landing gear project final report

57
Project 3: Landing Gear Design & Analysis December 19 th , 2014 1

Upload: kevin-osman

Post on 13-Apr-2017

477 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Landing Gear Project Final Report

Project 3: Landing GearDesign & Analysis

December 19th, 2014

Kevin Osman1

Page 2: Landing Gear Project Final Report

Table of Contents:Executive Summary.....................................................................................................................................3

Introduction.................................................................................................................................................4

Inputs/Details of Analysis........................................................................................................................9

Results of Analysis.....................................................................................................................................10

Discussion of Results.................................................................................................................................11

Summary and Conclusion..........................................................................................................................12

Appendix A: Assembly Drawings...............................................................................................................13

Appendix B: Detail Drawings.....................................................................................................................18

Appendix C: Graphs & Calculations...........................................................................................................35

FEA Analysis Fringe Plots & Convergence Plots.....................................................................................36

Piston Cylinder Displacement vs Time...................................................................................................43

Force vs. Displacement At Each Pin (Retraction and Deployment)........................................................44

Hand Calculations..................................................................................................................................51

Executive SummaryUsing the Creo 2.0 Parametric software for modeling, the objective of this project is to design, model, animate and test a landing gear for planes. Given limited

2

Page 3: Landing Gear Project Final Report

dimensions in the parts that were required in the assembly of this landing gear, good engineering judgment was essential in the entirety of this project. Most of the parts shown in further in this project required the basic knowledge of statics, dynamics, solid mechanics and science in engineering materials. Certain criteria and features needed to be fulfilled in order to adhere the projects requirements. The Landing gear assembly needs to maintain the vertical displacements from Pin F to fuselage as well as Pin F to the ground (2 and 44 inches respectively). Nine components were requested to be used: 4 links (1,3,4,7) a shock absorber, a piston cylinder, a wheel and tire assembly (with a wheel axle serving as a pin), and at least six pins with caps. Proper material were assigned to their respective parts (whose values were found from MatWeb) in order to perform a finite-element analysis and observe the stress distribution and strain energy on each pin. Two servo motors were required for the assembly as well as spring totaling three different simulations that the landing gear had to undergo. The servo motors were inputted into the piston cylinder whose velocity was a function of time in order to allow the pins to slowly approach their max stress values during deployment and retraction. For the spring analysis, a spring was inputted into the shock absorber and was observed as a force of 26,500 lbf was imposed on the tire from the ground. Pins were constrained to links as pin connections and were observed during these simulations in order to analyze the maximum loads on each of the pins as well as the angular velocity and acceleration. The maximum forces on each of the pins were then applied to each part individually to observe stress distribution and strain energy through the use of FEA. In addition the angular velocities at each of the pins were measured as well. After interpreting the data and collecting important mechanical properties of each pin, hand calculations were made in order to compare the accuracy of Creo. By comparing the three methods and seeing that their percent error was relatively low, the computer generated calculations were considered accurate and reliable. Lastly, safety factors were observed on each of the pin to establish the overall structural safety of the landing gear mechanism. After verifying that the project requirements were met, and critically analyzing the results, Creo 2.0 had verified that the design of this landing gear perfectly safe to be used and manufactured for aircrafts.

3

Page 4: Landing Gear Project Final Report

IntroductionThe Landing plays a significant role in the

world of jets and planes. Its importance in

maintaining its structural integrity allows

planes to land smoothly as well as takeoff

efficiently. Most, if not all airline

companies, allow the landing gear to fold

up inside the fuselage in order to increase

the efficiency of the plane’s travel (this

reduces the surface area of the plane thus decreases drag). Figure 1 depicts the generic

version of the landing gear extended in its deployed position. Pins F, A, and D are

considered grounded or “fixed” points thus restricting their motion as the four-bar linkage

both deploys and retracts. Naturally because of this the dimensions of these pins are to

maintain the precise dimensions that were given in the project requirements. Some other

features whose dimensions were to be maintained were the explicit dimensions of the tire

and wheel, the vertical distance (42 inches) separating the ground to the fuselage, and the

distance between the centers of each of the joints. Lastly, the shock absorber assembly

needed to be designed in such a way that mechanism could properly compress during

retraction. The rest of parts included in Figure 1 lacked definitive dimensions since they

were either not included or produced global interferences after modeling/assembling.

This lack of information therefore required the designer to utilize good engineering

judgment in order to determine the proper dimensions to use as well as efficiently piece

4

Figure 1 Generic View of the Project Three Landing Gear

Page 5: Landing Gear Project Final Report

the missing dimensions together. Ultimately, there were a variety of modifications that

needed to be implemented in order to effectively execute the everyday functions of an

average landing gear. Requiring the knowledge of materials science, statics, dynamics

and solid mechanics, the following modifications described below were taken under

heavy consideration and later implemented in the design. The following figure (3)

depicts one of these modifications as the wheel axle takes a unique shape from most of

the designed pins in this design. Although very unique from other pins, its exact

dimensions were required in order to create a snug yet stable

constraint with the wheel and tire assembly. Next to the figure is

the conventional generic pin used in

the assembly to show the general

level of ingenuity and engineering

judgment required due to the vague

dimensions given to the designer

(figure 2).

5

Figure 3- Generic Pin (required dimensions) with a total length of 2.75 in

Page 6: Landing Gear Project Final Report

Another important modification that should be noted is the design of the piston that

attaches to the cylinder. The general dimensions of the original design did not allow the

free movement of the Link 1 bar in order for the landing gear to properly retract and

deploy. Utilizing Creo’s simulation and global interferences applications, the problem

was easily found.

The global

interferences tool

supplied the

designer with a

quantitative measurement of the interference by displaying the total number of volume of

intersection. After noting the issue, it was an appropriate revision to reduce the end

diameter of the rod attaching the two pronged rings on the piston. The two pronged rings

were kept in the final revision because it would later be helpful in maintaining the

symmetry of the entire mechanism which allowed easier stress analysis and calculation.

Figure 4 displays the modified piston whereas figure 5 displays the original outlook of

the piston. Note that the part was also rounded by the modifications in order to reduce

stress concentrations in sharp edges.

6

Figure 4- Modified Piston. Oriented in order to convey the varying curves required for the part. Shaded with edges to enlarge the texture of the rounds.

Page 7: Landing Gear Project Final Report

Figure 5- Original design of the piston. The end of the 1.97 diameter

connecting the ring maintained its diameter throughout the 23.5 inches.

The most obvious modification of the

landing gear however is the shock

absorber. The shock absorber needed to

be evaluated as a rigid structure during

deployment and retraction analysis. Yet

it also needed to compress when a spring was implemented inside the shock absorber and an

external force was exerted onto the tire. To increase the freedom of the compression and reduce

possible friction generated during the spring simulation, both sides of the piston were free to

move along the central axis of the shock absorber. It is important making two freely moving

sliders because it allows the landing gear to deploy/retract without causing buckling of one of the

sliders if let rigid. Also note that the diameter at the opposite sides of the rings of the sliders

have a diameter of 3.0 inches, creating a tight yet snug fit between the sliders and the shock

absorber during the landing gears operations. This restricts the angle of rotation that the sliders

can undergo with the shock absorber thus decreasing the chances of buckling and snapping from

torque. Figure 6 is the modified shock absorber assembly.

Figure 6- Shock Absorber assembly (Sub Assembly II). The sliders are free to move along the central axis of the shock absorber

yet are constrained within the edges of the shell of the shock absorber.

7

Page 8: Landing Gear Project Final Report

The right slider of the shock absorber in figure 6 (termed as link 2 slider 2 in the detailed

drawing section of this report), has also been modified. This length of this slider had been

reduced and expanded outwards in order to prevent global interferences with link 7 during the

landing gear’s deployment operation. Shown below is link 2 slider 2 (highlighted in yellow) as it

allows link 7 (highlighted in orange) to freely pass during deployment. The two pronged rings

also served the purpose of making the entirety of the landing gear symmetrical (useful for same

reasons described when discussing the piston cylinder assembly).

Figure 7- Deployment Simulation. Without the reduced length of link 2 slider 2, link 7 would go through this slider thus causing

global interference thus making deployment an impossible process.

8

Page 9: Landing Gear Project Final Report

Inputs/Details of Analysis:After proper pin placement and constraints, a snapshot was taken at precisely 44 inches

down from Pin F. After simulating the shock absorber as a rigid body, gravity was

enabled in order to make the retraction simulation more realistic. Both servo motors for

deployment and retraction had inputted velocity as a cosine function. This allows the

mechanism to slowly yet safely retract and deploy while shocking the landing gear pins

with an instant force. Simulation requirements included a motor that allowed the entire

wheel to fit above into the fuselage (retraction), as well as a motor that extended the edge

of the wheel to precisely 44 inches (acting as the ground). During this simulation,

measurements were placed on each of the pins (force vs. displacement). As shown in the

picture on the cover of this report, the entire mechanism is symmetrical, indicating that

reaction forces theoretically are the same on either side (pins A,D, and B should therefore

experience the same force reactions at their respective connections due to symmetry). In

order to further understand the efficiency of the landing gear, FEA was utilized. Each of

the pins underwent finite-element analysis to simulate testing for failure. The maximum

forces measured and recorded during deployment

and retraction were imposed on the respective

areas of each pin as shown in Figure 8.

9

Figure 8- Finite-element Analysis (FEA) of Pin D generated by the forces from Link 1

Page 10: Landing Gear Project Final Report

Results of Analysis:

Table 1- Max Force, Max Stress, and Safety Factor at each of the Pins

Pin Maximum Force (lbf) Maximum Stress (psi) Safety Factor

A 11075.69 17637.5 3.628632

B 11082.62 23042.1 2.777525

C 30929.6 25821.3 2.478574

D 41957.71 48080 1.331115

E 33825.66 38240.5 1.673618

F 33837.92 29178.5 2.193396

Wheel Axle 16565.8 36123.7 1.77169

Table 2- Hand Calculations: Bending Moment on Pin D & Shear Stress imposed on Pin F (smallest pin). Spring force and Angular velocity are shown as well.

CREO Value Calculated Value % Error

Bending Moment (Pin D) 48080 psi 42069 psi 14.28

Resultant Stress (Shear on Pin F) 291785.5 psi 35097.79 psi 16.87

Spring Force N/A 29997.50 psi N/A

Angular Velocity 6.8 rad/sec 6.7 rad/sec 1.32%

Force onSpring :k∗∇ sEquation 1-Force on a Spri0ng

Factor of Safety (N )=UltimateYield StressDesignStress

Equation 2- Factor of Safety

10

Page 11: Landing Gear Project Final Report

Discussion of Results:After generating results, stress evaluations for each of the pins are essential in evaluating the conditions

that each undergo due to the applied simulations (retraction, deployment, and applied force with a

spring). Note that it is essential to set the boundary conditions and applied forces in the appropriate

spots in order to generate the most accurate information.

Boundary conditions were set at each end of the pins. This

seemed to be the most appropriate method of measurement

for each of the pins because setting the boundary conditions at

each end theoretically imposes the largest bending stress that

a pin can undergo. Because the stresses will be higher with

these conditions, this will supply the designer with the lowest

safety factors that a pin undergoes (observe Formula 1 for

safety factor). Utilizing good engineering judgment, pin D was further analyzed by hand calculating the

bending moment. Although the project required that the hand calculation was for the largest pin, it

seemed more important to evaluate the bending moment were the smallest safety factor occurred (pin

D had a safety factor of 1.33 whereas the largest pin had a value of 2.77). As shown at the end of the

report, the hand calculation revealed a bending stress of 42069.00 psi. Compared to Creo’s value of

48080.00 psi, there was a percent error of only 14.29%. This reveals to the designer that although Creo

can simulate stresses distributed throughout the pin, its value should not be fully trusted. Similarly, a

hand calculation at Pin F revealed a shear stress of 35097.79 psi, whereas Creo’s FEA revealed a shear

stress of 29178.50 psi. The percent error calculated was 16.87% thus supporting the claim above to not

trust Creo’s calculations without further analysis. Nevertheless, the percent error was within 20% of the

hand calculations, and since each of the analysis established boundary conditions for maximum possible

11

Figure 9- Imposing the cylinder's measured force on Pin F. This is inputted by the designer in order to review stresses and strain energy via FEA.

Page 12: Landing Gear Project Final Report

bending moment, the FEA results shown at the end of the report are reliable and sufficient for design.

In addition, the angular velocity percent error was approximately 1.32%, thus making Creo’s kinematic

analysis very accurate and reliable.

Summary and Conclusion:After creating all necessary parts and assemblies required for the landing gear, it is affirmed that the

landing gear mechanism adheres to the desired conditions and requirements stated on the project

description. Dynamical and kinematical analysis were performed on the landing gear mechanism under

realistic scenarios that most landing gears undergo. Maximum radial forces were observed after running

the simulation and examining the force vs. displacement graphs produced by the piston cylinder. From

here, finite-element analysis allowed us to observe the stress and strain energy conducted on all of the

pins. Table 1 shows the other safety factors for each of the pins utilized in the mechanism. Many main

landing gear structures require a safety factor of 1.25. After comparing some of these safety factor

values to the 1.25 safety factor, all of the pins surpass the 1.25 safety factor thus establishing a

satisfactory performance throughout the entire landing gear mechanism. Some even pass with flying

colors (Pin A and B have a safety factor of 3.623 and 2.77 respectively). Lastly, the maximum bending

movement and shear stresses calculated by Creo were validated by hand calculations, and were

observed to be within 20% error. After designing the landing gear in many different ways, it is also

important to note that the symmetric design seemed to be the most efficient way for reducing the

maximum stress exerted on each of the pins. Finally, it was very valuable to compare Creo’s generated

results with hand calculations. The lesson learned is that there are tradeoffs to using computer

generated calculations in Creo. Although FEA analysis saves time and is fairly accurate, it is not as

accurate or as good as the conventional method of hand calculations.

12

Page 13: Landing Gear Project Final Report

Appendix A: Assembly Drawings:

Sub Assembly 1………………………………………………………………………………………………………………………………..……14

Sub Assembly 2……………………………………………………………………………………………………………………………….……15

Sub Assembly 3 ..…………………………………………………………………………………………………………………….……………16

Final Assembly……………………………………………………………………………………………………………………………………….17

13

Page 14: Landing Gear Project Final Report

Appendix B:

Detail Drawings:

Piston………………………………………………………………………………………………………………………………………………….19

14

Page 15: Landing Gear Project Final Report

Cylinder……………………………………………………………………………………………………………………………….………………20

Wheel……………………………………………………………………………………………………………………….…………………………21

Tire……………………………………………………………………………………………………………….………………………………….….22

Link 2 Slider 1……………………………………………………………………………………………….……………………………………..23

Link 2 Slider 2…………………………………………………….………………………………………….…………………………………….24

Shock Absorber Slider……………….………………….……………………………………….…………………………………………….25

Link 1………………………………………………………………………………………………………………………………………………..…26

Link 3 &4……………………………………………………………………….…………………………………………………………………….27

Link 7…………………………………………………………………………………………………………………………………………………..28

Axle Wheel…………………………………………………………………………………….…………………………………………………….29

Pins F & A…………………………………………………….……………………………………………………………………………………….30

Pins D & C…………………………………………………………………………………………………………………………………………….31

Pin E…………………………………………………………………………………………………………………………………………………….32

Pin B…………………………………………………………………………………………………………………………………………………….33

Generic Cap……………………………………………………………………………………………………..………………………………….34

15

Page 16: Landing Gear Project Final Report

16

Page 17: Landing Gear Project Final Report

17

Page 18: Landing Gear Project Final Report

18

Page 19: Landing Gear Project Final Report

19

Page 20: Landing Gear Project Final Report

20

Page 21: Landing Gear Project Final Report

21

Page 22: Landing Gear Project Final Report

22

Page 23: Landing Gear Project Final Report

23

Page 24: Landing Gear Project Final Report

24

Page 25: Landing Gear Project Final Report

25

Page 26: Landing Gear Project Final Report

26

Page 27: Landing Gear Project Final Report

27

Page 28: Landing Gear Project Final Report

28

Page 29: Landing Gear Project Final Report

29

Page 30: Landing Gear Project Final Report

30

Page 31: Landing Gear Project Final Report

31

Page 32: Landing Gear Project Final Report

Appendix C: Graphs & Calculations:

Pin A…………………………………………………………………………………………………………………………………………………….36

Pin B…………………………………………………………………………………………………………………………………………………….37

Pin C…………………………………………………………………………………………………………………………………………………….38

Pin D…………………………………………………………………………………………………………………………………………………….39

Pin E……………………………………………………………………………………………………….…………………………………………….40

Axle Wheel (Pin)……………………………………………………………………………………………………………………………….….41

Pin F……………………………………………………………………………………………………….…………………………………………….42

Piston Cylinder (Displacement vs time)………………………………………………….…………………………………………….43

Force vs. Displacement at Each Pin (Retraction and Deployment)………………………………………………………..44

Hand Calculations………………………………………………………………………………………………………………………………….51

Bending Moment Validation………………………………………………………………………………………….………….52

Shear Stress Validation……………………………………………………….…………………………………………………….53

Angular Velocity……………………………………………………………………….……………………………………………….54

FEA Analysis Fringe Plots & Convergence Plots

32

Page 33: Landing Gear Project Final Report

Spring:

Pin A1 to link 4A

Spring Force:

Pin B to link 4A

33

Page 34: Landing Gear Project Final Report

Retraction Force:

Pin C to Shock Absorber

34

Page 35: Landing Gear Project Final Report

Spring Force:

Pin D to link 1

35

Page 36: Landing Gear Project Final Report

Spring Force:

Pin E to piston

36

Page 37: Landing Gear Project Final Report

Spring Force:

37

Page 38: Landing Gear Project Final Report

Wheel axle to link 7

Spring Force:

38

Page 39: Landing Gear Project Final Report

Pin F to piston

39

Page 40: Landing Gear Project Final Report

Piston Cylinder Displacement vs Time

40

Page 41: Landing Gear Project Final Report

Force vs. Displacement at Each Pin (Retraction and Deployment)

41

Page 42: Landing Gear Project Final Report

42

Page 43: Landing Gear Project Final Report

43

Page 44: Landing Gear Project Final Report

44

Page 45: Landing Gear Project Final Report

45

Page 46: Landing Gear Project Final Report

46

Page 47: Landing Gear Project Final Report

Hand Calculations

47

Page 48: Landing Gear Project Final Report

48

Page 49: Landing Gear Project Final Report

49

Page 50: Landing Gear Project Final Report

50