labarjournal june-july 2007 finalfiles.lsba.org/documents/publications/barjournal/journal... ·...
TRANSCRIPT
Louisiana Bar Journal Vol. 55, No. 4 267
RECENTDevelopments
ADR TO PROFESSIONAL LIABILITY
Alternative Dispute
Resolution
Loyola Establishes
Katrina Construction Law
Mediation Clinic
The Loyola University New Orleans
College of Law has established a Media-
tion Clinic to help resolve claims be-
tween Road Home applicants and build-
ers-contractors. The mediators are Loyola
law students who are enrolled in and
have received mediation training from
the Loyola Mediation Clinic. The stu-
dent-mediators will mediate the cases
under the supervision of Loyola clinical
faculty members. Funding for the Media-
tion Clinic was provided by ICF Emer-
gency Management Services, L.L.C.,
contractor for the Road Home Program.
The clinic will mediate approximately
350 civil consumer-contractor cases,
some involving allegations of contractor
fraud. The mediations are confidential,
and the mediators will not discuss the
cases with others outside of the media-
tions. Mediations will be held on the
Loyola Law College campus, and the
clinic will operate for an initial 12-month
service period (which began Sept. 1,
2007). For more information on the clinic,
contact Leila Bonilla at (504)861-5590.
Party’s Waiver of the
Right to Arbitrate
Arkel Constructors, Inc. v. Duplantier
& Meric, Architects, L.L.C., 06-1950
(La. App. 1 Cir. 7/25/07), 965 So.2d 455.
A subcontractor filed suit against the
general contractor on a construction
project to recover funds allegedly owed
for contracted work. After filing suit, the
subcontractor filed a motion to compel
arbitration and to stay proceedings pend-
ing arbitration. The general contractor
recognized that the agreement governing
the relationship between the general con-
tractor and subcontractor contained an
arbitration clause, but argued that the
subcontractor waived its right to arbitra-
tion by filing suit without asserting its
right to arbitrate the dispute.
The subcontractor appealed the trial
court’s ruling denying its motion to com-
pel arbitration, and the court of appeal
converted the appeal into an application
for supervisory writs. The court, recog-
nizing that an undisputed arbitration
agreement existed between the parties,
held that under La. R.S. 9:4203, issues of
waiver are to be handled by an arbitrator,
not the trial court. Therefore, determining
whether the right to arbitrate had been
waived by the subcontractor was held to be
a function of the arbitrator. Consequently,
the court of appeal reversed the judgment
of the trial court, rendered judgment grant-
ing a stay pending arbitration and ordered
the parties to submit to arbitration.
MAPS ismediation,
arbitration,
and more...
free monthly breakfast seminars
Metairie/ New Orleans:Lakeway One- 3900 N. Causeway Blvd.- 2nd Floor
January 24, 2008: Evidence in the Personal Injury
SPEAKER: To Be Announced
Baton Rouge:Kiva’s Ristorante • 7622 Old Hammond Hwy.
January 25, 2008: Evidence in the Personal Injury
SPEAKER: To Be Announced
Shreveport:400 Texas St. • Suite 1400
February 13, 2008: Evidence in the Personal Injury
SPEAKER: To Be AnnouncedFor more information contact MAPS:
800.443.7351 504.831.2141
504.837.2566 (fax)
Email: [email protected]
Website: www.maps-adr.com
Robert A. Jenks Michael J. Moran Roger J. Larue
MAPS has a panel of over 50 mediators throughoutLouisiana and Mississippi with experience in a broadrange of specialties to accommodate any mediationeven on short notice.
268 December 2007 / January 2008
Arbitration Agreement
Executed as Part
of Installment Sale Contract
Easterling v. Royal Manufactured
Housing, L.L.C., 07-0192 (La. App. 3
Cir. 6/6/07), 963 So.2d 399.
The proceeding arose from a contract
between the plaintiff and the defendant
providing for the sale of a manufactured
home. Though the defendant gave the
plaintiff an option to pay for the home in
installments, the plaintiff obtained financ-
ing elsewhere and paid cash for the home.
The plaintiff later signed additional docu-
ments, one of which was an arbitration
agreement. The agreement, in pertinent
part, provided:
This Arbitration Agreement
(“Agreement”) is executed contem-
poraneously with, and becomes part
of, the Retail Installment of Sales
Contract (“Contract”) for the pur-
chase of a manufactured home . . . .
After the plaintiff moved into the manu-
factured home, various defects were dis-
covered, and the plaintiff filed suit for
redhibition. The defendant thereafter filed
a motion to compel arbitration. The trial
court denied the motion.
The court of appeal affirmed the trial
court’s denial, holding that the first sen-
tence of the arbitration agreement ren-
dered the agreement unenforceable. The
arbitration agreement provided that it
was executed contemporaneously with
and became part of an installment-sales
contract. Because an installment con-
tract never existed, there was no valid
arbitration agreement to be enforced.
Arbitration Provision
in Contract Between
Architect and Hospital
Town of Homer, Inc. v. Gen. Design,
Inc., 42,027 (La. App. 2 Cir. 5/30/07),
960 So.2d 310.
A hospital brought an action against
an architect for negligence and breach of
contract. In response, the architect filed a
motion to stay proceedings pending arbi-
tration. The trial court granted the mo-
tion, and the hospital sought supervisory
review.
The court of appeal held that a prior
contract between the hospital and archi-
tect governing a major hospital renova-
tion did not apply to the architect’s later
work on an addition made for medical-
records storage. Thus, the earlier
contract’s arbitration provision did not
apply to the negligence and breach-of-
contract claims arising from problems
with the later addition. Though the court
acknowledged that no written contract
governed the addition project and that
the parties’ dealings were similar for
both projects, the court held that oral or
written authorization was required to
make the initial contract’s provisions
applicable to the later project. Moreover,
the court noted that the earlier written
contract expressly required a new meet-
ing of the minds to bring services related
to future facilities within the reach of the
provisions of the initial contract. Finding
that no written contract existed mandating
arbitration of the claims, the court of appeal
reversed the ruling of the district court.
Arbitration Provision Was
Adhesionary and,
Therefore, Unenforceable
Lafleur v. Law Off. of Anthony G.
Buzbee, 06-0466 (La. App. 1 Cir. 3/23/
07), 960 So.2d 105.
The plaintiff filed suit against his at-
torneys alleging negligent representation.
The defendant attorneys thereafter filed
motions to stay the proceedings and to
compel arbitration. The motions were
denied, and the defendants appealed.
The court of appeal affirmed the judg-
ment of the trial court, holding that the
arbitration provision sought to be en-
forced was adhesionary and, therefore,
unenforceable. In reaching its decision,
the court noted that the attorney-client
relationship is more than a contractual
relationship; the relationship is fiduciary
and, therefore, requires that an attorney
provide “full and fair disclosure of all the
rights and interests which are materially
affected by the contract.” Moreover, the
court noted that the arbitration provision
was unduly burdensome in that it bound
only the client to the arbitration require-
ment and required that all arbitration
expenses be borne solely by the client,
regardless of the arbitration’s outcome.
Finally, the court recognized a client’s
unequal bargaining position when ini-
tially contracting with an attorney by
signing a pre-printed form prepared by
the attorney.
— Bobby Marzine Harges
Member, LSBA Alternative Dispute
Resolution Section
Loyola University New Orleans
College of Law
7214 St. Charles Ave., CB 901
New Orleans, LA 70118
Louisiana Bar Journal Vol. 55, No. 4 269
CARDONE LAW FIRMA P R O F E S S I O N A L L AW C O R P O R A T I O N
Select Referrals Concentrating In:• NURSING HOME LIABILITY CASES• SERIOUS PERSONAL INJURY &
WRONGFUL DEATH CASES
State-wide practice with offices located in
CLIFFORD E. CARDONENEW ORLEANS • WESTBANK • METAIRIE
(504) 581-1394
AV RATED
Criminal
Law
Excessive Sentence for
Malfeasance in Office
State v. McGuffie, 42,069 (La. App. 2
Cir. 8/1/07), 962 So.2d 1111.
Woodson McGuffie, an assistant par-
ish administrator for the Ouachita Parish
Police Jury, had a parish tree-trimming
crew work on his personal property.
McGuffie offered to pay the employee
for his work, but instead the employee
was instructed by his supervisor to make
out a work order so that the tree trimmer
was paid overtime from parish money for
the work performed. At trial, McGuffie
denied ordering the work and stated that
his wife had offered to pay the employee
money for the work performed. He fur-
ther testified that he had paid the supervi-
sor directly for other tree-trimming work.
McGuffie was indicted for one count
of malfeasance in office and convicted
after a jury trial. He was sentenced to the
maximum five-year sentence, two years of
which were suspended, and a $3,500 fine.
McGuffie did not file a motion to
reconsider his sentence. Thus, on appeal,
he was limited to a claim of unconstitu-
tional excessiveness, but he prevailed on
that issue. The court noted that the pur-
pose of the malfeasance charge is to deter
public officials from abusing their au-
thority and public resources. In this case,
McGuffie’s position was not particularly
powerful, and the loss to the parish was
not substantial. Further, McGuffie had
lost his job for misuse of resources and
had been publicly humiliated by his pros-
ecution.
Finally, McGuffie was a 58-year-old
first offender with no criminal record of
any sort, who suffered from serious medi-
cal conditions. The presentence investi-
gation noted that the cost of McGuffie’s
medication alone during incarceration
would be approximately $3,000 per
month over and above the cost of incar-
ceration.
In light of the loss of under $300 to the
parish, the court remanded for resentenc-
ing. The appellate court did not recom-
mend a jail sentence, but stated that the
maximum sentencing range that would
be affirmed would be one year without
hard labor and a fine of no more than
$3,000.
Lustful Disposition
Evidence Under
La. C.E. 412.2
State v. Richard Cotton, 42,509 (La.
App. 2 Cir. 9/19/07), ____ So.2d ____.
Richard Cotton was convicted of one
count of sexual battery of his step-grand-
daughter, who was 6 years old at the time
of the offense, for inappropriately touch-
ing her through her clothing at a family
function. At trial, the victim’s mother,
who was the defendant’s stepdaughter,
testified that she had been molested by
the defendant as a child, as did his niece.
Cotton admitted molesting the mother,
but blamed his post-traumatic stress dis-
order. He stated he had been in counsel-
ing since 1979 for his experiences in
Vietnam. He denied molesting his niece
or the victim before the court.
Cotton was convicted by a unanimous
jury and sentenced to five years at hard
labor without benefit of parole, proba-
tion or suspension of sentence. He ap-
pealed his conviction and sentence.
On appeal, the defendant argued that
the conviction was based on highly preju-
dicial “lustful disposition” evidence that
did not pass the Louisiana Code of Evi-
dence article 403 balancing test. The
270 December 2007 / January 2008
court of appeal found that the notice
requirement of Code of Evidence article
412.2 had been satisfied, and that the
prosecution stated that it was using the
evidence to show intent to commit the
offense, to show lustful disposition to-
wards children and to demonstrate that
the instant offense was part of a pattern of
behavior towards children. Between the
facts of the case and the limiting instruc-
tion given the jury (closely resembling a
limiting instruction for Code of Evidence
article 404), the court of appeal found no
error in the presentation of the past bad acts
to the jury. Based on the admissibility of the
evidence at trial, there was likewise no
error in using the past bad acts as a factor in
sentencing the defendant.
— Michael S. Walsh
Chair, LSBA Criminal Law Section
Lee & Walsh
628 North Blvd.
Baton Rouge, LA 70802
and
Joseph K. Scott III
Member, LSBA Criminal Law Section
830 Main St.
Baton Rouge, LA 70802
Environmental
Law
LDEQ Groundwater
Certification Program
Discontinued
Since November 1989, the Louisiana
Department of Environmental Quality
(LDEQ) has required regulated facilities
undertaking construction activities in-
volving subsurface intrusive techniques,
such as excavation and the installation of
footings, pilings or drill shafts or other
support structures, in connection with air
permits, modifications or exemptions, to
submit a formal groundwater certifica-
tion to the LDEQ demonstrating that
those activities will not affect existing
groundwater quality. The LDEQ has now
recognized that potential subsurface im-
pacts are being adequately addressed/
assessed through existing notification and
remediation regulations, RCRA correc-
tive action and/or other assessment prac-
tices necessary to obtain financing for
such projects and has concluded that
protection of the subsurface environment
can be attained without the need for for-
mal groundwater certifications. There-
fore, as of Nov. 1, 2007, the LDEQ will
no longer require groundwater certifica-
tions for construction activities associ-
ated with LDEQ air permits, modifica-
tions or exemptions.
No Bifurcation of Liability
and Damages in Oilfield
Legacy Suit
La. R.S. 30:29 governs the litigation
of claims for environmental damage
caused by oilfield operations (a/k/a
“legacy suits”). The statute requires the
party found liable for environmental dam-
age caused by past oilfield operations to
submit a remediation plan to the Depart-
ment of Natural Resources (DNR). The
statute also provides for the submission
and consideration of a response to that
plan by the plaintiff, a public hearing on
the proposed plans by the DNR, selec-
tion of the most feasible remediation
plan by the DNR, and the court’s issu-
ance of judgment adopting the most fea-
sible plan. The liable party must deposit
the cost of implementing the selected
plan into the registry of the court, and the
deposited funds may only be used to fund
remediation of the environmental dam-
age. The statute notably does not “preclude
an owner of land from pursuing a judicial
remedy or receiving a judicial award for
private claims suffered as a result of envi-
ronmental damage” nor does it:
preclude a judgment ordering dam-
ages for or implementation of addi-
tional remediation in excess of the
requirements of the plan . . . as may be
required in accordance with the terms
of an express contractual provision.
In Brownell Land Co. v. Oxy USA,
Inc., 2007 WL 3046203 (E.D. La. 2007),
defendants in a legacy suit moved via a
motion in limine to exclude all testimony
and evidence regarding the need for and
the extent and cost of plaintiff’s pro-
posed remediation plan during the initial
trial, claiming that consideration of such
evidence is appropriate only after the
court has determined that environmental
damage exists and that defendant is re-
sponsible for that damage. Citing an un-
published decision of the Louisiana 4th
Circuit in Duplantier Family Partner-
ship v. B.P. Amoco, 07-0293 (La. App. 4
Cir. 5/16/07, 955 So.2d 763, (which the
court noted was not controlling on it or
any other court) and the wording of the
subject statute, the Federal Eastern Dis-
trict denied defendant’s motion, conclud-
ing that the statute did not require a
separate determination of liability and
damages and noting that:
There is nothing wrong with a jury
determination of the amount of dam-
ages. Thereafter DNR will decide
(with the court’s approval) how
much of those damages are to be
used for remediation.
Property Owner’s Claim
Extends to Adjoining
Contaminated Properties
In the case of Consolidated Compa-
nies v. Union Pacific Railroad. Co., 499
F.3d 382 (5 Cir. 2007), plaintiff had
purchased a tract of land that formed a
portion of a former railroad yard owned
and operated by the defendant’s prede-
cessor in interest (the Railroad). It was
undisputed that the Railroad’s activities
had resulted in contamination over the
entirety of the former railroad yard, in-
cluding the plaintiff’s parcel. After dis-
covering contamination on its parcel and
incurring certain response costs, plaintiff
filed suit against the Railroad’s succes-
sor in interest, pleading causes of action
under the Resource Conservation Re-
covery Act (RCRA) and the Louisiana
Environmental Quality Act (LEQA).
Plaintiff sought monetary damages and
Louisiana Bar Journal Vol. 55, No. 4 271
injunctive relief, directing the defendant
to clean up the contamination on not only
plaintiff’s property but throughout the
entire former railroad yard.
On appeal, the 5th Circuit addressed
both the issue of plaintiff’s standing to
assert claims for contamination existing
on adjoining properties not owned by
plaintiff and whether the term “facility”
as used in RCRA and the LEQA was
limited to only the property owned by
plaintiff or extended to all of the property
constituting the former railroad yard that
suffered contamination.
On the first issue, the court held that
plaintiff had standing, concluding that the
contamination existing on the adjoining
properties threatened further contamina-
tion of plaintiff’s parcel through migration.
As to the second issue, the court
rejected defendant’s contention that the
term “facility” for purposes of plaintiff’s
RCRA claims should be limited only to
the property owned by plaintiff. Citing
the expansive definition of facility in both
RCRA and the Comprehensive
Environmental Response, Compensation
and Liability Act (CERCLA), and noting
that a division of the former railroad yard
into “several separate facilities along
current property lines would require
plaintiffs to bring numerous suits to
effectuate their remediation of one large,
discreet pollution source” and further that
“if a single source of contaminants, like
the former railroad site, is to be
adequately cleaned up, it must be done
in a comprehensive fashion,” the court
concluded that under § 6972(a)(1)(b) of
RCRA, the term encompassed the entire
former railroad site. Similarly, the court
concluded that the term “facility” for
purposes of the LEQA is not limited by
property boundaries and instead
encompasses the “entire location of a
discharge of contaminants.”
— Timothy J. Poché
Vice President, LSBA
Environmental Law Section
Taylor, Porter, Brooks
& Phillips, L.L.P.
451 Florida St., Chase Bank, 8th Flr.
Baton Rouge, LA 70801
Family Law
Custody
Pounds v. Spears, 06-2375 (La. App. 1
Cir. 3/23/07), 960 So.2d 92.
Although the father was named the
domiciliary parent, the trial court’s visi-
tation schedule had the child living pri-
marily with the mother in order to attend
school in Bogalusa where she lived, rather
than in Hammond where the father lived.
The court of appeal reversed, finding that
this negated the father’s designation as
domiciliary parent, and ordered that the
visitation schedule be changed to place
the child primarily with the father. It also
reversed the trial court’s determination
of the child’s pediatrician, as that, too,
deprived the father of the decision-mak-
ing authority granted to him as domicili-
ary parent.
Child Support
Strange v. Strange, 42,318 (La. App. 2
Cir. 6/20/07), 960 So.2d 1223.
After Ms. Strange remarried, had an-
other child and quit her job, she moved to
reduce the child support she was paying
to Mr. Strange for their two children. The
trial court found that she was voluntarily
under-employed and reduced her sup-
port for 29 months, subject to review on
motion by the father. The court of appeal
affirmed, finding no abuse of discretion
even though the trial court failed to cal-
culate the child support that would have
been due under the child support guide-
272 December 2007 / January 2008
lines, although it did give reasons for its
deviation.
Spousal Support
Martello v. Martello, 06-0594 (La. App.
1 Cir. 3/23/07), 960 So.2d 186.
Even though the trial court found the
parties mutually at fault, Ms. Martello
was still entitled after this determination
to an award of interim spousal support
until the date of the divorce. The trial
court amended the amount of interim
support awarded because it did not ap-
propriately consider Mr. Martello’s abil-
ity to pay and funds needed for his own
support. Mr. Martello’s having the chil-
dren 42.85 percent of the time did not
create a shared custody arrangement so
as to require Worksheet B. Although
there was no contradictory evidence of-
fered, the trial court determined Mr.
Martello’s business expenses to be less
than he presented them to be, and the
court of appeal affirmed, finding this to
be an “inherent credibility call.” The trial
court found Ms. Martello voluntarily
under-employed, even though she was
caring for the parties’ disabled child. She
had previously worked, was capable of
returning to work and the child was above
the age of 5. The court vacated the child-
support award, remanding for a new de-
termination after considering her earning
capacity and imputed income.
The parties’ letter agreement before a
notary and two witnesses after the peti-
tion for divorce was filed to cancel their
prenuptial separate-property contract was
valid and enforceable, despite his claims
that he signed the agreement to try to save
the marriage and because of financial
difficulties. The court did not address the
effect of the document, as it was not
before the court. There was no abuse in
the trial court’s not awarding rental to
him for her use of the matrimonial domi-
cile where he had requested use, but not
made an alternative claim for rent, and
where she had sought use but he had not
reconvened for rent.
Property
Sanders v. Sanders, 06-1401 (La. App. 1
Cir. 5/4/07), 961 So.2d 464.
Even though the trial court authorized
the parties to enter a community property
settlement attached to the petition for
divorce, it did not approve or sign the
judgment itself. Thus, the judgment was
not a judicial partition, and Mr. Sanders
successfully had it rescinded for lesion.
Clemons v. Clemons, 42,129 (La. App. 2
Cir. 5/9/07), 960 So.2d 1068.
The parties’ pre-termination line of
credit was required by the bank post-
termination to be converted to a perma-
nent loan. Subsequently, Dr. Clemons
refinanced the loan with another bank at
a lower interest rate. The court of appeal
held that the present debt was still a
community debt because it encompassed
the same debt and because he was re-
quired to prudently manage the commu-
nity obligations as well as its assets. Be-
cause he used his separate property post-
termination to make payments on this
debt, he was entitled to reimbursement.
The court of appeal reversed the award to
Ms. Clemons under La. Civ.C. art. 121,
finding that she had benefited for six
years after his graduation by accumu-
lated community property, even if not by
an improved lifestyle.
The trial court did not err in accepting
Dr. Clemons’ value of cattle and horses
and a reimbursement to him for post-
termination expenses for them because
he was familiar with valuing and main-
taining livestock and presented an objec-
tive methodology by which he valued
them. The court of appeal also affirmed
the deduction of $4,000 in bad debts
from the value of his veterinary practice
after reviewing Ms. Clemons’ argument
that they were merely uncollected, not
uncollectible. The court of appeal did not
allow him reimbursement for payments on
a truck loan where he had exclusive use. A
settlement of a suit by Dr. Clemons against
another veterinarian for breach of a non-
compete contract was part community and
part separate. The separate portion was for
damages to the goodwill of the business.
Procedure
Nguyen v. Le, 07-0081 (La. App. 5 Cir.
5/15/07), 960 So.2d 261.
The court found that “the Post-Sepa-
ration Family Violence Relief Act can-
not be [pled] for the first time on appeal,
as it requires the trial court to make a
specific determination of ‘a history of per-
petration of family violence.’” Ms. Nguyen
had sought sole custody under La. Civ.C.
art. 132 and had presented evidence of
alleged abuse at trial. The trial court did not
err in granting joint custody.Best advertising tool on the market today.
Phone rings geographically
based on your area code.
Call NOW
to see if your area code is available!
281-615-4269 Ask for John.
1-800-LAWYERSThis could be your
office phone number!
Ellison v. Ellison, 06-0944 (La. App. 1
Cir. 3/23/07), 960 So.2d 155.
Ms. Ellison’s petition for nullity on
the grounds of fraud and ill practice was
perempted due to her failure to investi-
gate the status of the partition suit after
Louisiana Bar Journal Vol. 55, No. 4 273
she had knowledge of facts, including the
death of her attorney, sufficient to cause
a reasonable person to make further in-
vestigation into the matter.
Welborn v. 19th Jud. Dist. Ct., 06-2307
(La. App. 1 Cir. 5/4/07), 961 So.2d 394.
The 19th Judicial District Court and
the East Baton Rouge Parish Family Court
have concurrent subject matter jurisdic-
tion over actions brought under the Do-
mestic Abuse Assistance Act and/or the
Protection from Dating Violence Act
when the victim is a “dating partner” or
unrelated “household member” of the
alleged perpetrator.
— David M. Prados
Member, LSBA Family Law Section
Lowe, Stein, Hoffman, Allweiss
& Hauver, L.L.P.
Ste. 3600, 701 Poydras St.
New Orleans, LA 70139-7735
A LAWYER’S LAWYER
TOLLFREE 800.884.9939 FAX 504.838.9555 WWW. ADRINCORPORATED.COM
THOMAS KEASLER FOUTZ,
recently chosen by fellow
attorneys and mediators
for inclusion in
Best Lawyers in America,
field of alternative
dispute resolution.
MEDIATION • ARBITRATION
JURY FOCUS GROUPS • SEMINARS
MEDICAL REVIEW PANELS
MEDIATED SETTLEMENT DAYS
Insurance,
Tort, Workers’
Compensation
and Admiralty
Law
Plaintiff Precluded from
Asserting Federal Common
Law Causes of Action
Wright v. Allstate Ins. Co., 500 F.3d 390
(5 Cir. 2007).
Wright brought suit against Allstate
Insurance Co., a Write-Your-Own insur-
ance company that issued his federal-
flood-insurance policy. Wright’s home
sustained damage in 2001 as a result of
Tropical Storm Allison. Unsatisfied with
the amount paid under his flood-insur-
ance policy, Wright filed suit against
Allstate and one of its employees, assert-
ing claims for breach of contract, as well
as state law claims for fraud and negli-
gent misrepresentation. Wright later
sought leave of court to add federal com-
mon-law claims for fraud and negligent
misrepresentation. The district court dis-
missed the state-law extra-contractual
claims, holding that these claims were
pre-empted by federal law. The court
also denied leave to amend to add the
federal common-law claims. The court
further held that Allstate was equitably
estopped from asserting Wright’s alleged
failure to provide an adequate proof of
loss, but determined that Wright had failed
to prove that all of his claimed damages
were the result of flooding. The court
awarded Wright $24,029, following a
bench trial.
Wright appealed, and the U.S. 5th
Circuit held that his state-law claims were
indeed pre-empted by the National Flood
Insurance Act. See Wright v. Allstate Ins.
Co., 415 F.3d 384 (5 Cir. 2005). The
court further held that Wright’s claim of
equitable estoppel was not viable in this
case. Id. at 388. Significantly, however,
the court did not foreclose the use of
equitable estoppel in the appropriate case.
Id. The court remanded the case to the
district court, however, for clarification
of the basis for the denial of Wright’s
motion for leave to add the federal com-
mon-law claims. Id. at 391. On remand,
the district court rejected the federal com-
mon-law claims, stating that it was “not
aware by the pleading or otherwise of any
federal common law cause(s) of action
that might be asserted by [Wright].”
Unsatisfied with the district court’s
explanation on remand, Wright again
appealed. In his second appeal, Wright
contended that the National Flood Insur-
ance Act expressly authorizes extra-con-
tractual federal common-law claims for
fraud and negligent misrepresentation.
As grounds for this argument, Wright
asserted that the Standard Flood Insur-
ance Policy specifies that disputes aris-
ing under the policies will be governed
by federal common law. Alternatively,
he claimed that the Act impliedly autho-
274 December 2007 / January 2008
rizes such claims. As support for this
claim, Wright asserted that the language
and purpose of the National Flood Insur-
ance Act implied such a cause of action.
The 5th Circuit rejected both argu-
ments. With regard to the express autho-
rization argument, the court reviewed the
Standard Flood Insurance Policy and the
National Flood Insurance Act and deter-
mined that neither contained any indicia
of a congressional intent to allow the
extra-contractual causes of action. To
determine whether a right of action was
implicitly authorized, the court reviewed
the four factors set forth in Cort v. Ash,
95 S.Ct. 2080 (1975). The court held that
Wright’s alternative argument was uncon-
vincing, and stated that it perceived no
evidence that Congress implicitly intended
that policyholders by able to file claims
against Write-Your-Own insurers other than
those claims specifically provided for in
the National Flood Insurance Act.
flooded. The hurricane also caused water
damage to the second story of the duplex,
as well as the contents of the Bests’
apartment. The Bests made a claim to
State Farm under the contents portion of
their policy, based upon their assertion
that the source of the water on the second
floor was holes in the roof caused by
wind damage. State Farm denied the claim
based upon its determination that the
source of the water on the second floor
was flooding. After reviewing all evi-
dence presented by the Bests and by
State Farm, the trial court held that the
damage to the contents of the plaintiffs’
home was caused by wind, not flooding.
The trial court awarded the Bests the full
amount of the limits of the renter’s policy,
and assessed statutory penalties against
State Farm, in accordance with La. R.S.
22:658, as it was in effect prior to its
amendment on Aug. 15, 2006.
On appeal, the Bests asserted that the
trial court erred in finding that the pre-
amendment version of La. R.S. 22:658
applied. The pre-amendment version of
the statute provided that, when an insurer
failed to make payment on a property-
damage claim within 30 days after re-
ceipt of satisfactory proof of loss and
such failure was found to be “arbitrary,
capricious, or without probable cause,”
the court may assess penalties in the
amount of 25 percent of the amount found
to be due from the insurer to the insured,
or $1,000, whichever is greater. Effec-
tive Aug. 15, 2006, the statute was
amended to provide for a 50 percentInternational Law
penalty and to provide an assessment of
reasonable attorneys’ fees and costs.
The Bests submitted their satisfactory
proof of loss on or before Jan. 3, 2006,
but State Farm continuously denied the
claim up until the time of trial. In deter-
mining which version of the statute to
apply, the appellate court noted the trial
judge’s finding that the cause of action
under the statute arose when State Farm
failed to pay the Bests’ claim within 30
days of notice of the claim. As such, the
appellate court stated, “Even though State
Farm’s failure to pay the Bests’ claim
extended beyond the effective date of the
2006 amendments to La. R.S. 22:658,
their cause of action arose prior to the
effective date.” The appellate court held
that the Bests were not entitled to the
increased penalty provided by the statute
as amended in 2006.
— Brendan P. Doherty and
Rachel G. Webre
Members, LSBA Insurance, Tort,
Workers’ Compensation
and Admiralty Law Section
Gieger, Laborde & Laperouse, L.L.C.
One Shell Square, Ste. 4800
701 Poydras St.
New Orleans, LA 70139-4800
Determination of Extent of
Penalties Owed by Insurer
Aronson v. State Farm Fire and Cas.
Co., 07-0573 (La. App. 4 Cir. 10/10/07),
____ So. 2d ____.
Plaintiffs, Katheryn Aronson Best and
Mark Best, rented half of a two-story
duplex. The Bests had a policy of renter’s
insurance issued by State Farm that pro-
vided coverage for wind damage, but not
for flooding. As the result of Hurricane
Katrina, the first floor of the duplex was
World Trade Organization
Intellectual Property
Dispute Settlement
China — Measures affecting the protec-
tion and enforcement of intellectual prop-
erty rights (WT/DS362).
On Sept. 25, 2007, the World Trade
Organization’s (WTO) Dispute Settle-
ment Body established the first dispute-
settlement panel to review China’s pro-
tection and enforcement of intellectual
property rights. The United States initi-
Louisiana Bar Journal Vol. 55, No. 4 275
World Class Technology.Local Commitment.
DOCUSOURCE DISCOVERY MANAGEMENT offers best practices consulting and services including:• Management Plans • Training • ESI Processing • Collection • Review • Production • Mock Trial
Visit Docusource-lss.com/resources for your free pocket guide to electronic discovery “Digital Discovery Guide”
New Orleans Baton Rouge Lafayette
D O C U S O U R C ED I S C O V E RY
MANAGEMENT
DDM is Louisiana's largest independent provider of consultingservices and document outsourcing. For over 20 years,Docusource Discovery Management has providedexperts in the field including practicing attorneys, analystsand information technology professionals.
• Certified E-discovery Consultants• Certified Trial Consulting• Certified Concordance Training• Certified Summation Training• Certified Case Map Training
Call today 1-800-588-1779 or (504) 588-2679
201 St. Charles Ave., CapitalOne Bldg., Suite 1401, New Orleans, LA 70170 www.docusource-lss.com
ated consultations with China on April
10, 2006, regarding various alleged defi-
ciencies in China’s domestic intellec-
tual-property regime. The dispute-settle-
ment panel will resolve several issues,
including:
� whether China has implemented ap-
propriate criminal procedures and pen-
alties in cases involving willful trade-
mark counterfeiting or copyright pi-
racy pursuant to Articles 41.1 and 61
of the WTO Agreement on Trade-
Related Aspects of Intellectual Prop-
erty Rights (TRIPS Agreement);
� whether China maintains appropriate
measures under TRIPS articles 46 and
59 to appropriately dispose of confis-
cated goods that infringe intellectual
property rights; and
� whether China is acting inconsistently
with TRIPS articles 9.1 and 14 by
denying the protection of its copy-
right law to creative works of author-
ship that have not been cleared for
publication or distribution within
China (the Chinese law allegedly de-
nies copyright protection for works
poised to enter the market but await-
ing Chinese censorship approval).
One of China’s defenses is that the
United States is seeking to impose extra
obligations on a developing country in
violation of the TRIPS Agreement. See
TRIPS Agreement arts. 65 & 66. The
WTO Agreements do not define what
constitutes a developing country, and the
panel for the first time will have to ad-
dress the issue of whether China qualifies
for special and differential treatment as a
developing country within the context of
the TRIPS Agreement.
shrimp processors and other businesses
engaged in harvesting and processing
domestic shrimp (including many
Louisiana businesses) previously
obtained an Antidumping Order on
imported shrimp from Brazil, China,
Ecuador, India, Thailand and Vietnam.
See Antidumping Orders on Certain
Frozen or Canned Warmwater Shrimp
and Prawns, Department of Commerce
Case Nos. A-351-838 (Brazil); A-570-
893 (China); A-331-802 (Ecuador); A-
533-840 (India); A-549-822 (Thailand);
and A-552-802 (Vietnam). In response
to the order against it, Ecuador lodged a
case at the World Trade Organization
(WTO) complaining about the United
States Department of Commerce’s
“zeroing” methodology for the
calculation of dumping margins. The
controversial “zeroing” methodology
allows the Department of Commerce to
exclude transactions that have a negative
dumping margin; in essence, where the
Antidumping Duties and
Procedures Regarding
Imported Shrimp
A coalition of domestic shrimpers,
276 December 2007 / January 2008
foreign producer is not selling the subject
product at less than fair value in the
United States, the Department of
Commerce has the option to exclude that
transaction from the total weighted
average, resulting in a higher overall
average than would occur if the
transaction were included. The WTO
dispute-settlement panel found the
practice a violation of the WTO
Antidumping Agreement Article 2.4.2,
first sentence. See United States-Anti-
Dumping Measure on Shrimp from
Ecuador (WT/DS335/R). As a result of
the ruling, the antidumping margins on
shrimp from Ecuador were deemed de
minimis and the Department of
Commerce revoked the Antidumping
Orders on imported shrimp and prawns
from Ecuador. See 72 Fed. Reg. 48,257
(Aug. 23, 2007).
The Department of Commerce’s
acceptance of the WTO Ecuador ruling
and subsequent elimination of the orders
on shrimp from Ecuador illustrates a
significant shift from prior “zeroing”
rulings where the Department of
Commerce did not reverse the practice
and appealed the decision to the WTO
Appellate Body. See e.g. United States-
Laws, Regulations and Methodology for
Calculating Dumping Margins (Zeroing)
(WT/DS294/AB/R); United States-
Measures Relating to Zeroing and Sunset
Measures, (WT/DS322/AB/R). WTO
dispute-settlement panel (and Appellate
Body) rulings apply only to the parties
in the case and have no stare decisis or
precedential effect on other cases. See
Japan-Taxes on Alcoholic Beverages
(WT/DS8.10.11/AB/R).
The compatibility of the zeroing
practice with the WTO Antidumping
Agreement is ultimately subject to a
ruling by the WTO Ministerial
Conference, which has the ultimate
authority to interpret the WTO Agreements,
and is currently being negotiated in the
WTO Doha Round negotiations.
Rodney A. “Rocky” Seydel, Jr.
M e d i a to r & M e d i c a l R e v i e w Pa n e l A t to r n e y C h a i r p e r s o n
Automobile • Dramshop Liability • Landlord & Tenant • Medical Malpractice
Personal Injury • Premises Liability • Product Liablity
New Orleans Metro AreaFor dispute resolut ion services, contact MAPS:
Two Lakeway Center • Suite 4003850 N. Causeway Blvd.Metairie, LA 70002800.443.7351 504.831.2141
Fax: 504.837.2566Email: [email protected]: www.maps-adr.com
2191-2194. Congressional approval of
the agreements is performed in “mock”
markup negotiating sessions without the
opportunity to insert changes or amend-
ments to the agreement (so-called “fast
track” procedure). Congress can vote only
yeah or nay on the terms of the agreement
as presented by the President and as
outlined in the implementing legislation
submitted by the President with the agree-
ment. Id. The President’s Trade Promo-
tion Authority expired under the existing
statute at midnight on July 1, 2007. Id. at
§3803(c)(1)(B). However, the four agree-
ments were presented to Congress prior to
the statute’s expiration and will be consid-
ered under the terms of the now-expired
statute. There is no current proposal to
renew or re-enact the President’s Trade
Promotion Authority, essentially eliminat-
ing the current Administration’s ability to
negotiate any new Free Trade Agreements,
including any conclusion to the ongoing
WTO Doha Round negotiations.
— Edward T. Hayes
Member, LSBA International
Law Section
Saporito & Hayes, L.L.C.
Ste. 2100, 639 Loyola Ave.
New Orleans, LA 70113
United States Free Trade
Agreements
The United States recently signed Free
Trade Agreements with Colombia,
Panama, Peru and South Korea. All four
agreements are unique in that they con-
tain new, stronger provisions on environ-
mental and labor protection. Each agree-
ment awaits congressional approval un-
der the procedures outlined in the United
States Trade Promotion Authority Act
(Trade Act of 2002). See 19 U.S.C. §§
Louisiana Bar Journal Vol. 55, No. 4 277
Lloyd T. Bourgeois
m e d i a t o r
Automobile • Insurance Liability • Personal Injury
Premises Liability • Property Damage • Real Estate
Houma/ Thibodaux/
Lafayette Metro AreasFor dispute resolut ion services, contact MAPS:
Two Lakeway Center • Suite 400
3850 N. Causeway Blvd.Metairie, LA 70002800.443.7351 504.831.2141Fax: 504.837.2566Email: [email protected]
Website: www.maps-adr.com
Labor and
Employment
Law
No Coverage
or Duty to Defend
Henly v. Phillips Abita Lumber Co., 06-
1856 (La. App. 10/3/2007), ____ So.2d
____.
The traditional notion that commer-
cial-general-liability policies do not cover
employment issues is still alive and well in
the 1st Circuit of Louisiana. This case gives
a clear explanation of this principle.
Abita Lumber Co. supervisor Jeffrey
Bruce is alleged to have committed im-
proper workplace behavior against a fe-
male employee both on and off the pre-
mises of the lumber yard, including both-
ering her while both were at work at the
lumber yard site by improper touching,
solicitations and sexual comments. One
particular allegation was the focus of the
attention of the 1st Circuit: the supervi-
sor, while giving the female employee a
ride to work, allegedly pulled off the road
and exposed himself to her. When she
rebuffed his unwelcome advances, he
threatened her with the loss of her job,
yelled at her, threw chairs and, on one
occasion, pushed or kicked her in the
back, forcing her forward into a wall and
causing a lower back injury that eventu-
ally required surgery.
Abita Lumber Co. filed a demand
against its commercial-general-liability
company for liability coverage and a
defense to the claims of the plaintiff
female employee, including reimburse-
ment of litigation expenses already in-
curred. The insurance company, Travel-
ers Property Casualty Co. of America,
filed an answer denying coverage and a
duty to defend on the basis of policy
exclusions, including the workers’ com-
pensation exclusion, the “bodily injury
to an employee” exclusion, the employ-
ment-related practices exclusion, and the
discrimination exclusion.
After a hearing, the district court granted
Traveler’s motion for summary judgment
as to both coverage and defense and denied
Abita’s motion, stating that:
the Travelers policy clearly and un-
ambiguously excludes coverage for
the acts alleged in the petition of
. . . [the supervisor] and Travelers
does not have a duty to defend . . .
Abita against the allegations of . . .
[the female worker].
Abita appealed.
The 1st Circuit reiterated all of the
usual principles of summary judgment,
insurance policy interpretation and the
duty to defend (the “eight-corners rule”).
In its analysis, the 1st Circuit limited
its review because the lumber company
conceded that the workplace allegations
were not covered in that the policy unam-
biguously excluded coverage for all ex-
cept the exposing incident. Also, the lum-
ber company appealed only the duty-to-
defend decision and did not appeal the
coverage issue.
An occurrence is, under the policy,
one that takes place during the policy
period and within the coverage territory.
There is no dispute that the exposing
incident took place during the policy
period and the coverage territory. The
decision turned on a specific inquiry to
determine whether the supervisor was
within the course and scope of his em-
ployment when he allegedly exposed him-
self to her. The factual allegations of the
petition show that it did not occur on the
lumber yard property nor during working
hours, inasmuch as they were on their
way to work but had not yet arrived.
Because an employee usually does not
begin work until he reaches his employer’s
premises, his travel to and from work is
generally considered outside the course
278 December 2007 / January 2008
of his employment, unless he has a duty
to perform en route. There was no evi-
dence that he had to perform a work-
related duty, nor did the supervisor’s
duties have anything to do with the kind
of activities he was employed to perform
for the lumber company. His improper
sexual conduct was “certainly not so
closely connected in time, place, and
causation to his employment duties with
the lumber yard that it could be regarded
as a risk of harm fairly attributable to its
business.” The court concluded that Bruce’s
actions were a “purely personal mission
entirely extraneous to his employment.”
— Gregory K. Moroux
Member, LSBA Labor
and Employment Law Section
The Onebane Firm
Ste. 300, 1200 Camellia Blvd.
Lafayette, LA 70502-3507
Professional
Liability
Physician-Patient
Confidentiality Privilege
Coutee v. Beurlot, 06-2943 (La. 9/5/07),
964 So.2d 304.
Mr. Coutee sued Dr. Beurlot for dis-
closing private and confidential informa-
tion during an ex parte pretrial meeting
with an attorney who did not have the
plaintiff’s authorization to participate in
such a conference. The trial and appel-
late courts found that Dr. Beurlot had
undermined the confidence between phy-
sician and patient by violating this “con-
fidential, personal and professional rela-
tionship between physician and patient.”
The trial court awarded $20,000 in dam-
You’ll call him an
S e r v i n g A c a d i a n a f o r 3 0 Ye a r s
1101 S College Rd., Suite 400 / Lafayette, LA 70503 / 337.233.5025 / www.psassoc.com
Respected and trusted by both plaintiff and defense lawyers, Dr. Darrell L. Henderson is one of the nation’s leading reconstructive and plastic surgery experts. Throughout his 30 year practice, he has followed single cases for multipleyears, giving him the experience and knowledge to makeaccurate projections on future patient care. But it's not justhis legal expertise that patients appreciate: his genuinecare and compassionate bedside manner keeps them comingback, year after year. He understands that just because thecase is closed, doesn’t mean it’s over.
Total Care for the Patient.It’s the way we operate. It’s the way we practice medicine.
Darrell L. Henderson, MD
ExpertExpertYour clients
will call him an
Witness.Physician.
ages for emotional injuries, and the court
of appeal reduced the award to $10,000.
The Supreme Court reversed, ruling that
Coutee failed to prove two necessary
elements of his case: causation and dam-
ages. This decision allowed the court to:
find it unnecessary to discuss
whether or not Dr. Beurlot’s giving
of a new, different opinion at the ex
parte meeting constituted a viola-
tion of the doctor-patient privilege,
or whether a violation of the dis-
covery statutes constitutes a com-
pensable tort.
One concurring opinion stated that
Coutee failed to prove any “legally com-
pensable damages,” and a second con-
curring opinion posited that violations of
the physician-patient privilege are gov-
erned by Louisiana Code of Evidence
article 510(G), which states that a patient’s
remedy in such a case is against the
Louisiana Bar Journal Vol. 55, No. 4 279
JOHN CAULKING J. GREGG COLLINS TOM FOUTZ JOEL FRIEDMAN RICHARD GANUCHEAU
PHELPS GAY JOEL GOOCH BEN HANCHEY MAURICE HEBERT, JR.CAROLYN GILL- JEFFERSON
KATHY HOBSON DANIEL HURLEY LAVONNE MARTIN JOE MURRAY JOHN MUSSER, IV
STEVEN PLOTKIN J. VAN ROBICHAUX, JR. ANDY SCHAFFER DAVID WILLIAMS
MEDIATION
JURY FOCUS GROUPS
ARBITRATION
MEDICAL REVIEW PANELS
MEDIATED SETTLEMENT DAYS
SEMINARS
TOLLFREE 800.884.9939
FAX 504.838.9555
WWW.ADRINCORPORATED.COM
attorney, not the physician. It should be
noted that Coutee did not file a HIPAA
complaint against the physician.
Penalties for Not Timely
Paying Settlement Funds
the PCF, would determine the amount
due Medicare through negotiations and
provide the tax identification informa-
tion requested.
Seven weeks later, the defendants ad-
vised the plaintiffs that they had not re-
ceived the requested information and in-
quired about the status of the Medicare
discussions. Two months later, the de-
fendants sent a draft of settlement docu-
ments to the plaintiffs.
The defendants contended that sev-
eral additional months then lapsed with
no response from the counsel for the
plaintiffs and, on March 24, 2004, de-
fense counsel contacted Medicare and
learned that no request had been made by
anyone to determine the lien information
that was communicated to plaintiffs’
counsel, who in turn contacted Medi-
care.
The defendants contended that they
waited another year for a response and,
having received none, attempted to coor-
dinate efforts with the PCF for a joint
settlement. They claimed that again they
got no response from plaintiffs’ counsel
and that yet another year went by with no
activity relative to the settlement until
March 22, 2006, when counsel for the
PCF advised that there was no Medicare
lien and that the plaintiffs had rejected
the PCF’s settlement offer.
On April 28, 2006, the draft settle-
ment documents were again sent to
plaintiff’s counsel. Another month
elapsed before they heard from plaintiff’s
counsel and still they had not been pro-
vided with the payee information.
The plaintiffs contended that by their
letter of April 1, 2003, they advised de-
fendants that designating Medicare as a
payee on the settlement check was unac-
ceptable because they anticipated a dis-
pute with Medicare. They also asserted
that the defendants accepted this “coun-
teroffer” by stating that they were willing
to make payments upon resolution of the
Reiners v. St. Landry Hosp. Serv. Dist.
Two, 07-0158 (3 Cir. 5/30/07), 958 So.2d
783.
The plaintiffs filed a petition to en-
force a written agreement to settle a medi-
cal-malpractice case and for penalties
pursuant to La. R.S. 22:1220.
The defendants had extended a writ-
ten settlement offer on April 1, 2003,
specifying that Medicare would be a
named payee on the settlement check and
that defendants would be provided with
payee information for all of the plaintiffs
and their attorney. The plaintiffs re-
sponded that same date, accepted the
offer and informed the defendants that
they would seek excess damages from
280 December 2007 / January 2008
Medicare lien. Furthermore, the plain-
tiffs contended that once the defendants
were advised that there was no Medicare
lien, there was nothing to prevent the
defendants from issuing the settlement
check, yet over three years elapsed be-
tween the time of the settlement agree-
ment and the date the plaintiffs filed the
petition to enforce the settlement.
The trial court granted the plaintiffs’
petition to enforce the settlement and
awarded penalties of $35,000 ($5,000
per plaintiff).
The defendants contended on appeal
that they were not in bad faith because the
plaintiffs did not provide the necessary
payee information and had refused to
accept a settlement check that included
Medicare as a payee. Federal law forbids
issuing a settlement check with only the
plaintiffs as payees unless there is an
assurance that the Medicare lien would
be, or had been, satisfied, and the defen-
dants argued that the plaintiffs did not
notify them that there was no Medicare
lien until three years after the settlement
agreement was reduced to writing.
The court of appeal affirmed the trial
court’s ruling that:
defendants acted in bad faith be-
cause the settlement agreement did
not state or include any specific
amount that may be due Medicare
and because three and one-half years
had elapsed with no tender of a
settlement check.
The award of penalties for the
defendant’s conduct, which the trial court
found was “arbitrary and capricious,”
was affirmed.
— Robert J. David
Gainsburgh, Benjamin, David,
Meunier & Warshauer, L.L.C.
Ste. 2800, 1100 Poydras St.
New Orleans, LA 70163-2800
SOLACE / Support of Lawyers/Legal Personnel All Concern Encouraged
The Louisiana State Bar Association/Louisiana Bar Foundation’s Community Action Committee supports the SOLACE program.
Through the program, the state’s legal community is able to reach out in small, but meaningful and compassionate ways to
judges, lawyers, court personnel, paralegals, legal secretaries and their families who experience a death or catastrophic illness,
sickness or injury, or other catastrophic events. For assistance, contact a coordinator.
Area Coordinator Phone E-mail
Alexandria Area Elizabeth Erny Foote (318)445-4480 [email protected]
Baton Rouge Area Ann G. Scarle (225)214-5563 [email protected]
Covington/Mandeville Area Suzanne E. Bayle (504)524-3781 [email protected]
Denham Springs Area Mary E. Heck Barrios (225)664-9508 [email protected]
Houma/Thibodaux Area Danna Schwab (985)868-1342 [email protected]
Jefferson Parish Area Pat M. Franz (504)455-1986 [email protected]
Lafayette Area Susan Holliday (337)237-4700 [email protected]
Lake Charles Area Joel Lutz (337)433-0022 [email protected]
Monroe Area Daniel J. Ellender (318)647-3311 [email protected]
Natchitoches Area Peyton Cunningham, Jr. (318)352-6314 [email protected]
(318)481-5815
New Orleans Area Helena N. Henderson (504)525-7453 [email protected]
Opelousas/Ville Platte/Sunset Area John L. Olivier (337)662-5242 [email protected]
(337)942-9836
(337)232-0874
Shreveport Area Patti Guin (318)222-3643 [email protected]
For more information, go to: www.lsba.org/2007InsideLSBA/solace.asp.