![Page 1: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/1.jpg)
LARP
Commissioning Plansfor the
LHC Synchrotron-Light Monitors
Alan FisherSLAC National Accelerator Laboratory
LARP CM13 Port Jefferson, NY 2009-11-04
![Page 2: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/2.jpg)
CERN Collaborators
Stéphane Bart-Pedersen Andrea Boccardi Gérard Burtin Aurélie Goldblatt Ana Guerrero Thibaut Lefevre
![Page 3: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/3.jpg)
Synchrotron-Light Monitors
Two applications: BSRT: Imaging telescope, for transverse beam profiles BSRA: Abort-gap monitor, to verify that the gap is empty
When the kicker fires, particles in the gap get a partial kick and might cause a quench.
Two particle types: Protons and lead ions
Three light sources: Undulator radiation at injection (450 GeV) Dipole edge radiation at intermediate energy (2 to 3 TeV) Central dipole radiation at collision energy (3.5 to 7 TeV) Spectrum and focus change during ramp.
![Page 4: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/4.jpg)
Layout: Emission and Extraction
To RF cavities and IP4
To arc
Cryostat
Extracted light sent below the
beamline.
1.6 mrad
70 m
26 m 937 mm560 mm
420 mm
D3 U
10 mD4
194 mm
![Page 5: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/5.jpg)
Spectrum of Central Dipole Radiation
Spectrum near Critical Frequency
Normalized emission energy in dipole
Frequency normalized to critical frequency
Camera responds from near IR to near UV.
Proton emission wavelength is too long at injection.
Ion emission is too long below 3 TeV. i.e., dipole setting equivalent to 3-TeV protons
Critical Wavelength vs Beam Energy
Lead ions
Protons
Camera’s response
![Page 6: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/6.jpg)
Undulator versus Dipole
Peak of Undulator Spectrum Critical Wavelength in Dipole
Undulator provides response at proton injection.
But response is still poor for ions at injection.
Lead ions
Protons
Camera’s response
Lead ions
Protons
Camera’s response
![Page 7: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/7.jpg)
Photoelectrons per Particle at Camera
Protons Lead Ions
Dipole center
Undulator
Combined
Dipole edgeUndulator
CombinedDipole center
Dipole edge
In the crossover region between undulator and dipole radiation: Weak signal Two comparable sources: poor focus over a narrow energy range
Focus moves with energy: from undulator, to dipole edge, and then to dipole center.
Dipole egde radiation is distinct from central radiation only for >> c
![Page 8: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/8.jpg)
Particles per Bunch and per Fill
Protons Lead Ions
Particles in a pilot bunch 5109 7107
Particles in a nominal bunch 1.151011 7107
Bunches in early fills 1 to 43 1 to 62
Bunches in a full ring 2808 592
![Page 9: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/9.jpg)
Beam Size and Critical Wavelength
BeamEnergy
Beam Size atSource Point
Calculated Size on the Camera
Increase over Magnified Size
(M = 0.3)
(TeV) (m RMS) (m RMS) (m RMS)
x y x y x y
Protons
0.45 1302 1244 391 373 1.002 0.999
3.5 473 447 146 139 1.030 1.035
7 334 315 98.5 111 0.983 1.179
Ions
0.45 1304 1246 392 375 1.003 1.004
3.5 473 447 144 135 1.013 1.006
7 335 315 104 98.8 1.033 1.044
Calculation includes geometric optics, depth of field, and diffraction.
400-nm wavelength is used, except at injection, where the undulator spectrum is shifted to the red and infrared.
![Page 10: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/10.jpg)
Photoelectrons in the Peak Pixel
Protons Lead Ions
In one turnIn 20 ms
Pilot bunchSingle nominal bunchFull ring
Emission increases with energy while beam size shrinks, giving a strong variation of the signal on the peak pixel.
![Page 11: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/11.jpg)
Abort-Gap Monitor
Gated photomultiplier gets ~15% of collected light. PMT is gated off except during the 3-s abort gap:
High gain needed during gap. No saturation when filled bunches pass by.
Pick off before all slits or filters for maximum light. Digitize the gap signal in 30 100-ns bins.
Sum over 100 ms and 1 s. Longer integration needed when emission in PMT band is
weak (protons at crossover and ions at injection). Worst case signal-to-noise is 10 for 1-s integration at 10% of
threshold.
Requirement: Detect whether any bin has a population over 10% of the quench threshold.
![Page 12: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/12.jpg)
Protons/100ns at Quench Threshold
Original threshold specification (given only at 0.45 and 7 TeV) was too generous.
BLM group provided improved models. We used Sapinski’s calculation. Ions fragment on beam screen, and deposit energy equivalent to Z protons
at same point in ramp.
Original specification
Model for BSRA (Q4 quench) (M. Sapinski)
General quench model (B. Dehning)
![Page 13: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/13.jpg)
Re-examining the Optical Design
Optical: Add focus adjustment, since source moves during the ramp. Add a calibration source.
Mechanical: The optics were housed in a tube (left over from LEP). Replace with an optical table.
More space for optics. Better access for adjustment.
Calculations: Light level from protons and ions Can the undulator stay on at high energy? Minimize blurring from diffraction and depth of field. Improve the optics for better imaging. Monitoring abort gap even with weak light at injection.
![Page 14: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/14.jpg)
Original Optics Housed in a Tube
![Page 15: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/15.jpg)
Poor Access with the Present Layout
![Page 16: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/16.jpg)
Layout of New Optical Table
Alignment laser
Focustrombone
F1 = 4 m
PMT and 15% splitter for abort gap
Intermediate image
Table Coordinates [mm]
Cameras
Slit
Calibration light and
target
F2 = 0.75 m
Beam
Table
Extraction mirror
Shielding
![Page 17: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/17.jpg)
New Table Installed under Beamline
![Page 18: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/18.jpg)
4-Pass Focus Trombone
600-mm translation stage Outer trombone: 2 passes gives a 1200-mm range. Inserting 2 mirrors converts trombone to 4 passes.
With a fixed extra path, the 4-pass mode spans 600 to 3000 mm.
![Page 19: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/19.jpg)
Intensified and Gated Cameras
Gated camera (turn
by turn)
Intensified camera
Neutral-density filters
40% beamsplitter
![Page 20: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/20.jpg)
Abort-Gap Monitor
PMT
Neutral-density filters
Pulsed LED
Motorized slit
Amplifier
![Page 21: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/21.jpg)
Commissioning: Setup for First Beam
Undulator at full field Extraction mirror inserted Trombone at minimal delay (100 mm)
Source (undulator) is at longest distance Inner trombone switched out
No neutral-density or color filters inserted Maximum gain for intensified camera and PMT Maximum integration time for gated camera
![Page 22: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/22.jpg)
Commissioning: 450-GeV Pilot Bunch
BSRA (Abort-Gap Monitor): Set a wide gate that includes the pilot bunch. Steer first two mirrors to find a signal on the PMT.
Avoid damaging PMT: Software alarm or feedback on high voltage Insert filters as needed. Shorten the gate. Verify timing using the pilot bunch. Calibrate the signal level with the pilot bunch. Reset the gate to span only the abort gap. Remove filters for sensitivity to threshold gap population.
![Page 23: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/23.jpg)
Commissioning: 450-GeV Pilot Bunch
BSRT Cameras: Adjust steering as needed to get light on cameras.
Check that light remains on the PMT. 10-mm diameter photocathode, placed at intermediate waist.
Adjust intensifier gain and gated-camera integration as needed. Focus by scanning the trombone (expect ±100 mm).
Determine steering needed to keep light on center of cameras. Determine settings for:
Pilot bunch, 1 turn (gated camera) and 20 ms (intensified camera) Nominal bunch, 1 turn and 20 ms Multiple nominal bunches
![Page 24: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/24.jpg)
Commissioning: Ramping the Pilot
Don’t change light path at first: Measure beam displacements. Measure intensity changes.
But keep the detectors from saturating.
At end of ramp: Resteer the light. Adjust intensity. Recalibrate the BSRA and cameras.
Build up a calibration table for each energy step: Steering Intensity control
![Page 25: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/25.jpg)
Commissioning: Automatic Operation
Automatic (software) control depending on: Particle type (proton/ions) Beam charge Bunch charge Beam energy
Adjustments: BSRA settings:
Neutral-density filters and PMT high voltage Motorized mirrors Motorized slit on the focal plane of first focusing mirror Camera settings:
Color and neutral-density filters Gain and shutter for intensified camera Integration time and framing speed for gated camera
![Page 26: LARP Commissioning Plans for the LHC Synchrotron-Light Monitors Alan Fisher SLAC National Accelerator Laboratory LARP CM13 Port Jefferson, NY 2009-11-04](https://reader035.vdocuments.us/reader035/viewer/2022062520/5697bfc11a28abf838ca4586/html5/thumbnails/26.jpg)
Schedule
Stored beam expected in the next couple of weeks. I will go to CERN on Nov. 28 and stay until the
holiday shutdown (Dec. 19). A proton photo album for CM14?