la dotd bid analysis lite

38
LA DOTD Bid Analysis Lite Charles Nickel, P.E. LADOTD Cost Estimate and Value Engineering Director Phone: (225) 379-1078

Upload: hoangtuyen

Post on 09-Dec-2016

225 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: LA DOTD Bid Analysis Lite

LA DOTD Bid Analysis Lite

Charles Nickel, P.E. LADOTD Cost Estimate and Value Engineering Director Phone: (225) 379-1078

Page 2: LA DOTD Bid Analysis Lite

• Many of the designers who prepare estimates were interested in running their own bid analysis.

• Installing BAMS/DSS on all their machines did not seem practical at the time.

• Nearly everyone has Microsoft Excel installed and I loved the challenge.

LA DOTD Bid Analysis Lite

Page 3: LA DOTD Bid Analysis Lite

• Links to wTrns•port’s Oracle Database to pull in real time bid results.

• A stand alone version pulls data from a static database file that has to be updated from time to time.

• Does not have all the functionality of BAMS/DSS.

• User friendly and readily available.

LA DOTD Bid Analysis Lite

Page 4: LA DOTD Bid Analysis Lite

• Based on Wisconsin DOT Construction and Materials Manual, Section 2.1.2.1.1, revised 10/98, as shown in Attachment B on FHWA’s website.

LA DOTD Bid Analysis Lite

http://www.fhwa.dot.gov/programadmin/contracts/ta508046.cfm

Page 5: LA DOTD Bid Analysis Lite

Bid analysis is performed when:

• the Department becomes aware of an error in a quantity of an item shown in the bidding documents

• an item is found to be both significant to the contract and significantly unbalanced.

LA DOTD Bid Analysis Lite

Page 6: LA DOTD Bid Analysis Lite

• Items with bid extended amounts differing from the estimated extended amounts by greater than:

– For contracts < $2,000,000;

• 0.50% of the total contract amount.

– For contracts => $2,000,000;

• 0.25% of the total contract amount.

• (Extended Amount = Unit Price X Quantity)

Items Significant to the Contract

Page 7: LA DOTD Bid Analysis Lite

• Items with a bid unit price that differ from the estimated unit price by

• Greater than

• +50% of the estimated unit price

• or Less than

• -75% of the estimated unit price.

Items Significantly Unbalanced

Page 8: LA DOTD Bid Analysis Lite

• ITEMS SIGNIFICANT TO THE CONTRACT

And

• SIGNIFICANTLY UNBALANCED

LA DOTD Bid Analysis Lite

Page 9: LA DOTD Bid Analysis Lite
Page 10: LA DOTD Bid Analysis Lite
Page 11: LA DOTD Bid Analysis Lite
Page 12: LA DOTD Bid Analysis Lite
Page 13: LA DOTD Bid Analysis Lite
Page 14: LA DOTD Bid Analysis Lite
Page 15: LA DOTD Bid Analysis Lite
Page 16: LA DOTD Bid Analysis Lite
Page 17: LA DOTD Bid Analysis Lite
Page 18: LA DOTD Bid Analysis Lite
Page 19: LA DOTD Bid Analysis Lite
Page 20: LA DOTD Bid Analysis Lite
Page 21: LA DOTD Bid Analysis Lite

LA DOTD Item Bid History

Charles Nickel, P.E. LADOTD Cost Estimate and Value Engineering Director Phone: (225) 379-1078

Page 22: LA DOTD Bid Analysis Lite

• Many of the designers who prepare estimates were interested in quick and easy access to actual bid history and other minor statistical item bid information.

• Nearly everyone has Microsoft Excel installed and I loved the challenge.

LA DOTD Item Bid History

Page 23: LA DOTD Bid Analysis Lite

• Links to wTrns•port’s Oracle Database to pull in real time bid results.

• A stand alone version pulls data from a static database file that has to be updated from time to time.

• Does not have all the functionality of wTrns•port or CES.

• User friendly and readily available.

LA DOTD Item Bid History

Page 24: LA DOTD Bid Analysis Lite
Page 25: LA DOTD Bid Analysis Lite
Page 26: LA DOTD Bid Analysis Lite
Page 27: LA DOTD Bid Analysis Lite
Page 28: LA DOTD Bid Analysis Lite
Page 29: LA DOTD Bid Analysis Lite
Page 30: LA DOTD Bid Analysis Lite
Page 31: LA DOTD Bid Analysis Lite
Page 32: LA DOTD Bid Analysis Lite
Page 33: LA DOTD Bid Analysis Lite
Page 34: LA DOTD Bid Analysis Lite
Page 35: LA DOTD Bid Analysis Lite
Page 36: LA DOTD Bid Analysis Lite
Page 37: LA DOTD Bid Analysis Lite
Page 38: LA DOTD Bid Analysis Lite