laconia savings bank, concord - nh
TRANSCRIPT
At A Glance: Site Location: Main Street, Concord Site Profile: Former Cumberland Farms
Gas Station
DES Reimbursements: $151,259 Outcomes:
� 1,219.4 tons of contaminated soil
removed and properly disposed of.
� Comprehensive site investigation
and groundwater monitoring
program completed.
� The property was successfully
redeveloped into a bank branch.
Overview The former Cumberland Farms gas station
on Main Street in Concord became
redundant when Cumberland Farms
acquired all of the former Exxon gas
stations in New Hampshire. Cumberland
Farms now owned gas stations directly
across the street from each other with a
Hess station less than a tenth of a mile
away. Cumberland Farms
decommissioned its tanks and sold the
former station to Laconia Savings Bank,
which successfully redeveloped the
property into a bank branch.
History
The former Cumberland Farms gas station has been used for retail sale of gasoline since at least
1947. Cumberland Farms became the owner in 1986 when they purchased the station from
Chevron USA. The property was sold to Laconia Savings Bank and was redeveloped into a
branch office.
Environmental Assessment and Cleanup
A total of 12 gasoline, diesel, waste oil and heating
oil tanks were present over time at this facility. Tanks
were removed in 1992, 2006 and 2008 from the
property. The 750-gallon waste oil UST and 1,000-
gallon fuel oil UST were removed from the site on
July 29, 1992. Limited contamination was discovered
and the release was quickly closed. On November 19,
2002, there was a report of vapors in the on-site
building. Emergency response efforts consisted of the
repair of leaky tank top components and sealing of all
electrical conduits leading from the tank top manifold
sumps to the interior of the building. This
significantly improved the indoor air problems.
Picture of 2006 tank removal project.
Laconia Savings Bank, Concord
On April 16, 2003, ECSMarin submitted a
report documenting that higher
concentrations of benxene, toluene,
ethylbenzene, xylenes and methyl tertiary-
butyl ether (MTBE) were detected in the two
air interior samples, as compared to a sample
collected outside. DES requested that
Cumberland Farms complete and initial site
characterization (ISC) in response to the
indoor air problem. On November 14, 2003,
ECSMarin submitted the requested ISC
documenting indoor air quality monitoring,
soil boring, monitoring well installation, and
groundwater sampling activities conducted at
the site. The June 2003 indoor air quality
results for MtBE were significantly better
than the March results.
Groundwater samples collected from all site monitoring wells during ISC activities exceeded
state standards for MTBE and multiple wells exceeded standards for benzene, toluene,
ethylbenzene, xylenes and/or naphthalene. Based on the groundwater contamination, DES
requested a comprehensive investigation of the site. After a series of delays prompted by a
problem in obtaining access to the adjacent property, a site investigation report was submitted in
June 2006. This report recommended soil excavation as the presumptive remedy for the site.
Around this time, the decision was made to discontinue operating this facility and the tanks were
put into temporary closure on August 11, 2006. By October 2006, four 8,000 gallon gasoline
tanks were excavated and removed from the site. During the tank removal, 288 tons of
contaminated soil was excavated from the site from the vicinity of the tank grave. Coordination
of the soil excavation with the tank closure saved the Oil Discharge and Disposal Cleanup Fund
(ODD Fund) significant amounts of money for mobilization and equipment rental. Groundwater
monitoring continued during this time period to evaluate the effectiveness of the soil removal.
In 2008 Cumberland Farms approached DES about coordinating a soil excavation project with
the proposed site redevelopment. DES agreed and approved a budget for contaminated soil
delineation. The soil delineation report was submitted on November 3, 2008 and after an
expedited review of the report DES approved a soil excavation work scope and budget on
November 18, 2008. During the soil excavation project three underground storage tanks were
found under and around Court Street. One of the tanks was removed and the two tanks that were
directly under the street were closed in place. Closing the two tanks in place prevented a future
collapse in a portion of Court Street when the tanks eventually lose structural integrity. A report
documenting the removal of 931 tons of contaminated soil was submitted February 3, 2009. The
bank building construction project started in the spring and by the summer of 2009 replacement
groundwater monitoring wells were installed at the completed project. The property itself is now
clean; however, a limited groundwater monitoring program continues because it was not possible
to remove contamination under Main Street and the sidewalk. The groundwater monitoring
ensures that the city of Concord and NHDOT are aware of potential construction issues, if Main
Street utilities or road repairs are made.
Redevelopment Project Success
In many states there is a significant problem with gas stations that are shuttered but not
redeveloped. Major oil companies look at the bottom line economics of redeveloping their
closed gas stations and base their decision on that economic reality. In New Hampshire’s case,
the ODD Fund reimburses for the cleanup costs and the decision to proceed with a
redevelopment project such as this one is straight forward. Cumberland Farms decided that it
was in its economic best interest to redevelop the gas station, and Concord’s Main Street
benefited from an attractive new business replacing a shuttered gas station.
Demolition of the former gas station was coordinated with the contaminated soil removal project.
This made the soil excavation project more efficient and ensured that the development project
could proceed without concerns about encountering soil contamination. As typically happens
during redevelopment of old gas station sites, there were surprises. As mentioned, three
previously unknown underground storage tanks were found partially under Court Street. The
role the ODD Fund played in paying for and addressing uncertainties, such as the cost impact of
unknown older tank installations and new areas of contamination, reduced concerns about
environmental cleanup cost estimation and was important for redeveloping this old gas station
site.
Picture of the finished redevelopment project.