la guarde creek bridge crossing, siphon creek … · the scope of our work is outlined in our...
TRANSCRIPT
GEOTECHNICAL REPORT
LA GUARDE CREEK BRIDGE CROSSING,SIPHON CREEK ROAD, 40 KM NORTHEAST
OF FORT ST. JOHN, B.C.
Prepared for
B.C. MINISTRY OF TRANSPORTATION AND INFRASTRUCTUREPRINCE GEORGE, B.C.
Prepared by
GEONORTH ENGINEERING LTD.3975 18 AVENUEth
PRINCE GEORGE, B.C., V2N 1B2Phone: 250-564-4304 Fax: 250-564-9323
PROJECT No. K-4274
January 18, 2016
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
TABLE OF CONTENTS
Page No.
1.0 INTRODUCTION 1
2.0 SITE AND PROJECT DESCRIPTION 2
3.0 GEOLOGICAL BACKGROUND 3
3.1 Surficial Geology 3
3.2 Bedrock Geology 3
3.3 Review of Aerial Photographs 3
4.0 SITE INVESTIGATION 4
5.0 SUBSURFACE CONDITIONS 5
5.1 Bridge Foundations 5
5.2 Existing Pavement Structure 7
6.0 DISCUSSIONS AND RECOMMENDATIONS 8
6.1 Bridge Foundations 9
6.2 Bridge End Fill 12
6.3 Pavement Structure 12
6.4 Aggregates and Fill 13
7.0 CONSTRUCTION REVIEW 15
8.0 CLOSURE 15
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
APPENDICES
APPENDIX A
Site Location Plan Drawing 4274-A1
Site Plan and Profile Drawing 4274-A2
APPENDIX B
Summary Logs 6 pages
Materials Classification Legend 1 page
APPENDIX C
Transition Detail: Existing to New Road Structure Plate 4274-C1
Typical Embankment Widening Detail Plate 4274-C2
APPENDIX D
Site Photographs Plates 4274-P1 to P2
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
1.0 INTRODUCTION
The British Columbia Ministry of Transportation and Infrastructure (BCMoT) is planning
to replace an existing multiplate culvert crossing of La Guarde Creek on Siphon Creek Road with
a 28 m long, clear span bridge. The crossing is located about 40 km northeast of Fort St. John,
B.C., and is accessed by the Rose Prairie Road, then about 22 km east on Cecil Lake Road and
30 km north on Siphon Creek Road. The site location is shown on Drawing 4274-A1, in
Appendix A.
BCMoT commissioned GeoNorth Engineering Ltd. to carry out a geotechnical
investigation for design and construction of the proposed bridge foundations and approaches.
The scope of our work is outlined in our proposal dated September 29, 2015 to Mr. Brent Case,
P.Eng. of BCMoT. Mr. Case authorized us to proceed with the work in an email dated
September 30, 2015.
Conceptual design sketches by BCMoT show that the new bridge will be a 28 m long,
12 m wide two lane bridge. At the time of this report, design of the proposed bridge had not
been carried out but we understand the structure will likely use precast concrete or steel girders
and precast concrete abutments placed on pile or spread footing foundations. A site plan
showing the existing crossing is on Drawing 4274-A2, in Appendix A.
This report presents the results of our site investigation, and provides geotechnical
recommendations for design and construction of the proposed bridge foundations and
approaches.
Page 1 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
2.0 SITE AND PROJECT DESCRIPTION
The present crossing consists of a 3.6 m diameter, 28.3 m long, structural plate
corrugated steel pipe (SPCSP). The upstream (south) side of the SPCSP was recently damaged
and about 12 m length of pipe was removed. An emergency repair was made to the road
consisting of rip-rap slope protection, a short concrete locking block wall on the south side and
fill placed out over the north side to shift the road north, away from the eroded upstream bank.
The road is currently open for singe-lane traffic only.
Site plans and cross section profiles dated August 2015 by McElhanney Consulting
Services Ltd., survey consultants for the project, show there is between 2.0 to 2.5 m of soil cover
over the culvert. The pipe inlet and outlet are at elevations 672.1 and 671.3 m, respectively. The
lowest point of the creek bed upstream of the culvert is at about elevation 670.6 m, lower than
the culvert inlet and the high water mark is at approximately elevation 674.2 m. The site plans
show an existing beaver dam located near the original culvert inlet.
The cause of the culvert failure is unknown, but might have been due to buoyant uplift
forces caused by air inside the pipe when it became partially blocked by the beaver dam and
other debris. Other possible causes include joint separation from differential settlement or poor
construction, piping or scour below the culvert inlet due to poorly compacted backfill, inadequate
erosion protection, or holes in the pipe from corrosion.
The existing road consists of two 3.6 m wide, paved lanes and about 0.5 m wide gravel
shoulders, for a total width of about 8.2 m. The bridge surface will likely consist of two 3.6 m
wide lanes, 2.0 m wide shoulders and an allowance for bridge parapets, for a total width of about
12 m. To accommodate an increased road width, we understand the grade of the road at the
proposed bridge crossing will be slightly lowered. Conceptual design sketches show the existing
creek channel will be moved slightly east and the channel skew angle relative to the bridge will
be increased from 29 to 35 . Overview photos of the site are shown on Plates 4274-P1 and P2o o
in Appendix D.
Page 2 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
3.0 GEOLOGICAL BACKGROUND
To obtain geological background information for this project, we reviewed published
surficial and bedrock geological maps and reports, and aerial photographs.
3.1 Surficial Geology
Map 1460A, by Geological Survey of Canada, at a scale of 1:250,000, shows the area
along the Doig River valley is underlain by deposits from Glacial Lake Peace and the uplands
on each side of the valley are underlain by drumlinized till. The site, located near the south edge
of the Doig River valley at about elevation 670 m, is well below the level of Glacial Lake Peace,
shown at about elevation 700 m on the map. Glacial lake sediments typically consist of layered
silt, clay and fine grained sand. Glacial till is typically a heterogeneous mixture of sand to cobble
size particles in a silt and clay matrix, deposited from below glacial ice that once covered
the area.
3.2 Bedrock Geology
Map NO-10-G, by Geological Survey of Canada, at a scale of 1:500,000, shows that
bedrock in the area is Lower to Upper Cretaceous in age. The bedrock is identified as fine clastic
sedimentary rocks including dark grey marine shale, siltstone and sandstone of the Fort St. John
Group and the Kotaneelee Formation.
3.3 Review of Aerial Photographs
We reviewed digital aerial photographs available from GeoBC from flight lines
30BCB95008 dated 1995, 15BCB97013 dated 1997, and 15BCC05124 dated 2005. The photos
show the project area on flat terrain that has a mottled surface and dendritic drainage patterns,
characteristic of areas underlain by glacial lake sediments. Starting just upstream of the bridge
crossing, La Guarde Creek channel has cut into the flat lying glacial lake sediments, and created
Page 3 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
a steep-sided, incised draw that becomes progressively deeper and with more unstable sidewalls
to the confluence with Doig River. Most of the surrounding land is cultivated farmland or tree
covered. The photos show Siphon Creek Road, the culvert crossing at La Guarde Creek and
ponded water at the culvert inlet. In the 1995 photos the ponded water can be seen extending
more than 1 km upstream. In the later photos, ponding is mostly isolated to a marshy area
directly upstream of the culvert.
4.0 SITE INVESTIGATION
On October 7 and 8, 2015, personnel from our office observed soil and groundwater
conditions in two drill holes, designated DH15-1 and 2, that were advanced to 27.2 and 24.4 m
depth, respectively, on each side of the crossing. The holes were advanced by Peace Drilling and
Research Ltd. of Fort St. John using a truck-mounted rig and solid-stem augers. Sampling was
carried out at regular intervals using Standard Penetration Tests (SPTs) (ASTM D1568) and
Shelby tubes (ASTM D1587). We also collected samples from the auger flights and carried out
shear vane (ASTM D2573) tests in the drill holes. Drill hole locations were measured from site
landmarks and elevations were surveyed using an engineering level and rod. The locations of
the drill holes are shown on Drawing 4274-A1, in Appendix A. Drill hole elevations were
referenced to the culvert inlet and outlet elevations and are shown on the drill hole logs. A cross
section profile showing the existing centre line profile and stick logs of subsurface conditions
are also shown on Drawing 4274-A1.
We logged soil and groundwater conditions encountered in the drill holes as they were
advanced and collected representative samples for laboratory tests and classification. Selected
samples were tested in our laboratory for natural moisture content, Atterberg plasticity limits
(ASTM D4318) and grain size distribution. Drill hole summary logs describing subsurface
conditions and showing the laboratory test results are in Appendix B. An explanation of terms
and symbols used on the logs is also included in Appendix B.
Page 4 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
The SPT involves driving a standard 50 mm diameter sampling tube into the bottom of
the drill hole using a 62 kg weight, free-falling from a height of 760 mm. The SPT provides
information on the relative density of the soil and allows a sample to be collected. Shelby tube
sampling involves pushing a 75 mm diameter thin-walled tube into the ground to obtain a
relatively undisturbed sample. Field shear vane tests involve pushing a four-bladed vane into
undisturbed soil below the bottom of the drill hole and rotating it from surface while measuring
the torque required to shear a cylindrical surface. The shear vane is used to measure the
undrained shear strength of the soil.
5.0 SUBSURFACE CONDITIONS
5.1 Bridge Foundations
The drill holes encountered similar conditions consisting of the following soil units:
Unit 1 - Loose to compact granular fill with trace to some fines, over
Unit 2 - Stiff to very stiff silty clay fill with a variable amount of sand and gravel, over
Unit 3 - Varved and layered, soft to stiff clay and silt, over
Unit 4 - Very stiff, silty clay till with a trace of sand and gravel, over
Unit 5 - Extremely weak to very weak siltstone bedrock.
Unit 1, the granular fill was encountered in both drill holes to about 0.9 m depth. The
granular fill in DH15-1 consists of loose sandy gravel used to shift the road north. In DH15-2,
the granular fill consists of compact sand and gravel used in the existing pavement structure.
The existing pavement structure is described in the following section.
Unit 2, the silty clay fill was encountered below Unit 1 in both drill holes to 3.1 and
5.5 m depth, respectively. Field shear vane and pocket penetrometer tests indicate the strength
of the silty clay fill decreases with depth with an undrained shear strength between 75 and
125 kPa. Laboratory Atterberg limit tests, used to define the plasticity of the soil and to infer its
Page 5 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
general engineering characteristics, were carried out on four samples of the silty clay fill. The
results indicate the fill has properties of intermediate to high plasticity, with a plastic limit of
about 24% and a liquid limit between 45% and 52%. The plastic limit defines the moisture
content at which soil behaviour changes from a semisolid to a plastic material, and the liquid
limit defines the moisture content at which soil behaviour changes from a plastic material to that
of a viscous liquid. The natural moisture content of the silty clay fill is typically near the
plastic limit.
Unit 3, the varved and layered clay and silt was encountered below Unit 2 to 16.5 m
depth in DH15-1 and 17.5 m depth in DH15-2. The unit is from Glacial Lake Peace and contains
frequent gypsum crystals throughout the deposit. The undrained shear strength of the natural
clay and silt for the full depth of the unit is between about 25 and 60 kPa based on field shear
vanes. Atterberg limit tests indicate the clay has properties of high plasticity, with a plastic limit
of about 26% and a liquid limit between 58% and 71%. The silt layers are low to intermediate
plasticity, with a plastic limit of about 22% and a liquid limit between 33% and 37%. The
natural moisture content of the clay is typically higher than the plastic limit but lower than the
liquid limit and the natural moisture content of the silt is typically near the liquid limit.
Over-consolidation ratio (OCR) is an important geotechnical parameter to evaluate the
potential for foundation settlement. It is defined as the preconsolidation pressure divided by the
present effective stress state of the soil. Soil preconsolidation pressure is the maximum stress
that the soil has previously experienced and can be higher than the existing stress conditions due
to changes in groundwater levels, erosion of materials that previously covered an area, or
construction of a preload fill. Foundation loads that do not cause the effective stress in the
underlying soil to exceed the preconsolidation pressure will result in less settlement than loads
that exceed the preconsolidation pressure.
A correlation based on normalized field vane strength to OCR shows the natural clay and
silt is over-consolidated to about 8.5 m depth, with an OCR between 1.3 and 5, and normally to
slightly over consolidated below 8.5 m depth, with an OCR between 1 and 1.3. This indicates
Page 6 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
that the natural clay and silt at depth has not experienced significantly more vertical stress than
the existing overburden pressure and will therefore be susceptible to significantly more
settlement than if the deposit was over-consolidated.
Unit 4, the clay till was encountered below Unit 3 in DH15-1 and extends to 18.6 m
depth. The clay till has properties of intermediate plasticity, with a plastic limit of 19% and a
liquid limit of 37%. The natural moisture content of the till is about 15%. The undrained shear
strength of the clay till is about 100 kPa based on pocket penetrometer tests.
Unit 5, the siltstone bedrock was encountered below Unit 4 to the end of both drill holes
at 27.2 m and 24.4 m depth, respectively. The bedrock was easily penetrated with augers during
drilling. The siltstone bedrock is poorly lithified, extremely weak and highly weathered in the
top 1 to 3 m depth. Below 1 to 3 m depth the bedrock has isolate shale layers, is very weak and
moderately weathered. We estimate the uniaxial compressive strength of the siltstone is between
1 and 5 MPa.
No groundwater seepage was observed in the drill holes.
5.2 Existing Pavement Structure
DH15-2, located at the south side of the east approach, generally encountered the
following pavement structure:
• 75 mm of Asphalt Pavement, over
• 775 mm of Base Coarse and Subbase, over
• Geogrid and non-woven geotextile, over
• Clay subgrade
Page 7 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
The base coarse and subbase generally consists of a mixture of gravel and sand sized
particles with between 7% and 13% fines. The aggregate is typically less than 75 mm diameter
and is rounded to subangular. The subgrade consists of very stiff, intermediate to high plastic,
silty clay fill with a variable amount of sand and gravel.
6.0 DISCUSSIONS AND RECOMMENDATIONS
The crossing is generally underlain by a significant thickness of embankment fill, over
glaciolacustrine sediments from Glacial Lake Peace, over a thin layer of gravelly clay till below
one side of the crossing, over bedrock at between 17.5 and 18.6 m depth.
The natural soft to firm clay and silt has low bearing capacity, high potential for
settlement and is highly susceptible to frost heave caused by the development of ice lenses. The
glacial lake sediments in the region are also known to contain minerals that cause it to shrink and
swell in response to changes in moisture content. The existing embankment fill is susceptible
to differential settlement and is not suitable for support of spread footing foundations.
Given the relatively weak, compressible soil conditions, the shrink and swell potential
of the soil, and the significant thickness of existing fill, we recommend against using spread
footing foundations to support the proposed bridge. Instead, we recommend supporting the
bridge structure on driven pile foundations end-bearing on the relatively shallow bedrock, as
described below.
The following recommendations are based on the necessary assumption that ground
conditions encountered in the drill holes are representative of conditions elsewhere below the
project site. The bedrock surface appears to be relatively flat but could be deeper than
encountered in the drill holes. Please contact our office for additional recommendations if
conditions encountered during construction differ in any way from those described in this report.
Page 8 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
6.1 Bridge Foundations
Steel pipe piles driven to the bedrock will be suitable for support of the proposed bridge
structure. The piles will gain most of their capacity from end-bearing in the bedrock.
6.1.1 Axial Capacity
To estimate bridge foundation loads we assume the bridge will be constructed using
Type 2 concrete box stringers, concrete abutments, and a 100 mm thick concrete overlay. We
also assume the bridge will be designed to carry BCL-625 live loads. Based on these
assumptions we estimate the ultimate limit states (ULS) live and dead loads will be about
7,000 kN at each abutment.
Based on information from the drill holes, we carried out preliminary pile capacity
analyses using several methods outlined in the Canadian Foundations Engineering Manual
(CFEM) (Canadian Geotechnical Society, 2006). The methods use undrained shear strength,
effective stress and SPT ‘N’ values. BCMoT’s Supplement to the Canadian Highway Bridge
Design Code specifies a geotechnical resistance factor of 0.35 for design based on SPT
information. Assuming each abutment will have six piles connected to a pile cap, each pile will
need to have a geotechnical resistance of about 1,200 kN and the required ultimate geotechnical
resistance of 3,400 kN.
Pile capacity will depend largely on end-bearing resistance, as well as shaft friction, the
pile stiffness (wall thickness and length), the energy of the pile driving equipment, and the
penetration resistance at end-of-driving. We analysed the estimated embedment depth and
driveability of 610 mm and 762 mm diameter open-ended steel pipe piles. The piles are likely
to penetrate the siltstone bedrock between 1 and 3 m. We analysed pile driveability using the
computer program GRLWEAP (GRLWEAP, 2005), assuming end bearing in the bedrock at
about elevation 658 m. A summary of the analyses is shown in Table 1, below.
Page 9 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
Table 1, Summary of Pile Driving Analyses for 610 and 762 mm Diameter Open-End Pipe Piles
610 mm Diameter,
12.7 mm Wall Thickness
762 mm Diameter,
12.7 mm Wall Thickness
Factored Geotechnical Resistance 1,200 kN 1,500 kN
Anticipated Tip Elevation 657 m 657 m
Driving Energy 120 kJ 160 kJ
Penetration Resistance 250 blows/m 260 blows/m
Maximum Pile Stress 250 MPa 280 MPa
Based on the estimated maximum pile stress we recommend using piles manufactured
with Grade 3 steel (ASTM A252). Use an inside-fit cutting shoe to reduce the potential for
damage to the tip of the pile while driving into the bedrock. We recommend the axial capacity
be confirmed using Pile Driving Analysis (PDA) (ASTM D4945) method Case Pile Wave
Analysis Program (CAPWAP) if conditions do not appear to be straightforward or if there are
any concerns regarding the efficiency of the hammer energy being delivered to the pile, or if
there are any indications of damage to the pile. Information on pile capacity from a PDA with
a CAPWAP will also allow the use of a geotechnical resistance factor of 0.5 (BCMOT, 2007).
Allow at least 72 hours between pile installation and testing.
We recommend that additional analyses be carried out once bridge design and loads are
known.
6.1.2 Pile Settlement
Pile settlement occurs primarily due to the transfer of stress to the soil and elastic
shortening of the pile. Settlement in the granular soil around the pile will generally occur as the
pile begins to carry loads during construction of the bridge, although a small portion of the
settlement will occur as plastic creep over time.
Page 10 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
We estimate the settlement of the soil around and below a pile using methods described
in the CFEM. Using specified loads of 1,000 and 1,400 kN for 610 and 762 mm diameter piles,
respectively, with the load evenly distributed between shaft and end bearing resistance, both pile
sizes will settle less than 5 mm. Differential settlement between each abutment could be as high
as the total settlement.
6.1.3 Lateral Pile Capacity
The abutment will be subjected to lateral loads from earth pressures and vehicle breaking.
These loads generally act along the long axis of the bridge and will likely be transmitted through
bridge girders to the opposite abutment wall and bridge end fill, resulting in no significant loads
being transferred to the piles. We recommend additional analyses be carried out once the bridge
design loads are known.
6.1.4 Seismic Design Considerations
The 2012 British Columbia Building Code defines the “Site Classification for Seismic
Site Response”, Table 4.1.8.4.A, which is based on the soil conditions to a depth of 30 m. Based
on our drill hole observations, we estimate the silty clay and clayey silt underlying the site has
an average undrained shear strength between 50 and 100 kPa, and the Site Classification for
Seismic Site Response is no worse than Site Class “D”, as defined in Table 4.1.8.4.A.
Based on our observations that the site is underlain by a thick deposit of soft to stiff silty
clay and clayey silt over bedrock, we recommend the following Canadian Highway Bridge
Design Code (2014) seismic hazard values for the project:
Site
ClassSa(0.2) Sa(0.5) Sa(1.0) Sa(2.0) Sa(10.0) F(0.2) F(0.5) PGA PGV
D 0.138 g 0.088 g 0.050 g 0.024 g 0.0031 g 1.24 1.47 0.079 g 0.058 g
Note: Determined for a 2% in 50 year (0.000404 per annum) probability of exceedence.
Page 11 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
6.2 Bridge End Fill
BCMoT’s Standard Specifications for Highway Construction (BCMoT, 2011) requires
bridge end fill (BEF) extend a distance of 8 m from the bridge abutment with a 1.5 Horizontal
to 1.0 Vertical (1.5H:1V) backslope. Prior to placing BEF, remove organic material and soft,
wet or deleterious soil and compact the subgrade surface to at least 98% Standard Proctor
Density (SPD) (ASTM D698). Place BEF in layers not exceeding 150 mm thickness and
compact each layer to at least 100% SPD.
6.3 Pavement Structure
The recommended base and subbase thicknesses are intended to provide for a long first
cycle life and long-term support for moderate axle loads, provided the pavement surface is
rehabilitated at appropriate intervals. We recommend the following pavement structure to
provide similar strength to that of the existing:
• 75 mm of Asphalt Pavement (Class 1), over
• 200 mm of 25 mm Well Graded Base (WGB), over
• 600 mm of Select Granular Subbase (SGSB), over
• Biaxial geogrid, over
• Nonwoven geotextile, over
• A prepared subgrade.
Construct all components of the new pavement structure with at least a 2% crossfall to
the outside. Where the new structure ties into the existing structure we recommend using a saw
cut between 20E and 30E from perpendicular to road centreline. At the face of the saw cut, leave
an undisturbed width of existing crushed base 500 mm wide, then begin excavation of a
transition slope of 4 Horizontal to 1 Vertical (4H:1V) to accommodate the new pavement
structure thickness. A conceptual transition detail are shown on Drawing 4274-C1, in Appendix C.
Page 12 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
Use a medium weight nonwoven geotextile that meets or exceeds the following
Minimum Average Roll Values (MARV):
• Minimum Grab Tensile Strength (ASTM D4632), 900 N
• Minimum Puncture Strength @ 50% or More Elongation (ASTM D6241), 2.3 kN
• Minimum Trapezoidal Tear (ASTM D4533), 350 N
• Apparent Opening Size (ASTM D4751), 0.2 mm ± 0.02 mm
Use a polypropylene biaxial geogrid that meets or exceeds the following values:
• Minimum Tensile Strength in Machine Direction @ 5% Strain
(ASTM D6637), 11 KN/m
• Minimum Tensile Strength in Cross Machine Direction @ 5% Strain
(ASTM D6637), 19 KN/m
• Aperture Size, 15 to 35 mm
• Minimum Flexural Stiffness (ASTM D5732), 750 mg-cm
6.4 Aggregates and Fill
6.4.1 Base, Subbase and Bridge End Fill
Three material types are specified for construction of the pavement structure and bridge
embankment noted above:
• 25 mm Well Graded Base (WGB),
• Select Granular Subbase (SGSB),
• Bridge End Fill (BEF).
Use material that meets BCMoT’s specifications noted in Section 202 of the 2012
Standard Specifications for Highway Construction.
Page 13 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
6.4.2 Highway Embankment and Subgrade Fill
We recommend constructing the embankment using mineral soil free of organic and
deleterious material and containing less than 15% by volume of rock larger than 150 mm.
Granular material excavated from the existing embankment at the start and end of the project and
from both new bridge end-fill areas, can be reused as embankment fill. We recommend using
embankment fill slopes no steeper than 2H:1V for granular fill and slopes no steeper than 3H:1V
for cohesive embankment fill and the natural clay and silt. The stream channel below the bridge
may require revetment to prevent on-going channel erosion from undermining the slopes leading
up to the bridge abutments.
In some areas the surface of the existing embankment will be covered with winter road
sand, grass, and brush. We recommend stripping the surface of the embankment to expose
compact mineral soil. Key new fill into the existing embankment using benches. Cut the
benches into the existing embankment using a minimum bench width of 1.5 m and a maximum
height of 1.2 m. If suitable, the material from the bench can be incorporated into the new
embankment. Slope the bench surface at a gradient of 2% towards the outside slope face. A
conceptual cross section showing this detail is on Drawing 4274-C2, in Appendix C.
Place the embankment fill in thin, uniform layers and compact each layer to at least 95%
SPD, and to at least 100% SPD within 300 mm of the top of subgrade, at a moisture content
within 2% of optimum. The maximum layer thickness will depend on several factors, including
compactor type, size and energy, and the soil type and moisture content, but do not use a layer
thickness more than 200 mm. Add water and dry the fill as necessary to attain the specified
density and moisture content. Where the embankment is relatively narrow between about
Stations 102+20 and 102+50, if necessary, construct the embankment slopes no steeper than
3H:1V by widening the base as described above. Protect the toe of the slope from erosion as
required for that length of slope below the projected 200 year return period flood level.
Page 14 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
7.0 CONSTRUCTION REVIEW
We recommend that we review final design drawings to confirm that the intent of our
recommendations have been applied, that the recommendations in this report are appropriate and
that sufficient geotechnical investigation has been carried out.
We recommend that an experienced geotechnical engineer, or their designate, review
critical aspects of the project to confirm that soil conditions are as expected and that construction
materials, their placement and their level of compaction are as specified. If soil conditions or
construction materials are different than expected, we can provide additional recommendations
to address the actual conditions. We consider the following geotechnical aspects of the work as
being critical to the project:
• Removal of soft or deleterious soil below areas of fill,
• Gradation, durability, placement and compaction of fill, and
• Pile installation, and whether a PDA with a CAPWAP are required.
8.0 CLOSURE
This report was prepared by GeoNorth Engineering Ltd. for the use of B.C. Ministry of
Transportation and Infrastructure and their consultants. The material in it reflects GeoNorth
Engineering’s judgement in light of the information available to us at the time of preparation.
Any use which Third Parties make of this report, or any reliance on decisions to be made based
on it, are the responsibility of such Third Parties. GeoNorth Engineering Ltd. accepts no
responsibility for damages, if any, suffered by any third party as a result of decisions made or
actions based on this report.
Page 15 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
REFERENCES
B.C. Ministry of Transportation and Infrastructure, 2007. Bridge Standards and Procedures
Manual, Volume 1, Supplement to CHBDC S6-06.
B.C. Ministry of Transportation and Infrastructure, 2011. 2012 Standard Specifications for
Highway Construction, Volume 1.
Canadian Geotechnical Society, 2006. Canadian Foundation Engineering Manual, 4 Edition.th
Canadian Standards Association, 2014. CSA-S6 - Canadian Highway Bridge Design Code.
GRLWEAP Wave Equation Analysis of Pile Driving, 2005. [Computer Software], Cleveland,
Ohio, USA, Pile Dynamics, Inc.
McElhanney Consulting Services Ltd., 2015. Plan & Profiles, Siphon Creek Road, La Guarde
Creek. Drawing NR-XXX-101, August 6, 2015. Submitted to British Columbia Ministry
of Transportation and Infrastructure.
Natural Resources Canada (2015): Determine 2015 Seismic Hazard Values for Nation Building
Code and Canadian Highway Bridge Design Code, URL<http://www.earthquakescanada.
nrcan.gc.ca/hazard-alea/interpolat/index_2015-eng.php>, November 2015.
Page 17 of 17
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
A P P E N D I X A
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
A P P E N D I X B
GW-GM
CL
CH
0.91m
3.05m
1
2
34
5
6
7
8
9
10
11
12
23
112
95
87
95
GRAVEL, sandy, trace fines, loose, brown,damp (FILL).
CLAY, silty, trace gravel, trace sand, stiffto very stiff, intermediate plasticity, brown,rust staining, MC<PL (FILL).- between 1.2 and 1.8m, some gravel.
CLAY, silty, varved, firm, high plasticity,grey, occasional gypsum crystals, MC>PL.- between 3.0 and 3.8m, frequent gypsumcrystals.
- between 5.8 and 6.4m, layered with lowplasticity, clayey silt.
Sieve (Sa#1)G:59% S:34% F:7%
Atterberg (Sa#3):PL:24% LL:47%
Atterberg (Sa#7):PL:28% LL:71%
Atterberg (Sa#11):PL:26% LL:70%
ELE
VA
TIO
N (
m)
1
2
3
4
5
6
7
8
9
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
1
2
3
4
5
6
7
8
9
Driller: Jesse Rushton
Drill Make/Model: Truck Mounted
CLA
SSIF
ICAT
ION
Location: Siphon Creek Road, 40 km northeast of Fort St. John, B.C.
Date(s) Drilled: Oct. 7, 2015
Drilling Method: Solid Stem AugersCoordinates taken with GPS
Project: La Guarde Creek Bridge Crossing
SUMMARY LOG
L#-Lab SampleW-Wash(mud return)
Elevation: 677.87 m
677
676
675
674
673
672
671
670
669
668
Geonorth Engineering LtdPrepared by:
Logged by: JAH Reviewed by:
SO
IL S
YM
BO
L
RE
CO
VE
RY
(%
)
SA
MP
LE N
O
SA
MP
LE T
YP
E
SOILDESCRIPTION
00
Page 1 of 3
DE
PT
H (
m)
DR
ILLI
NG
DE
TA
ILS
Datum: 10V
Alignment: Existing
10
0
Station/Offset: 101+84 6.4m Lt
Northing/Easting: 6267211 , 657491
Final Depth of Hole: 27.2 mDepth to Top of Rock: 18.6 m
Drill Hole #: DH15-1
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Peace Drilling
DYNAMIC CONE (BLOWS/300 mm)
MO
T-S
OIL
-RE
V1
427
4-G
INT
-RE
V1B
-MO
T-D
H L
OG
S.G
PJ
MO
T-D
RA
FT
-RE
V1A
.GD
T 1
6/0
1/14
LW %W %
20 40 60 80P W%
SPT "N" (BLOWS/300 mm)
SHEAR STRENGTH (kPa) POCKET PEN
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400
110
7
8
7
6
CL-ML
CH
CL
12.8m
14.02m
16.46m
18.59m
13
14
15
16
17
18
92
105
92
103
103
CLAY, silty, varved, firm, high plasticity,grey, occasional gypsum crystals, MC>PL.(continued)
CLAY, and SILT, trace fine grained sand,layered, soft, intermediate plasticity, grey,MC>PL, slow dilatancy.
CLAY, silty, varved, firm, high plasticity,grey, MC>PL.
- at 14.6m, 20mm thick layer of mediumgrained, wet sand.
CLAY, silty, trace to some gravel, tracesand, very stiff, intermediate plasticity,brown-grey, MC<PL (TILL).
BEDROCK, siltstone, poorly lithified,extremely weak (R0), highly weathered,light grey.
Atterberg (Sa#15):PL:22% LL:37%
Atterberg (Sa#17):PL:19% LL:37%Sieve (Sa#17)G:24% S:15% F:61%
ELE
VA
TIO
N (
m)
11
12
13
14
15
16
17
18
19
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
11
12
13
14
15
16
17
18
19
Driller: Jesse Rushton
Drill Make/Model: Truck Mounted
CLA
SSIF
ICAT
ION
Location: Siphon Creek Road, 40 km northeast of Fort St. John, B.C.
Date(s) Drilled: Oct. 7, 2015
Drilling Method: Solid Stem AugersCoordinates taken with GPS
Project: La Guarde Creek Bridge Crossing
SUMMARY LOG
L#-Lab SampleW-Wash(mud return)
Elevation: 677.87 m
667
666
665
664
663
662
661
660
659
658
Geonorth Engineering LtdPrepared by:
Logged by: JAH Reviewed by:
SO
IL S
YM
BO
L
RE
CO
VE
RY
(%
)
SA
MP
LE N
O
SA
MP
LE T
YP
E
SOILDESCRIPTION
1010
Page 2 of 3
DE
PT
H (
m)
DR
ILLI
NG
DE
TA
ILS
Datum: 10V
Alignment: Existing
20
10
Station/Offset: 101+84 6.4m Lt
Northing/Easting: 6267211 , 657491
Final Depth of Hole: 27.2 mDepth to Top of Rock: 18.6 m
Drill Hole #: DH15-1
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Peace Drilling
DYNAMIC CONE (BLOWS/300 mm)
MO
T-S
OIL
-RE
V1
427
4-G
INT
-RE
V1B
-MO
T-D
H L
OG
S.G
PJ
MO
T-D
RA
FT
-RE
V1A
.GD
T 1
6/0
1/14
LW %W %
20 40 60 80P W%
SPT "N" (BLOWS/300 mm)
SHEAR STRENGTH (kPa) POCKET PEN
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400
6
9
BR
27.2m
19
20
21
22
4
16
10
BEDROCK, siltstone, poorly lithified,extremely weak (R0), highly weathered,light grey. (continued)
- below 21.0m, isolated shale layers, veryweak (R1), moderately weathered, darkgrey.
End of drill hole at 27.2m.No seepage encountered.
ELE
VA
TIO
N (
m)
21
22
23
24
25
26
27
28
29
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
21
22
23
24
25
26
27
28
29
Driller: Jesse Rushton
Drill Make/Model: Truck Mounted
CLA
SSIF
ICAT
ION
Location: Siphon Creek Road, 40 km northeast of Fort St. John, B.C.
Date(s) Drilled: Oct. 7, 2015
Drilling Method: Solid Stem AugersCoordinates taken with GPS
Project: La Guarde Creek Bridge Crossing
SUMMARY LOG
L#-Lab SampleW-Wash(mud return)
Elevation: 677.87 m
657
656
655
654
653
652
651
650
649
648
Geonorth Engineering LtdPrepared by:
Logged by: JAH Reviewed by:
SO
IL S
YM
BO
L
RE
CO
VE
RY
(%
)
SA
MP
LE N
O
SA
MP
LE T
YP
E
SOILDESCRIPTION
2020
Page 3 of 3
DE
PT
H (
m)
DR
ILLI
NG
DE
TA
ILS
Datum: 10V
Alignment: Existing
30
20
Station/Offset: 101+84 6.4m Lt
Northing/Easting: 6267211 , 657491
Final Depth of Hole: 27.2 mDepth to Top of Rock: 18.6 m
Drill Hole #: DH15-1
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Peace Drilling
DYNAMIC CONE (BLOWS/300 mm)
MO
T-S
OIL
-RE
V1
427
4-G
INT
-RE
V1B
-MO
T-D
H L
OG
S.G
PJ
MO
T-D
RA
FT
-RE
V1A
.GD
T 1
6/0
1/14
LW %W %
20 40 60 80P W%
SPT "N" (BLOWS/300 mm)
SHEAR STRENGTH (kPa) POCKET PEN
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400
Refusal, 50 for 1"
Refusal, 50 for 4"
Refusal, 50 for 3"
AP
GM1
CL-CH
CH
0.08m
0.85m
5.49m
1
2
3
4
5
6
7
8
9
10
11
36
43
89
84
92
ASPHALT.SAND, and GRAVEL, some fines,compact, brown, damp (FILL).- at 0.85m, geogrid over nonwovengeotextile.CLAY, silty, trace gravel, trace sand, stiffto very stiff, intermediate to high plasticity,brown, rust staining, MC>PL (FILL).- at 0.9m, a layer of geogrid andgeotextile.- at 1.5m, organic soil layer about 5cmthick.
- between 2.7 and 3.5m, trace to someorganic soil content.
- below 4.3m, isolated gypsum crystals.
CLAY, silty, varved, soft, high plasticity,grey, isolated gypsum crystals, MC>PL. PP=30 to 50
Sieve (Sa#1)G:40% S:47% F:13%
Atterberg (Sa#4):PL:25% LL:52%
Atterberg (Sa#6):PL:23% LL:45%
Atterberg (Sa#8):PL:25% LL:49%
Atterberg (Sa#10):PL:25% LL:58%
ELE
VA
TIO
N (
m)
1
2
3
4
5
6
7
8
9
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
1
2
3
4
5
6
7
8
9
Driller: Jesse Rushton
Drill Make/Model: Truck Mounted
CLA
SSIF
ICAT
ION
Location: Siphon Creek Road, 40 km northeast of Fort St. John, B.C.
Date(s) Drilled: Oct. 8, 2015
Drilling Method: Solid Stem AugersCoordinates taken with GPS
Project: La Guarde Creek Bridge Crossing
SUMMARY LOG
L#-Lab SampleW-Wash(mud return)
Elevation: 677.15 m
677
676
675
674
673
672
671
670
669
668
Geonorth Engineering LtdPrepared by:
Logged by: JAH Reviewed by:
SO
IL S
YM
BO
L
RE
CO
VE
RY
(%
)
SA
MP
LE N
O
SA
MP
LE T
YP
E
SOILDESCRIPTION
00
Page 1 of 3
DE
PT
H (
m)
DR
ILLI
NG
DE
TA
ILS
Datum: 10V
Alignment: Existing
10
0
Station/Offset: 102+22 2.8m Rt
Northing/Easting: 6267206 , 657532
Final Depth of Hole: 24.4 mDepth to Top of Rock: 17.5 m
Drill Hole #: DH15-2
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Peace Drilling
DYNAMIC CONE (BLOWS/300 mm)
MO
T-S
OIL
-RE
V1
427
4-G
INT
-RE
V1B
-MO
T-D
H L
OG
S.G
PJ
MO
T-D
RA
FT
-RE
V1A
.GD
T 1
6/0
1/14
LW %W %
20 40 60 80P W%
SPT "N" (BLOWS/300 mm)
SHEAR STRENGTH (kPa) POCKET PEN
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400
11
8
ML-CL
CL
12.65m
13.72m
17.53m
12
13
14
15
16
17
18
19
20
110
110
92
108
36
CLAY, silty, varved, soft, high plasticity,grey, isolated gypsum crystals, MC>PL.(continued)
- at 11.3m, dropstone.
SILT, and CLAY, trace sand, layered, soft,low to intermediate plasticity, grey,MC>PL, rapid dilatancy.
CLAY, silty, varved, layered with clayeysilt, stiff, intermediate plasticity, grey,MC>PL.
- below 16.8m, no silt layering.
BEDROCK, siltstone, poorly lithified,extremely weak (R0), highly weathered,light grey.
Atterberg (Sa#14):PL:23% LL:30%
Atterberg (Sa#16):PL:19% LL:40%
ELE
VA
TIO
N (
m)
11
12
13
14
15
16
17
18
19
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
11
12
13
14
15
16
17
18
19
Driller: Jesse Rushton
Drill Make/Model: Truck Mounted
CLA
SSIF
ICAT
ION
Location: Siphon Creek Road, 40 km northeast of Fort St. John, B.C.
Date(s) Drilled: Oct. 8, 2015
Drilling Method: Solid Stem AugersCoordinates taken with GPS
Project: La Guarde Creek Bridge Crossing
SUMMARY LOG
L#-Lab SampleW-Wash(mud return)
Elevation: 677.15 m
667
666
665
664
663
662
661
660
659
658
Geonorth Engineering LtdPrepared by:
Logged by: JAH Reviewed by:
SO
IL S
YM
BO
L
RE
CO
VE
RY
(%
)
SA
MP
LE N
O
SA
MP
LE T
YP
E
SOILDESCRIPTION
1010
Page 2 of 3
DE
PT
H (
m)
DR
ILLI
NG
DE
TA
ILS
Datum: 10V
Alignment: Existing
20
10
Station/Offset: 102+22 2.8m Rt
Northing/Easting: 6267206 , 657532
Final Depth of Hole: 24.4 mDepth to Top of Rock: 17.5 m
Drill Hole #: DH15-2
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Peace Drilling
DYNAMIC CONE (BLOWS/300 mm)
MO
T-S
OIL
-RE
V1
427
4-G
INT
-RE
V1B
-MO
T-D
H L
OG
S.G
PJ
MO
T-D
RA
FT
-RE
V1A
.GD
T 1
6/0
1/14
LW %W %
20 40 60 80P W%
SPT "N" (BLOWS/300 mm)
SHEAR STRENGTH (kPa) POCKET PEN
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400
7
10
9
51
BR
24.38m
21
22
31
52
BEDROCK, siltstone, poorly lithified,extremely weak (R0), highly weathered,light grey. (continued)
- below 21.0m, isolated shale layers, veryweak (R1), moderately weathered, darkgrey.
End of drill hole at 24.4m.No seepage encountered.
ELE
VA
TIO
N (
m)
21
22
23
24
25
26
27
28
29
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
21
22
23
24
25
26
27
28
29
Driller: Jesse Rushton
Drill Make/Model: Truck Mounted
CLA
SSIF
ICAT
ION
Location: Siphon Creek Road, 40 km northeast of Fort St. John, B.C.
Date(s) Drilled: Oct. 8, 2015
Drilling Method: Solid Stem AugersCoordinates taken with GPS
Project: La Guarde Creek Bridge Crossing
SUMMARY LOG
L#-Lab SampleW-Wash(mud return)
Elevation: 677.15 m
657
656
655
654
653
652
651
650
649
648
Geonorth Engineering LtdPrepared by:
Logged by: JAH Reviewed by:
SO
IL S
YM
BO
L
RE
CO
VE
RY
(%
)
SA
MP
LE N
O
SA
MP
LE T
YP
E
SOILDESCRIPTION
2020
Page 3 of 3
DE
PT
H (
m)
DR
ILLI
NG
DE
TA
ILS
Datum: 10V
Alignment: Existing
30
20
Station/Offset: 102+22 2.8m Rt
Northing/Easting: 6267206 , 657532
Final Depth of Hole: 24.4 mDepth to Top of Rock: 17.5 m
Drill Hole #: DH15-2
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Peace Drilling
DYNAMIC CONE (BLOWS/300 mm)
MO
T-S
OIL
-RE
V1
427
4-G
INT
-RE
V1B
-MO
T-D
H L
OG
S.G
PJ
MO
T-D
RA
FT
-RE
V1A
.GD
T 1
6/0
1/14
LW %W %
20 40 60 80P W%
SPT "N" (BLOWS/300 mm)
SHEAR STRENGTH (kPa) POCKET PEN
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400
Refusal, 50 for 3"
Refusal, 50 for 6"
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
A P P E N D I X C
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure January 18, 2016Geotechnical Report, La Guarde Creek Bridge Crossing,Siphon Creek Road, 40 km Northeast of Fort St. John, B.C. File No. K-4274
A P P E N D I X D