land at flass lane, cutsyke - iema · predict impact on environment identify baseline prepare /...
TRANSCRIPT
2
Report Author ............................................ Alastair Cliffe
Report Date ........................................... November 2014
Project Number ....................................................... 3794
Document Reference ........ P0‐TP‐SPA‐RP‐P3794‐0008‐A
Spawforths has been accepted as a registrant to the Institute of Environmental Management and Assessment's (IEMA) EIA Quality Mark scheme. The EIA Quality Mark demonstrates Spawforths commitment to excellence when providing environmental impact assessment services.
3
Introduc on ............................................................................................................................................................. 4
EIA Process ............................................................................................................................................................... 4
Site Descrip on ........................................................................................................................................................ 5
Development Descrip on ........................................................................................................................................ 6
Planning Policy Context ............................................................................................................................................ 7
The Need .................................................................................................................................................................. 8
Considera on of Alterna ves ................................................................................................................................ 10
Highways and Transporta on ................................................................................................................................ 14
Noise ...................................................................................................................................................................... 16
Water Environment................................................................................................................................................ 16
Air Quality ............................................................................................................................................................. 17
Interac on of Effects ‐ Construc on ...................................................................................................................... 18
Interac on of Effects ‐ Opera on .......................................................................................................................... 19
Cumula ve Effects ................................................................................................................................................. 20
Conclusion .............................................................................................................................................................. 21
Contents
4
Introduction
EIA Process
This is the non-technical summary for an Environmental
Statement (ES) which has been prepared on behalf Harworth Estates Ltd, to accompany a hybrid planning application for
residential-led mixed use development at land off Flass Lane, Cutsyke, near Castleford in West Yorkshire. The site forms
part of the housing allocation H23 (Wakefield Council’s Site
Specific Policies Local Plan, September 2012).
A hybrid planning application is one that seeks outline
planning permission and full planning permission for different development proposals on the same site. This document is a
summary of the ES that has been submitted as part of the
hybrid planning application having regard to the Town and Country Planning (Environmental Impact Assessment)
Regulations 2011. The report describes the physical characteristics of the development, its land use requirements,
an outline of the main alternatives considered and a
description of the potential effects on the environment of the
development.
These include:
Direct, indirect or secondary effects
Cumulative effects
Short, medium or long term effects
Permanent or temporary effects
Positive effects
The report also identifies any measures required to mitigate
potential adverse impacts of the proposals within and around the application site. Full details can be found within the
Environmental Statement.
Identify Proposed Development
Scoping Submission
LPA 5 Week Review Period
Review Response & Prepare EIA Report
Predict Impact on Environment
Identify Baseline
Prepare / Finalise Environmental Statement
Consider mitigation
Assess Significance of Impacts
Feedback and consideration of alternatives / Update and amend
masterplan for site
5
Site Description
The application site is located off Flass Lane, Cutsyke near
Castleford. Castleford is located in West Yorkshire, to the
east of Leeds and Wakefield as shown on the plan below.
The site is located between the areas of Cutsyke and
Glasshoughton, suburbs of the settlement of Castleford, the
largest of the five towns of the Wakefield Metropolitan
District. Castleford itself is a former mining town, sited at
the convergence of the River Aire and River Calder. The
settlement is located around 9 miles to the north east of
Wakefield City Centre and around 12 miles to the south east
of Leeds. The southern extent of Castleford, in which the
application site is located, adjoins the east-west route of the
M62 motorway.
To the east of the site is the Glasshoughton leisure, retail and
commercial developments, which include the XScape leisure
complex, Junction 32 retail outlet and associated ongoing
commercial developments on the site of the former
Glasshoughton colliery.
The application site is located on existing agricultural land
which is now allocated for residential development within the
development plan (Site Specific Policy Local Plan, September
2012 Reference HS23). The land around the site to the north
and east is currently subject to a number of regeneration
developments for a number of potential uses which include
commercial / office development, residential development
and potential leisure uses (planning permission obtained for
rugby league stadium). To the western edge of the site lies
Premier Way (Coalfields Link Road) which connects
Glasshoughton with Normanton and Wakefield itself.
The application site relates to an area of land of
approximately 24.76 hectares (61.18 acres) in extent and
includes a large area of the site in use for agricultural
purposes.
The site itself has significant topographical features and slopes
significantly downwards from the southern boundary adjacent
to the M62 to the north alongside the Carr Beck which
forms the northern boundary of the site. In addition the site
slopes downwards towards Premier Way at the western
boundary.
WMDCs hydraulic model results for Carr Beck confirm that
the majority of the site is at a low risk of fluvial flooding.
Minor areas of Flood Zone 3 are located within the north-
western corner of the site, adjacent to Carr Beck.
There are a series of existing trees, woodland and scrub
located within the site which will need to be addressed as
part of any development.
The site constraints plan indicates the area which is most
affected by noise from the M62 motorway, this is along the
southern part of the site to the north of a route to be
safeguarded for a potential future link road.
The steepest gradients within the site are located within the
western part of the site running north to south and will need
to be taken into account as part of the development
proposals.
An existing pond and watercourse is located on the site to
the north east with the watercourse running north to south
across the site in this part. Existing trees are also located
within this area.
There is some evidence of archaeological interest within
areas of the site which would be subject to further
investigation prior to construction.
6
Development Description
The planning application is a hybrid with part of the proposals
for the site applied for in full and part in outline.
The development of up to 560 dwellings, up to 930 m2 of
restaurant/pub uses (A3/A4) and up to 4,700 m2 of B1 (office and light industrial) use will also be accompanied by two
electricity substations and a pumping station. Recreational
open space will also be provided, along with ecological mitigation areas, predominately in areas around the proposed
water attenuation ponds. Internal access routes will be confirmed through the application for approval of Reserved
Matters but the pedestrian and cycle links are shown on the
Parameters Plan and the Indicative Masterplan shows how other routes and connections (pedestrian, cycle and
vehicular) could be provided.
Matters in Outline:
Outline application for the erection of a new build housing
development for up to 560 residential dwellings (C3), up to 930 m2 of restaurant/pub uses (A3/A4), up to 4,700 m2 of B1
(office and light industrial) use, two electricity substations, a pumping station, recreational open space, ecological
mitigation areas, internal access routes, ground modelling and
drainage works including SuDS, ponds and swales, parking provision, footpaths, cycle routes and associated works
including access and landscaping details at land to south of Flass Lane, Cutsyke.
Matters in Detail:
Full application for earthworks, ground modelling and remediation to provide development platforms for
development of site for up to 560 dwellings and ancillary commercial and business uses at land to south of Flass Lane,
Cutsyke.
Applica on Site Boundary
7
Planning Policy Context
Planning Policy supports schemes that will assist in
regeneration and encourage growth and investment into Wakefield.
The statutory development plan for the consideration of this application comprises the Wakefield Local Development
Framework (LDF):
Core Strategy (CS), April 2009
Development Policies (DP), April 2009
Site Specifics Proposals Document (SSPD), 12
September 2012
The LDF replaces many of the policies in the Wakefield
Unitary Development Plan First Alteration adopted January 2003 (UDP). However the remaining saved policies of the
UDP, including Retail, Leisure and Open Space policies, remain part of the statutory plan.
The Council adopted the Site Specifics Policies – Local Plan
Document (SSPD) on 12 September 2012. The SSPD provides a set of site allocations and proposals to meet the
vision, objectives and development strategy of the Core Strategy. The document includes land allocations to meet
anticipated development needs relating to housing,
employment and mixed use development. These proposals replace equivalent allocations and designations in the saved
UDP.
The SSPD was submitted to the Secretary of State in early
2011 and the Inspector held public hearing sessions during
December 2011 and January 2012. The Council received the Inspector's Report about the Examination of the SSPD on 8
June 2012. The Inspector concluded that in general terms, the SSPD is generally sound, and subject to the Council
adopting the Inspector's recommended modifications, the
SSPD satisfies the criteria for soundness in accordance with the NPPF (which are; positively prepared, justified, effective
and consistent with national policy.
The application site forms the majority of housing allocation
(Policy HS23 – Flass Lane, Cutsyke), which identifies the site
for housing, to be developed within the plan period. Policy HS 23 states:
This greenfield site is situated to the west of SPA5.
If access is taken from Glasshoughton Coalfields Link Road, then
the impact on that road and its junctions would need to be assessed in a transport assessment. The wider network would also
need to be considered, including M62 J32. One potential access road through the site has planning permission as part of the
proposed new stadium and associated development on the
adjoining former Glasshoughton Colliery site. Mitigation measures will be required to improve accessibility to local services and public
transport, for which developer contributions may be required. A travel plan must accompany the transport assessment for this site
in order to minimise the impact of traffic on the strategic road
network. The need for physical mitigation measures on the strategic road network must be investigated. The details of any
proposed mitigation measures, including their funding and implementation, should be agreed with the Council and the
Highways Agency.
Flood risk is a significant issue in this area and all development proposals must be accompanied by a flood risk assessment which
should address all relevant issues. Housing units will be excluded from the areas covered by flood zones 3a. These areas could be
used for ancillary open space, subject to safety considerations.
Phasing will need to be co-ordinated with the upgrading of the waste water treatment works. The site lies within an Air Quality
Management Area and will require an air quality assessment. Proposals will be required to contribute to air quality improvement
measures. Public rights of way will need to be maintained and
improved to provide pedestrian / cycling routes to Glasshoughton station, Xscape and Pontefract Park. Development proposals must
take full account of the Wildlife Habitat Network status of the site. In view of the site's former uses, a phase I desktop
contaminated land study will be required for proposed housing
areas. A bus service enhancement package will be required and should feature in masterplanning for this site. Local provision of
natural greenspace will be required. A Health Impact Assessment will need to be undertaken. The site coincides with an area of high
archaeological potential therefore a desk-based archaeological
assessment will be required, but if this cannot assess the interest a field evaluation will be required.
This site is located in an area where there is a key policy objective to provide employment and skills development opportunities for
local residents. The Council will seek to secure these opportunities as far as possible.
8
The Need
The Index of Multiple Deprivation for England (IMD 2010)
ranks Wakefield as 67th most deprived out of 354 Local Authorities. Therefore people in the District are living in
neighbourhoods among the top 10% most deprived in England and which accounts for 12.5% of Wakefield’s
population. The Index of Multiple Deprivation shows the
District has high levels of deprivation in employment, income, health, education and skills, with the highest levels
concentrated in pockets of main urban areas, particularly Wakefield and Castleford.
Castleford is the second largest settlement in the Wakefield
District, after the main urban centre of Wakefield. It has historically had a coal mining focus and more recently an
industry focus (particularly chemical industry), both of which have seen significant decline. This is reflected with Castleford
identified as one of the most deprived areas within
Wakefield. Some areas in Castleford fall within the 5% most deprived wards in England, according to the Indices of
Multiple Deprivation. Unemployment rates in Castleford are higher than the Wakefield and Regional average.
This has resulted in the need for significant regeneration of
the area. The major development of leisure, employment and retail at Glasshoughton adjacent to the M62 Motorway
Junction 32 (Xscape) has helped to kick start the regeneration of the area and encourage growth and
investment. The application site is located adjacent to and
within the former operational land of the former Glasshoughton Colliery, the buildings and pit head of which
was sited on the current site of the Xscape leisure development and surrounding retail and leisure uses. On this
basis, there is clearly an identified economic imperative within
the locality to increase investment and regeneration and the area is undergoing a series of regeneration initiatives designed
to address the economic decline and associated issues as a result of the collapse of the coal mining industry.
In respect of housing, there is a significant need to deliver
housing in Wakefield and this has been confirmed within the evidence base for the LDF. As a District, Wakefield’s housing
requirements, originally set out in the Regional Strategy (2008), are reflected in the LDF as a minimum of 1,600
dwellings per annum up until 2026. WMDC’s housing objectives are to provide an adequate and continuous supply
of housing in sustainable locations to meet the housing
requirement set out in the LDF. In addition to this there is a need for a range of housing types, sizes and affordability that
is appropriate for its location.
In WMDC’s Core Strategy (15 April 2009), Wakefield Castleford and Pontefract are identified as the main centres
where the Spatial Vision, Spatial Objectives and Policy CS1 (Location of Development) is for these settlements to be
where the most homes, jobs and services are to be located,
which also have links to the Leeds housing market. Castleford is a Principal Town in the District settlement
hierarchy and as such needs to accommodate a share of at least 20% of the District’s housing requirement, being a focus
for local development and services and reflecting its capacity
for growth, urban renaissance priorities and urban regeneration.
The site has been allocated to help meet the housing requirement as one of the sites considered appropriate to
accommodate this growth (Policy HS23 in WMDC’s Site
Specific Policies Local Plan, September 2012). The application site forms part of this wider site allocation for residential
development and will assist in delivering new housing within the District. The need for the application site to come
forward for housing has therefore been fully considered
through the LDF where the application site and wider site allocation have been considered to be a key element of the
housing delivery necessary to meet the District’s needs.
The site allocation, in which the application site is located, is
not identified for development within a later phase of the
plan period, and therefore there are no restrictions on the timescales for development coming forward in this location.
On this basis, through the development plan process, the Plan accepted that the site was deliverable immediately, and
therefore should come forward within the first five years of
the plan. Furthermore, recent housing data set out within the Annual Monitoring Report for 2013 indicates that the
Council is currently falling significantly short of delivering housing completions to the target set out within the
development plan. On this basis there is an identified need
to increase delivery of new homes and make a concerted effort to address recent shortfalls in housing delivery as soon
as possible.
The planning application submission indicates that, subject to
the expected remediation and earthworks and normal site start up works, that there would be no limitation to the
delivery of homes on the site within a relatively short period
of time.
9
The Need Continued . . . Alongside Pontefract, Castleford is the largest of the Five
Towns in Wakefield. The Five Towns are also part of Wakefield’s urban renaissance programme. The Five Towns
were identified in the Community Strategy as an area needing regeneration. The aim of the Five Towns is to create a group
of inter-dependant and self-sustaining, but distinct
settlements, seeking to reverse the decline of the areas after the decline of mining. They are to attract development and
address transport issues, creating new communities and high quality places to live and work as well as attract investment.
As identified in WMDC’s Core Strategy, the Five Towns are
settlements that share strong historic, economic, and cultural links based around the growth and subsequent decline of coal
mining and other industries. The Strategic Vision in WMDC’s Core Strategy is to transform the Five Town
settlements, providing new housing, economic opportunities,
good quality transport links and high quality environment. For Castleford, the focus is also urban transformation with
redevelopment opportunities as well as relocation opportunities.
Housing led regeneration is recognized at a national level and
within the Five Towns SDF as a significant and powerful tool to regenerate such areas. This indicates that such
development would lead to increase spending power within those areas, along with additional employment opportunities
and associated community benefits. The SDF proposes that
the renaissance of Castleford should be delivered through a mix of uses including residential, retail and commercial
development all of which will provide a strong regeneration agenda.
The current wider economic context in the country is also
relevant to the proposed development. The economic decline and the depressed housing and investment market
have continued over a number of years and opportunities for such investment remain high on the Government's priorities.
The Localism Act, NPPF and Ministerial Statements and
Budgets (including Planning for Growth and the recent Housing and Growth Statements) recognise the significant
economic imperative of encouraging new development proposals within appropriate locations, and the planning
system plays a key role in this approach to facilitating new development proposals. In particular, the Government’s
Planning for Growth strategy requires significantly more
development in suitable and viable locations with an expectation that the answer to growth should be ‘yes’ except
where it compromises key sustainable development principles. The National Planning Policy Framework (NPPF,
2012) also supports this with an extremely strong emphasis
on sustainable development and growth with a clear
presumption in favour of sustainable development.
As well as meeting the housing requirements for the area, the
location of the site with good accessibility to the centre of Castleford means that it also provides an opportunity to
support the regeneration and rejuvenation of Glasshoughton
and Castleford, by maximizing the potential to retain expenditure within the immediate economy and stimulate
local business growth.
The areas identified for commercial uses within the
application site are more suited to that purpose rather than
being sterilized due to their unsuitability for residential development. On this basis, the incorporation of other
commercial uses, which offer an opportunity for further investment and the creation of local job opportunities
represents an additional opportunity over and above the
housing development assumed within the allocation. The additional land uses can therefore be seen to be consistent
with the overarching principles of the Plan, and of the policies within the Framework, which seek to support sustainable
development unless there are significant and demonstrable
impacts to indicate otherwise.
The scheme will deliver both housing and commercial
developments which will contribute to the local economy in different, but complimentary ways throughout both
construction and operational stages of the development.
Commercial elements, including office uses, leisure (restaurant) and related development, would contribute to
employment creation throughout the construction and operational lifetime of the scheme, supporting and being
supported by the main residential elements of the scheme.
Based on the National Housing Federation “Home Truth 2013/2014: The Housing Market in England” information an
average of 2.3 jobs are created in the wider economy for each house constructed. For the application proposals this
will create 1288 jobs.
The proposed development would clearly represent a significant economic investment within the area which would
have long term economic and related socio-economic benefits to the local and wider areas.
There is therefore a proven need for the proposed development to come forward, which is further supported
through the allocation of the site for housing, the need for
regeneration in the area, the current significant under delivery of housing and the Government’s focus on
sustainable growth and development.
10
Consideration of Alternatives
Do Nothing
To do nothing with the site would mean the site was retained
as existing and therefore as agricultural fields, scrub land and
trees. This would mean that the housing needs in the
District would not be met through the development of the
most sustainable sites. The effect of this would be to sterilize
the redevelopment of sustainably located sites. This would
therefore not allow the significant need for new housing to
be met, which would be contrary to local and national
planning policy as well as fundamentally contrary to the Core
Strategy, Site Allocations Local Plan and NPPF.
Whilst the retention of the site as agricultural fields may have
some environmental benefits, there are a number of
environmental improvements that would not be
secured. The ability to secure management of the green
infrastructure within the site and the enhancement of
ecological habitats would be lost as would a managed
drainage strategy for the site, which creates
betterment. Whilst the scheme is viability led, and this will
determine the level of necessary planning contributions, these
will include affordable housing which would not be secured
on this site if the proposed development did not come
forward. Subject also to the viability of the scheme, the
development could also potentially contribute to the
enhancement of existing play space and education provision,
and again this would be lost without the development of the
site.
There are also a series of socio economic benefits as a result
of the proposals, that would be lost if the scheme was not
delivered. These are detailed within the ‘Need’ section
above, but include helping to address the regeneration needs
of Castleford, given its ranking as a deprived area; increasing
investment in the area; provision of employment
opportunities, direct, indirect, short term and long term
through construction and end uses; and support and
underpinning of existing and new services and facilities by
providing additional residents and employees in the area.
The alternative to the redevelopment of the application site
would mean that development would have to be provided
elsewhere. Given the sustainability of the site, close to
Castleford, development elsewhere would ultimately be in a
less sustainable location and would put pressure on further
Green Belt release. This would lead to increased impacts on
the environment, especially from those associated with
traffic, noise and air quality with the development of less
sustainable sites and potentially greater impacts on ecology
and the landscape.
Preferred Option - Compliance with Development
Plan
There is a significant need for development and growth in
Wakefield to provide the houses and jobs needed as well as
to secure the much needed regeneration. The application
site is part of a wider site allocation (Policy HS23 in WMDC’s
Site Specific Policies Local Plan, September 2012) that is
allocated for residential development through the Local
Development Framework (LDF). As the site is allocated
within the LDF it has been subject to a Sustainability
Appraisal undertaken by WMDC. This means that the site
was considered comparatively with many other sites and was
therefore chosen as the best alternative to meet the
identified needs in this location. The environmental merits of
this have been considered in detail through the evolution of
the LDF in consideration of sites for allocation.
There have been a number of iterations to the scheme to
reach the proposed development, which have been
influenced by the quantum of development and
environmental and design considerations.
11
Consideration of Alternatives Continued . . . Preferred Option – Design Evolution
Following the confirmation of the preferred use for the site, the detailed layout for the site has evolved, with
consideration of the technical constraints and environmental impacts being key to the design evolution in order to
minimise its environmental impact. This has been heavily
influenced by the environmental assessment work as well as community consultation and stakeholder engagement.
The mix of development proposed has evolved through consideration of the environmental constraints of the site.
No alternative access points to the site were considered,
given the existing access to the Premier Way/A6539/B6421 roundabout and the need to incorporate the safeguarded
route for the Link Road through the site, this was considered the best location for an access point rather than constructing
an alternative one in an alternative location along Premier
Way. As such consideration was only given to the need to improve the roundabout junction, which was dictated by
highway safety and junction design requirements.
As part of the proposals, there is a need to include a
safeguarded route for a propose link road from the land to
the north east through the site to Premier Way. In this case, the protected route is not prescriptive and as such these
proposals include a safeguarded route for an alternative route along the southern edge of the site, as opposed to the
approved route which crossed the centre of the site.
The site is allocated for residential development, however the proposals include elements of employment (A3/4 and B1
uses). These are identified on areas that are not suitable for residential development, due to noise impacts from the
motorway. This therefore ensures the most effective and
efficient use of land so these areas are not sterilized from development or any effective use. It also enables a mix of
uses to be accommodated on the site, creating needed job opportunities which bring socio economic benefits and
additional buffers between the residential development and
the noise generated by the M62 Motorway.
To the north of the site, a standoff from the northern
boundary was required to ensure residential development was outside the areas of flood risk and therefore entirely
within Flood Zone 1. Areas were required for surface water attenuation to serve the development, which were identified
for the lower lying areas of the site and therefore also close
to Carr Beck, but also so as not to drain across other
existing water features within the site. These would also
maximize the retention of trees and vegetation in areas to the north of the site and maximize opportunities for
ecological benefits as a result of development.
The final proposals locate the attenuation areas to the north
west of the site. These were chosen to balance the need to
incorporate these areas close to the beck, enable them to work effectively as part of the drainage strategy for the site,
and the need to minimise cut and fill within the site and therefore the import of material, which has other
environmental impacts in respect of traffic flows and noise
and dust.
Various options have been considered to achieve appropriate
finished levels across the site, whist looking to minimize the change in levels across the site by minimizing cut and fill to
minimise the need for the import of material. This also
needed to be balanced against the need to achieve a drainage strategy that works, and an appropriate level and design of
development. From consideration of design and layout, there was a need to achieve the ability to create streetscenes that
would follow the contours of the site, avoiding the steepest
gradients. From the consideration of the quantum of development, the proposals need to be capable of helping to
meet the housing need in the area by achieving an effective and efficient use of this sustainable site, thereby also reducing
the need for additional housing in less sustainable locations.
The location of the public open space within the site also underwent various alternative designs. As a result of
reducing the size of the surface water attenuation pond it was possible to locate much of the POS in areas to the north
of the site, providing a pleasant environment and amenity
area for the site as well as maintaining the corridor along the beck for ecological benefit. With the location of the main
attenuation ponds to the north west of the site, two varying areas of open space could be created, one around the main
attenuation pond and the other to the north east of the site,
which would also create the potential for kick about area close to a retained area of scrub and woodland, as well as
close to a proposed pedestrian/cycle connection with the Public Right of Way (PROW) to the north of the site. The
concentration of these areas to the north of the site has the ability to create environmental benefits by maintaining and
enhancing the corridor for the beck, particularly in respect of
ecology and nature conservation, visual, landscape, drainage and flood risk.
12
Consideration of Alternatives Continued . . . The proposals seek to retain as much of the vegetation and
trees as possible within the site, whilst also trying to achieve
an effective and efficient use of the site to meet the housing
needs of the area, and balanced against the need to minimise
other environmental impacts that result from cut and fill and
the import of material and achieve an effective drainage
strategy for the site. By not incorporating an acoustic barrier
to the southern boundary of the site, the trees and
vegetation along this boundary could be retained. By
prioritizing the importance of the corridor along Carr Beck
and watercourse to east of site area, the vegetation and trees
within these areas could be retained as far as possible and
areas of open space incorporated to maximize these as green
corridor areas. Whilst every effort has been made to retain
the hedges and trees within the body of the site, this has not
been possible in all instances given the topography of the site
and the need to create development platforms as well as
make the most effective and efficient use of the site.
However, landscaping is an important component of the
proposals and suitable landscaping will be part of the
redevelopment to contribute towards the vegetation lost.
From the noise assessment work, not only was there a
requirement for a buffer area to be created between the
motorway and residential development, but the orientation
of dwellings was also recognised as an important
consideration to ensure appropriate noise levels for internal
and external residential spaces can be met. In addition an
area where physical barriers to private external amenity
areas has also been identified towards the south of the site.
Therefore, the Parameters Plan identifies areas where
residential development must face onto the main routes, such
as the safeguarded Link Road and Premier Way, to create
continuous frontages of development and the area where the
physical barriers to private external amenity space will need
to be considered as part of any final scheme (supported by
further noise assessment work). This meant that, where
possible garden areas would be to the rear of the properties
and gaps between buildings managed with physical barriers
(close boarded fencing or walls), the exact location and
height of which would be determined through the detailed
design stage, but as a minimum would be 1.8m in height and
on the indicative masterplan, between 2.1 and 2.5m in height.
The Indicative Masterplan shows how this could be
achieved .For good design, it was also considered that other
areas should also be identified for building frontages, such as
along around the areas of open space/surface water
attenuation and fronting onto Premier Way.
Through the noise assessment work, the need for a noise
attenuation barrier to the M62 Motorway was also
considered. However, given the location of the employment
development proposed as part of the scheme, the buffer
already incorporated between the motorway and the
proposed residential development as well as design
considerations as to the orientation of properties and the
incorporation of trickle venting and appropriate glazing, it
was considered that an additional acoustic barrier to the
motorway would not be of any additional benefit to reduce
the noise from the motorway for the residential properties.
This was also balanced against the visual appearance of such a
barrier and the loss of the vegetation to the southern
boundary of the site that would need to occur to
accommodate it.
Pedestrian and cycle links have been incorporated and have
been re-visited each time the masterplan has evolved to
ensure suitable connections can be provided. These are
identified on the Parameters Plan. The redline has been
extended to the south east of the site to enable a connection
to be made to the PROW beyond the south east of the site.
The location of the pumping station has also been
considered ensuring sufficient standoff can be achieved to
residential dwellings for reasons of noise and air quality. An
underground option has also been considered most
appropriate to avoid the need for any buildings or stacks to
reduce its visual impact.
14
Highways and Transportation
The Traffic and Transportation Paper considers the effects of
the proposed residential led development upon the traffic
and transportation conditions within the vicinity of the Flass
Lane, Cutsyke development.
The impacts of the proposals have been assessed both during
its construction phase and also during the operational phase,
when all of the houses and businesses are fully occupied.
The impacts of the proposals have been assessed through a
comparison of the traffic and transport conditions within the
surrounding area both without the development and with the
development. A Transport Assessment (TA) supports the
application; this report contains full technical details of how
the development has been assessed. The transportation
section of the Environmental Statement (ES) summarised the
impacts of the development on a more easily digestible
format for readers without the technical knowledge to fully
understand the TA.
Baseline data has been collected through specially
commissioned surveys including roundabout vehicle turning
counts, queue length surveys, daily and weekly link flow
counts, speed surveys and procurement of accident data.
The scale of impacts identified through the assessment
process has been defined for each of the traffic and
transportation parameters and these have been categorised
as impacts which are either substantial, high, moderate, minor
or negligible based upon a set of appropriate assessment
criteria.
The study area for the assessment of traffic and
transportation impacts has been set out through the
submission of a scoping note to Wakefield Council and the
Highways Agency. Detailed assessment of the highway
network has been assessed at the following:
Cutsyke North Roundabout;
A639 Leeds Road/A6539 Premier Way roundabout;
Asda/A6359 roundabout;
Colorado Way/Tomahawk Trail roundabout;
Retail Access (west);
Retail Access (east);
M62 Junctions 31 and 32 Slip Road Assessments
A large number of committed developments in the area have
also been taken into consideration in the assessment through
either the specific inclusion of the traffic associated with
those development predicted as part of their approved
planning applications or through the application of growth to
the traffic counts. This specific element of the methodology
has been agreed in full with the Highways Agency and
Wakefield Council.
The results of the junction capacity assessment have shown
that all tested junctions will continue to operate within
operational capacity with the exception of the Asda / Leeds
Road roundabout. This junction is predicted to operate in
excess of operational capacity even without the Flass Lane
development. A mitigation scheme has been proposed that
will increase the capacity of the roundabout such that it
operates no worse with the addition of the Flass Lane
development traffic.
It has been calculated that the traffic levels during the
construction phase are significantly lower than the volume of
traffic generated by the proposals during its operational phase
and therefore the traffic-related environmental impacts
associated with the proposals during the construction phase
will therefore be lower than during the operational phase.
The analysis has shown that all of the impacts during the
construction phase will be negligible.
The overall environmental impacts of the development
proposals in traffic terms has been shown to range from
negligible to minor adverse impacts across each of the
potential impacts following the implementation of the Asda
roundabout mitigation scheme.
16
Noise A noise assessment has been undertaken with regard to
assessing the potential noise effects of the Proposed Development.
Given the proximity of the Site to the M62, the principal consideration as part of the assessment is to establish the
effect of noise on future residents within the site. Minimising
noise levels within the site to protect external amenity was an integral part of the evolution of the illustrative masterplan
and parameters plan. Detailed noise modelling has been undertaken to establish the suitability of the proposed
residential development with the requirement for additional
mitigation which will need to be considered during the detailed design stages also identified. The additional
mitigation measures include a suitable scheme of sound insulation to dwellings which is anticipated to include the
requirement for alternative ventilation, such as trickle vents,
to be provided for some dwellings to meet acceptable internal noise levels. In private external amenity areas, where
it is not feasible to provide screening from the M62 and Premier Way by orientating private amenity spaces (gardens)
to the rear of dwellings, barriers (e.g. close boarded fences)
will be required to be considered. The assessment undertaken demonstrates that acceptable levels of amenity
will be afforded to future residents. The requirement to
address these matters, which are dependent on a finalised
building layout, can be enforced through the use of a suitably worded planning condition.
With regard to the construction phase, at this stage of the process, the assessment of noise and vibration effects have
been scoped out. This is on the basis that through standard
mitigation measures implemented by the Contractor and enforced through suitably worded planning conditions, levels
of unacceptable noise and vibration will not be generated during this phase.
During the operational phase, an assessment has been
undertaken with regard to the change in traffic flow on the internal road network within the site boundary and off-site
roads. The change in noise level at all off-site residential properties will not be perceptible.
Committed developments have been taken into account
within the assessment. This includes the Castleford Tigers Stadium link road which runs along the southern part of the
site even though the delivery of the stadium is still uncertain with the link road conditioned to be delivered as part of that
scheme.
No significant sources of vibration will occur during the
operational phase of the assessment.
The site is predominantly situated in Flood Zone 1 with no
significant risk of fluvial flooding for the residential
development in that area. A small part of the site is in Flood
Zones 2 and 3 with moderate to high risk of fluvial flooding
but no built development is planned in this area and therefore
no mitigation is required.
Surface water run-off will be mitigated on site by appropriate
Sustainable Urban Drainage Systems, related surface drainage
techniques, including attenuation storage in swales and ponds,
and discharged to the off-site watercourse, Carr Beck, at the
site boundary at the Greenfield rate. The residual impact will
consequently be negligible.
Subject to a Yorkshire Water feasibility study, foul sewage
will be discharged to the public sewer system via a new
pumping station and rising main designed to serve the new
development.
There will be minor adverse impacts at both construction
and operational phases relating to runoff and water quality
and foul sewage disposal which will be mitigated by best
practice, leading to negligible residual impacts.
Water Environment
17
Air Quality
An Air Quality assessment has been undertaken with regard
to assessing the potential air quality effects of the Proposed
Development, in accordance with the methodology and
parameters described within the ES Technical Report.
The main emissions during construction are likely to be dust
and particulate matter generated during earthworks,
construction and trackout. Mitigation measures have been
included within the Construction Management Plan (CMP) in
accordance with the Institute of Air Quality Management
Guidance. Incorporating these mitigation measures into the
CMP will result in a negligible impact at all receptors.
During the operational phase, transportation is identified as
the dominant emissions source that is likely to cause
potential risk of exposure of air pollutants at receptors. The
principal traffic derived pollutants likely to impact local
receptors are nitrogen dioxide (NO2) and particulate matter
(PM10). As such, the air quality assessment has determined
the predicted impact of changes in ambient nitrogen dioxide
(NO2) and particulate matter (PM10) as a result of the
proposed development generated traffic flow on the local
road network. The changes have been compared to EU air
quality limits and UK air quality objectives. Local and national
planning policies have also been referenced accordingly.
Detailed air dispersion modelling has been undertaken to
establish the changes in emission levels. The assessment has
concluded that the overall impact of the proposed
development ranges from ‘negligible’ to ‘minor adverse’, with
no significant effects predicted to occur. A further cumulative
assessment which includes the proposed Castleford Tigers
Stadium Link Road (a committed development) has also
concluded that effects in terms of NO2 and PM10 are not
significant.
As such, the development is not considered to be contrary
to any of the national, regional or local planning policies.
Receptor Plan
18
Interaction of Effects of Construction
C
O
N
S
T
R
U
C
T
I
O
N
I
M
P
A
C
T
S
En
viro
nm
enta
l Eff
ects
Co
nst
ruct
ion
Ph
ase
Tra
ffic
an
d
Tra
nsp
ort
Wat
er E
nvi
ron
men
t N
ois
e A
ir Q
ual
ity
Mit
igat
ion
Incr
ease
in c
onst
ruct
ion
Tra
ffic
x
x
x
Con
stru
ctio
n M
anag
emen
t Pl
an
Eart
hwor
ks /
Con
stru
ctio
n x
x x
x
Prov
isio
n of
a c
onst
ruct
ion
man
agem
ent
plan
Surf
ace
wat
er r
un-o
ff an
d al
tera
-
tion
or d
isru
ptio
n to
exi
stin
g
wat
erco
urse
x
Con
stru
ctio
n M
anag
emen
t Pl
an a
nd t
empo
rary
sur
face
wat
er
man
agem
ent
Wat
er q
ualit
y / w
ater
pol
lutio
n
x
Con
stru
ctio
n M
anag
emen
t Pl
an
19
Interaction of Effects of Operational
O
P
E
R
T
I
O
N
A
N
L
I
M
P
A
C
T
S
En
viro
nm
enta
l Eff
ects
Op
erat
ion
Ph
ase
Tra
ffic
an
d
Tra
nsp
ort
Wat
er E
nvi
ron
men
t N
ois
e A
ir Q
ual
ity
Mit
igat
ion
Incr
ease
in T
raffi
c
x
x x
Tra
vel P
lan
Off-
site
junc
tion
impr
ovem
ents
– A
sda
Junc
tion
(A65
39/A
639)
Si
te A
cces
s ju
nctio
n im
prov
emen
t to
cre
ate
four
arm
rou
nda-
bout
Fu
ndin
g to
war
ds h
oppe
r bu
s se
rvic
e
Inte
rnal
and
ext
erna
l noi
se le
vels
from
exi
stin
g no
ise
sour
ces
x
App
ropr
iate
gla
zing
and
ven
tilat
ion
sche
me
(det
ails
to
be c
on-
firm
ed a
t de
tail
desi
gn s
tage
)
Barr
iers
to
exte
rnal
gar
den
area
s (i.
e. w
alls
or
fenc
ing)
(de
tails
to
be c
onfir
med
at
deta
il de
sign
sta
ge)
Cha
nge
in s
urfa
ce w
ater
run
off
x
Surf
ace
Wat
er M
anag
emen
t Sc
hem
e
Add
ition
al L
oad
on p
ublic
foul
sew
erag
e sy
stem
x x
x
Pum
ping
sta
tion
with
app
ropr
iate
sta
nd-o
ff di
stan
ce t
o re
side
ntia
l
deve
lopm
ent
Cha
nge
in w
ater
qua
lity
due
to
spill
age
of o
ils, f
uels
etc
..
x
Ree
d be
ds in
ope
n po
nds
and
swal
es
20
Cumulative Effects
There are a number of developments that need considering
given the likely impact they will have cumulatively with the
application development. These include developments with
planning permission but which are not yet built; sites
allocated for development or any other known future
proposals.
A list of committed developments have been agreed with the
HA and WMDC for consideration as part of the traffic work
and therefore are also considered as part of the noise and air
quality assessments. These committed developments have
been considered through the consideration of the
development proposals as part of the environmental
assessment and as such are not considered further as part of
the assessment of cumulative development. The Stadium
Link Road (SLR), for which a safeguarded link is proposed as
part of the application proposals is however considered as
part of the cumulative assessment for traffic and transport,
noise and air quality.
There are not considered to be any cumulative effects in
terms of water environment due to the distance and/or
relationship of the sites from the application site or because
the developments are already near completion on site. Each
of these schemes will in any case need to control their
surface water run off so as not to create any flood risk issues
to other areas both during construction and operation
phases.
The introduction of the Stadium Link Road (SLR) would
minimise the effect of the development on the highway
network as it would allow the redistribution of traffic.
In order to produce an extremely robust assessment of the
traffic using the local highway network the Transport
Assessment work undertaken has not taken into account the
proposed SLR. This approach is agreed with both the
Highways Agency and Wakefield Metropolitan District
Council and is considered appropriate given that the delivery
of the Stadium is still uncertain and the SLR is conditioned to
be delivered as part of that scheme.
In the event of the SLR being brought forward by a third
party, it will serve to reduce the volume of the traffic on the
assessed local highway network by routing them more
directly to the strategic highway network at Junction 32. It is
therefore an extremely robust assessment method that is
contained in the Transport Assessment identifying the worst
case position. This is also the position assessed by noise and
air quality.
In terms of air quality (N02 and particulate matter), the
cumulative effects are assessed as negligible when applying
the ES methodology. As with the highway cumulative
assessment, this is a worst case scenario as it assumes no
reduction in background air quality concentrations beyond
2011; it does not assume improved emission rates associated
with road traffic; and it does not consider any reductions in
traffic on other roads as a result of the SLR.
In terms of noise, standard double glazing will bes ufficient
whilst the requirement remains for alternative ventilation to
be provided to habitable rooms in areas closest to the M62.
As such significant effects are avoided. For some garden
areas, a slight increase in noise is predicted, with garden areas
located within the indicative layout in Phase 5 (which are
positioned side on to the SLR and M62) predicted to
marginally exceed 55dB, but are below 60dB so are
considered not significant.
Overall it is considered that the cumulative development,
post mitigation, would have an overall beneficial effect due to
the local and district wide benefits which would be delivered,
including increased employment and expenditure in the area
and opportunities for regeneration and investment.
21
Conclusion
The main purpose of the ES is to provide an objective
assessment of the Environmental Impacts of the proposed
development. This Non-Technical Summary provides a
summary of the main issues identified within the ES Part 1
and ES Part 2.
The separate Technical Papers within the ES Part 2 of the
Environmental Statement provides a detailed analysis of
impacts and mitigation of the development during the
construction and operational phases against a range of topics
including:
Traffic and Transportation
Water Environment
Noise and Vibration
Air Quality
These separate papers contain the detailed analysis of impacts
and mitigation and should be referred to for the complete
assessment of impact. This ES Part 1 report aims to provide
an overview of the predicted effects and how it is proposed
to mitigate the impacts. It should be noted that the
information submitted for this planning application is
extensive given the nature of the site, however, the detailed
mitigation strategies will be controlled via the use of planning
conditions and the Section 106 Agreement.
Following the mitigation set out in Section 8 of the ES Part 1
the residual effects for the impacts associated with water
environment and traffic and transportation are assessed as
negligible. For air quality and noise the residual impacts
following mitigation are assessed as negligible to minor
adverse with two receptors to the south west of the site
being moderate adverse for noise.
As described in the ES, it is not considered that there will be
any potential environmental impacts that cannot be suitably
mitigated and which would prevent the proposals from being
granted planning permission.
Spawforths Junction 41 Business Court, East Ardsley, Leeds, West Yorkshire. WF3 2AB t: 01924 873873, f: 01924 870777, [email protected], www.spawforths.co.uk
Spawforths is a trading name of Spawforth Rolinson Ltd. Incorporated in England, Company Registration Number 2247289