l4t bending power converters: ‘ implications of monitoring the current to 5% and 0.5%’ l4 bcc -...
TRANSCRIPT
L4T Bending Power Converters: ‘Implications of monitoring the current to 5% and 0.5%’
L4 BCC - 10 Nov 2011David Nisbet
TE EPC
Porteuse
cmd
GAIN
Mesure_IL_HF
GAIN
I
Kp_I
Kp_Taux_IGAIN
Mesure_Imagnet
LIMITYt
Iref
GAIN
Amortissement_fi l tre_Kv
GAIN
Porteuse1
cmd1Mesure_IL_HF1
GAIN
Kc
GAIN
Mesure_Vmagnet
GAIN
I
Kp_U
Kp_Taux_U
GAIN
GAIN
Amortissement_fi l tre_Ki
Amortissement_fi l tre_Ku
LIMIT
GAIN
Kc1
GAIN
I
Kp_U1
Kp_Taux_U1
Bending Power Converter
• The power electronics and control architecture:
10/11/2011 TE-EPC - David Nisbet 2
TE EPC
Y
Y
Magnet
DC Inductance
Diodesrectifier
Transformer50Hz-Y
BrakeChopper Capacitors bank
IGBT Hbridge
HF Filter
400V
Output voltage ±450V
Output current ±900 A
Pulse repetition rate 1.11 Hz
Flat-top precision ~100 ppm
From the workpackage:
The same parameters are valid for all the bending converters• (L4T: BHZ, BVT) • (LT: BHZ20, BHZ30, BHZ40)
Controlling the magnet current
• FGC3 in the PSB (Nov 2011)
• For L4 bending: control of arbitrary current function to 100ppm accuracy
10/11/2011 TE-EPC - David Nisbet 3
TE EPC
An example of ‘state of the art’
• The current of the LHC main quads and dipoles (50Hz samples):
• Measurements are always subject to sources of noise and perturbations
10/11/2011 TE-EPC - David Nisbet 4
TE EPC
756.906 A
756.911 A
30mA
Imeas of
RB (A56, A67)
RQF (A56, A67)
RQD (A56, A67)
The converter interlock architecture
10/11/2011 TE-EPC - David Nisbet 5
TE EPC
The converter interlock architecture
10/11/2011 TE-EPC - David Nisbet 6
TE EPC
Analog comparison for ‘lower’ performance but highly reliable
Digitise for high performance, but requires software, etc
Converter ON/OFF
The converter BIC interface
• Simple AND of up to 3 conditions to generate a BEAM PERMIT :1. ‘Reliable and robust’ analog threshold validation: ±5% of nominal2. ‘Hi resolution but software’ threshold validation: ±0.5% of nominal3. Power converter state (‘ON’ and ‘NO FAULT’)
• Up to 4 separate PERMITS for each power converter:– For example, allows evaluation of destinations and energy levels
10/11/2011 TE-EPC - David Nisbet 7
TE EPC
Only w
hen
need
ed
Monitoring the magnet current
• Example of a scenario for the L4T Horizontal Bending (L4T and L4Z destinations)
10/11/2011 TE-EPC - David Nisbet 8
TE EPC
~150ms
Monitoring the magnet current
Typical scenario of information available in the Control Room
• FGC will publish warnings if deviation from a pre-determined performance level is detected (eg 100ppm , 10-4)
– Data can be viewed through CCC alarm monitors– Operator (or control room software) may take appropriate action – Experts will be automatically informed
• Maximum deviation from reference value can be made available to SIS– SIS may inhibit subsequent pulses based on a pre-determined threshold (eg between 10 -3 and 10-4 )
• BEAM PERMIT will be given to BIS if measured value is within ±0.5%– If for any reason a software bug is present, the analog channel will guarantee the BEAM PERMIT is given only if real
measured current value is also within ±5%
10/11/2011 TE-EPC - David Nisbet 9
TE EPC
Conclusion
• In an operational environment, we are wary of very tight thresholds affecting equipment availability
– Electromagnetic compatibility, network perturbation
• Signals for the BEAM PERMIT cannot be heavily filtered as fast dynamic response is required
• The power group considers that a ‘Keep It Simple’ approach is the most appropriate method to ensure a reliable and robust BEAM PERMIT interface
– A redundant signal architecture will be maintained for coherence with the BIS architecture– The signal is made available for subsequent treatment by the BIS
• The proposed approach is a compromise to achieve the tight tolerances requested – Analog comparison to obtain a robust permit signal path, but the tolerances must be consequently relaxed (±5%)– Digital comparison to obtain a precise interlock, but this also requires software
• The extensive reporting and diagnostics available from the FGC3 generation of power systems allows a phased approach if deviation from the reference currents is detected
– Intelligent and complementary use of experts, warnings, SIS and BIS
10/11/2011 TE-EPC - David Nisbet 10
TE EPC