lap manual 11-d march 2016 consultant procurement

97
LAP Manual 11-C March 2016 Consultant Procurement Updated December 2017

Upload: phungdung

Post on 14-Feb-2017

223 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 11-C March 2016 Consultant Procurement

Updated December 2017

Page 2: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-1 December 2017 Project Development

Chapter 12 PROJECT DEVELOPMENT 12.1 Project Scoping 12.2 Plan Design 12.3 Project Budget, Schedule and Estimates 12.4 Public Involvement 12.5 Plan submittals 12.6 Advertisement and Award

Project Development Checklists – included in each respective section INTRODUCTION Project Development Process The Project Development Process guides Preliminary Engineering processes through the use of multi-disciplinary concurrent efforts. It establishes a framework for increased involvement of all stakeholders in the project development lifecycle and promotes coordination and communication, ultimately improving the efficiency and quality of the project. Offered as a reference, the process documentation may be accessed at: Project Development Process. Tiered Approach to Project Oversight VDOT employs a tiered approach to project oversight. District Offices have delegated review and approval responsibilities for specific, lower-risk projects, identified as Tier 1 projects. Higher risk projects, identified as Tier 2 projects, require VDOT Central Office review and approval. Instructional and Informational Memorandum IIM-LD-249 provides the implementation process for this tiered project oversight process. With few exceptions, the tiered project oversight process is generally transparent to local governments administering federal or state-aid projects. Project oversight for locally administered projects will follow the same approval processes as VDOT-administered projects. Where clarification is necessary, the “VDOT Responsibilities” sections of this chapter will be identified as applying to Tier 1, Tier 2 or both processes. Project Oversight Definitions: Tier 1 projects typically are smaller projects with few risks, are non-federal oversight projects and have construction values of less than $10 million. Tier 1 Locally

Page 3: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-2 December 2017 Project Development

Administered projects will follow the applicable project review processes established by VDOT’s districts in accordance with the guidance provided by IIM-LD-249. Tier 2 projects include large projects, design build projects and all federal oversight and non-federal oversight projects having construction values greater than $10 million. Tier 2 Locally Administered projects will continue to have VDOT Central Office Division oversight and will follow the review processes outlined in this chapter. Federal Oversight: FHWA updated the definition for federal project oversight based on identifying Projects of Division Interest (PoDI). Information regarding this approach to project oversight is located in the archived FHWA document titled “Projects of Division Interest (PoDI)/Projects of Corporate Interest (PoCI) Guidance.”

Page 4: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-3 December 2017 Project Development

12.1 - PROJECT SCOPING

12.1 PROJECT SCOPING

This chapter includes the following topics

12.1.1 Introduction

12.1.2 Applicability

12.1.3 Scoping Process Requirements

12.1.4 Tasks / Submittals / File Documentation

12.1.5 References

Project Scoping Checklist

NEPA document

concurrence form submitted

Agreement executed

LPA

LPA prepares and conducts

Scoping

Meeting

LPA develops estimate 12.1.3 &

12.3.4

LPA develops schedule 12.1.3 & 12.3.3

LPA submits scoping

documentation to

VDOT

VDOT

Page 5: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-4 December 2017 Project Development

12.1.1 Introduction

Project Scoping defines the project. During the Scoping process, the LPA Project

Manager (PM) will identify those elements of the project that influence how the

project will be developed and delivered. The VDOT Project Coordinator (PC) is

available to assist the LPA Project Manager to facilitate the Scoping process based

on project complexity. This section outlines the processes and responsibilities

associated with Project Scoping for federal-aid projects and can be used by the LPA

to scope their state-aid projects. During project scoping, the project team, under the

leadership of the LPA Project Manager, defines the physical limits and features of

the project, establishes project estimate and schedule and determines the project

oversight level in accordance with Chapter 9.4.2. In most cases, the scoping phase

and report should be completed at the conclusion of the preliminary field inspection

(PFI) milestone phase. If this duration exceeds twelve months from the execution of

the project administration agreement, the LPA must obtain District concurrence.

VDOT’s Project Management Guide can be used as a reference during the scoping

process to assist the LPA in defining the activities that will be followed throughout

the project lifecycle. Additionally, the LAP Schedule Tool is available and

recommended for local governments use in developing preliminary engineering

project schedules.

Page 6: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-5 December 2017 Project Development

12.1.2 Applicability

Project scoping and the processes outlined in the section are required for all

federal-aid projects and those state-aid projects that are developed to qualify as

federal-aid eligible.

Project Scoping

Federal-aid State-aid / VDOT

Maintained

State-aid / LPA Maintained

X * * * Formal project scoping and coordination with VDOT is strongly encouraged for all projects. All projects must consider bicycle and pedestrian accommodations.

Special Program Requirements are noted at the end of each section.

12.1.3 Scoping Process Requirements

Project scoping is the first major project development phase milestone. During this

time the project purpose is refined and all available data related to the project such

as old plans, aerial photos and any miscellaneous documents are gathered. The

project team is also finalized. Each discipline represented on the project team

investigates the proposed project from the perspective of their discipline.

In accordance with Commonwealth Transportation Board’s (CTB) Policy, approved

on March 18, 2004, all projects shall consider the accommodation of

bicycles and pedestrians at the project scoping stage. Resources

regarding Bicycle and Pedestrian Facilities can be accessed at

http://www.virginiadot.org/programs/bk-default.asp (Biking and Walking in Virginia).

Determination of bicycle and pedestrian accommodations must be documented in

the project file.

When the scoping meeting is held, the LPA Project Manager and the project team

will present and discuss their respective project findings. The LPA Project Manager

Page 7: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-6 December 2017 Project Development

will consolidate the findings into a scoping report for submission to the VDOT Project

Coordinator for review.

Scoping must be completed within twelve months of execution of

the project administration agreement unless concurrence is

otherwise obtained from the District. Failure to complete scoping

within this time frame may result in the reevaluation of the locality’s ability to

administer the project in accordance with the Project Administration

Agreement.

By the end of project scoping, the LPA is required to prepare and submit

to the Project Coordinator a scoping report which includes the following:

Define project limits

Identify project issues that may affect project development, such as

environmental issues, right of way, design, utilities, construction, etc.

Finalize the purpose and need of the project

Refine preliminary project estimates to develop the initial construction cost

estimate

Identify project risks (cost, quality, safety, etc.) and develop risk mitigation

strategies

Finalize a project schedule (each team milestone should be clarified with all

team members and reviewed to ensure commitment). For additional

information on project scheduling see Section 12.3.3.

Determine the level of citizen involvement and level of NEPA documentation

required

Determination of Bicycle – Pedestrian Accommodations in accordance with

CTB Policy

For federal-aid bridge projects, preliminary touch-down points and the most

recent bridge inspection report (for bridges maintained by the LPA)

For SMART Scale funded projects, the scoping report will include a

certification statement that indicates either of the following statements:

Page 8: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-7 December 2017 Project Development

o No changes or additions in scope have been made since the

application for SMART Scale funds was submitted that will impact the

project benefit regardless of impact to budget.

<OR>

o Scoping changes did occur and the project was re-evaluated and re-

scored if necessary.

The PM-100 and accompanying functional area scoping worksheets may be used by

the LPA to document project scoping; however, VDOT signatures are not

required. The information necessary to meet scoping report requirements may be

contained within the application for projects requiring separate project applications,

such as TA or HSIP Projects.

VDOT Responsibilities:

Determine if the project will be developed as a Tier 1 or Tier 2

project.

The Project Coordinator will review the submitted scoping report and

ensure that it addresses all scoping needs as identified above.

If the project has not been created in the project pool, the Project

Coordinator will create a project at this time and will include

appropriate VDOT staff as team members in the iPM

Communications and Divisions tab.

All project decision or milestone-related documents, including the

scoping report, must be uploaded into the iPM documents tab.

The Project Coordinator will upload the initial scoping estimate into

PCES.

The Project Coordinator will enter milestone dates using the Project

Schedule based on the information provided by the LPA. Milestone

dates required are found in Section 12.3.3.

Oversight expectations for Project Development and preliminary

oversight expectations for Project Delivery will be identified and

provided to the LPA.

Page 9: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-8 December 2017 Project Development

Discussion of any potential project costs which may be ineligible for

reimbursement

The Project Coordinator will provide project scoping and

environmental documents to Civil Rights for review to ensure

compliance with Title VI

Page 10: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-9 December 2017 Project Development

Special Program Requirements

Transportation Alternatives Projects

Project Sponsors of TA Projects are required to submit quarterly status

reports, to their VDOT Project Coordinators, in order to ensure projects are

progressing appropriately toward their required four-year completion period.

These reports are due in January, April, July, and October and should identify

the critical milestones completed to date, as well as any delays or difficulties

encountered. The quarterly report may be accessed on the LAD external

forms site.

Urban Construction Initiative

UCI Municipalities are required to submit Life to Date Project Summary

Schedules with each federal reimbursement request for UCI Projects. These

summary schedules should be submitted every 30 days to the VDOT Project

Coordinator or as frequently as invoicing VDOT for federal reimbursement. In

addition, an Annual Project Financial Status Report should be provided to the

Local Assistance Division (LAD) in order to ensure projects are progressing

appropriately and to identify project costs and expenditures. The Annual

Project Financial Status Reports are due on August 31st of each year.

Additional information regarding the Life to Date Project Summary Schedule

Reports and the Annual Project Financial Status Reports can be found in

Appendix N of the Urban Construction and Maintenance Manual (aka Urban

Manual).

Page 11: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-10 December 2017 Project Development

12.1.4 Key Submittals / Requirements Task/Submittal/File

Documentation Locality

Responsibility (PM) VDOT PC

Responsibility Submittal Timing/

Recordkeeping Requirements

Review project and solicit information relative to project to establish project team

Determine what information is needed in coordination w/PC

Assist the PM Document the Project Team in iPM.

N/A

Plans, maps, aerials, and other supporting data to identify project area

Distribute materials to the project team

N/A

Not less than 15 days in advance of the scoping meeting

Scoping Coordination or Meeting

Plan, lead, and facilitate scoping coordination or a meeting, if held

The PC may attend if project complexity warrants

N/A

Determine scope and develop complete schedule, and project budget

Prepare and submit Scoping documentation to the PC and project team

Ensure documentation is uploaded to iPM Documents

LPA should retain through project closeout. For state aid projects, documentation must be kept in LPA project files.

Review and outline all tasks and deliverables necessary for project development

Prepare and submit schedule, with milestone dates to the PC

Document tasks and durations in the iPM Schedule. Monitor and update schedule based on locality input.

N/A

Scoping estimate Provide accurate project scoping estimate in PCES

Ensure project estimate is entered and updated in PCES

N/A

Quarterly Status Report – TA Projects

Submit to Project Coordinator

Ensure documentation is uploaded to iPM Documents

N/A

12.1.5 References

VDOT has an established scoping process that is used for VDOT administered

projects. This process includes helpful information such as checklists and forms that

may be beneficial for the project scoping process. The process is outlined in two

procedures, Initiate Project Scope and Final Project Scope. The LPA is encouraged

to use these reference documents as they move through the project scoping

process.

Page 12: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-11 December 2017 Project Development

Chapter 12.1 – Project Scoping Checklist These checklists can be found in their entirety in the VDOT on line forms library

CH 12.1 - Project Scoping

The project scope, developed by the project team under the leadership of the LPA Project Manager, defines the physical limits and features of the project, establishes the project budget and determines the project oversight level in accordance with Ch 9.4.2 and VDOT Central Office oversight in accordance with IIM-226.5.

SUBMIT COMPL F S-V S-L T-A UCI Requirement Reference LAP Other

X X1 X

1 X

1 X Project Scoping; include

discussion of all tasks and deliverables, project limits and footprint

12.1.1 12.1.3

X X X X X Develop Project budget and Project Cost Estimate

12.1.3

X X X X X Develop Project schedule 12.1.3

X X X X X Submit Scoping Report and documentation

2, includes

items outlined in 12.1.3. Project scoping should be completed within 12 months of the Project Agreement being executed.

12.1.3 2.7(b) 23CFR652.565

1 Formal project scoping and coordination with VDOT is strongly encouraged for all projects

2CTB Policy on Bicycle / Pedestrian Accommodations must be considered and submitted for all projects; a

complete scoping report is required for any federal-aid project

Page 13: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-12 December 2017 Project Development

12.2 PLAN DESIGN

This chapter includes the following topics

12.2.1 Introduction

12.2.2 Applicability

12.2.3 Design Standards

12.2.4 Design Exceptions and Waivers

12.2.5 Design Elements

12.2.5.1 Title Sheets

12.2.5.2 Surveys

12.2.5.3 Geotechnical Investigations

12.2.5.4 Traffic Control Devices / Intelligent Transportation Systems (ITS) /

Roadway Lighting

12.2.5.5 Americans with Disabilities Act (ADA)

12.2.5.6 Hydraulics

12.2.5.7 Landscaping

12.2.5.8 Transportation Management Plans (TMP)

12.2.5.9 Noise Barriers

12.2.5.10 Value Engineering

12.2.5.11 Constructability Reviews

12.2.5.12 Utilities

Plan Design Checklist

Page 14: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-13 December 2017 Project Development

12.2.1 Introduction

Plan Design is considered part of Preliminary Engineering (PE), which includes all

work from preparation of feasibility studies, conceptual, preliminary and final designs

up through and including the preparation of bidding documents. This chapter

outlines design standards, provides links to relevant VDOT guidelines and

addresses considerations for key design elements.

All final plans and specifications shall be sealed and signed by a Professional

Engineer, Landscape Architect or Land Surveyor licensed to practice in the

Commonwealth of Virginia and in accordance with State Department of Professional

Occupation Regulation (DPOR) requirements.

12.2.2 Applicability

Processes in this manual apply to federal-aid projects, projects on the NHS

and Primary Routes, and projects to be maintained by VDOT, regardless of

funding.

State-aid projects, off the NHS and maintained by the LPA, will be designed

in accordance with this manual; however, VDOT oversight of these designs is

limited to technical assistance as requested by the LPA.

Plan Design

Federal-aid State-aid / VDOT

Maintained

State-aid / LPA Maintained

X X X* * Projects are to be designed in accordance with this manual; however, VDOT oversight to these designs is limited to technical assistance as requested by the LPA

Special Program Requirements are noted at the end of each section.

Page 15: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-14 December 2017 Project Development

12.2.3 Design Standards

VDOT has adopted the AASHTO A Policy on Geometric Design of Highways and

Streets, commonly referred to as the AASHTO “Green Book,” as minimum design

standards. VDOT’s Road Design Manual meets, or exceeds, all AASHTO Green

Book design standards.

All LPA administered projects to be maintained by VDOT, regardless of funding

source, shall be designed in accordance with VDOT’s Road Design Manual or seek

a design waiver and/or design exception.

VDOT publishes a series of Instructional & Information Memoranda as well as other

Manuals and Guides, which provide additional guidance and clarification regarding

design standards. Local governments are encouraged to use these as additional

resources when considering the design features of their projects to ensure

consistent state-wide design.

All LPA administered projects to be maintained by the LPA shall be designed in

accordance with AASHTO’s Policy on Geometric Design of Highway and Streets

(the “Green Book”) or seek a design exception.

LPAs may develop their own design standards and construction specifications,

which meet or exceed VDOT and AASHTO. However, they must be reviewed and

approved by the VDOT State Location and Design Engineer for projects off the

National Highway System, and also by FHWA for projects on the National Highway

System. Local governments are expected to notify the VDOT Project Coordinator

whenever alternative designs and specifications are being utilized and provide a list

of the proposed modified designs and specifications and how those modifications

differ from VDOT’s.

Page 16: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-15 December 2017 Project Development

For projects to be maintained by VDOT, the LPA Project Manager shall

provide the VDOT Project Coordinator a complete electronic plan assembly

in single page PDF format to be filed in the VDOT Plan File Library when:

right of way plans have been completed and approved for right of way

acquisition

project design plans have been completed and approved to advertise

12.2.4 Design Exceptions and Waivers

Design Waivers

Designs for projects maintained by VDOT that do not meet VDOT’s “minimum”

design standards, but exceed AASHTO’s design standards require a written Design

Waiver. The LPA or its consultant shall prepare and submit the Design Waiver Form

(LD-448)

and any accompanying documentation to the VDOT Project Coordinator as soon as

it becomes apparent that a waiver is required. The design waiver review process

should take approximately two (2) weeks from the time of receipt of a complete

submittal. The VDOT Project Coordinator will forward the design waiver to the

District Location and Design Engineer for review and action (approval or denial).

Once the review has been completed and action taken, the Design Waiver request

will be sent back to the VDOT Project Coordinator for coordination with the Locality

LPA Project Manager. Design waivers are not required on projects that will be

maintained by the locality.

For more information on the Design Waiver process for road projects, refer to LD-

IIM-227.

Page 17: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-16 December 2017 Project Development

VDOT Responsibilities:

Design Waivers are processed at the District Location and Design

Office.

The VDOT Project Coordinator will forward the Design Waiver

request to the District Location and Design Engineer for review and

action (approval or denial).

The VDOT Project Coordinator will notify the LPA of the decision.

All documents relating to the Waiver and the approval notification

must be uploaded into iPM.

Design Exceptions

Designs that do not meet the minimum design standards contained in the AASHTO

“Green Book” require a written Design Exception. The locality or its consultant shall

prepare and submit the Design Exception Form (LD-440) and any accompanying

documentation to the VDOT Project Coordinator as soon as it becomes apparent

that an exception is required. The design exception review process should take

approximately two weeks from the time of receipt of a complete submittal.

VDOT Responsibilities:

VDOT Project Coordinator will forward the Design Exception request

through the District L&D Section, to the State Location and Design

Engineer for review and action (approval or denial). Once the review has

been completed and action taken, the Design Exception request will be

sent back to the VDOT Project Coordinator for coordination with the LPA

Locality Project Manager.

All documents relating to the Exception and the approval notification

must be uploaded into iPM by the PC.

The Design Exception Form can be accessed at: LD-440

Page 18: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-17 December 2017 Project Development

For more information on the design exception process for road and bridge projects,

refer to LD-IIM-227.

Page 19: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-18 December 2017 Project Development

12.2.5 Design Elements

The following is a list of design elements that are typically required in a set of

roadway and bridge plans:

12.2.5.1 Title Sheets

VDOT prepared Title Sheet templates for Federal-aid Tier 1 and Tier 2 Projects and

for State-aid Projects shall be used. LPA’s are responsible for ensuring that the

most current version of the applicable title sheet is being used in the plan assembly.

Title sheet templates for Federal-aid Projects Tier 1 and Tier 2 Projects and State-

aid Projects are available in the VDOT CADD Cell Library. The specific file links are

below:

TIER 1 TITLE LAP FED TIER 2 TITLE LAP FED TITLE LAP STA

In addition, VDOT has prepared title sheets to be specifically used with Design-

Build/PPTA projects. These include a RFQ/RFP Plans Submittal title sheet, a Right

of Way Submittal title sheet, a Construction Submittal title sheet and an As-Built title

sheet. The specific file links are:

TITLE LAP DB (RFP/RFQ) TITLE_LAP_DB_ROW TITLE_LAP_DB_CONST TITLE_LAP_DB_ASB (As-Built)

For assistance, LPA’s or design firms should contact the CADD Support Helpdesk at

[email protected] .

For information on Title Sheet requirements, refer to IIM-LD-204.

LPA’s are responsible for ensuring that title sheets have the required signatures and

that project plans are properly signed and sealed in accordance with Department of

Professional and Occupational Regulations (DPOR). For information on Sealing and

Signing Requirements/Title Sheet Signatures, see Section 12.5.3.

Page 20: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-19 December 2017 Project Development

Special Program Requirements

Transportation Alternatives

All trail, roadside, and bridge plans must be reviewed by the Department; however,

Transportation Alternatives / Enhancement projects do not require Department

signatures on the title sheet. When plans are submitted for review, the title sheet

should include the project name, state / federal project numbers, local signature

boxes, and a professional engineer’s seal. It should also specify the standards and

specifications under which the project is to be constructed; but they should not be

submitted for VDOT signature.

Urban Construction Initiative

UCI projects do NOT require VDOT signatures on Title Sheets. The Title Sheet

must be signed by a person of responsible charge with the municipality. By this

signature, the municipality is certifying that the plans have been prepared, by staff or

consultants, to an appropriate level of completion and accuracy, that the designer

has followed accepted standards, procedures, policies, methods of practice, etc.,

that are consistent with the engineering and design of plans for such work.

12.2.5.2 Surveys

The first step in physical project development is identifying the project site. In some

cases the land may be owned by the State or local government. In other cases, it

may be necessary to purchase land for the project. In those cases where the land is

already owned by state or local government, it will be necessary to conduct project

design surveys to specify where the new construction will take place.

Survey Procedures

Section 33.2-1011 of the Code of Virginia requires that advance notice be provided

to property owners prior to entering their property to ascertain its suitability for

Page 21: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-20 December 2017 Project Development

highway purposes. VDOT’s Survey Manual, which can be accessed at

http://www.virginiadot.org/business/locdes/manual-survey-index.asp, is a resource

for local governments and outlines VDOT’s business practices regarding survey. A

copy of VDOT’s form letters is available from the Right of Way and Utilities

Management System (RUMS) forms repository.

Project design surveys – The purpose of a project design survey is to identify the

project site sufficiently to allow the development of detailed engineering plans,

specifications, and cost and material quantity estimates. Project design surveying

must be performed under the supervision of a Land Surveyor (LS) licensed to

practice in the Commonwealth of Virginia by the Virginia Department of

Occupational Regulation (DPOR). Project design surveys often involve aerial

mapping and Global Positioning Survey (GPS) techniques, as well as placement of

physical markers. In addition to the project design survey, a survey will be needed

for the purposes of legal title transfer.

If the project is on state property, right of entry will be allowed under the project

administration agreement. Before a LPA can begin work (including surveying) on a

roadway that is part of the interstate, primary or secondary system of highways, it

must secure a land use permit from VDOT. This permit is issued through the VDOT

Residency and usually will be issued at no cost.

Survey for land acquisition and title transfer - If the LPA is purchasing land for the

transfer to state ownership (underlying fee ownership) or for a federal aid project, the

requirements outlined in VDOT’s survey manual must be followed. If the LPA is

purchasing land for the locally maintained system without federal funds, the LPA can

follow its own survey and title requirements.

12.2.5.3 Geotechnical Investigations

LPA’s are required to provide geotechnical engineering data consistent with the

requirements outlined in the Materials Manual of Instructions, Chapter 3. Local

Page 22: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-21 December 2017 Project Development

jurisdictions shall coordinate with the VDOT Project Coordinator in advance of

performing subsurface exploration. Laboratory testing for VDOT projects requires

that the testing laboratory be certified by the AASHTO Materials Reference

Laboratory (AMRL). Chapter 3 of the Manual of Instructions can be accessed at the

following link:

http://www.virginiadot.org/business/resources/bu-mat-MOI-3.pdf

The use of alternate bid items or speculative amounts in the bidding process is

generally NOT an acceptable replacement for complete geotechnical investigations.

12.2.5.4 Traffic Control Devices/Intelligent Transportation Systems (ITS) /

Roadway Lighting

VDOT’s Traffic Engineering Design Manual, which can be accessed at

http://www.virginiadot.org/business/locdes/traffic-engineering-manual.asp, is VDOT’s

standard and recommended for design elements related to traffic control devices,

ITS and Roadway lighting.

12.2.5.5 Americans with Disabilities Act (ADA)

The Americans with Disabilities Act of 1990 (ADA) is legislation intended to provide

adequate accessibility to all persons. Title II of ADA applies to State and Local

Governments and its requirements affect design, construction and maintenance of

all transportation projects, regardless of the funding source.

VDOT’s policy is to provide facilities for persons with disabilities in accordance with

the Code of Virginia, Section 15.2 –2021.

For more information on ADA requirements related to transportation facilities, refer

to LD-IIM-55.

Page 23: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-22 December 2017 Project Development

The ADA requires that all new construction, reconstruction and alterations to

existing pedestrian facilities be constructed in accordance with federal accessibility

standards. Pedestrian facilities include sidewalks, shared use paths or other public

walkways. Where such facilities intersect a street, the portion of the street used by

pedestrians, whether marked as a crosswalk or not, is also considered part of the

pedestrian facility.

Project activities are considered an “alteration” if they involve changes to the

structure, grade, function or use of the street or sidewalk. Examples include full

depth pavement replacements, widening, resurfacing, signal installation, pedestrian

signal installation and other work of similar scale and effect.

When the scope of a transportation project includes modifications to existing

pedestrian facilities, those facilities must be brought up to current accessibility

standards. For example, if a street resurfacing project alters the sidewalk, curbs or

street surface in the crosswalk area, curb ramps must be installed as part of the

project. If curb ramps already exist, but do not meet the current accessibility

standards, those ramps must be either reconstructed or retrofitted to meet the

current accessibility standards.

FHWA and the Department of Justice (DOJ) issued a Joint Technical Assistance

(JTA) memorandum on the requirements to provide curb ramps, in accordance with

Title II of the ADA, whenever roads are altered through resurfacing. The JTA

memorandum clarifies the definition of an “alteration” during road surfacing activities,

requiring compliance with Title II of the ADA. The memorandum can be accessed

at http://www.ada.gov/doj-fhwa-ta.htm. Also, see TE-377 for additional information.

12.2.5.6 Hydraulics

All projects that will be maintained by VDOT, except those improvements

undertaken through the Rural Rustic Roads program, must be designed in

accordance with VDOT’s Drainage Manual, which can be accessed at

Page 24: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-23 December 2017 Project Development

http://www.virginiadot.org/business/locdes/hydra-drainage-manual.asp, and is

available as a resource for local governments.

12.2.5.7 Landscaping

It is recommended that all Landscape Plans, which will be maintained by the

Department, be designed in accordance with VDOT’s Guidelines contained in

Appendix B (1) of the Road Design Manual as well as LD-IIM-253.

12.2.5.8 Transportation Management Plans (TMP)

23 CFR 630 Subpart J, also referred to as the Work Zone Safety and Mobility Final

Rule, applies to all State and local projects that receive Federal-aid highway funding

and provides a decision-making framework known as Transportation Management

Plans (TMP) that consider broader safety and mobility impacts of work zones across

project development stages, and the adoption of additional strategies that help

manage these impacts during project implementation. The TMP is not a separate

document, but is used in the development of traffic control in construction plans. A

TMP is a set of strategies which working together, should improve the safety and

functionality of temporary traffic control during construction. These strategies are

divided into three broad groups which are captioned as: 1) Temporary Traffic

Control, 2) Public Information; and 3) Transportation Operations. The degree of a

project’s TMP requirements is based on the project’s level of complexity. VDOT’s

guidelines categorize a project into one of three types of transportation

management. The Guidelines are available at:

http://www.extranet.vdot.state.va.us/locdes/electronic_pubs/iim/IIM241.pdf

12.2.5.9 Noise Barriers

When warranted based on noise analysis, noise wall profiles should be included in

the plans. Most noise barriers are designed by the contractor with local review and

approval on the locally maintained system. VDOT concurrence is required on roads

that will be maintained by the Department.

Page 25: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-24 December 2017 Project Development

12.2.5.10 Value Engineering

Federal regulations outline requirements for Value Engineering (VE) studies and the

Code of Virginia requires a VE study on all projects exceeding $5 million in

construction cost. The locality will complete the VE process and, all

recommendations must be submitted to VDOT. The final decision as to which

recommendations are incorporated into the final plans is made by the Chief

Engineer for all federal aid projects and any project to be maintained by VDOT.

VDOT has a VE team which is available to assist, guide or lead LPAs in the

development of the VE process and or study. Additional information regarding value

engineering studies can be found on the VDOT Value Engineering Web site.

Special Program Requirements

Urban Construction Initiative

For UCI Projects, the municipality will oversee and perform the value engineering

process. Final decisions regarding which recommendations are incorporated into

the project will be made by the municipality’s person of responsible charge. A final

copy of the VE study must be submitted to the VDOT project coordinator for record

keeping purposes; however, no VDOT action is necessary.

12.2.5.11 Constructability Reviews

The purpose of a constructability review is to determine if a project can be

constructed as designed with the information provided on the drawings,

specifications and copied notes.

Constructability reviews shall be conducted by the LPA for all projects to be

maintained by VDOT and for federal aid projects. Constructability reviews are

recommended for any other projects on the locally maintained system. Additional

Page 26: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-25 December 2017 Project Development

information on performing constructability reviews can be found in VDOT’s Road

Design Manual, Chapter 2G-5.

12.2.5.12 Utilities

Private utility companies may be reimbursed for relocating utilities that are in conflict

with the project, at project expense, when they have been located on easement or

have prior rights in the existing location. It is also recognized that some localities

have franchise agreements with utility companies that require the company to move

its utility because of a project, at the company’s expense. In that case, the locality

shall enforce the terms of its agreements in order to save project funds. Utility

relocations have to be viewed as regional efforts, since all utility relocations within a

region compete for a utility’s time and resources. Early coordination with utility

owners is highly recommended.

In order to pay for utility adjustments as a project expense, a detailed utility plan and

cost estimate needs to be prepared. Eligible project expenses for utilities basically

result in the in-kind replacement of any utilities that are in conflict with the project.

Any county without an existing utility franchise agreement when administering a

VDOT sanctioned project under a land use permit or transportation project

agreement shall have the same authority as the Department pertaining to the

relocation of utilities. In accordance with the above, it is recognized that in some

instances the locality’s utility facility owner may want to provide upgraded utilities or

to install new utilities while the highway is being disturbed for construction purposes.

This is known as “betterment,” and is generally not an eligible project cost. It makes

sense to perform betterment work at the same time the project is being constructed,

so the contractor may perform the work during construction, with the utility facility

owner being responsible for the cost of the betterment portion from a different

funding source. For information pertaining to local participation in the cost of utility

adjustments and storm sewer improvements (betterment), see IIM-LD-146.

Page 27: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-26 December 2017 Project Development

VDOT’s Right of Way and Utilities Manual, Volume II

(http://www.virginiadot.org/business/row-default.asp) provides additional references

to the processes and procedures regarding utility relocations and betterments.

Page 28: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-27 December 2017 Project Development

Chapter 12.2 – Plan Design Checklist

These checklists can be found in their entirety in the VDOT on line forms library

CH 12.2 - Plan Design

Plan Design is considered part of Preliminary Engineering (PE), which includes all work from preparation of feasibility studies, conceptual, preliminary and final designs up through and including the preparation of bidding documents. This chapter outlines design standards, provides links to relevant VDOT guidelines and addresses considerations for key design elements.

SUBMIT COMPL F S-V S-L T-A UCI Requirement Reference LAP Other

X X -- X -- Design meets VDOT Standards 12.2.3

X X X X X Design meets AASHTO Standards 12.2.3

X X -- X X Approved plans submitted electronically (PDF format) at advertisement

12.2.3

X X X X X LD-440 for Design Exception (to AASHTO standards)

12.2.4

X1 X -- X -- LD-448 for Design Waiver (to VDOT

Standards) 12.2.4

X X -- X --

Use VDOT prepared title sheet templates

12.2.5.1

X X X X X Compliance with Americans with Disabilities Act (ADA)

12.2.5.5

X X -- X X Preparation of TMP 12.2.5.8

X X X X X Value Engineering for Projects over $5 million

12.2.5.10

X X -- X X Conduct constructability review 12.2.5.11

1 Federal-aid projects on locally maintained roads do not require design waiver; AASHTO is minimum standard

Page 29: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-28 December 2017 Project Development

12.3 PROJECT BUDGET, SCHEDULE, AND ESTIMATES

This chapter contains the following topics:

12.3.1 Introduction

12.3.2 Applicability

12.3.3 Project Schedules

12.3.4 Project Budgets and Estimates

12.3.4.1 Project Budgets

12.3.4.2 Project Estimates

12.3.4.3 Quantity Summaries/Engineer’s Estimates (prior to

advertisement)

12.3.5 Tasks / Submittals / File Documentation

12.3.6 References

Budget, Schedule and Estimates Checklist

Page 30: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-29 December 2017 Project Development

12.3.1 Introduction

This chapter outlines the actions required to develop, update and monitor project

development schedules, estimates and budget. The LPA’s Project Manager is

responsible for the development and management of the schedule, estimates and

budget for Preliminary Engineering, Right of Way and Construction throughout the

entire project life cycle. It is critical that both schedules and estimates be updated

regularly within VDOT’s systems (iPM Schedule and PCES), because they are

utilized for developing our annual federal strategy for obligation of funds.

Project scheduling is essential in monitoring and managing project development. At

project scoping, a schedule must be established reflecting key milestones in project

development. As these milestones are met, or when the timeframe must be

changed, the schedule must be updated and documented in the iPM Schedule by

the VDOT Project Coordinator.

Estimates must be current and maintained in VDOT’s Project Cost Estimating

System (PCES). The purpose of PCES is to collect data for a specific project and,

based on the data entered; determine a budget for that project. Project budgets

should be reviewed and estimates must be updated at every project milestone.

Project budgets will be affected by significant changes in the project scope and or

schedule and should be updated accordingly.

12.3.2 Applicability

Accurate schedules and estimates should be established and updated regularly for

all project categories by the locality, in coordination with their VDOT Project

Coordinator.

Project Budget, Schedule, & Estimates

Federal-aid State-aid / VDOT

Maintained

State-aid / LPA Maintained

X X X

Page 31: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-30 December 2017 Project Development

Special Program Requirements are noted at the end of each section.

12.3.3 Project Schedules

Every project requires a schedule and the LPA Project Manager is responsible for

the overall development and management of the project schedule with collaboration

and support from project team members. Scheduling encompasses a combination

of required tasks and project information to relate unique project characteristics with

available resources and time requirements. A complete project schedule should be

developed during the scoping process with input from the team members. The

number of tasks required in the schedule will depend on the complexity of the

project.

A Schedule Tool is available and recommended for LPA use that will accommodate

the majority of project types and varying circumstances. The schedule tool uses

default “typical” tasks and durations which can be modified to fit individual project

needs. The Schedule Tool utilizes basic scheduling logic to develop a realistic

schedule that correlates with the VDOT local project scheduling templates.

The LPA Project Manager shall submit, as part of the scoping package, a final

baseline project schedule to include at a minimum the following key milestone dates:

Scope Project

Project Definition Form (EQ 429) Submittal , when applicable

NEPA Document Completion

Right of Way & Utilities Federal Authorization Request / Submission of complete

R/W Plans and RW301/EQ201

Right of Way Acquisition start date (when applicable)

Permit Acquisition (when applicable)

Advertisement Date

Page 32: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-31 December 2017 Project Development

VDOT’s strategy for the expenditure of federal funds is prepared

utilizing the project schedule and key milestone dates for preliminary

engineering, right of way and construction that is developed during the

scoping process for each project. It is critical that the locality develops and

submits realistic dates for each of these phases. Annually VDOT submits its

expenditure strategy to FHWA with the expectation that localities will meet the

projected dates. Localities are accountable for meeting the submitted

schedule, and failure by the LPA to meet project schedules may risk future

funding for locally administered projects.

VDOT Responsibilities:

The Project Coordinator will enter, monitor and maintain the following key

milestones in the iPM Schedule module at the beginning of the project:

Scope Project (22)

Environmental Review Process (17E) when applicable

SERP (18) when applicable

Authorize R/W and Utilities (52)

Plan Submission Date (PS&E Submittal Date) (72X)

Environmental Reevaluation (66)

Construction Authorization (79)

Advertise Project (80)

The Project Coordinator or VDOT Construction Project Monitor, as

applicable, will input the following dates for tracking purposes within 10

business days of completion of the activity:

Award Contract (84)

Administer Contract (Construction start and complete dates) (91).

After construction completion and submission of C-5, project status

changed to ‘Construction Complete’ and dates entered in the Project Pool.

Page 33: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-32 December 2017 Project Development

12.3.4 Project Budgets and Estimates

12.3.4.1 Project Budgets

The LPA is fully responsible for monitoring the project budget. When estimates (see

section 12.3.4.2 below) identify a budget shortfall, the LPA Project Manager must

identify available funding sources. If additional funding is necessary, the VDOT

Project Coordinator must be notified so that the Project Administration Agreement

can be modified and any impacts to the SYIP or SSYP can be addressed.

The federal obligation strategy is based on schedules and estimates provided by

LPAs for LPA administered projects. LPAs are expected to meet the schedule to

ensure that federal obligations are not lost. The VDOT Project Coordinator has the

responsibility, after consultation with the LPA Project Manager, to delay scheduled

activities, if in the Project Coordinator’s judgment; the schedule is unrealistic and will

have an adverse impact on the federal obligation strategy or the funding program.

VDOT Responsibilities:

Schedules and estimates for locally administered projects must not be

changed without the locality’s concurrence. However, when the

schedule is unrealistic and may create funding problems, the Project

Coordinator may request that the schedule be modified. Any

modifications must first be discussed with the LPA Project Manager

and coordinated through the District Planning and Investment Manager

and Central Office Infrastructure Investment Division.

Authorization to begin activities in each phase will not be issued until

the phase is fully funded or funds to complete the phase have been

identified.

When projects are “limited funding,” that is the project will not receive

additional federal or state-aid, the LPA is responsible for securing

additional funding necessary to complete the phase/project and

identifying the funding in the project administration agreement.

Page 34: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-33 December 2017 Project Development

12.3.4.2 Project Estimates

The LPA is required to provide a revised project estimate at key project milestones

and as necessary when the project estimates change due to scope, funding or other

modifications. The LPA may use VDOT’s estimating system (PCES) or their own;

however, all estimates must be included in PCES. For LPAs that use their own

estimating systems, the estimate can be manually uploaded into PCES. When

uploading estimates to PCES, the PCES Alternate Right-of-Way Worksheet and/or

Alternate Utilities Worksheet must be used. The use of a lump-sum estimate is not

adequate for submittal to FHWA for RW authorization.

The LPA Project Manager is responsible for preparing and uploading the project

estimate in PCES. In doing so, the locality must select the current milestone stage

using drop-down selection and recommended estimate in PCES at the intervals

stated in the previous paragraph.

The PCES system will automatically generate a budget adjustment revision request

if the updated project estimate results in a 10 percent increase or decrease or a

difference of $50,000 or more.

Special Program Requirements

Urban Construction Initiative

UCI Municipalities have access to VDOT’s PCES and are expected to enter project

estimates.

Page 35: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-34 December 2017 Project Development

12.3.4.3 Quantity Summaries / Engineer’s Estimates (Prior to Advertisement)

Quantity summaries should be computed and developed utilizing quantity take-offs

from the plans. An accurate summary of quantities is critical to prospective

contractors interested in submitting a bid on the project. This information leads

directly to the Engineer’s Estimate, which combines the computed quantities of work

and the estimated unit bid prices. The Engineer’s Estimate should be updated, as

necessary, up until the bids are opened.

12.3.5 Key Submittals / Requirements Task/Submittal/File

Documentation Locality

Responsibility VDOT Project Coordinator

Responsibility

Submittal Timing/ Recordkeeping Requirements

Establish project schedule

Develop and provide a project schedule to include all tasks needed to complete the project to the VDOT Project Coordinator.

Enter appropriate milestones dates in the iPM Schedule.

After completed scoping process

Maintain project schedule

Provide the VDOT Project Coordinator with schedule changes in a timely manner. Provide the VDOT Project Coordinator dates scheduled tasks are completed in a timely manner.

Monitor and update the project schedule in iPM, as appropriate based on input from the LPA Project Manager.

N/A

Provide timely and accurate estimates in PCES

Enter the project estimate in PCES and update

Review estimates and provide technical assistance

At key project milestones or as necessary

12.3.6 References

Project Cost Estimates - 23 CFR 630 (a) (4)

Project Development Schedules -

http://www.virginiadot.org/business/resources/Project_Development_Schedules.pdf

Project Development Budget and Estimates -

Page 36: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-35 December 2017 Project Development

http://www.virginiadot.org/business/resources/Project_Development_Budget_and_E

stimates.pdf

PCES Users Guide - http://isyp/scoping/docs/PCES.pdf

Page 37: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-36 December 2017 Project Development

Chapter 12.3 – Budget, Schedule and Estimates Checklist These checklists can be found in their entirety in the VDOT online forms library

CH 12.3 - Budget, Schedule & Estimates

The LPA is responsible for the development and management of the schedule, estimates and budget for Preliminary Engineering, Right of Way and Construction throughout the entire project life cycle.

SUBMIT COMPL F S-V S-L T-A UCI Requirement Reference LAP Other

X X X X X Submit schedule related forms as part of the scoping package

12.3.3

X X X X X Submit updated schedule at key milestones and as needed

12.3.3

X X X X X Submit updated project estimates at key milestones and as needed

12.3.4

Page 38: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-37 December 2017 Project Development

12.4 PUBLIC INVOLVEMENT

This chapter includes the following topics:

12.4.1 Introduction

12.4.2 Applicability

12.4.3 Purpose of Public Participation

12.4.4 Types of Public Involvement

12.4.5 Public Participation Requirements

12.4.6 Public Participation Procedures

12.4.7 Transcript of Public Hearing

12.4.8 Location and/or design approval for projects on which a hearing or

hearings are held

12.4.9 Location and/or design approval for projects on which a posting of

notice of willingness to hold a hearing

12.4.10 Tasks / Submittals / File Documentation

12.4.11 Regulatory References

12.4.12 Miscellaneous References

Public Involvement Checklist

Page 39: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-38 December 2017 Project Development

12.4.1 Introduction

This section discusses the processes and responsibilities associated with Public

Information and Participation for federal-aid projects. The final outcome of this

process should be that all projects are developed in a manner that provides the

general public with a well-publicized opportunity to both review and discuss the

proposed plans and potential impacts for the project.

During the development of transportation projects it is essential that public

participation be considered. LPA's have a responsibility to provide residents of their

community and other interested parties with an opportunity to participate, by

expressing their viewpoints and concerns, in the development of the project. It is

incumbent upon the LPA to include public participation opportunities before the

project has reached a point where it becomes impractical to make extensive

modifications. LPA's across the Commonwealth have robust public participation

processes in place for their land planning and zoning programs, and are encouraged

to broaden the scope of those existing processes to include transportation projects.

Public participation may range from individual meetings with affected residents to

informal community meetings or area wide project development workshops and

citizen information meetings to formal Public Hearings on a project. LPA's

undertaking transportation projects, whether the project is state funded or federally

funded, must adhere to the requirements outlined in this chapter for an opportunity

for a public hearing under certain circumstances.

Where a locally administered project requires the preparation of an Environmental

Assessment (EA) or Environmental Impact Statement (EIS), the LPA is required to

hold a public hearing on the project, in accordance with the requirements of this

chapter.

Page 40: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-39 December 2017 Project Development

12.4.2 Applicability

Federal-aid Highway Projects and State-aid Highway Projects that are NOT

federally exempt must follow the processes defined in this chapter.

State-aid Highway Projects that have a federal exemption must follow processes

defined in §15.2-2204, §15.2-2239, § 15.2-1800 and any other sections of the Code

of Virginia applicable to a LPA’s capital improvement program. The LPA will certify

adherence to those processes as noted in Chapter 5 (state funded projects) of this

manual.

Public Involvement

Federal-aid State-aid / VDOT

Maintained

State-aid / LPA Maintained

X * * * State-aid projects that are not federally exempt shall follow the processes applicable to Federal-aid

projects.

12.4.3 Purpose of Public Participation

Public Hearings and Public Information Sessions provide the general public with a

well-publicized opportunity to both review and discuss proposed plans for a highway

project. Project information should be provided in sufficient detail to allow property

owners along a project corridor or others with an interest in a project to identify

specific features or property that may be impacted by the proposal, discuss those

with a member of the project team and if necessary, provide a mechanism for the

expressing and documenting concerns or views related to the project.

VDOT’s Public Involvement Manual serves as an excellent resource for public

participation processes.

Page 41: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-40 December 2017 Project Development

12.4.4 Types of Public Involvement

Willingness to hold a public hearing - If a project is noncontroversial, does not

have the potential to substantially impact adjoining property, and is unlikely to

generate requests for a hearing, a willingness to hold a public hearing may be

used rather than scheduling a public hearing.

Individual (one-on-one) – When an interested party has requested that a public

hearing be held, often a separate meeting with that interested party can be held

to address concerns. If the interested party’s concerns are adequately

addressed, a separate public hearing is not required.

Formal Public Hearing – The formal public hearing process is conducted as a

structured meeting between the project team and public audience at a

designated time. The project team presents the project to the audience and then

the audience is provided an opportunity, one at a time, to respond with

comments and questions. All activities and comments are recorded and entered

into a hearing record. The record is held open for at least 10 days after the

hearing for additional written comments to be submitted. Prior to the formal

process individuals may discuss the proposed project with team members for an

one-on-one explanation and discussion about their specific concerns and

questions. Individuals have the opportunity to have their comments and

questions recorded verbally, in writing or delivered directly to the project team as

a part of the formal hearing activities.

Open Forum Public Hearing – The open forum public hearing is conducted in

an open meeting format. Individuals may arrive at various times, be given a brief

hearing orientation and directed to project team members for one-on-one

explanations and discussions about their specific concerns and questions.

Individuals have the opportunity to have their comments and questions recorded

verbally or in writing for the hearing record. No structured meeting is conducted

as part of the open forum public hearing.

Page 42: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-41 December 2017 Project Development

12.4.5 Public Participation Requirements

According to federal regulations found in 23 CFR 771.111(h)(2)(iii) one or more

public hearings or the opportunity for hearing(s) must be held for any federal-aid

project which requires: significant amounts of right-of-way; substantially changes the

layout or functions of connecting roadways or of the facility being improved; has a

substantial adverse impact on abutting property; otherwise has a significant social,

economic, environmental, or other effect; or for which FHWA determines that a

public hearing is in the public interest.

Federal-aid projects which are processed with a Categorical Exclusion (CE), or a

Programmatic Categorical Exclusion (PCE), by definition, have been found to not to

have any significant social, economic or environmental effects. When none of the

other criteria exist, and the document availability requirements for a public hearing

(PCE and CE) have been considered, then these projects may not require a formal

public participation or public hearing process. Anytime an environmental

assessment is necessary, a public hearing must be held or an opportunity for a

hearing must be offered.

LPAs must ensure that other Virginia Code requirements applicable to local

governments have been met. VDOT takes a more conservative approach in their

project administration by providing an opportunity for a public hearing for nearly all

construction projects.

The decision regarding the level of public involvement must be documented during

the scoping process with the concurrence of the VDOT Project Coordinator. The

burden of proof that a public hearing or an opportunity for a public hearing

(i.e. posting of a willingness) is not necessary, lies with the local government

administering the project and should be fully documented during the scoping

process. For example, a sidewalk construction project on existing right of way

would be an example of a project which does not normally meet the criteria for a

public hearing and may proceed without one provided the criteria that requires a

hearing is not met.

Page 43: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-42 December 2017 Project Development

The following are guidelines which may be used for determining when public

hearings are to be held, or when a "willingness to hold a public hearing" is sufficient.

They are:

Projects on roadway corridors, which are completely on new location, require a

location public hearing followed by a design public hearing.

Projects within the existing roadway corridor with a predominant portion of the work

on new location require a combined location and design public hearing.

Projects within the existing roadway corridor that have a significant social, economic

or environmental impact require a design public hearing.

Projects within the existing highway corridor where significant social or

environmental impacts, or both, are anticipated require publication of a notice of

willingness to hold a design public hearing. The locality will hold a design public

hearing if a request for such a hearing is made, and the issues raised in relation to

the request cannot be resolved through any other means.

When a significant period of time has passed since an initial public hearing or

willingness notification, the potential impacts of the project and the concerns of

affected citizens may change. Accordingly, there may be a need for additional

public participation. If changes in land use, population or impact to the environment

have taken place within the project area, a public hearing may be necessary.

VDOT Responsibilities:

Project Coordinator will review determination of public involvement

requirements at scoping.

12.4.6 Public Involvement Procedures

Public Notification – Public notices are published as a means to inform the public

of various proposals and invite public participation. Minimally, public notice in a

newspaper is required but additional methods should be pursued if the locality

believes that they will help in reaching the public and improve public involvement in

Page 44: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-43 December 2017 Project Development

the project. Methods of public notification for a public hearing or a willingness to

hold a public hearing include:

o Paid public notice must be made in a local newspaper – at least twice – the

first notice must appear 30 days before the hearing date and the second

notice between five days to twelve days before the hearing.

o News releases

o Letters to adjacent property owners

o Posting of notice in local businesses and public facilities

o Notifications of special interest groups and affected governmental agencies

o Signs and/or message boards within the project corridor or limits

o Postings on a public or project website

o Newsletters (project, home owners association, community, etc.)

Newspaper notification must include:

o Date, time, place and type of meeting

o Description of project

o Statement that tentative Project schedules will be discussed

o Right of way relocation and assistance information

o Statement of opportunity for written and oral comments

o Statement of availability of project information 30 days prior to the hearing

and the availability of the environmental assessment (EA) or draft

Environmental Impact Study (DEIS) (if Federally funded) at specified

locations prior to the hearing. Environmental information is to include 106

and Agricultural Forestal District statements

o Availability of project materials (plans, brochure and environmental

documentation

o Non- discrimination clause (found in Chapter 17)

When an Environmental Assessment (EA) or Environmental Impact Statement

(EIS) is required, it must be available for comment a minimum of 15 days prior to

the public hearing and must be available for review at the public hearing.

Comments must be accepted for 15 days after the public hearing if it was

Page 45: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-44 December 2017 Project Development

available 15 days prior. EAs only need to be available for a total of 30 days for

public comment.

EISs have additional public notice requirements that are beyond the scope of

discussion of this manual. When an EIS is necessary, the LPA will be required to

enter into a separate memorandum of agreement (see Chapter 15.2.1), which

will include public involvement requirements.

General - Because of the unique nature of highway projects, particularly the use

of many visual aids, plans and charts, it is recommended that public participation

activities be undertaken at a facility that can accommodate public review of these

items.

To encourage input from all interested parties, public hearings and the facilities

where they are held must:

o be ADA compliant

o accommodate the hearing impaired

o accommodate the visually impaired

In addition, the following are required:

o Public Hearings be preceded by a period where the public can review project

documents

o Provide for the recording of and/or transcription of verbal comments

o Public hearings are to remain open for an additional 10 calendar days after

adjournment in order to receive written comments (Note: Comment for

environmental assessments must be accepted for a total of 30 days).

VDOT Responsibilities:

Project Coordinator will review notice of public hearing or notice of

willingness to hold public hearing for federally funded projects.

Project Coordinator will review Project Information Sheet and coordinate

reviews, as needed, by District Preliminary Engineer and Public Affairs.

Page 46: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-45 December 2017 Project Development

12.4.7 Transcript of Public Hearing

Whenever a public hearing is held, a record of the hearing must be prepared to

provide documentation of the proceeding. The Transcript must include:

A title page including project information

table of contents,

Hearing details (date, time and location)

Sign in sheet

Oral comments

Written comments

Any other documents submitted for the record

Copy of public notice and documentation of public notification

Brochure

Reproductions of any other displays from the hearing

Copies of the transcript must be forwarded to the VDOT Project Coordinator and for

review and transmittal to FHWA and the Commonwealth Transportation Board as

appropriate.

VDOT Responsibilities:

Project Coordinator will review transcript and will process for approval

according to the 2 Tiered Approach to Project Oversight.

12.4.8 Location and/or design approval for projects on which a hearing or

hearings are held

After study of the comments received from the public, environmental considerations,

costs, design standards and the evaluations of any studies completed as a result of

the public involvement procedures, the transcript will be compiled. The transcript will

be summarized and issues addressed by the LPA Project Manager to develop a

recommendation. This recommendation will be to be forwarded by the VDOT

Project Coordinator to the District Administrator’s Designee for distribution to the

Page 47: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-46 December 2017 Project Development

appropriate approving authority in accordance with VDOT’s Tier 1/Tier 2 approval

processes and VDOT’s Public Involvement Manual, Location and/or Design

Approval Process Flow Charts (pages 42 and 43 of 89).

The District Administrator’s Designee will distribute the transcript, proposed

responses and recommendations to the appropriate VDOT contacts and decision

makers who will coordinate location/design approvals as required by state and

federal law.

Once the recommendation is approved, the LPA is encouraged to advise those who

provided comments during the public hearing. This response should note any

changes in the proposal as presented at the public hearing and respond directly to

the individual’s comments or questions.

12.4.9 Location and/or design approval for projects with a posting of notice of

willingness to hold a hearing:

For projects on which the Notice of Willingness to hold a public hearing process is

sufficient to satisfy the public involvement requirements, final location/design

approval is coordinated by the VDOT Project Coordinator in accordance with

VDOT’s Public Involvement Manual, Location and/or Design Approval Process Flow

Charts (pages 42 and 43 of 89) and applicable state and federal laws.

Once the approvals are obtained, the locality is encouraged to advise those who

provided comments during the public hearing. This response should note any

changes in the proposal as presented at the public hearing and respond directly to

the individual’s comments or questions.

12.4.10 Tasks/ Submittals / File Documentation Task/Submittal / File Documentation

Locality Responsibility

VDOT PC Responsibility

Submittal Timing / Recordkeeping Requirements

Determination of public participation requirements

Prepare and submit to PC

Concur with locality decision

At Scoping

Page 48: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-47 December 2017 Project Development

Notice of Public Hearing in newspaper (2x) and posting

Post and send notice to PC

N/A

Not less than 30 days prior to PH approximately one week prior to PH

Notice of Willingness to Hold a Public Hearing in newspaper (2x) and other appropriate notifications

Post and send notice to PC

PC Reviews for completeness. Support is available from Public Affairs Office if needed.

Not less than 15 days prior to the expiration of willingness period and approximately one week prior to expiration date of willingness.

Draft of Project Information Sheet(s) Section 3.03 and Appendix A-1 of the Public Involvement Manual includes a listing of the suggested documents for Public Information session / Public Hearing.

Prepare and submit to PC

PC Reviews for completeness. Support is available from Public Affairs office if needed.

30 days prior to hearing

Draft Project Information Sheet(s)

N/A

Review and provide comments to locality. Support is available from Public Affairs office if needed.

10 business days

Final Project Information Sheet(s)

Prepare for public hearing

N/A 5 days prior to hearing

Conduct the Public Hearing - Section 3.05 and Appendix A-3 of the Public Involvement Manual provides guidance on holding a Public Hearing

N/A N/A

N/A

PH Transcript Appendix A-5 (Transcript Submission) of the Public Involvement Manual outlines the preparation of the Transcript

Prepare and submit to PC

Process in accordance with 2 Tiered Project Oversight process

Prepared and submitted to VDOT PC 15 days after close of written comment period; final comments provided to LPA within 15 days of their submittal

Location and/or design approval in accordance with Tier 1 / Tier 2 processes and VDOT’s Public Involvement Manual, Location and/or Design Approval Flow Charts.

N/A

CTB for location, Chief Engineer for design

45 days for CTB approval, 30 days for design approval

12.4.11 Regulatory References

23 CFR 771.111 (h)

23 CFR 771.119

§ 33.2-208 subsection B of the Code of Virginia

Page 49: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-48 December 2017 Project Development

23.128 §51.5-40 of the Code of Virginia

40 CFR 1500-1508 § 33.2-332 of the Code of Virginia

Executive Order 12898 - Environmental Justice

§ 33.2-333 of the Code of Virginia

24 VAC 30-380 (Virginia Administrative Code)

12.4.12 Miscellaneous References

VDOT Policy Manual for Public Participation in Transportation Projects

VDOT’s Public Involvement Manual defines how VDOT conducts the public

participation process on its projects and documents specific requirements for how

VDOT addresses FHWA’s public involvement regulations. This manual also

includes helpful information such as templates for hearing notices and project

information brochures and checklists for hearing activities. Accordingly, the LPA is

encouraged to use this manual as a reference.

http://www.virginiadot.org/business/resources/LocDes/Public_Involvement_Manual.p

df

VDOT CADD Manual

VDOT’s CADD manual includes many references for the production of Public

Hearing Displays. Localities and their consultants are encouraged to utilize these

guidelines and templates as they prepare for public hearings. These can be found in

in the VDOT CADD Manual, Appendix G

Page 50: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-49 December 2017 Project Development

Chapter 12.4 – Public Involvement Checklist These checklists can be found in their entirety in the VDOT online forms library

CH 12.4 - Public Involvement

This section outlines the processes and responsibilities associated with Public Information and Participation for federal-aid projects. The final outcome of this process is that all projects are developed in a manner that provides the general public with a well-publicized opportunity to both review and discuss proposed plans and potential impacts for the project.

SUBMIT COMPL F S-V S-L T-A UCI Requirement Reference LAP Other

X X X X** X Public Hearing Requirements determined at Scoping

12.1 12.4.1 12.4.3

23CFR771.111 23USC128

X X X X X Offer public involvement opportunities as directed by applicable code. Projects with a CE, PCE or BCE may not require public involvement opportunity.

12.4.2

If opportunity is offered, or a

public hearing is held:

X * * X X Project information documents & public notice prepared and submitted to PC for review by district PE manager, DCRO and Public Affairs

12.4.6 Public

Involvement Manual

X * * X X Notice of Public Hearing or Willingness Published 2x and submit

12.4.5 12.4.6

Public Involvement

Manual

X * * X*** X Public Hearing Transcript Prepared & Submitted (within 15 days of close of written comment period)

12.4.7

23CFR771.111 23USC128

X * * X Location and Design Approval 12.4.8 12.4.9

Public Involvement

Manual

* If determined by VDOT that a Willingness or Public Hearing is required, then this item is applicable

** Public involvement opportunity given during application process

*** If a second public hearing is held during the project development process

Page 51: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-50 December 2017 Project Development

12.5 PLAN SUBMITTALS

This chapter contains the following topics:

12.5.1 Introduction

12.5.2 Applicability

12.5.3 Sealing and Signing Requirements / Title Sheet Signatures

12.5.3.1 – Sealing and Signing Plans

12.5.3.2 – Title Sheet Signatures

12.5.4 Plan Reviews

12.5.5 Location and/or Design Approval

12.5.6 Right of Way Plan Approval

12.5.7 Advertisement Plan Approval Process

12.5.8 Tasks / Submittals / File Documentation

12.5.9 References

12.5.10 Regulatory References

Plan Submittals Checklist

Appendices

Appendix 12.5 - A – UCI Right of Way Phase Certification Form

Appendix 12.5 - B – UCI Construction Phase Certification Form

Page 52: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-51 December 2017 Project Development

12.5.1 Introduction

This chapter outlines the actions required for plan review, submittal, and approval.

The purpose of these reviews is to ensure that the plans have been developed in

accordance with the Plan Design section of this Guide and meet applicable federal

and state design guidelines. VDOT’s reviews will focus only on the

completeness, comprehensiveness, constructability and biddability of the

plans and must not be considered a quality control review. The LPA and its

responsible charge engineer are fully responsible and liable for the adequacy and

accuracy of the project design.

Generally, plans should be reviewed by VDOT prior to the Public Hearing, prior to

Right of Way Acquisition, and prior to Advertisement, or at approximately the 30

percent, 60 percent, and 90 percent plan development stages. The scope and

complexity of the project will determine VDOT’s oversight activities (see Chapter 13)

and the actual number of reviews and milestone meetings will vary. Three is the

typical number of plan reviews; however, there may be fewer, or more, as project

complexity and project risk necessitates. The LPA Project Manager and the VDOT

Project Coordinator will, together, make the final determination regarding the number

of reviews and milestone meetings during project scoping.

Special Program Requirements

Transportation Alternatives

TA projects should generally require only two plan reviews – one at 50% complete

and then a final review when plans are at 90% - 100% complete. In cases where the

project involves the construction of rehabilitation of a building, VDOT will rely on the

locality’s building official to provide a code compliance review and issue any required

building permits. Certification of this will be required at the PS&E stage. VDOT

does not review building plans except in cases where the structure will be on State-

owned property. If the building plans include site improvements, such as parking

lots, walkways, lighting or landscaping, VDOT will require a plan review for the site

improvements. Note: The Virginia Department of Historic Resources must review

Page 53: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-52 December 2017 Project Development

building plans for historic structures or structures within a historic district. Those

reviews must be made in conformance with Chapter 15.4 of this Manual.

Urban Construction Initiative

The municipality must design a project so that it meets minimum American Association of State

Highway and Transportation Officials (AASHTO) standards. A municipality may have different

standards and specifications that meet or exceed AASHTO standards, but these need to be reviewed

and approved by VDOT and FHWA before they are authorized for usage. The municipality must

ensure that design flexibility does not jeopardize safety and mobility.

Projects will be evaluated utilizing the Risk Based Assessment process provided in

LAP Manual Appendix 9C and Appendix 13.1-B to determine the appropriate level of

plan review and oversight required. Utilization of the Risk Based Assessment Form

will provide project documentation on the oversight level of the plan reviews as

determined.

All reviews will focus on relative completeness of the plans, comprehensiveness,

constructability, and adherence to sound engineering practice and principles and will

not focus on format, packaging, etc. VDOT will not be looking at "format" issues, per

se, but what makes the plans have value for subsequently advertising and

constructing the project. For project reviews, the locality should submit to VDOT a

copy of the road and bridge plans in an single page electronic format (tag image

files-".tif") to facilitate the review process.

12.5.2 Applicability

Applicable on all projects utilizing federal funds, projects developed to qualify for

federal aid, and state funded projects on the VDOT maintained system.

Plan Submittals

Federal-aid State-aid / VDOT

Maintained

State-aid / LPA Maintained

X X N/A

Page 54: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-53 December 2017 Project Development

12.5.3 Sealing and Signing Requirements / Title Sheet Signatures

12.5.3.1 Sealing and Signing Plans

LPA’s are required to meet Virginia Department of Professional and Occupational

Regulation (DPOR) requirements for the sealing and signing of plans by a

Professional Engineer, Landscape Architect or Land Surveyor licensed to practice in

the Commonwealth of Virginia. For reference, VDOT has internal process

documents which outline the requirements for sealing and signing plans and

documents for VDOT administered projects in IIM-LD-243.10.

When submitting for final approvals of federal phase authorizations for Right-of-Way

and Advertisement, the title sheet must also be signed by the appropriate

responsible officials, in accordance with local government procedures. However, at

a minimum, the Director of Public Works or other locality department director with

the most direct supervision over the project must sign the title sheet. The local

government signatures certify that the plans are complete, constructible, and

biddable (ready for contract advertisement), that the necessary right-of-way has

been addressed and accounted for, and that adequate funding has been identified to

complete the project. The LPA is also certifying, by the signatures, that the plans

were prepared by staff or consultants that exercised the appropriate standard of care

and followed accepted standards, procedures, policies, methods of practice, etc.,

that are consistent with the engineering and design of plans for such work.

12.5.3.2 Title Sheet Signatures

VDOT has an internal process which outlines the requirement for title sheet

signature for VDOT administered projects as referenced in IIM-LD-204. VDOT has

prepared signature blocks for Title sheets for locally administered Federal-aid, State-

aid, and Design-Build / PPTA Projects. Links to samples for each of these are

located in section 12.2.5.1, Local Governments must utilize these digital versions.

Title sheets can be downloaded through VDOT’s CADD Manual web site at:

Page 55: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-54 December 2017 Project Development

http://www.virginiadot.org/business/locdes/vdot_cadd_manual.asp

Federal-aid, and Design Build title sheets must be signed by the Locality and VDOT;

while State-aid title sheets require only locality signatures.

Special Program Requirements

Transportation Alternatives

Transportation Alternatives / Enhancement projects do NOT require VDOT

signatures on Title Sheets.

Urban Construction Initiative

UCI projects do NOT require VDOT signatures on Title Sheets.

12.5.4 Plan Reviews

At the project milestones requiring reviews by VDOT as mentioned in

Section 12.5.1, the LPA Project Manager will submit a copy of the roadway

and bridge plans in single page PDF format to the VDOT Project

Coordinator to be placed in Falcon and linked to iPM.

12.5.5 Location and/or Design Approval

Location and/or Design Approval shall be obtained in accordance with VDOT’s

Public Involvement Manual, Location and/or Design Approval Process Flow Chart

(pages 42 & 43 of 89).

12.5.6 Right of Way Plan Approval

Prior to Right of Way acquisition, the LPA Project Manager will submit a right of way

plan package, which includes a current estimate, to the VDOT Project Coordinator to

be processed for approval. The submittal will include the Right of Way data sheet,

Right of Way plan sheets and the original Project Title Sheet for Right of Way

Page 56: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-55 December 2017 Project Development

Authorization signed by the person of responsible charge from the locality. By its

signature, the LPA is certifying that the plans are complete and accurate for the

acquisition of right of way and the relocation of utilities.

The LPA Project Manager will also submit the PM130 and the Right of Way and

Utilities Plan Review Checklist (RW-301) to the VDOT Project Coordinator with the

submittal. Detailed discussion of the Right of Way Plan approval and authorization

process can be found in Chapter 16.

It is imperative that the LPA NOT incur any land acquisition or utility relocation

expenses until federal authorization and VDOT Notice to Proceed with

acquisitions are approved, as costs incurred prior to federal authorization

SHALL NOT be reimbursed and will be the responsibility of the locality.

Please note, if the locality incurs any such expenses prior to federal

authorization, they risk loss of federal participation on the project.

VDOT has internal process documents which outline the submission and review

process for Right of Way Plans for VDOT administered projects. LPAs may utilize

these as a reference.

http://www.extranet.vdot.state.va.us/locdes/electronic_pubs/iim/IIM234.pdf

VDOT Responsibilities:

The VDOT Project Coordinator will verify that the LPA has utilized

the latest version of the appropriate title sheet. If not, the LPA will

be required to submit the correct version.

Circulate the title sheet for signatures (the title sheet can be on

paper or mylar) and submit the original signed title sheet to Room

705, CO L&D Plan Library/Room 1005, CO S&B Plan File Room to

be filed.

The VDOT Project Coordinator will coordinate the submission of

the PM130 and RW-301/EQ-201forms to the District R/W manager.

The VDOT Project Coordinator will prepare and submit the LD-368 form

after review of the LPA’s Right-of-Way plans.

Page 57: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-56 December 2017 Project Development

Additional discussion on the Environmental approval process is

contained in Chapter 15.

Normally it takes a minimum of 30 business days, from receipt of a

complete package, to obtain authorization to proceed with Right of Way.

When this authorization is issued, the locality will be notified by the VDOT

Project Coordinator that it may begin negotiations/acquisition. This

authorization will usually occur within the 60-90 day window for VDOT

review of the complete package. LPAs are encouraged to submit

complete right of way packages as early as practicable to ensure

scheduled phase dates are met.

Special Program Requirements

Urban Construction Initiative

When the municipality is ready to initiate the right-of-way phase for a federal project,

a request must be submitted to VDOT’s Project Coordinator. The Municipality shall

submit a Project Certification for Right of Way and include copies of the final right-of-

way plans including a signed Title Sheet, the information necessary for VDOT (see

PM-130) to complete the environmental re-evaluation, a cost estimate, and the cost

for utilities, broken down by utility company for cost accounting purposes. VDOT’s

Project Coordinator will then initiate the R/W evaluation process. Normally, this

authorization will take fifteen (15) business days. For federal projects, it is important for the

municipality not to incur any right-of-way expenses until federal authorization is received. Also, if

additional funds are needed, other than those shown in the SYIP, a source for these funds is to be

identified by the municipality. Please note that if the municipality incurs R/W expense prior to FHWA

authorization they risk loss of federal participation in the project.

With the Municipality’s request for Right of Way Authorization, attach a completed

Right of Way Phase Project Certification letter as illustrated in Appendix 12.5A.

The Right of Way and Utilities Division's Project Scheduling and Certification

Section will enter the information into the Right of Way and Utilities

Management System (RUMS). The VDOT Project Coordinator will notify the

locality once authorization is received.

Page 58: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-57 December 2017 Project Development

12.5.7 Advertisement Plan Approval Process

When plans are ready for advertisement for construction, the LPA Project Manager

will provide a PS&E submittal package to the VDOT Project Coordinator for

construction authorization.

The submittal will include the original Title Sheet for Authorization to Advertise

signed by the person of responsible charge from the LPA and signed and sealed by

the Responsible Person (Licensed Professional Engineer, Certified Landscape

Architect or Licensed Land Surveyor) in accordance with DPOR. By signature, the

locality is certifying that the plans were prepared by staff or consultants that

exercised the appropriate standard of care and followed accepted standards,

policies, procedures, methods of practice, etc., that are consistent with the

engineering and design of plans for such work and all plan review comments have

been addressed.

Once the project design has been completed and approved to advertise, the

LPA Project Manager shall provide the VDOT Project Coordinator with a CD of

the complete plan assembly in single page PDF format to be stored in the

VDOT Plan File Library.

The LPA must receive an Advertisement Authorization prior to advertisement

or the project may become ineligible for reimbursement. A separate

Authorization to Award the contract and begin construction is also required

and will be provided after bids are received, tabulated and submitted to VDOT

as addressed under the Authorization and Award section of this Guide.

VDOT Responsibilities:

Circulate the title sheet for signatures (the title sheet can be on

paper or mylar) and submit the original signed title sheet to Room

705, CO L&D Plan Library/Room 1005, CO S&B Plan File Room to

be filed.

Page 59: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-58 December 2017 Project Development

The VDOT Project Coordinator will coordinate the submission and

provide a PM-130 form to the District Environmental Manager for

environmental reviews and certification. The VDOT Project

Coordinator will also coordinate review of the bid documents as

outlined in the Advertisement and Award Chapter (Ch 12.6).

Additional discussion on the Environmental approval process is

contained in Chapter 15.

Normally it takes 30 business days, from receipt of a complete

package, to obtain federal authorization to advertise a project.

When this authorization is received from FHWA, the LPA will be

notified by the VDOT Project Coordinator in writing. This

authorization will usually occur within the 60-90 day window for

VDOT review of the complete package.

Special Program Requirements

Urban Construction Initiative

When a federal project is ready to be advertised for construction, the

municipality must first receive the project advertisement authorization from

the FHWA. The Project Certification for Construction Letter as provided in

Appendix 12.5B addresses the information that the municipality must submit

to VDOT’s Project Coordinator. The municipality must also submit the project

Title Sheet signed by an officer of responsible charge for the locality; and

signed and sealed by a Professional Engineer in accordance with Department

of Professional and Occupational Regulation. If additional funds are needed

beyond those shown in the Six Year Improvement Program (SYIP), a source

needs to be identified. Normally it takes thirty (30) business days to obtain

federal approval for a project's advertisement. For federal projects, it is

important for the municipality not to advertise the project until authorization is

received. The municipality will be notified by VDOT once this authorization is

received.

12.5.8 Key Submittals / Requirements

Page 60: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-59 December 2017 Project Development

Task/Submittal /

File Documentation

Locality Responsibility

VDOT PC Responsibility

Submittal Timing / Recordkeeping Requirements

Plan Reviews Submit plans for review

Coordinate VDOT Reviews of plans – focused on constructability and bidability

Based on the schedule agreed upon by the Local PM & VDOT PC

Right of Way Plan Approval

Submit PM130, RW-301 and RW plans for approval/authorization package to the VDOT PC

Process VDOT reviews and approvals of plans and, prepare and submit LD-368 and secure RW authorization

60-90 days before initiation of RW phase

Construction Plan Approval

Submit CN plans for approval/authorization package to the VDOT PC

Process VDOT reviews and approvals of plans and secure CN authorization

60-90 days prior to advertisement

12.5.9 References

Location & Design Instructional & Information Memoranda

http://www.virginiadot.org/business/locdes/rd-ii-memoranda-

index.asp

Location & Design Forms

http://vdotforms.vdot.virginia.gov/

http://vdotforms.vdot.virginia.gov/SearchResults.aspx?lngDivisionID=14

Environmental Forms

http://vdotforms.vdot.virginia.gov/

Right of Way Forms

http://vdotforms.vdot.virginia.gov/

12.5.10 Regulatory References

VDOT/FHWA Virginia Division Stewardship Oversight Agreement, June 2015

23 CFR 635 Construction and Maintenance

23 CFR 771 Environmental Impact and Related Procedures

23 CFR 771.129 (c) Environmental Re-evaluation at Right of Way Authorization

23 CFR 645 Utility Relocations, Adjustments and Reimbursement

DPOR §54.1-400 (Sealing & Signing of Plans)

Page 61: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-60 December 2017 Project Development

Chapter 12.5 – Plan Submittals Checklist These checklists can be found in their entirety in the VDOT online forms library

CH 12.5 - Plan Submittals

This section outlines the actions necessary for plan review, submittal and approval. The purpose of these reviews is to ensure that the plans have been developed in accordance with the Plan Design section of this Guide and meet applicable federal and state design guidelines. The LPA and its responsible charge engineer are fully responsible and liable for the adequacy and accuracy of the project design.

SUBMIT COMPL F S-V S-L T-A UCI Requirement Reference LAP Other

X X -- X X 30/60/90 percent Plan Submittal

1

(TA projects are reviewed at 50 & 90-100 percent)

12.5.1 12.5.4

X X -- -- -- Title sheets prepared Use VDOT title sheet templates

12.2 12.5.3

Templates in VDOT CADD Cell

Library

X X X X X Plans & Title Sheets Signed

& Sealed 12.5.3 DPOR

Regulations

X X -- X X* R/W Plan Review Approval2 12.5.6

16 23CFR771.129

X X -- X X PM 130 RW review & Env. Re-evaluation

X X -- X X RW 301

X X -- X X EQ201, EQ-200, EQ-103

X -- -- X X RR Agreement developed if RR property involved

23CFR635.214(b)

635.216(d)

X X -- X X* Submit PSE package for approval / authorization

12.5.7 23CFR771.129 (c)

1 As determined by Project Complexity / Risk

2 R/W Certification Approval is only required for federal-aid projects and when underlying fee ownership of

R/W will be transferred to VDOT. Otherwise R/W Plan Review will be performed only ensure that appropriate R/W is acquired to meet future highway maintenance needs

X*

Certification letter required from UCI locality

Page 62: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.5 – A-1 December 2017 Project Development

Appendix 12.5A

UCI Right of Way Phase Certification Form

Page 63: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.5 – A-2 December 2017 Project Development

CITY LETTERHEAD

Date:

District Administrator:

Attn: Project Coordinator

District Address:

Project Street Name

Project Number

Project UPC Number

From:

To:

Subject: Project Certification - Right of Way Phase

Dear District Administrator:

This project consists of: (complete description from beginning to end of the location and the

type of project, i.e. relocation of families and businesses, curb and gutter, intersection

improvement, etc).

Reference is made to the agreement between the City of _________________________ and

the Virginia Department of Transportation (VDOT) dated ____________________.

This project has been developed in accordance with all applicable Federal and State laws,

regulations and in accordance with the VDOT’s Urban Construction Initiative Program

Administration Guide.

The project development has been in accordance with the National Environmental Policy Act

(NEPA).

Additionally, the project was developed in accordance with Federal and State laws and

regulations governing public involvement. A Public Hearing was held on ___________.

The hearing location and date were properly advertised and posted, plans were available for

review and comment, the NEPA document was available for review, a comment procedure

was provided and all comments have been given due consideration.

Or

A Notice of Willingness was posted and expired on _______________. The Notice of

Willingness was properly advertised and posted including the procedure for requesting a

public hearing, plans were available for review and comment, and the NEPA document was

available for review.

Page 64: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.5 – A-3 December 2017 Project Development

This Project has been designed in accordance with AASHTO Design Criteria utilizing

current engineering practice, methodology and process suitable for the project scope and

complexity. A Quality Assurance and Quality Control Review has been completed for this

phase of project development.

All required checklist have been previously submitted or are attached hereto.

I certify that the above is accurate and correct and reflects the project development process

and documents on file which are available for review upon request.

Further, I approve the design features of this project for the City or Town of __________ and

request VDOT to provide design approval and authorization to proceed with the acquisition

of right of way.

____________________________________ ___________________

City Manager or Director of Public Works Date

or City Engineer

cc: Urban Program Manager

VDOT Project Coordinator

Attachments: EQ-121 Hazardous Materials Due Diligence Document

Project Title Sheet (signed by a Municipality Official in

responsible charge of the work)

VDOT Project Coordinator Copy List:

Local Assistance Division Director

Programming Davison Director

State Location and Design Engineer

State Right of Way and Utilities Director

State Environmental Director

State Structure and Bridge Engineer (when appropriate)

State Construction Engineer

District Construction Engineer

District Preliminary Engineering Manager

District Right of Way Manager

District Environmental Manager

District Structure and Bridge Engineer (when appropriate)

Central Office Plan Coordination Section

Page 65: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.5 – B-1 December 2017 Project Development

Appendix 12.5B

UCI Construction Phase Certification Form

Page 66: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.5 – B-2 December 2017 Project Development

CITY LETTERHEAD

Date:

District Administrator:

Attn: Project Coordinator

District Address:

Project Street Name

Project Number

Project UPC Number

From:

To:

Subject: Project Certification - Construction Phase

Dear District Administrator:

This project consists of: (complete description from beginning to end of the location and the

type of project, i.e. relocation of families and businesses, curb and gutter, intersection

improvement, etc).

Reference is made to the agreement between the City of ____________________ and the

Virginia Department of Transportation (VDOT) dated ____________________.

This project has been developed in accordance with all applicable Federal and State laws,

regulations and in accordance with the Urban Construction Initiative Program Administration

Guide.

In accordance with State and Federal Code, all necessary rights of way have been acquired or

legal right of entry onto each parcel has been obtained for the advertisement and construction

of this project. Also, all affected utilities have been relocated or they are included as in-plan

work to be performed by the project construction contractor. (If Federal Funds participated

in this project, reference to FHWA requirements should also be included.) To the best of our

knowledge, there are no contaminants contained within the soil on the property purchased.

The project development has been completed in accordance with the National Environmental

Policy Act (NEPA). An approved environmental document has been prepared and all

identified environmental commitments have been included in the plans and proposal. A

completed Environmental Certification/Commitments Checklist (EQ-103) is attached. All

applicable construction permits have been obtained.

Additionally, the project was developed in accordance with Federal and State laws and

regulations governing public involvement. A Public Hearing was held on __________ and

Design approval was provided on ____________. Or A Notice of Willingness was posted

and expired on ___________, and Design approval was provided on __________.

Page 67: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.5 – B-3 December 2017 Project Development

Also, this Project has been designed in accordance with AASHTO Design Criteria utilizing

current engineering practice, methodology and process suitable for the project scope and

complexity. If necessary, Design Exception(s) or Waiver(s) have been obtained and

identified on the Title Sheet for the project. A Quality Assurance and Quality Control

Review has been completed for each phase of project development.

All required checklist have been previously submitted or are attached hereto.

Attached are copies of the project plans, a current engineer’s estimate and the City’s

proposed advertisement for construction package. If Federal Funds are involved, include the

statement “The advertisement package includes all appropriate federal aid project

information including Minimum Wage rates and EEO provisions.”

I certify that the above is accurate and correct and reflects the project development process

and documents on file which are available for review upon request.

____________________________________ ___________________

City Manager or Director of Public Works Date

or City Engineer

cc: Urban Program Manager

VDOT Project Coordinator

Attachments: EQ-103 Environmental Certification/Commitments Checklist

Project Title Sheet (signed and sealed by a professional engineer in

responsible charge of the work who shall be duly registered

to practice engineering in the Commonwealth of Virginia.

Project Plans

Engineer’s Estimate

Advertisement for Construction Package

VDOT Project Coordinator Copy List

Local Assistance Division Director

Programming Division Director

State Location and Design Engineer

State Right of Way and Utilities Director

State Environmental Director

State Structure and Bridge Engineer (when appropriate)

State Construction Engineer

District Construction Engineer

District PE Manager

District Right of Way Manager

District Environmental Manager

District Structure and Bridge Engineer (when appropriate)

Urban Program Manager

Central Office Plan Coordination Section

Page 68: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual December 2017 Project Development

Auth to Award 45 to 60 Days

12.6 ADVERTISEMENT AND AWARD

30 to 60 Days Auth to ADV 60 to 90 Days

RO

W

Civ

il R

igh

ts

Con

str

uctio

n

IID

/ F

PM

D

Pro

ject

Co

ord

ina

tor

En

vir

on

men

tal

LPA submits PS

& E Package

12.6.7

Comments to LPA

Project Coordinator

Requests PS & E Review 12.6.7

Project ADV 21 Days Minimum

12.6.8

Goal Setting / DBE

Requirements 12.6.5 17.3

Construction

Review

Bids reviewed / tabulated /

Request to Award 12.6.9

Project Coordinator

Review / Submit Request to Award

Review for DBE

Goal Conformance

Concurrence to Award for FO

projects

Bid Review /

Concurrence to Award

Revise Project Agreement (if

necessary)

Project Coordinator

Receives Concurrence to

Award

LPA Awards

Funding

Verification for Award

Concurrence to

Award Notification Prepared

Funding Verification / auth

to ADV. Fed Authorization

NE

PA

Re

-ev

al

Co

mp

lete

En

v C

ert

Co

mp

lete

RO

W C

ert

Co

mp

lete

LP

A P

rep

are

s

IFB

12

.6.3

Page 69: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-61 December 2017 Project Development

CHAPTER 12.6 - ADVERTISEMENT AND AWARD

12.6.1 Introduction

12.6.2 Applicability

12.6.3 Development of the IFB

12.6.4 Bid Proposal and Contract Requirements

12.6.4.1 Sole Source and Proprietary Items

12.6.4.2 Retainage

12.6.4.3 Liquidated Damages

12.6.4.4 Incentives and Disincentives

12.6.5 Mandatory Federal Aid Provisions

12.6.6 Other Federal aid requirements

12.6.7 Plans Specifications and Estimates Submittal Package

12.6.8 Advertisement

12.6.9 Project Award

12.6.9.1 Bid Opening and Analysis

12.6.9.2 Submittal of the Award Package

12.6.9.3 VDOT Concurrence to Award

12.6.9.4 Dashboard

12.6.10 Local Force Construction

12.6.11 Key Submittals / Requirements

12.6.12 References

Appendices

Appendix 12.6-A – Advertisement and Award Submittals Checklist

Appendix 12.6-B – Locality/VDOT Certification of Documents

Appendix 12.6-C – Advertisement and Award Checklist

Page 70: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-62 December 2017 Project Development

12.6.1 Introduction

This chapter outlines the requirements associated with advertisement and award of

federal-aid projects. State-aid projects, included in the SYIP or the SSYP, must receive

concurrence to award and submit a Project Award Submittal Package to the Project

Coordinator prior to contract letting.

It is not acceptable to use contracting methods such as alternate bids,

speculative amounts, change orders, etc., as a replacement for complete

and thorough design/investigations during project development.

12.6.2 Applicability

All federal-aid projects and projects developed to qualify for federal-aid.

*State-aid projects funded with formula allocations must receive funding verification

and authorization from VDOT prior to award. A Project Award submittal package

must be submitted to the VDOT Project Coordinator. This package must also

include a completed Appendix 5-A Certification Form for State Funded Projects.

Advertisement & Award

Federal-aid State-aid / VDOT Maintained

State-aid / LPA Maintained

X * *

*Note exemption in section 12.6.4.2 regarding Retainage

Special Program Requirements are noted at the end of each section.

12.6.3 Development of Invitation for Bid / Contract Documents

The LPA is responsible for preparing the bid package which contains the plans,

addenda, special provisions, supplemental specifications, and the bid proposal. When

Page 71: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-63 December 2017 Project Development

using federal-aid, LPAs must comply with 23 CFR 635 which describe federal

regulations governing construction contracts. Exceptions to these requirements are

provided for some off-right of way projects (see Chapter 5 for additional discussion).

Lump Sum Contracts

Lump sum contracts are allowable by both federal and state laws. However, significant

deliberation should be made between the LPA Project Manager and the VDOT Project

Coordinator before determining that a lump sum contract is in the LPAs best interest

and will be pursued. This determination should be made early in the design process.

Lump sum contracts generally should be limited to “simple” projects that have a low risk

of unforeseen conditions and low possibility of changes. Regardless, contracts must

also account for the possibility of contract modifications and include language regarding

how potential change orders will be addressed. Payments for lump sum contracts must

be made based on a pre-determined and agreed-upon pay-out schedule, which must be

included in the final contract.

Lump sum payments must be based on estimated project completion,

deliverables, major work items, and/or milestones. Payments based

solely on contract time are not allowable.

When lump sum contracts are the chosen delivery method on a federal-aid project,

frequent consultation with the VDOT Project Coordinator throughout the project

development process is necessary.

12.6.4 Bid Proposal and Contract Requirements:

The bid proposal and contract must contain the following elements:

Instructions to Bidders

General Contract Provisions

Proposal / Agreement forms / Terms of the Contract

Schedule of Bid Items, Fuel Adjustment, Steel Adjustments, etc.

Page 72: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-64 December 2017 Project Development

Reference to VDOT specifications including any modifications to VDOT

specifications or local specifications being used (note: additional time for review of

these may be necessary)

Addenda Sheet(s)

Subcontractor Solicitations

Permits and Permit Requirements

LPA’s are reminded that Invitations for Bids (IFB’s) must NOT contain any negotiation

clause(s) or any reference to a locality policy that provides for contract negotiation. Bid

negotiation is strictly prohibited as set forth in 23 CFR 635.113.

In addition, IFB’s must NOT contain any reference to the withholding of retainage as

described in section 12.6.4.2.

12.6.4.1 Sole Source and Proprietary Items:

The use of sole source and proprietary items should be avoided except when there is

no other feasible or reasonable alternative. Special approvals are necessary to include

these types of items in a contract. There is often confusion on the definition and

differences between sole source and proprietary; this is clarified below.

• Sole Source Items

A Sole Source Item is any product or service used on a project where the product may

be procured from only one source, and therefore has no price competition. This is a

very rare situation and state procurement regulations require VDOT approval to utilize a

sole source item. Federally funded projects require FHWA approval.

• Proprietary Items

A Proprietary Item is a product, specification or process identified in the plans or

specifications as a "brand" or trade name (e.g. 3M, Corten). However, it may also be a

product so narrowly specified that only a single manufacturer can meet the

Page 73: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-65 December 2017 Project Development

specification. Proprietary Items are different from a sole source in that it is a specific

product typically available from only one manufacturer; however, it is sold by various

vendors.

The detailed procedures, processes and the required documentation for approval for the

use of proprietary items is defined in VDOT’s Construction Division Instructional and

Informational Memorandum, IIM-CD-2015-01.01 as approved on April 6, 2015.

Additional discussion on the use of Sole Source and Proprietary Items can be found in

section 3.9.5 of VDOT’s Urban Manual. Additional FHWA guidance can be found on the

FHWA FAQ page.

12.6.4.2 Retainage:

The withholding of retainage is not allowed on federal or state funded projects except

under very specific circumstances. Retainage will be allowed if the contractor’s

progress or performance has been identified as unsatisfactory as described in VDOT’s

Specifications or the LPA contract. This is considered to be withholding retainage for

cause. When it has been determined that the contractor’s progress or performance is

satisfactory once again, any previously withheld retainage must be released. The

withholding of retainage without cause is strictly prohibited unless a process for

incremental acceptances is identified in the IFB as set forth in 49 CFR 26.29(b)(3).

Therefore, IFB’s must NOT contain any reference to the withholding of retainage without

cause unless the incremental acceptance method is utilized. This does not preclude the

LPA from withholding payment for unsatisfactory or incomplete work, failure to provide

proper documentation (example: Buy America), and failure to provide required

submittals and schedule, if any.

12.6.4.3 Liquidated Damages:

Liquidated Damages allow LPAs to recover an agreed amount for their contract

administration costs and other damages that likely will be incurred by the LPA each day

the project is not completed beyond the contract fixed completion date. Standard rates

Page 74: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-66 December 2017 Project Development

for Liquidated Damages are available in the VDOT Road and Bridge Specification

Section 108.06 (b). These rates may be modified to meet project specific conditions.

Justification should be provided and must include a calculation that clearly identifies the

daily costs that the LPA likely will incur if the project is delayed, such as:

Direct labor (Inspectors, Construction Managers, Area Construction Engineers,

etc.), and

Non-salary direct costs (vehicles, fuel, computers, communication devices, etc.)

If the standard rates are not used, the project specific Liquidated Damages must be

included in the contract.

12.6.4.4 Incentives and Disincentives:

Incentives and disincentives encourage contractors to complete a project or phases of a

project, ahead of schedule to reduce impacts to the traveling public. Incentive amounts

should be calculated to include:

Contractor’s daily acceleration costs

LPA’s daily administration costs

Road user costs

Disincentive amounts are not penalties and should only be applied on projects that offer

incentives. The disincentive should be calculated to include:

LPA’s daily administration costs

Road user costs

The maximum incentive value of a project typically approaches 5% of the estimated

contract value. If a disincentive is utilized, the maximum value of disincentive should not

exceed the value of the incentive.

Supporting documentation detailing incentive and disincentive calculations must be

maintained by the LPA. The LPA’s daily administration costs may be calculated in a

similar fashion as the method used for Liquidated Damages. Road user costs must be

determined using a federally approved method for calculating impacts to the traveling

public. Consult with your VDOT Project Coordinator for additional guidance. FHWA

Page 75: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-67 December 2017 Project Development

Technical Advisory T 5080.10 also provides additional guidance for the development

and implementation of incentives and disincentives using contractor daily acceleration

costs.

Since disincentives include the LPA’s daily administration costs, it is important that

disincentives and Liquidated Damages never be applied concurrently. The contract

must be written so that Liquidated Damages can only be assessed once the contract

completion date has passed and the disincentive amount is no longer being applied.

Additionally, if multiple disincentives are set forth in the contract (i.e., disincentives

associated with multiple contract milestones and/or the contract completion date),

disincentive charges are only to be assessed for the corresponding milestone not yet

achieved. At no time shall more than one disincentive charge be assessed.

12.6.5 Mandatory Federal-aid Provisions:

Mandatory federal-aid provisions are listed and can be obtained from VDOT’s Web site

at: PDF version / Word version. The FHWA Form 1273 must be included in the

contract verbatim. No modifications are allowed. A detailed discussion of all mandatory

federal-aid contract provisions can also be found in the FHWA Contract Administration

Core Curriculum Participants Manual and Reference Guide.

In addition to those mandatory federal-aid provisions, the LPA must include the

following in their construction contracts:

Language to address any conflict between state or local contract language and

federal rules. When conflicts arise, the federal-aid or most conservative approach

must be taken. For off-system (off right of way) projects, State procurement laws

and regulations may apply (See Chapter 5 for further details).

Language to address or a reference to a contractor claims process.

Page 76: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-68 December 2017 Project Development

DBE language is required in all federal-aid contracts. VDOT will review and

potentially establish a DBE goal, on all federal-aid projects, with a construction value

over $100,000. The goal will be determined based on available DBEs in the project

area and on contract items amendable to work performed by those DBEs. NOTE:

a SWAM vendor may not necessarily also be a DBE contractor or meet the

requirements as a DBE contractor.

Mandatory Construction and Civil Rights forms and language that must be included

in each federal-aid contract are listed below:

o C-104 (Bidder Statement)

o C-105 (Bidder Certification)

o C-111 (Minimum DBE Requirements)

o C-112 (Certification of Binding Agreement)

o C-48 (DBE- Subcontractor/Supplier Solicitation and Utilization)

o C-49 (DBE- Good Faith Efforts Documentation)

Special Program Requirements

Urban Construction Initiative

A standardized construction contract bid document template was created for UCI

localities to use to meet federal/state requirements. That template can be found labeled

‘Standard Construction Contract Bid Document – Template’ at the following website:

http://www.virginiadot.org/business/local-assistance-firstCities.asp

12.6.6 Other federal-aid requirements

For traditional highway construction federal-aid projects, local

governments, with the exception of TA projects and UCI Municipalities,

must use VDOT Pre-qualified contractors.

Vendors who are, at the time of the bid opening, debarred from federal-aid work, are

not eligible for federal-aid projects.

LPAs may be required to accommodate an OJT program for project. This will be

determined by the VDOT Civil Rights Division during DBE goal-setting review.

Page 77: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-69 December 2017 Project Development

For federal-aid projects or for projects that will be maintained by VDOT, the LPA

shall submit a materials quality assurance plan (QAP) for review and approval, prior

to construction. It is recommended that QAPs be submitted prior to project

advertisement to prevent project delays. For additional information refer to Chapter

13.1.5.3.

12.6.7 PLANS, SPECIFICATIONS, AND ESTIMATES SUBMITTAL PACKAGE

Prior to the locality’s request for federal authorization to advertise, the following items

must be completed:

Right of Way Certification as outlined in Chapter 16 of this Manual is required for

federal-aid projects. Local governments certify their compliance with other right

of way acquisition requirements for non federal-aid projects.

Environmental Re-evaluation at PS&E, for federal-aid projects (see Chapter

15.11)

Environmental Certification, for federal-aid projects. For non federal-aid projects,

LPAs will certify their compliance with applicable environmental laws and

regulations (see Chapter 5).

When a federal or state-aid project (see Chapter 5 for exceptions) is ready to be

advertised for construction, the project must first receive an advertisement

authorization.

Failure to obtain federal authorization to advertise for construction will

jeopardize federal funding to the project. It is important for LPA’s to

ensure that this authorization has been obtained prior to advertisement.

Proceeding with advertisement without federal authorization will jeopardize

reimbursement of federal aid.

Page 78: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-70 December 2017 Project Development

To obtain this authorization, the LPA must submit a PS&E Submittal Package

to VDOT’s Project Coordinator. This submittal package will include the

following items:

(1) PS & E Submittal Form. This form will state that items #2 through #8, below

are being submitted and must be signed by the local official responsible for the

project. Item #9 is specific to SMART Scale funded projects and likewise must

be signed by the responsible local official when applicable.

(2) A current engineer’s estimate

(3) Final Invitation for Bid and Contract Documents – 2 sets

(4) Complete sets of plans

(5) Signed Title Sheet, containing appropriate VDOT signature blocks (separate

VDOT signature blocks are required for Tier 1 and Tier 2 projects).

(6) Locality/VDOT Certification of Documents. All boxes must be checked except

for those items that may not be applicable and have an “N/A” box. By completing

this form the LPA is certifying that the items listed on the form (required to obtain

Federal Authorization to Advertise the project) have been completed, checked

and the Proposal & Plans have been prepared in accordance with the standards

and requirements included in the LAP Manual (Appendix 12.6-B).

(7) If additional funds are needed than those shown in the SYIP or SSYP, a

source needs to be identified and the Project Administration Agreement must be

modified.

(8) Evidence that a willingness to hold a public hearing was posted or evidence

of having held a public hearing or that a decision that a willingness was not

necessary was made during scoping (See CH 12.4.5).

(9) For SMART Scale funded projects, the plan submission will include a

certification statement that indicates either of the following statements:

o No changes or additions in scope have been made since the

application for SMART Scale funds was submitted that will impact the

project benefit regardless of impact to budget.

<OR>

Page 79: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-71 December 2017 Project Development

o Scoping changes did occur and the project was re-evaluated and re-

scored if necessary.

If project plans are revised after authorization to advertise was issued,

the LPA must re-submit plans for review in accordance with Chapter

12.5. A replacement signed Title Sheet must also be submitted to the

VDOT Project Coordinator who will then forward it to the VDOT Plan Coordination

section with a request to obtain appropriate signatures.

VDOT Responsibilities (reviews or approvals at Central Office apply only

to Tier 2 projects)

The VDOT Project Coordinator will conduct an extensive review the

locality’s PS&E Package submittal, and request any additional

information from the LPA prior to forwarding to the Central Office Plan

Coordination Section.

Review and include in the PS&E package the Locality/VDOT

Certification of Documents form.

Complete and sign the VDOT District Certification section of the

Locality/VDOT Certification of Documents

For all federal oversight and non-federal oversight projects, review and

submit the PS&E package and signed Locality/VDOT Certification of

Documents. District staff will review the PS&E package and obtain

required District Title Sheet signatures prior to submission to

Construction Division, for Tier 1 projects. For Tier 2 projects, the

Project Coordinator will submit the completed PS & E Submittal Form

and LPA-signed title sheet to the L&D Plan Coordination section with a

request to obtain appropriate VDOT Central Office signatures.

Review and include in the PS&E submittal package the Locality/VDOT

Certification of Documents form.

The Project Coordinator will submit one copy of the IFB and a full set

of plans to the locally administered projects federal submissions officer

Page 80: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-72 December 2017 Project Development

(Construction Division). For Tier 1 projects, include the LPA and

District-signed Title Sheet.

Submit one copy of the IFB to the District Civil Rights Manager who will

review and forward to the Central Office Civil Rights office.

Construction Division will prepare a cost summary and forward to

Federal Program Management Division to obtain federal authorization

to award.

Comments on the bid documents and the DBE goal will be provided to

the Project Coordinator who will forward to the Locality Project

Manager to include in the final advertisement documents.

The Project Coordinator will notify the LPA Project Manager when

Federal Authorization to advertise has been obtained and State

funding verification is complete. A copy of the federal agreement will

be provided to the local government.

Where practical, the Project Coordinator will ensure all documents necessary

for advertisement approval are in files and uploaded into iPM, in the Project

Documents section.

Normally it takes 30 business days to obtain federal advertisement authorization after

submittal of a complete PS&E Package. The VDOT Project Coordinator will notify the

LPA Project Manager, in writing, after receiving the federal authorization.

Prior to advertisement the LPA must incorporate comments provided by the VDOT

federal submissions officer (advisory comments, excluded) and must incorporate the

DBE Goals provided by the VDOT Civil Rights Division. Should subsequent reviews or

audit reveal that required provisions were not included, VDOT may pursue

reimbursement of expended funds.

Special Program Requirements

Page 81: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-73 December 2017 Project Development

Urban Construction Initiative

UCI localities should follow the submittals as required under Section 12.5.7 - Special

Program Requirements of this manual to receive advertisement authorization and to

complete the PS&E process.

State Funded Projects

The LPA must request and receive funding verification prior to advertisement. The

VDOT Project Coordinator will notify the LPA Project Manager that funding verification

(IID-4) has been received. Funding verification takes 20 business days to complete.

VDOT Responsibilities

The District Planning and Investment Manager verifies and issues the IID-4

for Tier 1 projects and notifies the Project Coordinator. On Tier 2 projects, the

District Planning and Investment Manager requests Funding Verification from

the Infrastructure Investment Division (IID).

The Infrastructure Investment Division issues the signed IID-4 to the Planning

and Investment Manager (Tier 2 projects), who will notify the VDOT Project

Coordinator that funds have been verified.

Upon receipt of the signed IID-4, the VDOT Project Coordinator will notify the

LPA Project Manager that funding verification has been received and it may

proceed with advertising the project.

Special State-aid Projects

Projects funded strictly through special funding programs, such as access or revenue

sharing funds have previously received CTB authorization and do not require additional

Commissioner or CTB authorization to advertise or award. Right of Way Certification is

not necessary and the PS&E package is reviewed and approved at the District level.

Page 82: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-74 December 2017 Project Development

The LPA Project Manager must notify the VDOT Project Coordinator when the project is

advertised, when it is awarded, and the final award amount.

VDOT Responsibilities:

The Project Coordinator will enter the advertisement and award dates into the

project pool schedule and will update the project estimate.

12.6.8 ADVERTISEMENT

Federal-aid contracts must be advertised for a minimum of three weeks (21 days) 23 CFR 635.112. State-aid projects may be allowed a shorter time-frame in accordance with the Virginia

Public Procurement Act (VPPA).

LPAs must provide notice to the VDOT Project Coordinator that the contract is being

advertised and where the public notice and bid documents can be obtained.

12.6.9 PROJECT AWARD

12.6.9.1 Bid Opening and Analysis

The bid opening must be made in a public forum and read aloud. The LPA must record

the actual time and date of the bid openings and record any attendees.

The LPA will perform a preliminary evaluation of the bids for responsiveness and errors

and determine the apparent low bidder prior to submittal to VDOT for bid review and

final authorization. Any determination that a bid is non-responsive must be documented

and kept in the project file for a minimum of three years after the financial close-out of

the project. The following lists some, but not all, reasons a bid may be deemed

unresponsive:

(1) Failure to sign the bid or the bid is signed by an unauthorized individual;

Page 83: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-75 December 2017 Project Development

(2) Failure to furnish or sign a required bid bond;

(3) Failure to submit a price for each bid item;

(4) Failure to commit to DBE goals or demonstrate a good faith effort to do so, if

required in the IFB;

(5) Failure to be prequalified, if required in the IFB;

(6) The apparent low-bid is excessively over/under the engineer’s estimate.

For federal-aid contracts, the LPA Project Manager must consult with the VDOT Project

Coordinator and obtain concurrence from VDOT when making a determination that an

apparent low-bidder is non-responsive.

Determination of good faith efforts, when DBE goals have not been met

MUST be made in coordination with VDOT’s Civil Rights Division.

If the LPA determines that it will not award the contract to the lowest, responsive bidder,

it must contact the VDOT Project Coordinator and provide written justification for the

decision. The VDOT Construction Division must concur in the rejection of these bids. If

VDOT cannot concur with the LPA’s justification, the LPA will not be given authority to

award the contract to another bidder on the same contract at the same letting.

The LPAs bid analysis should address these points for the apparent low bid submitted:

Examine the unit bid prices for reasonable conformance with the Engineer’s

estimated prices

Include a thorough evaluation of obvious unit price unbalancing

Identify extreme variations with the Engineer’s Estimate

Reference 23 CFR 635-114(c),(d),(k)

Page 84: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-76 December 2017 Project Development

12.6.9.2 Project Award Submittal Package

After the LPA makes the determination of the apparent low-bidder, the LPA

shall submit to the VDOT Project Coordinator a request for bid review. This

request will contain the following:

1. A letter stating that the locality intends to award the contract to the apparent low-

bidder, to include:

Low bidders name

Mailing Address

Award amount including any proposed bid additives

Name of person (and title) that opened the bids

Advertisement date and where and when bids were opened.

2. A copy of the bid analysis including the tabulation of each bidding contractor’s

prices with the Engineers Estimate. Items that have a significant deviation from

the Engineers Estimate in the low bid unit prices are to be highlighted.

3. A detailed explanation if the award is to a bid that is greater than 10% over the

engineer’s estimate.

4. Required completed DBE Forms (C111, C112, C48, & C49)

5. Proof of required bonds

6. Required contractor certification forms (C104 & C105)

For any bid proposal and contract that received significant comments

during the PS&E Package review, VDOT may request that the LPA

submit the final bid proposal and contract for review, to ensure that all

mandatory items were included in the contract. VDOT will only review the final

bid proposal and contract for those items required to be included.

VDOT will make an independent evaluation of the bid, examining the unit bid prices for

reasonable conformance with the engineer’s estimated prices.

Page 85: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-77 December 2017 Project Development

VDOT will also review the bidder’s conformance with the DBE goals or, if necessary,

their documentation of good faith efforts to meet the DBE goal.

Special Program Requirements

Urban Construction Initiative

UCI localities can award contracts on their own but will still need Civil Rights

concurrence (if DBE Goal was established) and will need to provide select information

as shown below to their VDOT Project Coordinator in order for VDOT to update the

funding authorization agreement with FHWA, if necessary. The municipality must

provide the following;

For Civil Rights: the UCI locality needs to submit the following for review (as outlined in Chapter 12.6 in the LAP Manual for Civil Rights):

o DBE Forms C111, C112, C48, and C49

For Construction and Infrastructure Investment Divisions: In order for VDOT to receive funding verification and to update the federal-aid agreement with the FHWA, VDOT would need the following information from the UCI Locality (via email or letter):

o Advertisement date______________ o Bid Date__________ o Bidder Name ___________ o Home town and State_________ o Bid amount_______ o Contingency_________ o CEI___________ o Total amount__

12.6.9.3 VDOT Final Award Recommendation

After VDOT determines that the recommendation by the LPA is acceptable, project

funding is verified through the VDOT Infrastructure Investment Division. After funding

verification the Construction Division will forward to the Project Coordinator the

completed “funding distribution sheet.”

Page 86: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-78 December 2017 Project Development

Prior to final award the Project Administration Agreement must be

amended to adjust for funding expended during the preliminary

engineering and right of way phases, for the estimated construction

costs and (separation) of funding sources (See Chapter 10 of this Manual).

VDOT Responsibilities:

The Project Coordinator will accept and review the Project Award

Submission Package and forward the entire package with a

recommendation to Construction Division for Review;

The Project Coordinator will forward to the DCRM, who will review and

forward to Central Office Civil Rights Division the following:

o Recommended low bidders Name, Mailing Address and Low

Bid Amount and tabulation;

o Required completed DBE Forms (C111, C112, C48, & C49)

Construction Division and the Civil Rights Division will notify the Project

Coordinator if additional information as necessary. The Project

Coordinator will forward the request to the LPA and coordinate

obtaining additional information as necessary;

After resolution of any outstanding items, the Construction Division will

verify funding through the Infrastructure Investment Division and

provide a copy of the funding verification to LAD.

The Project Coordinator will amend the Project Administration

Agreement Appendix A to reflect actual expenses incurred during the

PE and ROW phases and the construction award amount.

Upon receipt of recommendation to award from Construction Division,

the Project Coordinator will notify the LPA Project Manager, in writing

that the project may be awarded.

Special Program Requirements

Urban Construction Initiative

Page 87: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-79 December 2017 Project Development

Civil Rights will review and determine if the DBE goal has been met on the UCI

project (if a DBE goal was set). In addition, the VDOT Project Coordinator will

work with Construction and Federal Programs Management Division to update

the federal-aid agreement with FHWA and to ensure that the project funding is

adequate to cover the recommended award amount including CEI and

contingencies. The UCI Locality will update PCES as necessary.

12.6.9.4 Dashboard (Regular and SMART Scale)

After the project is awarded, LPAs administering projects are required to regularly

coordinate with the VDOT Project Coordinator (PC)/Construction Project Monitor (CPM)

to provide milestone updates. The VDOT PC/CPM is responsible for ensuring the

Dashboard is updated. Projects which are not updated will be reported as late or over

expended according to the business rules of Dashboard. See LAP Manual Chapter

13.1.4.2 for additional details on the VDOT Dashboards and their respective

requirements.

12.6.10 Local Force Construction

Section 33.2-234 of the Code of Virginia provides that state and or locality employees

may be used for construction of projects estimated at $600,000 or less. In addition the

Commissioner of Highways may enter into an agreement with a locality to construct or

maintain any roads in the system of state highways provided the locality has obtained a

cost estimate of not more than $1 million and the locality has received fewer than two

bids from private entities to perform such work.

A “Finding of Cost Effectiveness” shall be submitted to VDOT’s Project

Coordinator and subsequently approved by FHWA. The locality must not

begin construction work utilizing its own forces until such time as it has

received concurrence to do so from the Project Coordinator.

Page 88: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-80 December 2017 Project Development

For non federal-aid projects, all requirements are the same as above, except that the

special federal regulations and a “Finding of Cost Effectiveness” are not required for use

of a locality’s forces to construct a project. However, if a locality requests authority to

perform construction work utilizing its own forces, the request shall be evaluated in the

same manner that VDOT evaluates requests to perform work with state forces. This

includes the requirement that a cost benefit analysis be prepared which indicates that

using locality forces results in lower cost and equal or faster project completion than the

competitive bid process. The cost benefit analysis and supporting documentation shall

be submitted to VDOT’s Project Coordinator. The LPA should not begin

construction work utilizing its own forces until such time as it has received

concurrence to do so from the Project Coordinator.

Page 89: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-81 December 2017 Project Development

12.6.11 Key Submittals / Requirements

Task/Submittal/File

Documentation LPA

Responsibility VDOT P.C.

Responsibility Submittal Timing/

Recordkeeping Requirements

PS&E Submittal Package Ensure a complete quality submittal

Review for completeness, upload pertinent info in iPM, forward to appropriate VDOT staff

LPA to submit at least 30 business days prior to target advertisement date; VDOT to approve & provide advertisement authorization within 20 business days

Project Award Submittal Package

Ensure DBE goals / good faith effort; package is complete;

Construction and Civil Rights Divisions to review

LPA to submit at least 20 business days prior to target award date

Construction Dashboard Information

Enter into VDOT Construction Dashboard

VDOT Construction Project Monitor will ensure projects are in Dashboard at first billing

Immediately after notice to proceed;

12.6.12 References

23 CFR 630, Subpart B Guidelines for Preparation of Plans, Specifications, and Estimates

23 CFR 633, Subpart A – Required Contract Provisions – Federal Aid Construction Contracts

23 CFR 635

Virginia Public Procurement Act; Code of Virginia Title 2.2 Chapter 43

FHWA Contract Administration Core Curriculum Manual

VDOT/FHWA Virginia Division Stewardship Oversight Agreement, June 2015 FHWA Guidelines on Preparing Engineer’s Estimate, Bid Reviews and Evaluation

http://www.fhwa.dot.gov/programadmin/contracts/ta508046.cfm

Page 90: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12-82 December 2017 Project Development

Appendices:

Appendix 12.6 A - Advertisement and Award Submittals Checklist

Appendix 12.6 B – Locality/VDOT Certification of Documents Form

Appendix 12.6 C – Advertisement and Award Checklist

Page 91: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.6 – A-1 December 2017 Project Development

Appendix 12.6 –A Checklist

Advertisement & Award Submittals for Construction

Page 92: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.6 – A-2 December 2017 Project Development

Projects Requiring Authorization to Advertise & Award Submittal for Review The following must be received by VDOT’s Project Coordinator 30 business days prior to advertisement.

1. __ Bid Documents

2. __ Estimate

3. __ Complete set of plans

Submission of Finalized Documents for Projects Requesting Authorization to Advertise The locality shall ensure that VDOT’s Project Coordinator has received the following information for submission to Construction Division no less than 20 business days prior to advertisement.

1. __ Request for authorization to advertise the project

2. __ Current Engineer’s Estimate to include CEI & Contingency

3. __ Copy of the proposal

4. __ Locality Certification of Documents (Complete and Sign Appendix 12.6-B) Submission of Documents for Projects Requiring Authorization to Award After receipt of bids the locality shall ensure that VDOT’s Project Coordinator has received the following information for it to be submitted to Construction Division no less than 20 business days prior to target award date.

1. A letter stating that the locality intends to award the contract to the apparent low-bidder, to include:

Low bidders name

Mailing Address

Award amount including any proposed bid additives

Name of person (and title) that opened the bids

Advertisement date and where and when bids were opened

2. A copy of the bid analysis including the tabulation of each bidding contractor’s prices with the Engineer’s Estimate. Items that have a significant deviation from the Engineer’s Estimate in the low bid unit prices are to be highlighted.

3. A detailed explanation if the award is to a bid that is greater than 10 percent over the engineer’s estimate.

4. Required completed DBE Forms (C111, C112, C48, & C49)

5. Proof of required bonds

6. Required contractor certification forms (C104 & C105)

•All Federally funded projects require VDOT authorization to award

Page 93: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.6 – B-1 December 2017 Project Development

Appendix 12.6B

Locality/VDOT Certification of Documents

Page 94: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.6 – B-2 December 2017 Project Development

(LAP 402A) CERTIFICATION OF DOCUMENTS

(To be completed by LPA Project Manager)

STATE PROJECT#: ________________________ FEDERAL PROJECT #: _____________________

UPC: ___________

NEPA Document Permits (if applicable) N/A Waivers & Design Exceptions (includes criteria) Right of Way Certification (includes Railroad & Utilities certifications) Agreements (includes Railroad, Utilities and Right of Way) Public Hearing/Willingness/Waiver requirements per LAP Manual Ch 12.4 have

been met Design is in accordance with appropriate Design Criteria or Waiver Sequence of Construction/Transportation Management Plan (TMP) (required for

roadway projects) N/A Plans / No-Plan Assembly Proposal

Required Forms Required Federal Provisions & Current Wage Rates Environmental Permits (if applicable) N/A Project Specific Provisions

Current Engineer's Estimate including Construction Engineering & Inspection (CEI), Contingency, Local Forces, Contract Requirements, & Railroad Cost for Budget

Environmental Certification EQ-103 (provided by VDOT) PS&E Re-evaluation (provided by VDOT) R/W Certificate No. __________ Date ____________ (provided by VDOT)

I certify for the subject project the required items listed above and necessary for federal authorization to advertise have been completed, checked and the Proposal & Plans have been prepared in accordance with the standards and requirements included in the Locally Administered Projects Manual and are attached.

__________________________ ______________________ _____________ Locality Project Manager Printed Name Date

VDOT DISTRICT CERTIFICATION

I certify for the subject project the required items listed above and necessary for federal authorization to advertise have been completed, reviewed by District staff, entered into iPM where applicable, and the Proposal & Plans have been prepared in accordance with the standards and requirements included in the Locally Administered Projects Manual and are attached.

VDOT District Project Coordinator Date

Page 95: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.6 – B-1 December 2017 Project Development

APPENDIX 12.6C

Advertisement and Award Checklist

CH 12.6 - Advertisement & Award

This section outlines the requirements associated with advertisement and award of federal-aid and certain state-aid projects. LPA's must follow the outlined procedures in order to ensure that they are fully reimbursed for eligible project costs.

SUBMIT COMPL F S-V S-L T-A UCI Requirement Reference LAP Other

X -- -- X X Submit IFB/Contract for Review

12.6.3 23CFR635

X -- -- X X Mandatory Federal-aid Provisions included in IFB/Contract (incl FHWA1273)

17.3.2 FHWA1273

X -- -- X X Civil Rights Language included in IFB/contract

12.6.5 17.3

X -- -- X X Review for and inclusion of DBE Goal in IFB/contract

12.6.5 17.4

23CFR635.107

X -- -- X X US DOL Minimum Wage Rates

17.3.7 23CFR635.309(f)

X -- -- X X OJT provisions included if

requested by VDOT

17.5 23CFR230.111

X -- -- -- -- Restrict bidders to VDOT Pre-qualified contractors

12.6.6

X X** X** X X PS&E Submittal Package1 - include PSE Submittal form

12.6.2 12.6.7

X X -- X X Engineer’s Estimate with cost summary (CEI, Contingency)

12.6.7

X X -- X X Complete set of plans 12.6.7

X -- -- X X Environmental conditions and commitments documented

15.2 23CFR635.309(j)

Page 96: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.6 – B-2 December 2017 Project Development

X -- -- X X Specifications shall include written instructions for constructing the project or reference VDOT's Road and Bridge Specifications

23CFR630.205(b)

X X -- X X Signed Title Sheet2 12.6.7

X -- -- X X Locality Certification of Documents Completed (Appendix 12-B)

12.6.7

X -- -- X X Evidence of Public Hearing, notice, or Willingness

12.6.7 12.4.5

X X -- X X Receive Construction Advertisement Authorization from VDOT

12.6.7

X X X X X Advertise 21 days &

maintain supporting documentation3

12.6.8 23CFR635.112 VPPA

X X -- X X Publicly read bid-opening & maintain supporting documentation

12.6.9

X -- -- -- X Verify that selected

contractor is prequalified

12.6.6 12.6.9.1

X -- -- X X Ensure selected responsible, low-bid contractor is not de-barred from federal work

12.6.6 49CFR29

X -- -- X X Unit prices do not vary significantly from engineer’s estimate (>25%); bids are not mathematically unbalanced

12.6.9.2 23CFR635.114

X -- -- X X Materials not significantly unbalanced

12.6.9.2 23CFR635.114

X X4 -- X X Submit Project Award Submittal Package for Review

12.6.9.2

X X5 -- X -- Award recommendation from VDOT

12.6.9.3

**State-aid projects funded with formula allocations must receive funding verification and authorization from

VDOT prior to award. A Project Award submittal package must be submitted to the VDOT Project Coordinator.

1PS&E Package is reviewed in Central Office for federal-aid projects; state-aid only are reviewed in District

2 Title sheet must include VDOT signature blocks for federal-aid projects except for TA & UCI

projects.

Page 97: LAP Manual 11-D March 2016 Consultant Procurement

LAP Manual 12.6 – B-3 December 2017 Project Development

3 State-aid projects may be advertised less than 21 days in accordance with VPPA

4 State-aid Formula-funded projects; Concurrence for Revenue Sharing and Access Projects is not required;

prior authorization through CTB action to allocate the funding

5 Award recommendation issued by VDOT