WWTP pump house (0.0 ft reduction)
– 28.3 upstream of Saratoga bridge (0.2 ft reduction)
– 28.3 in Las Colonias subdivision (0.4 ft reduction)
• Future Overbank / floodplain excavation (100 ft bottom width)
![Page 20: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/20.jpg)
2. Drainage Channel Excavation – La Volla Creek
• Airport Ditch down to Oso Creek (150 ft bottom width)
• Programmed for FY12-13 Design
• $17.5M Project Construction Estimate
• If in place in September 2010
– 23.9 at Greenwood WWTP pump house (4.2 ft reduction)
– 23.9 upstream of Saratoga bridge (4.6 ft reduction)
– 23.9 to 24.0 in Las Colonias subdivision (4.7 ft reduction)
Impact of Proposed CIP Projects
![Page 21: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/21.jpg)
Status & Future Actions
• Presented at December 14, 2010 City Council meeting – Subdivision Ideas Committee
• Citizens, City staff, City Council member
– Recognized community relief contributions
– Event Summary
– Engineering Analysis
• Less than 3 months after flood event occurred
Future Actions:
• Storm Water Master Plan and Drainage Criteria Adoption
• Storm Water Operation and Capital Improvement Revenue
• Floodplain Management and Drainage Design Review
![Page 22: Las Colonias Subdivision September 2010 Flood Study · •Programmed for FY12-13 Design •$17.5M Project Construction Estimate •If in place in September 2010 –23.9 at Greenwood](https://reader033.vdocuments.us/reader033/viewer/2022060515/5f8cc2386f9d7e628e5fbc09/html5/thumbnails/22.jpg)
• La Volla Creek Detention Improvements – HMGP Grant Application pending
• La Volla Creek Drainage Channel Excavation project (Saratoga Bridge to Oso Creek) – Currently in preliminary design
• Oso Creek Basin Drainage Enhancement Study – Alternatives to relieve several hydraulic choke points
– Study is underway
• TxDOT Bridge Replacement
Current & Future Actions