Bid Number: 20‐1490
ADDENDUM NO. 1 TO ALL PLANHOLDERS: The following items shall be incorporated into the Bidding/Contract Documents for the above described project and will supersede any provisions with which they may conflict. All other provisions not modified by this addendum shall remain in full force and effect.
Issued: June 4, 2020 CHANGES TO SPECIFICATIONS
Table of Contents:
1. The attached Table of Contents (Rev. 1) shall replace the Table of Contents in its entirety.
Section 01 30 50:
2. Insert the attached Specification Section 01 30 50 in its entirety.
Sections 01 75 00.01 through 01 75 00.03:
1. Insert the attached Specification (forms) Section 01 75 00.01, Section 01 75 00.02, and Section 01 75 00.03 in their entirety. These are startup reference forms required by Section 01 75 00.
Section 46 23 23:
1. Clarification for Section 46 23 23‐1.4.D.1.i – anchorage calculations, per Section 03 15 19, are required to be stamped and sealed by a Professional Engineer registered in the State of Washington.
2. Clarification for Section 46 23 23‐3.2.C.2.b – the vendor should plan to conduct a
minimum of two (2) separate tests on two (2) separate days. One (1) test will be during
a high flow period (at a time when the plant flow is projected to fall into the range
indicated) and the other test will be during a low flow period (at a time when the plant
flow is projected to fall into the range indicated). The test days may not be consecutive,
Page 2 of 3 02/18/2020
as the plant flow and weather conditions will determine the testing time, and the
vendor should plan for two (2) separate trips. The vendor will not be required to
otherwise manipulate influent to the system during testing and the flows during the test
will be subject to the flow into the plant at that time. Exact testing conditions can be
flexible. The number of samples taken during each test must be statistically defensible
(single grab samples will not be sufficient). Capture efficiencies can have an error of up
to five percent (5%).
CHANGES TO DRAWINGS
Drawing M2‐24:
1. Clarification for Drawing M2‐24, Grid 3B – the 4” GT and 1.5” C3 pipes entering the grit tank and routed to GU‐202 are shown nominally. The precise point of entry into the tank (for the C3 line) and interior routing (for both the GT and C3 lines) to the GU‐202 equipment shall be determined by the manufacturer (Section 46 23 23) and coordinated by the Contractor for Shop Drawing review and approval by the Engineer.
CLARIFICATIONS TO BID DOCUMENTS
GENERAL CONDITIONS:
1. Sections 54.6.1 through 54.6.3, inclusive, shall be superseded and replaced by the following:
54.6.1. When five percent (5%) of the total original Contract amount is earned, less Mobilization, Cleanup ,and Demobilization and excluding amounts paid for Materials on Hand, fifty (50) percent of the lump sum amount bid for Mobilization, Cleanup, and Demobilization, or five percent (5% ) of the total original Contract amount, whichever is the least, shall be paid.
54.6.2. When ten percent (10%) of the total original Contract amount is earned, less Mobilization, Cleanup ,and Demobilization and excluding amounts paid for Materials on Hand, seventy‐five percent (75%) of the lump sum amount bid for Mobilization, Cleanup, and Demobilization, or ten percent (10%) of the total original Contract amount, whichever is the least, shall be paid.
54.6.3. Upon completion of all work on this Project, payment for the remaining amount bid for Mobilization, Cleanup, and Demobilization in excess of ten percent (10%) of the total original Contract amount, shall be paid.
54.6.4. See Specification Section 01 71 14 for additional payment terms and requirements.
[This Page Left Blank Intentionally]
SPECIFICATIONS TABLE OF CONTENTS
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
SPEC ‐ i
TABLE OF CONTENTS (REV. 1)
DIVISION 01 — GENERAL REQUIREMENTS 01 11 00 ‐ SUMMARY OF WORK 01 11 10 ‐ OWNER FURNISHED EQUIPMENT 01 11 20 ‐ JOB CONDITIONS 01 14 19 ‐ USE OF SITE 01 25 13 ‐ PRODUCT SUBSTITUTIONS 01 26 13 ‐ REQUESTS FOR INFORMATION (RFI) 01 29 73 ‐ SCHEDULE OF VALUES (LUMP SUM PROJECTS) 01 30 00 ‐ SPECIAL CONDITIONS 01 30 50 ‐ WEB BASED CONSTRUCTION MANAGEMENT 01 31 19 ‐ PROJECT MEETINGS 01 32 17 ‐ CONSTRUCTION PROGRESS SCHEDULE 01 33 00 ‐ SUBMITTALS 01 33 04 ‐ OPERATION AND MAINTENANCE MANUALS 01 35 05 ‐ ENVIRONMENTAL PROTECTION AND SPECIAL CONTROLS 01 42 13 ‐ STANDARD ABBREVIATIONS AND SYMBOLS 01 45 33 ‐ SPECIAL INSPECTIONS AND TESTING PROGRAM 01 61 03 ‐ EQUIPMENT ‐ BASIC REQUIREMENTS 01 61 04 ‐ EQUIPMENT LIST 01 65 50 ‐ PRODUCT DELIVERY, STORAGE, AND HANDLING 01 71 14 ‐ MOBILIZATION AND DEMOBILIZATION 01 73 20 ‐ OPENINGS AND PENETRATIONS IN CONSTRUCTION 01 73 29 ‐ DEMOLITION, CUTTING AND PATCHING 01 74 13 ‐ CLEANING 01 75 00 ‐ SYSTEM STARTUP 01 75 00.01 ‐ MANUFACTURERS INSTALLATION CERTIFICATION 01 75 00.02 ‐ EQUIPMENT TEST REPORT FORM 01 75 00.03 ‐ TRAINING ATTENDANCE FORM
DIVISION 03 — CONCRETE 03 05 05 ‐ CONCRETE TESTING AND INSPECTION 03 09 00 ‐ CONCRETE 03 15 19 ‐ ANCHORAGE TO CONCRETE 03 35 00 ‐ CONCRETE FINISHING AND REPAIR OF SURFACE DEFECTS
DIVISION 04 — MASONRY 04 01 20 ‐ MASONRY CLEANING 04 05 13 ‐ MASONRY MORTAR AND GROUT 04 05 23 ‐ MASONRY ACCESSORIES 04 05 50 ‐ COLD AND HOT WEATHER MASONRY CONSTRUCTION 04 22 00 ‐ CONCRETE MASONRY
SPECIFICATIONS TABLE OF CONTENTS
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
SPEC ‐ ii
DIVISION 05 — METALS 05 12 00 ‐ STRUCTURAL STEEL 05 14 00 ‐ STRUCTURAL ALUMINUM
DIVISION 05 — METALS (CONTINUED) 05 50 00 ‐ METAL FABRICATIONS 05 52 02 ‐ ALUMINUM RAILINGS
DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES 06 82 00 ‐ FIBERGLASS REINFORCED PLASTIC FABRICATIONS 06 85 14 ‐ FLOCCULATION BAFFLES
DIVISION 07 — THERMAL AND MOISTURE PROTECTION 07 61 13 ‐ METAL ROOFING 07 92 00 ‐ JOINT SEALANTS
DIVISION 08 — OPENINGS 08 33 22 ‐ ALUMINUM ROLLING OVERHEAD DOORS
DIVISION 09 — FINISHES 09 96 00 ‐ HIGH PERFORMANCE INDUSTRIAL COATINGS
DIVISION 10 — SPECIALTIES 10 14 00 ‐ IDENTIFICATION DEVICES
DIVISION 13 — SPECIAL CONSTRUCTION 13 34 23 ‐ FRP SHELTERS
DIVISION 22 — PLUMBING 22 20 00 ‐ PLUMBING FIXTURES AND EQUIPMENT
DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING 23 05 93 ‐ HVAC SYSTEMS ‐ BALANCING AND TESTING 23 31 00 ‐ HVAC ‐ DUCTWORK 23 80 00 ‐ HVAC ‐ EQUIPMENT
DIVISION 26 — ELECTRICAL 26 05 00 ‐ ELECTRICAL ‐ BASIC REQUIREMENTS 26 05 19 ‐ WIRE AND CABLE ‐ 600 VOLT AND BELOW 26 05 26 ‐ GROUNDING AND BONDING 26 05 33 ‐ RACEWAYS AND BOXES 26 05 74 ‐ SHORT CIRCUIT AND COORDINATION STUDY, AND ARC FLASH REPORT 26 08 13 ‐ ACCEPTANCE TESTING 26 09 16 ‐ CONTROL EQUIPMENT ACCESSORIES 26 24 19 ‐ MOTOR CONTROL EQUIPMENT 26 27 26 ‐ WIRING DEVICES
SPECIFICATIONS TABLE OF CONTENTS
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
SPEC ‐ iii
DIVISION 26 — ELECTRICAL (CONTINUED) 26 28 00 ‐ OVERCURRENT AND SHORT CIRCUIT PROTECTIVE DEVICES 26 28 16 ‐ SAFETY SWITCHES 26 29 23 ‐ VARIABLE FREQUENCY DRIVES ‐ LOW VOLTAGE 26 36 00 ‐ TRANSFER SWITCHES 26 50 00 ‐ INTERIOR AND EXTERIOR LIGHTING
DIVISION 31 — EARTHWORK 31 10 00 ‐ SITE CLEARING 31 23 00 ‐ EARTHWORK 31 25 00 ‐ SOIL EROSION AND SEDIMENT CONTROL
DIVISION 32 — EXTERIOR IMPROVEMENTS 32 12 16 ‐ ASPHALTIC CONCRETE VEHICULAR PAVING
DIVISION 40 — PROCESS INTERCONNECTIONS 40 05 00 ‐ PIPE AND PIPE FITTINGS ‐ BASIC REQUIREMENTS 40 05 07 ‐ PIPE SUPPORT SYSTEMS 40 05 17 ‐ PIPE ‐ COPPER 40 05 19 ‐ PIPE ‐ DUCTILE 40 05 23 ‐ PIPE ‐ STAINLESS STEEL 40 05 24 ‐ PIPE ‐ STEEL 40 05 26 ‐ PIPE ‐ CAST‐IRON SOIL 40 05 31 ‐ PIPE ‐ PLASTIC 40 05 33 ‐ PIPE ‐ POLYETHYLENE (HDPE) 40 05 51 ‐ VALVES ‐ BASIC REQUIREMENTS 40 05 52 ‐ MISCELLANEOUS VALVES 40 05 53 ‐ HAND VALVE SCHEDULE 40 05 54 ‐ CONTROL AND SAFETY VALVE SCHEDULE 40 05 58 ‐ WATER CONTROL GATE SCHEDULE 40 05 59 ‐ FABRICATED STAINLESS STEEL SLIDE GATES 40 05 61 ‐ GATE VALVES 40 05 62 ‐ PLUG VALVES 40 05 63 ‐ BALL VALVES 40 05 65 ‐ GLOBE VALVES 40 05 66 ‐ CHECK VALVES 40 10 15 ‐ FIBERGLASS REINFORCED PLASTIC DUCT 40 42 00 ‐ PIPE, DUCT AND EQUIPMENT INSULATION 40 61 13 ‐ PROCESS CONTROL SYSTEMS GENERAL REQUIREMENTS 40 62 16 ‐ COMPUTER NETWORK AND HUMAN MACHINE INTERFACE (HMI) HARDWARE 40 63 43 ‐ PROGRAMMABLE LOGIC CONTROLLER (PLC) CONTROL SYSTEM 40 63 44 ‐ PLC IO SCHEDULE 40 67 00 ‐ CONTROL SYSTEM EQUIPMENT PANELS AND RACKS 40 71 00 ‐ FLOW INSTRUMENTATION
SPECIFICATIONS TABLE OF CONTENTS
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
SPEC ‐ iv
DIVISION 40 — PROCESS INTERCONNECTIONS (CONTINUED) 40 72 00 ‐ LEVEL INSTRUMENTATION 40 73 00 ‐ PRESSURE INSTRUMENTATION 40 74 00 ‐ INSTRUMENT SCHEDULE 40 90 05 ‐ CONTROL LOOP DESCRIPTIONS 40 91 10 ‐ PRIMARY METERS AND TRANSMITTERS 40 96 52 ‐ CONFIGURATION REQUIREMENTS ‐ HUMAN MACHINE INTERFACE (HMI) AND
REPORTS 40 97 00 ‐ CONTROL AUXILIARIES
DIVISION 43 — PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND STORAGE EQUIPMENT
43 21 00 ‐ PUMPING EQUIPMENT ‐ BASIC REQUIREMENTS 43 23 15 ‐ PUMPING EQUIPMENT ‐ SELF‐PRIMING CENTRIFUGAL PUMPS 43 23 17 ‐ PUMPING EQUIPMENT ‐ VORTEX (TORQUE‐FLOW) 43 23 54 ‐ PUMPING EQUIPMENT ‐ PERISTALTIC 43 41 43 ‐ POLYETHYLENE CHEMICAL TANKS
DIVISION 46 — WATER AND WASTEWATER EQUIPMENT 46 20 00 ‐ GRIT REMOVAL EQUIPMENT 46 23 23 ‐ GRIT REMOVAL SYSTEM 46 23 63 ‐ GRIT CLASSIFIER‐WASHER 46 43 22 ‐ FINAL CLARIFIER SOLIDS COLLECTION EQUIPMENT ‐ CIRCULAR TANK SUCTION
HEADER TYPE
APPENDICES APPENDIX A ‐ EXISTING GRIT WASHER REFURBISHMENT EQUIPMENT LIST APPENDIX B ‐ CONSERVATEK CLARIFIER COVER DRAWINGS APPENDIX C ‐ EVOQUA CLARIFIER DRIVE DRAWINGS & INSTALLATION INSTRUCTIONS APPENDIX D ‐ CONTROL PANEL CP‐244 RECORD DRAWINGS APPENDIX E ‐ DAFT CONTROL SYSTEM RECORD DRAWINGS
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 30 50 WEB BASED CONSTRUCTION MANAGEMENT
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 30 50 ‐ 1
SECTION 01 30 50 WEB BASED CONSTRUCTION MANAGEMENT
PART 1 GENERAL
1.1 SUMMARY
A. The Owner and Contractor shall utilize Bluebeam REVU for electronic submittal of all data throughout the duration of the Contract. Bluebeam REVU is a program for file sharing as well as coordinating Portable Document Format (PDF) documents, allowing for web‐based electronic access by multiple parties. Access to the construction session for this project will be made available by the Owner to all Contractors’ project personnel, subcontractor personnel, suppliers, consultants, and the Engineer. The joint use of this system is to facilitate electronic exchange of information, automation of key Contract processes, and overall management of the contract. Bluebeam REVU shall be the primary means of all project‐related information, submission, and execution of project‐related items and management of the project communication. When required by Contract and/or agreed by joint parties, the Project Representative and/or Contractor will also provide paper documents. In the event of discrepancy between the electronic version and paper documents, the paper documents will govern. Bluebeam REVU is a registered trademark of Bluebeam, Inc.
B. Contractor is required to obtain their own copy of Bluebeam REVU for access to upload and download files to the session created by the Owner. Contractor shall pay for costs for communications, labor, computer hardware, or other Contractor/ subcontractor/supplier costs to operate their own copy of the program.
C. The Owner will provide basic Bluebeam REVU access instructions to the Contractor at no cost to the Contractor. The instruction will not include detailed training, but will be basic instructions regarding access and logistics (workflow process) within the project session. This instruction will be provided after the notice to proceed at a time agreed to by the Owner and Contractor.
1.2 USER ACCESS LIMITATIONS
A. The Project Representative will control the Contractor's access to Bluebeam REVU by allowing access and assigning user profiles to accepted Contractor personnel.
1. Subcontractors and suppliers will be given access to Bluebeam REVU by the Contractor’s designated representative. Entry and accuracy of information exchanged and transferred between the Contractor and its subcontractors and suppliers on Bluebeam REVU shall be the responsibility of the Contractor.
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 30 50 WEB BASED CONSTRUCTION MANAGEMENT
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 30 50 ‐ 2
B. Joint Ownership of Data ‐ Data entered in a collaborative mode (entered with the intent to share as determined by permissions and workflows within the Bluebeam REVU system) by the Project Representative and the Contractor will be jointly owned.
C. Contractor is responsible to download and maintain their own archive copy of any items from Bluebeam REVU upon completion of the project.
1.3 AUTOMATED SYSTEM NOTIFICATION AND AUDIT LOG TRACKING
A. Review comments made (or lack thereof) by the Owner on Contractor‐submitted documentation shall not relieve the Contractor from compliance with requirements of the Contract Documents. The Contractor is responsible for managing, tracking, and documenting the Work to comply with the requirements of the Contract Documents. Owner’s acceptance via automated system notifications or audit logs extends only to the face value of the submitted documentation and does not constitute validation of the Contractor's submitted information.
1.4 SUBMITTALS
A. See Section 01 33 00.
1. All submittal procedures shall be executed and managed via the Bluebeam REVU program.
B. Pre‐construction Submittals: Submit list of Contractor's key Bluebeam REVU personnel for review and approval of Project Representative. Include descriptions of key personnel's roles and responsibilities for this project. Contractor should also identify their organization's administrator on the list.
1.5 COMPUTER REQUIREMENTS
A. The Contractor shall use computer hardware that meets the requirements of the Bluebeam REVU software.
1. Upgrading of the Contractor's computer systems will not be justification for a cost or time modification to the Contract.
2. The Contractor will ensure that connectivity to the Bluebeam REVU session (whether at the home office or jobsite) is accomplished through DSL, cable, T‐1, or wireless communications systems. It is recommended a faster connection be used when uploading pictures and files into the system.
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 30 50 WEB BASED CONSTRUCTION MANAGEMENT
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 30 50 ‐ 3
1.6 CONTRACTOR RESPONSIBILITY
A. The Contractor shall be responsible for the timeliness and validity of their information placed in Bluebeam REVU and for the abilities of their personnel.
1. Accepted users shall be knowledgeable in the use of computers, including Internet Browsers, email programs, CADD drawing applications, and PDF document distribution program.
2. The Contractor shall utilize the forms provided in the Contract Documents as an attachment to a submittal, RFI, or other uploaded information.
a. If a form does not exist in the Contract Documents, the Contractor may submit a suggested form for review and approval by the Owner.
b. File exchange shall be primarily through PDF documents.
c. PDF documents will be created through electronic conversion rather than optically scanned whenever possible.
3. The Contractor is responsible for the training of their personnel and their subcontractors/suppliers in the use of Bluebeam REVU and the other programs indicated above as needed.
4. User Access Administration ‐ Provide a list of Contractor's key Bluebeam REVU personnel for acceptance by the Project Representative.
a. Contractor is responsible for adding and removing Contractor‐controlled users from the system.
b. The Project Representative reserves the right to perform a security check on all potential users.
c. The Contractor will be allowed to add additional personnel and subcontractors to Bluebeam REVU upon acceptance of the additional personnel by the Project Representative.
d. The Contractor is responsible to maintain access and permissions for the Contractor‐controlled users and organizations.
1.7 CONNECTIVITY PROBLEMS
A. Access to the Bluebeam REVU session is subject to the inherent speed and connectivity problems of the Internet. The Contractor is responsible for its own connectivity to the Internet.
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 30 50 WEB BASED CONSTRUCTION MANAGEMENT
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 30 50 ‐ 4
1. Bluebeam REVU response time is dependent on the Contractor's equipment, including processor speed, Internet access speed, current traffic on the Internet, etc.
2. The Owner will not be liable for any delays associated from the usage of Bluebeam REVU including, but not limited to: slow response time, down time periods, connectivity problems, or loss of information.
3. Under no circumstances shall the usage of the Bluebeam REVU be grounds for a time extension or cost adjustment to the contract.
PART 2 PRODUCTS
2.1 DESCRIPTION
A. Bluebeam REVU software (no equal).
1. Provided by Bluebeam, Inc., https://www.bluebeam.com/.
PART 3 EXECUTION
3.1 BLUEBEAM REVU UTILIZATION
A. Design Document Submittals – All design drawings and specifications shall be submitted as PDF attachments to the Bluebeam REVU submittal work flow process and form.
1. Design Documents shall represent the original bid documents.
2. Contractor is responsible for conforming sets of documents for use in field.
B. Shop Drawings ‐ Shop drawing and design data documents shall be submitted as PDF attachments to the Bluebeam REVU submittal work flow process and form.
1. See Section 01 33 00 for submittal requirements.
C. Electronic O&M Manuals shall be submitted per Section 01 33 04.
D. Schedules shall be submitted per the requirements of Section 01 32 17.
E. Photographs – Pictures shall be uploaded as required by Contract as “.jpg” files to the Bluebeam REVU file location as determined by the Project Representative.
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 30 50 WEB BASED CONSTRUCTION MANAGEMENT
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 30 50 ‐ 5
F. Product Data (Product Review and Product Information Submittals) – Product catalog data and manufacturer’s instructions shall be submitted as PDF attachments to the Bluebeam REVU submittal work flow process and form.
1. See Section 01 33 00.
G. Samples – Contractor shall enter submittal data information into Bluebeam REVU with a copy of the submittal form(s) attached to the sample submitted as PDF attachments.
1. Submit number of samples as required per Section 01 33 00.
H. RFIs – Requests for Information shall be submitted utilizing the Bluebeam REVU workflow process per Section 01 26 13.
1. Attachments to RFIs shall be uploaded as PDF attachments.
I. Administrative Information – All correspondence and preconstruction information shall be submitted and managed in Bluebeam REVU submitted as PDF attachments. Examples of administrative information include, but are not limited to:
1. Digging permits and notices for excavation.
2. List of product substitutions.
3. List of contact personnel.
4. Notices for work outside regular hours and utility cut overs.
5. Bonds and insurance information.
6. Project permits, including hot work, and updates.
7. All project serial letters and official correspondence.
8. All Owner Field Directives will be issued via Bluebeam REVU.
9. All Owner Requests for Pricing will be issued via Bluebeam REVU and should be managed and processed utilizing the Bluebeam REVU workflow process.
10. Plans for safety, demolition, environmental protection, and similar activities as required by the Contract.
11. Quality Control Plan(s), Testing Plan and Log, Quality Control Reports, Production Reports, Non‐Conformance Reports, Punch Lists, Quality Control Specialist Reports, Start‐up and Testing Reports, Field Test Reports, Summary Reports, Rework Items List, Daily Work Logs, Cost Tracking Logs, Schedules, Monthly Reports, etc.
12. Meeting minutes for quality control meetings, progress meetings, pre‐installation meetings, and other Contract‐required meetings, etc.
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 30 50 WEB BASED CONSTRUCTION MANAGEMENT
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 30 50 ‐ 6
13. All general correspondence for the project should be through the Bluebeam REVU system as determined by the Project Representative (versus use of email).
J. Compliance Submittals – Test reports, certificates, and manufacturer’s field report submittals shall be submitted on Bluebeam REVU as PDF attachments. Examples of compliance submittals include, but are not limited to:
1. Field test reports.
2. Quality control certifications.
3. Manufacturer’s documentation and certifications for quality of products and materials provided.
K. Record and Closeout Submittals – Record and closeout submittals shall be submitted on Bluebeam REVU in locations specified by Project Representative as PDF documents during the approval and review stage as specified, with the actual set hard copy and electronic copy of documents submitted for final. Examples of record submittals include, but are not limited to:
1. Record Drawings: Final documents shall be submitted as specified.
2. Extra Materials, Spare Stock, etc.: Submittal forms shall indicate when actual materials are submitted.
3. Testing, training, and commissioning documents.
4. Guarantees/Warranties: Final documents shall be submitted as specified.
L. Financial Submittals – Schedule of Value, Pay Estimates, and Change Request Proposals shall be submitted and processed in the Bluebeam REVU workflow process and as required by the Contract Documents.
1. Supporting material for Pay Estimates, Change Requests, and other financial information shall be submitted on Bluebeam REVU as PDF attachments.
2. Examples of financial information to be submitted and processed include, but are not limited to:
a. Contractor’s Schedule of Values.
b. Contractor’s Monthly Progress Payment Requests.
c. Contract Change proposals requested by the Owner.
d. Contract Requests for Pricing requested by the Contractor.
e. Change Orders.
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 30 50 WEB BASED CONSTRUCTION MANAGEMENT
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 30 50 ‐ 7
f. Intent to Pay Certified Payroll.
1) Contractor shall submit Certified Payroll online per L&I standards.
g. Affidavits of Wages Paid.
h. Lien Releases.
i. All other financial supporting documents as required by the Contract.
END OF SECTION
[This Page Left Blank Intentionally]
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 75 00.01 MANUFACTURER’S INSTALLATION CERTIFICATION
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 75 00.01 ‐ 1
SECTION 01 75 00.01 MANUFACTURER’S INSTALLATION CERTIFICATION
Contract: Specification Section:
Owner:
Contractor:
Equipment Name: Equipment No.:
Manufacturer:
The undersigned manufacturer of the equipment item described above hereby certifies that he has checked the installation of the equipment and that the equipment, as specified in the contract, has been provided in accordance with the manufacturer’s recommendations and that the trial operation of the equipment item has been satisfactory and meets the contract requirements.
Comments
Date Manufacturer
Date Signature of Authorized Representative
Date Contractor
Date Signature of Authorized Representative
[This Page Left Blank Intentionally]
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 75 00.02 EQUIPMENT TEST REPORT FORM
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 75 00.02 ‐ 1
01 75 00.02 EQUIPMENT TEST REPORT FORM
Note: This example equipment test report is provided for the benefit of the Contractor and is not specific to any piece of equipment to be installed. The example is furnished as a means of illustrating the level of detail required for the preparation of equipment test report forms and shall be adjusted to meet the specific requirements of the Contract Documents.
Equipment Name:
Equipment Number:
Specification Reference:
Location:
PREOPERATIONAL CHECKLIST
MECHANICAL
Contractor Vendor Project Rep
Verified Date Verified Date Verified Date
Lubrication Alignment Anchor Bolts Seal Water System Operational Equipment Rotates Freely Safety Guards Valves Operational O&M Manual Information Complete Manufacturer’s Installation Certificate Complete
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 75 00.02 EQUIPMENT TEST REPORT FORM
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 75 00.02 ‐ 2
ELECTRICAL (Circuit Ring-Out and High-Pot Tehsts)
Contractor Vendor Project Rep
Verified Date Verified Date Verified Date
Circuits: Power to MCC Control to HOA Indicators at MCC: Red (Running) Green (Power) Amber (Auto) Indicators at Local Control Panel Wiring Labels Complete Nameplates: MCC Control Station Control Panel Equipment Bumped for Rotation
PIPING SYSTEMS
Contractor Vendor Project Rep
Verified Date Verified Date Verified Date
Cleaned and Flushed: Suction Discharge Pressure Tests Temporary Piping Systems in Place
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 75 00.02 EQUIPMENT TEST REPORT FORM
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 75 00.02 ‐ 3
INSTRUMENTATION AND CONTROLS
Contractor Vendor Project Rep
Verified Date Verified Date Verified Date
Flow Meter Calibration: Calibration Report No. Flow Recorder Calibrated: Against Transmitter VFD Speed Indicator Calibrated Against:
Independent Reference Discharge Over-Pressure Shutdown: Switch Calibration Simulate Discharge Over-pressure: Shutdown
INITIAL OPERATION
MECHANICAL
Contractor Vendor Project Rep
Verified Date Verified Date Verified Date
Motor Operation Temperature Satisfactory
Pump Operating Temperature Satisfactory
Unusual Noise, Etc.
Pump Operation: Measurement: Flow Pressure Test Gauge Number Alignment Hot Doweled In
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 75 00.02 EQUIPMENT TEST REPORT FORM
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 75 00.02 ‐ 4
REMARKS:
ELECTRICAL
Contractor Vendor Project Rep
Verified Date Verified Date Verified Date
Local Switch Function: Runs in HAND No Control Power in OFF
Timer Control in AUTO
Overpressure Protection Switch:
Functional in both HAND and AUTO
Overpressure Protection Switch Set at XX psig
PLC Set at 24 Hour Cycle, XX Minutes ON
OPERATIONS TEST
Continuous test. Pump cycles as specified, indicators functional, controls functional, pump maintains capacity, over pressure protection remains functional, hour meter functional.
RECOMMENDED
Contractor Representative Date
ACCEPTED
Project Representative Date
SPECIFICATIONS DIVISION 01 — GENERAL REQUIREMENTS SECTION 01 75 00.03 TRAINING ATTENDANCE FORM
HDR Project No. 10106807 Lakehaven Water and Sewer District March 2020 2020 LAKOTA LIQUID STREAM IMPROVEMENTS – PHASE II Bid Documents
01 75 00.03 ‐ 1
01 75 00.03 TRAINING ATTENDANCE FORM
Contract Name:
Contract No: Training Date:
Training Name:
Trainer: Company:
Phone No.: email address
Attendees:
Name Company Phone No. Email Address
[This Page Left Blank Intentionally]