kraken development

Upload: ayubkara

Post on 18-Oct-2015

39 views

Category:

Documents


1 download

DESCRIPTION

rte

TRANSCRIPT

  • 5/28/2018 Kraken Development

    1/440

    EnQuest Heather LimitedKraken Field Development Environmental Statement

    DECC Document Ref: D/4155/2013

    EnQuest Heather Limited Document Ref: ENQ-KRA-HS-00-STA-0002

    Issued 14thFebruary 2013

  • 5/28/2018 Kraken Development

    2/440

    This page is intentionally left blank

  • 5/28/2018 Kraken Development

    3/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 i

    STANDARD INFORMATION SHEET

    Project Name Kraken Field Development Area

    DECC Project Reference No. D/4155/2013

    Type of Project Field development with subsea wells connected to a Floating, Production,

    Storage and Offloading (FPSO) facility processing fluids from the Kraken

    reservoir.

    Undertaker Name EnQuest Heather Limited

    Undertaker Address 5th

    Floor Consort House, Stell Road, Aberdeen, AB11 5QF, United Kingdom

    Licences/Owners EnQuest ENS Limited (20%), EnQuest Dons (40%), Cairn Energy (25%) and

    First Oil (15%)

    Short Description EnQuest is planning to develop the Kraken area as three separate fields:

    Kraken North, Kraken Central and Kraken South. All three fields lie in Block

    9/02b, approximately 126 km east of the nearest landfall at Noss, Shetland

    Islands.

    This will be achieved by drilling 14 horizontal production subsea wells and

    11 horizontal water injector subsea wells in the Kraken development area.

    All wells will be tied back to an FPSO facility which will process and store

    the produced fluids and then export stabilised crude via shuttle tankers.

    The FPSO power demands will be met through the use of associated gas.

    The short fall in associated gas production will be supplemented by the use

    of either crude oil or diesel. It is understood that there may be future

    opportunity for gas import from the Vesterled line, this shall beinvestigated as an alternative source of fuel when the infrastructure is

    available.

    All production wells will require artificial lift and Hydraulic Submersible

    Pumps (HSPs) have been selected as the preferred technology. The HSPs

    will be powered from the FPSO; the power fluid is treated seawater as

    there will be little or no formation water produced from the reservoir. The

    spent power fluid will be combined with the well production fluids and

    returned to the FPSO. All produced water will be re-injected and seawater

    will be used for water injection to replace the oil and maintain reservoir

    pressure, voidage replacement and to sweep the oil to the producers.

    Anticipated Commencement of Works Q2 2014

    Previously Submitted EnvironmentalDocuments

    N/A

    Significant Environmental Impacts

    Identified

    Impacts resulting from:

    Atmospheric emissions during drilling, installation and commissioning

    activities and production operations,

    Seabed disturbance from flowline installation,

    Noise from piling activities and

    Loss of hydrocarbons/chemicals during spill, uncontrolled well flow or

    collision

    Statement Prepared By EnQuest in conjunction with

    RPS Energy HSE & Risk Management

  • 5/28/2018 Kraken Development

    4/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 ii

    This page is intentionally blank

  • 5/28/2018 Kraken Development

    5/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 iii

    Table of Contents

    STANDARD INFORMATION SHEET ........................................................................................................................ iNON-TECHNICAL SUMMARY .............................................................................................................................. ix

    Background ........................................................ ................................................................ .................................. ix

    Project Overview ........................................................... ................................................................ ....................... ix

    The Existing Environment .......................................................... ................................................................ ............. x

    Environmental Interactions, Impacts and Mitigation Measures ............................................................................ xiv

    Environmental Management ......................................................................... .................................................... xxxv

    Conclusions ............................................. ................................................................ ......................................... xxxv

    Abbreviations ..............................................................................................................................................xxxviiGlossary ...........................................................................................................................................................xli1 Introduction ........................................................................................................................................... 1-1

    1.1 Background and Document Objective ........................................................... .......................................... 1-1

    1.2 Overview of the Project .......................................................... ............................................................... 1-1

    1.3 The Applicant......................................................................................................................................... 1-4

    1.4 Environmental Impact Assessment ................................................................................................ ......... 1-5

    1.5 Structure of the Report ................................................................................................................. ......... 1-7

    1.6 Contact Addresses ........................................................ ................................................................ ......... 1-7

    2 The Proposed Development ..................................................................................................................... 2-12.1 The Kraken Fields .......................................................... ................................................................ ......... 2-1

    2.2 Development Objective and Justification ................................................................. ............................... 2-3

    2.3 Development Option Selection ........................................................... .................................................... 2-4

    2.3.1 Development options initial screening ............................................................. ............................... 2-4

    2.3.2 Facilities Option Selection .......................................................... .................................................... 2-9

    2.3.3 Development options description ......................................................... ......................................... 2-11

    2.3.4 Environmental comparative assessment .......................................................... ..............................2-14

    2.4 Outstanding Development Decisions ............................................................ ......................................... 2-14

    2.5 Summary of Selected Kraken Development Option ............................................................. ................... 2-14

    2.6 Proposed Development Schedule ................................................................. ......................................... 2-15

    2.7 Kraken Development Facilities Overview ................................................................. ..............................2-16

    2.7.1 Flowlines, Umbilicals and Subsea Infrastructure ......................................................... ................... 2-16

    2.7.2 The Kraken Installation .............................................................. ................................................... 2-21

    2.8 Kraken Development Project Phases ............................................................ ......................................... 2-24

    2.9 Installation and Commissioning Operations ............................................................. ..............................2-24

    2.9.1 Introduction ......................................................... ................................................................ ........2-24

    2.9.2 Installation of Flowlines, Umbilicals and Subsea Infrastructure ......................................................2-24

    2.9.3 Commissioning ............................................................... ..............................................................2-28

    2.9.4 Subsea Tie-Ins ....................................................... ................................................................ ........2-29

  • 5/28/2018 Kraken Development

    6/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 iv

    2.9.5 FPSO Installation ............................................................. ..............................................................2-29

    2.9.6 Riser System ......................................................... ................................................................ ........2-33

    2.9.7 Installation and Commissioning Fuel Consumption, Emissions and Discharges ................................2-36

    2.10 Development Drilling Operations ................................................................. ......................................... 2-37

    2.10.1 Overview .............................................................. ................................................................ ........ 2-37

    2.10.2 Drilling Rig ............................................................ ................................................................ ........ 2-39

    2.10.3 Well Construction ........................................................... ..............................................................2-40

    2.10.4 Drilling Chemicals ........................................................... ..............................................................2-43

    2.10.5 Cementing ............................................................ ................................................................ ........ 2-43

    2.10.6 Well Clean-up and Completion ............................................................. ......................................... 2-43

    2.10.7 Well Testing .......................................................... ................................................................ ........ 2-46

    2.10.8 Well Control Equipment ............................................................. ................................................... 2-46

    2.10.9 Support Operations ......................................................... .............................................................. 2-46

    2.10.10 Waste ........................................................ ................................................................ ................... 2-47

    2.10.11 Intervention and Workover Requirements ....................................................... .............................. 2-47

    2.10.12 Total Drilling Discharges and Emissions Summary ................................................................ ..........2-47

    2.11 Production Operations ............................................................ ..............................................................2-48

    2.11.1 Overview .............................................................. ................................................................ ........ 2-48

    2.11.2 Oil Processing, Storage and Export ....................................................... .........................................2-49

    2.11.3 Produced Water and Water Injection System................................................................................. 2-53

    2.11.4 Utility Systems and Quarters ................................................................ ......................................... 2-53

    2.11.5 Power Generation ........................................................... ..............................................................2-54

    2.11.6 Helifuel and Chemical Storage .............................................................. ......................................... 2-55

    2.11.7 Flare System ......................................................... ................................................................ ........2-55

    2.11.8 Cooling Water System ................................................................ ................................................... 2-55

    2.11.9 Waste Heat Recovery Unit / Heating Medium ............................................................. ................... 2-56

    2.11.10 Drain Systems ....................................................... ................................................................ ........2-56

    2.11.11 Waste Treatment and Disposal ............................................................. ......................................... 2-56

    2.11.12 Firewater System ............................................................ ..............................................................2-56

    2.11.13 Potable Water System ................................................................ ................................................... 2-57

    2.11.14 Oil Production Profile ................................................................ .................................................... 2-57

    2.11.15 Produced Water Profiles ............................................................ ................................................... 2-58

    2.11.16 Production Chemistry ................................................................ ................................................... 2-59

    2.11.17 Pipeline Maintenance ................................................................ ................................................... 2-61

    2.12 Decommissioning .......................................................... ................................................................ ........ 2-61

    3 Environmental Description ...................................................................................................................... 3-1

    3.1 Introduction ...................................................... ................................................................ .................... 3-1

    3.2 Site Survey ......................................................... ................................................................ .................... 3-13.3 Geography ......................................................... ................................................................ .................... 3-3

  • 5/28/2018 Kraken Development

    7/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 v

    3.4 The Seabed and Bathymetry ............................................................... .................................................... 3-4

    3.4.1 Bathymetry ........................................................... ................................................................ ......... 3-4

    3.4.2 The Seabed ........................................................... ................................................................ ......... 3-4

    3.5 Oceanography .............................................................. ................................................................ ........ 3-26

    3.5.1 Waves ....................................................... ................................................................ ................... 3-26

    3.5.2 Tides and Water Circulation ................................................................. ......................................... 3-26

    3.5.3 Temperature and Salinity ........................................................... ................................................... 3-28

    3.6 Air and Climate ............................................................. ................................................................ ........ 3-29

    3.6.1 Wind............................................................................................................... .............................. 3-29

    3.6.2 Air Quality ........................................................... ................................................................. ........ 3-30

    3.7 Flora and Fauna ............................................................ ................................................................ ........ 3-30

    3.7.1 Plankton ............................................................... ................................................................ ........ 3-30

    3.7.2 Seabed Communities ................................................................ .................................................... 3-31

    3.7.3 Fish...................................................................................................... ......................................... 3-38

    3.8 Offshore Seabird Distribution ............................................................. ................................................... 3-48

    3.8.1 Introduction ......................................................... ................................................................ ........3-48

    3.8.2 Key Offshore Seabird Species ............................................................... ......................................... 3-48

    3.8.3 Seabird Vulnerabilities ............................................................... ................................................... 3-51

    3.9 Marine Mammals .......................................................... ................................................................ ........ 3-54

    3.9.1 Cetaceans ............................................................. ................................................................ ........ 3-54

    3.9.2 Pinnipeds .............................................................. ................................................................ ........ 3-55

    3.9.3 Marine Reptiles .............................................................. ..............................................................3-58

    3.10 Protected and Sensitive Coastal Habitats ................................................................. ..............................3-59

    3.10.1 Overview .............................................................. ................................................................ ........ 3-59

    3.10.2 Candidate Marine Special Areas of Conservation ........................................................ ...................3-60

    3.10.3 Annex I Habitats in the Vicinity of the Proposed Development .......................................................3-60

    3.10.4 Annex II Species in the Vicinity of the Proposed Development .......................................................3-62

    3.10.5 Coastal Habitats .............................................................. ..............................................................3-63

    3.10.6 International Protected Sites ................................................................ ......................................... 3-65

    3.11 Human Environment ............................................................... ..............................................................3-66

    3.11.1 Commercial Fisheries ................................................................ .................................................... 3-66

    3.11.2 Shipping and Ports .......................................................... .............................................................. 3-74

    3.11.3 Pipelines, Wells and Submarine Cables ............................................................ ..............................3-77

    3.11.4 Military Activity .............................................................. ..............................................................3-77

    3.11.5 Wind Farms .......................................................... ................................................................ ........ 3-77

    3.11.6 Archaeology .......................................................... ................................................................ ........ 3-77

    3.11.7 Tourism and Leisure ........................................................ .............................................................. 3-77

    3.12 Key Environmental Sensitivities .......................................................... ................................................... 3-81

  • 5/28/2018 Kraken Development

    8/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 vi

    4 ENVIRONMENTAL ASPECTS, IMPACTS AND MITIGATION MEASURES ........................................................... 4-1

    4.1 Introduction ...................................................... ................................................................ .................... 4-1

    4.2 Environmental Impact Assessment Methodology ................................................................ .................... 4-2

    4.2.1 Aspect Identification ................................................................. ..................................................... 4-2

    4.2.2 Potential Impact Identification and Description .......................................................... .................... 4-2

    4.3 Risk Assessment ............................................................ ................................................................ ......... 4-4

    4.3.1 Combining Likelihood and Consequence To Establish Significance ................................................... 4-6

    4.3.2 Developing Mitigation Measures .......................................................... .......................................... 4-6

    4.3.3 Evaluating Residual Impacts ................................................................. .......................................... 4-6

    4.3.4 Environmental Aspects ............................................................... .................................................... 4-6

    4.4 Environmental Impact Assessment of Physical Presence ................................................................ ......... 4-9

    4.4.1 Introduction ......................................................... ................................................................ ......... 4-9

    4.4.2 Potential Interaction With Other Marine Users ........................................................... ................... 4-10

    4.4.3 Planned Mitigation Measures ............................................................... ......................................... 4-11

    4.4.4 Residual Impacts of Physical Presence ............................................................. ..............................4-12

    4.5 Environmental Impact Assessment of Seabed Disturbance ............................................................. ........4-13

    4.5.1 Introduction ......................................................... ................................................................ ........4-13

    4.5.2 Seabed Disturbance From Anchoring Operations ........................................................ ...................4-14

    4.5.3 seabed Disturbance From Pipeline and Umbilical Installation Operations .......................................4-15

    4.5.4 Seabed Disturbance From Flowline and Subsea Facilities Installation .............................................4-16

    4.5.5 Seabed Disturbance from Decommissioning ............................................................... ................... 4-20

    4.5.6 Planned Mitigation Measures ............................................................... ......................................... 4-20

    4.5.7 Residual Impacts ............................................................. ..............................................................4-20

    4.6 Environmental Impact Assessment of Noise ............................................................ ..............................4-21

    4.6.1 Introduction ......................................................... ................................................................ ........4-21

    4.6.2 Types of Noise Generated .......................................................... ................................................... 4-21

    4.6.3 Potential Impacts From Noise ............................................................... ......................................... 4-24

    4.6.4 Assessing The Likelihood of an Offence Under Offshore Marine Regulations ..................................4-33

    4.6.5 Planned Mitigation Methods ................................................................ ......................................... 4-34

    4.6.6 Residual Impacts of Noise .......................................................... ................................................... 4-35

    4.7 environmental Impact Assessment of Atmospheric Emissions ........................................................ ........4-35

    4.7.1 Introduction ......................................................... ................................................................ ........4-35

    4.7.2 Atmospheric Impacts Associated with the Drilling Phase ........................................................ ........4-35

    4.7.3 impacts Associated with the Installation and Commissioning Phase ...............................................4-37

    4.7.4 Impacts Associated with the Production Phase ........................................................... ................... 4-39

    4.7.5 Planned Mitigation Methods ................................................................ ......................................... 4-41

    4.7.6 Residual Impacts ............................................................. ..............................................................4-42

    4.8 Environmental Impact Assessment of Marine Discharges ............................................................... ........4-444.8.1 Introduction ......................................................... ................................................................ ........4-44

  • 5/28/2018 Kraken Development

    9/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 vii

    4.8.2 Potential Impacts Associated With Marine Discharges During Drilling Operations ...... ..... ...... ..... ....4-44

    4.8.3 Clean-Up and Completion Fluids ........................................................... ......................................... 4-45

    4.8.4 other discharges ............................................................. ..............................................................4-46

    4.8.5 Potential Impacts Associated with Marine Discharges During Installation and Commissioning

    Operations ................................................................ ................................................................ ................... 4-46

    4.8.6 Environmental Impacts Associated with Marine Discharges During Production Operations ..... ...... ..4-46

    4.8.7 Marine Discharges Mitigation Measures .......................................................... ..............................4-48

    4.8.8 Residual Impacts ............................................................. ..............................................................4-50

    4.9 Environmental Impacts Associated With Solid Wastes ........................................................ ...................4-51

    4.9.1 Introduction ......................................................... ................................................................ ........4-51

    4.9.2 Impacts Associated With Solid Wastes Disposal .......................................................... ................... 4-52

    4.9.3 Mitigation Measures ................................................................. .................................................... 4-52

    4.9.4 Residual Impacts ............................................................. ..............................................................4-53

    4.10 Transboundary Impacts of Planned Operations ........................................................ .............................. 4-53

    4.11 Cumulative Impacts from Planned Operations ......................................................... ..............................4-53

    4.12 Environmental Impacts Associated with Potential Oil and Chemical Spills ..............................................4-56

    4.12.1 Introduction ......................................................... ................................................................ ........4-56

    4.13 Potential Sources of Spill ......................................................... .............................................................. 4-56

    4.13.1 Likelihood of a Spill ......................................................... .............................................................. 4-57

    4.13.2 Worst Case Scenario Definition ............................................................ ......................................... 4-60

    4.13.3 Predicted Potential Impact on the Coastal Environment ........................................................ ........4-61

    4.13.4 Modelling Conclusion ................................................................ .................................................... 4-70

    4.13.5 Prevention and Mitigation Measures ............................................................... ..............................4-73

    4.13.6 Impact of a Spill .............................................................. ..............................................................4-76

    4.13.7 Oil Spill Response Strategy ......................................................... ................................................... 4-77

    5 Environmental Management .................................................................................................................... 5-1

    5.1 Introduction ...................................................... ................................................................ .................... 5-1

    5.2 EnQuests Business Management System (BMS) ..................................................................................... 5-1

    5.3 HSEQ Policy ....................................................... ................................................................ .................... 5-1

    5.4 Risk Management ......................................................... ................................................................ ......... 5-3

    5.5 Contractor Management ......................................................... ............................................................... 5-3

    5.6 Environmental Awareness Training.................................................... ..................................................... 5-3

    5.7 Emergency Response .............................................................. ............................................................... 5-3

    6. Conclusions ............................................................................................................................................ 6-1

    6.1 Key Environmental Sensitivities .......................................................... .................................................... 6-1

    6.2 Key Environmental Impacts ................................................................ .................................................... 6-1

    6.3 Key residual impacts ............................................................... ............................................................... 6-2

    7. References .............................................................................................................................................. 7-1

    APPENDIX A: ASPECTS TABLES ........................................................................................................................ A-1

    APPENDIX B: STATUTORY FRAMEWORK .......................................................................................................... B-1

  • 5/28/2018 Kraken Development

    10/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 viii

    APPENDIX C: DRILLING OPERATIONSSUPPORTING INFORMATION ................................................................. C-1

    APPENDIX D: PRODUCTION PROFILE TABLES ..................................................................................................... D-1

    APPENDIX E: HOCNS & HMCS .......................................................................................................................... E-1

    APPENDIX F: SITE SURVEY ............................................................................................................................... F-1

    APPENDIX G: SEABED IMAGERY ...................................................................................................................... G-1

    APPENDIX H- ATMOSPHERIC DISPERSION MODELLING ...................................................................................... H-1

    APPENDIX I - THE BMT OSIS MODEL .................................................................................................................. I-1

    APPENDIX JWEATHERING OF SPILT OIL .......................................................................................................... J-1

    APPENDIX KCOMMITMENT REGISTER .......................................................................................................... K-1

  • 5/28/2018 Kraken Development

    11/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 ix

    Non-Technical Summary

    Background

    During 2012, EnQuest plc (EnQuest) acquired interests in the licence for the Kraken discovery

    (P1027). EnQuest ENS Limited and EnQuest Dons hold a 20% and 40% interest in the Kraken field

    respectively, with their partners; First Oil (15%) and Cairn Energy (25%).

    The Kraken development will be undertaken in accordance with the EnQuest policy to manage all

    company activities such that the environmental impacts of its operations are minimised. To

    meet this policy and to ensure compliance with the Offshore Petroleum Production and Pipelines

    (Assessment of Environmental Effects) Regulations 1999 (SI No. 1999/360) this Environmental

    Statement has been prepared by EnQuest in conjunction with environmental consultants RPS

    Energy HSE & Risk Management.

    Project Overview

    The Kraken development area is in the southern part of the East Shetland Basin in the north ern

    North Sea approximately 126km east of the nearest landfall at Noss, the Shetland Islands and

    46km west of the UK/Norway trans-boundary median line (Figure 1.1).

    EnQuest is planning to develop the Kraken area as three separate fields: Kraken North, Kraken

    Central and Kraken South. This will be achieved by drilling fourteen horizontal production wells

    and eleven horizontal water injector wells from seven drill centres (see Figure 2.3). The wells will

    be drilled in pairs, using two semi-submersible (semi-sub) mobile drilling units (MODU) and will

    be suspended pending tie-in to the flowlines and FPSO. All wells will be tied back to an FPSO

    (Floating Production, Storage and Offloading) facility which will process and store the producedfluids and then export stabilised crude via shuttle tankers. The FPSO power demands will be met

    through the use of associated gas. The short fall in associated gas production will be

    supplemented by the use of either crude oil or diesel. It is understood that there may be future

    opportunity for gas import from the Vesterled line, this shall be investigated as an alternative

    source of fuel when t he infrastructure is available.

    The drill centres are located approximately 3.5km apart. The wells will be drilled using a

    combination of water based drilling mud (WBM) and low toxicity oil based mud (LTOBM). All

    cuttings from the wells which might be contaminated with LTOBM in addition to any used LTOBM

    will be returned to the MODU and skipped and shipped to shore for further processing and

    appropriate reuse or disposal. All production wells will require artificial lift and Hydraulic

    Submersible Pumps (HSPs) have been selected as the preferred technology. The HSPs will be

    powered from the FPSO; the power fluid is treated seawater as there will be little or noformation water produced from the reservoir. The spent power fluid will be combined with the

    well production fluids and returned to the FPSO. All produced water will be re-injected and

    seawater will be used for water injection to replace the oil and maintain reservoir pressure,

    voidage replacement and to sweep the oil to the producers.

  • 5/28/2018 Kraken Development

    12/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 x

    The Existing Environment

    The environmental impact assessment process requires a comprehensive review of the existingenvironment to provide a basis for assessing the potential for interactions with the proposed

    development. For the Kraken development, the existing environment has been characterised

    using existing data for the general northern North Sea, supplemented by a set of site specific

    survey data.

    During 2012, EnQuest conducted a combined geophysical and environmental baseline survey at

    the proposed Kraken Field site, undertaken between February-March 2012 by Fugro Survey Ltd.

    The geophysical survey was commissioned to provide seabed, sub-seabed and anchoring

    conditions for the location. It consisted of an 11km by 7km geophysical survey area and centred

    on the proposed location (Figure 3.1). Data were acquired via side scan sonar and multi beam

    echo sounders and a sub-bottom profiler, this was to define any potential hazards or factors of

    operational significance prior to the development (Fugro, 2012). The environmental survey

    comprised acquisition of seabed video and still photographic data, and grab samples. A grid

    sampling strategy was adopted to assign sampling stations at regular intervals (1360 m)

    throughout the survey area, although some flexibility in station locations was allowed to ensure

    full coverage of all sediments and habitats interpreted from the side scan sonar (SSS) and

    bathymetry data. Sampling effort was also concentrated in the immediate vicinity of the

    proposed development and across a total of 44 environmental sampling stations within the 11 km

    by 7 km survey area, providing sufficient coverage for characterisation of all seabed sediment

    types.

    Site specific data from the Kraken geophysical and environmental baseline survey (Fugro, 2012)

    has been incorporated, where relevant, throughout section 3 of the ES. However, a summary of

    the key aspects of the current environment within the proposed Kraken development area is

    identified below.

    Physical Environment

    The Kraken development is located in the southern part of the east Shetland basin, referred as

    the northern North Sea, approximately 126km east of the nearest landfall at Noss, on the

    Shetland Islands and approximately 46km west of the UK/Norway trans-boundary median line.

    Water depth within the proposed Kraken development location varies between 108m and 125m.

    Surveys indicated that the seabed was deepest in the west reaching a maximum of approximately

    123.8 m below LAT, and shoaling gradually towards the east to a minimum of approximately

    108.0 m below LAT. A negligible gradient (

  • 5/28/2018 Kraken Development

    13/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xi

    Biological Environment

    In the waters of this area, the variability of the average daily quantity of light through the seasons

    and changes to the nutrient and mixing regimes result in blooms of plankton. The largest of these

    blooms occurs in spring and the second in autumn. The phytoplankton community is dominated

    by dinoflagellates whilst calanoid copepods, tiny crustaceans, are the main component of the

    zooplankton in the area.

    In the northern North Sea, to the north of the 58th

    parallel, in water deeper than 100m, the water

    mass stratifies strongly in summer, effectively insulating the bottom water and seabed fauna

    from the large scale temperature changes that occur in the upper water column.

    The site specific surveys indicated that species diversity, richness and abundance of the seabed

    fauna (benthos) in the proposed development area are comparable to those in other parts of the

    northern North Sea with similar depth. The Kraken survey indicated that the epifuanal

    community was typically sparse, with many patches displaying no visible fauna. The most

    dominant taxa recorded within the survey area belonged to the polychaetes.

    There are a number of fish spawning areas and nursery areas in the development blocks,

    including spawning areas for haddock, whiting, saithe, Norway pout, cod and sandeel, with

    nursery areas for haddock, whiting, Norway pout, mackerel, blue whiting, herring, sandeel, ling,

    hake and anglerfish.

    The Kraken development is some 126km from the adjacent coastline at its nearest point.

    Although this represents a considerable distance from the internationally important colonies

    present in the Shetlands (Fetlar, North-east Unst etc.), foraging seabirds may travel 150km from

    their habitat and therefore may be present at sea in the development area. While interactions

    between seabirds and oil and gas developments are usually low, the potential for impact if

    hydrocarbons are spilt is significant. Vulnerability to an oil spill in the vicinity of the Kraken

    development is moderate to low for more than half the year in February, from April to June, from

    August to October and December. However, seabird vulnerability to oiling is generally high tovery high during January, March, April, and July whilst at its highest during November.

    Available data show that the most commonly occurring cetacean species sighted in the offshore

    waters in and surrounding the Kraken development are harbour porpoise, minke whales and

    white-beaked dolphins, with increased densities of harbour porpoise in July and August. Both

    grey and harbour seals may be found in the area but in relatively low numbers and are unlikely to

    spend any significant time in the vicinity due to the distance from shore.

    There are no protected sites or unique habitats in the Kraken development area and the site

    survey did not identify any species or habitats of conservation protected under the UKs Offshore

    Marine Conservation (Natural Habitats, &c.) Regulations 2010. The nearest protected sites are

    located along the adjacent coastlines of the Shetland Isles, some 126km distance from Kraken.

    These protected sites will not be at risk from normal operations associated with the planneddevelopment or production activities.

    Socio-Economic Environment

    The Kraken development lies in an area that ranks fishing effort as low and consistent with fishing

    effort for large areas of the northern North Sea. Pelagic and demersal species comprise the bulk

    of the catch, and to a lesser extent, shellfish. However, annual catch, in terms of tonnage landed

    and its monetary value is considered as relatively low.

    The Kraken development lies in an area that ranks fishing effort to catch demersal species (cod,

    haddock, ling, megrim, monk fish, saithe, whiting etc.) as moderate, effort to catch pelagic

    species (herring and mackerel mainly) low and effort to catch shellfish very low (squid, lobster

    and Nephrops) in relation to the other UK waters. The highest fishing effort is during March and

    September and the lowest effort occurs during December.

  • 5/28/2018 Kraken Development

    14/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xii

    The intensity of shipping traffic east of the Shetlands is relatively light with one to two vessels

    crossing the Kraken development area per day, many associated with other oil and gas facilities

    in the northern North Sea. A total of 8 routes pass within 10nm of the proposed Kraken well

    location, with a total of 510 vessels per year. The nearest large port for this area is Lerwick onmainland Shetland.

    The route for vessels travelling between Sognefjorden (Norway) and Firth of Clyde and between

    Milford Haven and Sognefjorden (Norway), pass within less than 3nm of the Kraken well

    locations, constituting approximately 21% and 10% of the traffic respectively. However, while

    the development will affect these routes there is sea room available in the surrounding area for

    the vessels on these routes to achieve an adequate clearance from the installations. Any impact

    on other routes is expected to be negligible.

    The closest surface platform to the Kraken development, lies approximately 28km to the south

    east, at the Bruce gas field.

    Charts and local surveys indicate that there are no charted wrecks in the area.

    Key Sensitivities

    In summary, the key environmental sensitivities, summarised in Table 1.1 at the proposed Kraken

    development location are:

    The blocks of interest include fish spawning areas for haddock, saithe, whiting, cod,

    sandeel and Norway pout. The blocks are also nursery areas for haddock, whiting, Norway

    pout, blue whiting, mackerel, herring, ling, hake, anglerfish and sandeel.

    In the blocks of interest, seabird vulnerability to oiling is generally low for more than half

    the year (3 to 4 on the Joint Nature Conservation Committee (JNCC) scale) in February,

    May, during April to June, August to October and December. However, seabird

    vulnerability to oiling is generally high (1 to 2 on the JNCC scale) during January, March,

    April, July and November.

    Cetacean numbers overall are low. The most common occurring species are harbour

    porpoise, minke whales and white-beaked dolphins, with increased densities of harbour

    porpoise during July and August.

    Grey seal (listed in Annex II of the Habitat Directive) may be found in the area. There is also

    potential for Harbour seals.

    No protected habitats as listed in Annex I of the Habitat Directive have been identified in

    the proposed development area.

    The nearest coastal environmentally designated sites are all on the Shetland Islands and

    include:

    - North Fetlar Special Area of Conservation (SAC) dry coastal heathland (200km);

    - Hascosay(SAC) sensitive coastal habitats (200km);

    - Yell Sound (marine SAC) with two Annex II species including otter and common seal

    approximately 212km from the development;

    - The nearest seabird colonies are the North-east Unst, Crussa field and West Unst;

    - In addition, there are a number of coastal protected sites adjacent to the blocks of

    interest on the Shetland Islands, including Fetlar, Hermaness, Saxa Vord and Valla Field

    and Otterswick and Graveland.

    Potential restrictions to seismic operations (Marine Scotland Period of concern):- Block 9/02 between January and June.

  • 5/28/2018 Kraken Development

    15/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xiii

    The overall fishing effort is low throughout the year; the highest fishing effort is noted in

    March and September. Catch is primarily of demersal and pelagic species, with very few

    mollusc and shellfish targeted.

    Moderate to low levels of shipping traffic pass through the area.

    There are a number of abandoned wells within the vicinity of the proposed development.

    There are currently no proposed offshore wind farms in the near vicinity of the proposed

    development.

    The planned Kraken development lies approximately 46 kilometres west of the trans-

    boundary line.

    Table 1.1. Seasonal Environmental Sensitivities

    Activity in Block 9/02b surrounding waters and adjacent coast

    Component Abundance/Activity J F M A M J J A S O N D

    Plankton Phytoplankton and zooplankton

    Benthic Fauna Benthic faunal communities

    Fish Haddock N N N N

    Whiting N N N N N

    Saithe

    Norway pout N N N N

    Mackerel N N N N N

    Blue Whiting N N N

    Herring N N

    Sand eel N N N N

    Ling N N N NHake N N N N N

    Anglerfish N N N N

    Cod

    Seabirds Block 9/02b Offshore Vulnerability 2 4 2 3 4 4 2 4 3 3 1 3

    Cetaceans Harbour porpoise

    Minke whale

    White beaked dolphin

    Resource Users Commercial fishing (ICES rectangle 48F1)

    Shipping and ports

    Military Activity

    Oil and gas activity (inc. pipelines / cables)

    Dredging and dumpingOffshore windfarms

    Marine SACs

    Coastal protected sites

    Tourism, recreation & leisure activities

    Numbers refer to the seabird vulnerability index used by JNCC (1999) ranging from highest vulnerability (1) to

    lowest (4).

    Coastal occurrence Activity in Block 9/02b and surrounding waters

    Peak Low None Peak High Low None N Nursery

    * Seabird vulnerability - High sensitivity: 1, Low sensitivity: 4, blank: no data (JNCC, 1999)

    ** Data compiled from the JNCC atlas, 2003. However, sightings by MMOs during surveys conducted in 2004 & 2006 have also

    been included for completeness.

  • 5/28/2018 Kraken Development

    16/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xiv

    Environmental Interactions, Impacts and Mitigation Measures

    The environmental assessment carried out on the development of the Kraken field, as proposedby EnQuest, indicates that the key interactions, resulting environmental impacts and measures to

    mitigate those effects are as follows:

  • 5/28/2018 Kraken Development

    17/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xv

    ROUTINE HAZARDS - DRILLING

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Physical Presence

    Disruption to other

    sea users

    Shipping, Commercial Fishing A safety exclusion zone will be designated extending to 500m from the MODU.

    An ERRV will be on stand-by and monitor vessels within the area to assist in keeping

    vessels away from the MODU.

    AIS and radar systems shall assist the ER RV and MODU in identifying approaching

    vessels.

    Notifications shall be made to the MCA and Hydrographic Office. Notices to

    Mariners, NAVTEX and NAVAREA warnings will be circulated and changes to

    schedule shall be advised.

    Regular runners in the r outes identified as being potentially impacted by the

    MODU location shall be notified prior to MODU arriving on s ite.

    Operators of radar systems installed at onshore bases will be made aware of the

    proposed activity so they can inform ves sels transiting in the area of the pre sence of

    the MODU.

    A Collision Risk Management Plan will be in place.

    Early and ongoing liaison with the SFF and other f ishing groups shall be maintained.

    Locations and safety zones shall be marked on appropriate charts.

    Good communications with local fishermen shall be maintained with the

    appointment of an onshore FLO to coordinate activities throughout the drilling and

    installation phase. Vessels will be contacted by VHF radio with regular broadcast to

    all vessels operating in the area.

    Low

    Seabed Disturbance

    Disturbance may

    occur from MODUanchors and anchor

    chains

    Water quality, Sediments, Seabed

    fauna

    Anchoring patterns will be reviewed to ensure they do not encroach any existing

    seabed infrastructure.

    Low

    Noise

    Noise from drilling

    operations may

    disturb marine

    fauna

    Marine Mammals, Fish Days on location of the semi-submersible MODU will be kept to a minimum.

    Operational and maintenance procedures on the MODU will aim to optimise the

    efficiency of equipment and schedule of operations.

    Optimise vessel movement by careful planning.

    Low

  • 5/28/2018 Kraken Development

    18/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xvi

    ROUTINE HAZARDS - DRILLING

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Atmospheric

    Emissions

    Emissions from

    power generation

    for the MODU and

    support vessels.

    Additional

    emissions for

    maintenance and

    flaring during well

    clean-up.

    Air quality Environmental critical elements (ECE) on the MODU will be identified and subject to

    specific maintenance routines. In particular, main power generation equipment will

    be well maintained and operated.

    Contracted vessels will be required to control processes, maintain equipment,

    manage energy and minimise usage wherever possible.

    Low sulphur diesel will be used wherever possible.All drilling activities will be planned so as to minimise duration and ensure efficient

    operations

    Optimise vessel movement by careful planning.

    Minimise quantities of oil and gas flared.

    Medium (power

    generation)

    Low (other)

  • 5/28/2018 Kraken Development

    19/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xvii

    ROUTINE HAZARDS - DRILLING

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Marine Discharges

    Discharge of ballast

    water, WBM and

    associated cuttings,

    cement, drainage

    water, sewage,

    food waste and

    well completion

    fluids

    Water Quality, Seabed Fauna, Fish,

    Shellfish, Offshore seabirds,

    Marine mammals

    Strict adherence to the rules governing discharge of ballast waters at sea.

    Use of a MODU/ vessels coming fr om previous North Sea operations or location for

    intake and discharge of ballast water within same region.

    A full Chemical Hazard Assessment and Risk Management assessment of the

    proposed chemicals will be undertaken. Where practicable chemicals with

    substitution warnings will be replaced with those with an improved environmentalprofile.

    Only spent WBM and associated cuttings will be discharged to sea; LTOBM and

    associated cuttings will be skipped and shipped to shore.

    Cuttings / mud cleaning equipment will ensure optimal cuttings cleaning of the

    WBM prior to discharge. Recovered WBM will be reused / re-circulated where

    practical.

    Cement and associated chemicals will be mixed offshore as needed to minimise

    quantities used.

    Environmental critical elements (ECE) on the MODU will be identified and subject to

    specific maintenance routines to ensure compliance with environmental legislation.

    The hydrocarbon content of the completion br ine will be monitored. Only fluids

    with an oil in water content, which does not produce a surface sheen, will be

    discharged to sea. If, oil is visible on the surface of the sea, all discharge shall cease

    and the water will be contained and shipped to shore for processing. Good

    housekeeping standards will be maintained on the MODU.

    Black (sewage) and grey water will be collected, treated (macerated) to meet the

    requirements of the MARPOL convention prior to being discharged to sea. Alldischarges will be treated and dis charged according to the MARPOL Convention,

    which prohibits discharge of any garbage or solid waster into the North East Atlantic

    Ocean.

    Good housekeeping standards will be maintained on the MODU to minimise

    hydrocarbons or chemicals in the drainage water.

    Suitable containment, treatment and monitoring systems for the drainage systems

    will be in place. Hazardous streams will be contained for treatment and will not be

    discharged overboard.

    Low

  • 5/28/2018 Kraken Development

    20/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xviii

    ROUTINE HAZARDS - DRILLING

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Solid Wastes

    Wastes will include

    spent LTOBM and

    associated cuttings,

    scrap metal,

    garbage, waste oil

    and chemicals

    Land Use, Air quality Procedures will be in place to ensure that filling, storage and removal of the

    containers will conform to strict guidelines to minimise the risk of accidental spillage

    of LTOBM. Recycling of LTOBM will be undertaken where possible.

    Thermal treatment of cuttings associated with LTOBM will be undertaken once at

    contractors site. Resulting process water will be used to dampen the dry cuttings

    before final disposal at a l andfill site. Drill cuttings that will be disposed of to landfill

    will be used for covering other material that has been disposed of at the landfill site.

    Auditing of waste management contractors to ensure compliance.

    A Waste Management Plan will be in place to ensure:

    Minimisation of the amounts generated at source;

    Segregation of waste by type;

    Storage in covered skips to prevent emissions and leaks.

    Recycling or re-use prioritised where possible, in particular for scrap metal,

    waste oil and surplus chemicals ;

    Waste sent to authorised landfills or incineration facilities, depending on its

    precise nature, when no other option is possible;

    Use of authorised waste contractors.

    Low

  • 5/28/2018 Kraken Development

    21/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xix

    ROUTINE HAZARDSInstallation and Commissioning

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Physical Presence

    Disruption to other

    sea users from

    presence of FPSO and

    vessels.

    Shipping, Commercial

    Fishing

    A safety exclusion zone will be designated extending to 500m around the FPSO and drill

    centres.

    An ERRV will be on stand-by and monitor vessels within the area to assist in keeping vessels

    away from the exclusion zones and installation activities.AIS and radar systems shall assist the ERRV and FPSO to identify approaching vessels.

    FPSO location and exclusion zones shall be notified to appropriate authorities and marked on

    charts.

    Continued liaison with SFF, fishing groups, MoD and other industries will ensure that the

    physical presence of facilities and vessels has minimum interference with other activities.

    All potential, long-term obstructions to fishing vessels will be notified to the appropriate

    authorities and marked on charts.

    All pipelines will be trenched and backfilled to minimise interference with fishing gear.

    Subsea facilities at the drill centres will be designed to be fishing friendly.

    Low

    Seabed Disturbance

    Disturbance may

    occur from anchors

    and mooring lines,

    trenching and

    backfilling, subsea

    infrastructure and

    protective/

    stabilisation

    materials

    Sediments, Seabed fauna Anchoring patterns will be reviewed to ensure they do not encroach on any existing seabed

    infrastructure.

    Working corridors will be minimised wherever re asonably practicable.

    All installation vessels will be dynamically positioned to minimise disturban ce by anchors.

    The amount of deposited material and the method of placement will be optimised in order to

    achieve stabilisation while minimising the area impacted.

    Medium

    (flowline

    installation)

    Low (other)

  • 5/28/2018 Kraken Development

    22/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xx

    ROUTINE HAZARDSInstallation and Commissioning

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Noise

    Noise from flowline

    installation, piling

    activities and vessel

    presence may disturb

    marine fauna

    Fish, Marine Mammals Operational and maintenance procedures on the vessels will aim to optimise the efficiency of

    equipment and schedule of operations.

    Vessels engaged in pipelay and installation a ctivities will be either stationary or operating at

    slow speeds during work activities.

    The method of placement will be optimised in order to achieve stabilisation while minimisingthe area impacted.

    FEPA consent with a comprehensive Marine Mammal Monitoring Programme. This will include

    Marine Mammal Observers and Passive Acoustic M onitoring package stationed offshore

    throughout the piling programme.

    Low (other)

    Medium (piling)

    Atmospheric

    emissions

    Emissions from

    power generation on

    installation vessels

    and FPSO during

    commissioning

    Air quality Environmental critical elements (ECE) on the FPSO will be identified and subject to specific

    maintenance routines. In particular, main power generation equipment will be well maintained

    and operated.

    Contracted vessels will be required to control processes, maintain equipment, manage energy

    and minimise usage wherever possible.

    Low sulphur diesel will be used wherever possible.

    All operations will be planned so as to minimise duration and ensure efficient operations.

    Optimise vessel movement by careful planning

    Medium

  • 5/28/2018 Kraken Development

    23/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xxi

    ROUTINE HAZARDSInstallation and Commissioning

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Marine Discharges

    Will include discharge

    of ballast water from

    FPSO and vessels,

    flowline testing and

    commissioning fluids,domestic sewage, food

    waste and drainage

    water.

    Water Quality, Plankton,

    Seabed fauna, Fish/Shellfish,

    Offshore seabirds, Marine

    mammals

    Strict adherence to the rules governing discharge of ballast waters at sea.

    Where possible the use of vessels coming from previous North Sea operations or location for

    intake and discharge of ballast water within same region.

    A full Chemical Hazard Assessment and Risk Management (CHARM) assessment of the proposed

    chemicals will be undertaken. Where practicable chemicals with substitution warnings will bereplaced with those with an improved environmental profile. All chemicals shall be approved by

    the OCNS.

    Good housekeeping standards will be maintained onboard vessels.

    Black (sewage) and grey water will be collected, treated (macerated) to meet the re quirements

    of the MARPOL convention prior to being discharged to sea.

    All discharges will be treated and dis charged according to the MARPOL Convention, which

    prohibits discharge of any garbage or solid waste into the North East Atlantic Ocean.

    Good housekeeping standards will be maintained on th e FPSO and vessels to minimise

    hydrocarbons or chemicals in the drainage water.

    Suitable containment, treatment and monitoring systems for the drainage systems will be in

    place.

    Hazardous streams will be contained for treatment and will not be discharged overboard

    Low

    Solid Wastes

    Wastes will include

    scrap metal, garbagewaste oil chemicals

    Land Use, Air quality Minimisation of waste generated.

    Bulk waste (e.g. Garbage, scrap, etc) generated on the installation vessels will be segregated by

    type and stored in covered skips. Periodically these will be transported to shore and the wasterecycled or disposed of in a controlled manner through authorised waste contractors.

    A waste management programme will be implemented to minimise the amounts generated and

    to ensure material such as scrap metal, waste oil and surplus chemicals are sent f or recycling or

    re-use as far as practicable. Other waste will be sent to authorised landfills or incineration

    facilities, depending on its precise nature.

    Low

  • 5/28/2018 Kraken Development

    24/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xxii

    ROUTINE HAZARDSProduction

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Physical Presence

    Disruption to other

    sea users

    Shipping, Commercial

    Fishing

    A safety exclusion zone will be designated extending to 500m around the FPSO and drill

    centres.

    An ERRV will be on stand-by and monitor vessels within the area to assist in keeping vessels

    away from the exclusion zones and installation activities.

    AIS and radar systems shall assist the ERRV and FPSO identify approaching vessels.

    FPSO location and exclusion zones shall be notified to appropriate authorities and marked on

    charts.

    Continued liaison with SFF, fishing groups, MoD and other industries will ensure that the

    physical presence of facilities and vessels has minimum interference with other activities.

    All potential, long-term obstructions to fishing vessels will be notified to the appropriate

    authorities and marked on charts.

    All pipelines will be trenched and backfilled to minimise interference with fishing gear.

    Subsea facilities at the drill centres will be designed to be fishing friendly.

    Low

    Seabed Disturbance

    Disturbance may

    occur from anchors

    and mooring lines,

    subsea infrastructure

    and protective/stabilisation

    materials

    Sediments, Seabed fauna The amount of deposited material will be optimised in order to minimise the area impacted. Medium (marine

    fauna colonising

    hard structures)

    Low (other)

  • 5/28/2018 Kraken Development

    25/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xxiii

    ROUTINE HAZARDSProduction

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Noise

    Noise from production

    and oil export

    operations and

    helicopter and support

    vessel movementsmay disturb marine

    fauna

    Fish, Marine Mammals Operational and maintenance procedures on the FPSO and vessels will aim to optimise the

    efficiency of equipment and schedule of operations.

    Equipment maintenance schedules will include minimisation of mechanical noise, e.g. pump

    cavitation.

    Tankers will be either stationary or operating at slow speeds in the Kraken area.Optimise vessel movement by careful planning.

    Optimise vessel and helicopter movement by careful planning.

    Low

    Atmospheric

    Emissions

    Emissions from

    power generation on

    the FPSO, support

    vessels and export

    tanker, Flaring during

    engine shutdown,

    tanker offloading,

    cleaning and

    maintenance

    Air quality Environmental critical elements (ECE) on the FPSO will be identified and subject to specific

    maintenance routines. In particular, main power generation equipment will be well maintained

    and operated.

    All machines to include Dry Low Emissions (DLE) technology, which minimises production of NOx

    and CO.

    Variable speed drives on pumps will allow to tailor speed (and associated energy consumption)

    to actual need.

    Fuel consumption and flaring on the FPSO will be regularly monitored to allow analysis of the

    efficiency of the systems and effectiveness of procedures.

    Contracted vessels will be required to control processes, maintain equipment, manage energy

    and minimise usage wherever possible.

    Low sulphur diesel will be used wherever possible.

    A vapour recovery unit will be installed to recover vapours from the separators and other oil

    processing equipment to minimise vapours routed to the flare system.

    Use of high combustion efficiency burners.

    Minimisation of emergency blow-down as a safety mitigation for confirmed fire and gas

    detection and not on process or compressor shutdown

    Low loss fittings. High integrity compressor and pump seals for high pressure systems.

    Closed drains for the hydrocarbon system.

    Loss of VOC during offloading will be minimised by the preferential selection of shuttle tankers

    with a VOC capture facility or VOC reduction capability.

    Medium

  • 5/28/2018 Kraken Development

    26/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xxiv

    ROUTINE HAZARDSProduction

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Marine Discharges

    Will include discharge

    of produced water

    during re-injection

    pump unavailability,

    production chemicals,displaced water,

    cooling water, ballast

    water, sewage, food

    waste and drainage

    water.

    Water Quality, Plankton,

    Seabed fauna,

    Fish/Shellfish, Offshore

    seabirds, Marine mammals

    Environmental critical elements (ECE) on the FPSO will be identified and s ubject to specific

    maintenance routines to ensure compliance with environmental legislation and EnQuest goals.

    Produced water will be re-injected into the reservoir except during short periods for maintenance

    or upset conditions. Any discharge of produced water will be treated to meet oil-in-water

    standards of < 30 mg/l and will be monitored and sampled in accordance with an approved OPPC

    permit.

    Independent storage management and monitoring systems in place in e ach oil storage tank.

    Coatings of storage tanks designed to inhibit bacterial growth and rag layer development.

    High and low oil level alarm systems in each of the storage tanks. Automatic shutdown

    sequence to prevent transfer of oil to a tank or shutdown oil ex port. All piping connections into

    the tanks within the water phase to prevent loss of oil containment. Leak detection system in

    place.

    Strict adherence to the rules governing discharge of ballast waters at sea.

    Black (sewage) and grey water will be collected, treated (macerated) to meet the r equirements

    of the MARPOL convention prior to being discharged to sea

    Good housekeeping standards will be maintained on the FPSO, and vessels to minimise

    hydrocarbons or chemicals in the drainage water.

    Suitable containment, treatment and monitoring systems for the drainage systems will be in

    place. Hazardous streams will be contained f or treatment and will not be discharged overboard.

    Hazardous drain system will be equipped with tr ip and alarm systems in place.

    Recovered oil from the open and closed drainage systems is returned to the process and waste

    water will be treated and monitored to ensure that the oil content is in line with appropriate

    standards prior to discharge overboard.

    A full Chemical Hazard Assessment and Risk Management assessment of the proposed chemicals

    will be undertaken. Where practicable chemicals with substitution warnings will be replaced

    with those with an improved environmental profile. Areas where chemicals may be laid down or

    stored will have bunding to c ontain any leaks; these will be routed to the open drains and then

    return to the process.

    Low

  • 5/28/2018 Kraken Development

    27/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xxv

    ROUTINE HAZARDSProduction

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Solid Wastes

    Wastes will include

    scrap metal, garbage

    waste oil chemicals

    Land Use, Air quality A Waste Management Plan will be in place to ensure:

    Minimisation of the amounts generated at source;

    Segregation of waste by type;

    Storage in covered skips to prevent emissions and leaks.

    Recycling or re-use prioritised where possible, in particular for scrap metal, waste oil and

    surplus chemicals ;

    Waste sent to authorised landfills or incineration facilities, depending on its precise

    nature, when no other option is possible.

    Use of authorised waste contractors.

    Low

  • 5/28/2018 Kraken Development

    28/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xxvi

    NON ROUTINE HAZARDS Drilling

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Physical presence /

    Seabed disturbance

    Debris dropped at

    sea

    Sediments, seabed fauna, seabed

    infrastructure

    Audits of all equipment brought onto, and taken off, the site.

    Debris is identified during the post work surveys or if dropped objects occur then

    these will be appropriately reported and procedures will be in place to ensure their

    recovery, wherever possible.

    Low

    Atmospheric

    emissions

    Emission of CO2/N2from firefighting

    equipment.

    Atmospheric

    pollution from

    uncontrolled gas

    release from well

    Air quality Fire fighting equipment not to be used in exercise scenarios.

    A shallow gas survey has been undertaken.

    Crews will be adequately experienced, trained in well control techniques and

    supervised. Emergency drills will be held regularly.

    Well design and construction reviewed by an independent well examiner.

    Weighted drilling fluids will provide the primary barrier and the well will be carefully

    controlled and monitored.

    The secondary barrier will be the BOP, which will be regularly maintained and

    tested.

    Production isolation valves will be included on the subsea Xmas tree and all safety-

    critical subsea valves will be ROV or diver operable.

    Emergency Response Plans, OPEP and equipment will be in place.

    Low

  • 5/28/2018 Kraken Development

    29/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xxvii

    NON ROUTINE HAZARDS Drilling

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Marine Discharges

    Loss of

    containment on

    the MODU due to

    ship collision or

    other major event

    Water Quality, Land use,

    Sediments, Plankton, Seabed

    fauna, Fish/Shellfish, Offshore

    seabirds, Marine mammals,

    Coastal seabirds, Fishing, Tourism

    A safety exclusion zone will be designated extending to 500 metres from the MODU.

    An ERRV will be on stand-by and monitor vessels within the area to assist in keeping

    vessels away from the MODU.

    AIS and radar systems shall assist the ERRV and MODU to identify approaching

    vessels.

    Notifications shall be made to the MCA and Hydrographic Office. Notices to

    Mariners, NAVTEX and NAVAREA warnings will be circulated and changes to

    schedule shall be advised.

    Regular runners in the routes identified as being potentially impacted by the

    MODU location shall be notified prior to MODU arriving on site.

    Operators of radar systems installed at onshore bases will be made aware of the

    proposed activity so they can inform vessels transiting in the area of the presence of

    the MODU.

    A Collision Risk Management Plan will be in place.

    Early and ongoing liaison with SFF and other fishing groups. Locations and safety

    zones shall be marked on appropriate charts.

    The appointment of a FLO to maintain communication and coordinate activities.

    Regular contact with vessels operating in the area via VHF radio broadcasts.

    Low

  • 5/28/2018 Kraken Development

    30/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002xxviii

    NON ROUTINE HAZARDS Drilling

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Marine Discharges

    Uncontrolled well

    flow during drilling

    Water Quality, Land use,

    Sediments, Plankton, Seabed

    fauna, Fish/Shellfish, Offshore

    seabirds, Marine mammals,

    Coastal seabirds, Fishing, Tourism

    Drilling will follow established drilling safety standards to minimise the r isk of well

    control loss.

    A shallow gas survey will be undertaken.

    Crews will be adequately experienced, trained in well control techniques and

    supervised. Emergency drills will be held regularly.

    Well design and construction reviewed by an independent well examiner.Weighted drilling fluids will provide the primary barrier and the well will be carefully

    controlled and monitored.

    The secondary barrier will be the BOP, which will be regularly maintained and

    tested.

    Production isolation valves will be included on the subsea Xmas tree and all safety-

    critical subsea valves will be ROV or diver operable.

    Emergency Response Plans, OPEP and equipment will be in place.

    The OPEP will include details of available capping devices, poss ible relief well

    locations and time frames to drill a relief well.

    Low to Medium

    depending upon

    environmental

    receptor

  • 5/28/2018 Kraken Development

    31/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xxix

    NON ROUTINE HAZARDS Drilling

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Marine Discharges

    Loss of

    hydrocarbons/

    chemicals during

    bunkering,

    refuelling andgeneral operations

    Loss of supply

    material to sea

    Water Quality, Land use,

    Sediments, Plankton, Seabed

    fauna, Fish/Shellfish, Offshore

    seabirds, Marine mammals,

    Coastal seabirds, Fishing, Tourism

    Environmentally critical equipment will be identified and specifically highlighted in

    the MODUs maintenance procedures and plans.

    Crews will be adequately trained, supervised and r egularly hold exercises to contain

    and clean up deck spills.

    If feasible, the drilling rig will arrive on site fully bunkered.

    Where practicable, re-fuelling and transfer of LTOBM, lubricants and other utility

    fluids will be undertaken during daylight and in good weather conditions.

    Non-return valves will be installed on LTOBM and fuel transfer hoses. Hoses will be

    tested and inspected as a part of a regular maintenance programme.

    Volumes of LTOBM will be reduced by drilling all top hole sections with WBM.

    Special containers will be used to store and ship the LTOBM and associated cuttings

    to shore for treatment and appropriate disposal.

    Transfer operations will be supervised at all times from both the supply boat and

    semi-submersible.

    Clean up materials will be available on the drilling rig and vessels to manage small

    deck spills.

    Minimisation of chemical transfers and loading operations.

    Operational controls for loading, unloading, and movement of materials.

    Double-checking containment of all materials for transfer to/from the drilling rig.

    Emergency response procedures available in the event of a chemical spill.

    Low to medium

    depending upon

    environmental

    receptor (others)

    Low (loss of

    supply material)

    NON ROUTINE HAZARDS Installation & Commissioning

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Physical presence /

    Seabed disturbance

    Debris dropped at

    sea

    Sediments, seabed fauna, seabed

    infrastructure

    Audits of all equipment brought onto, and taken off, the site.

    Debris is identified during the post work surveys or if dropped objects occur then

    these will be appropriately reported and procedures will be in place to ensure their

    recovery, wherever possible.

    Low

  • 5/28/2018 Kraken Development

    32/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xxx

    NON ROUTINE HAZARDS Installation & Commissioning

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Marine Discharges

    Uncontrolled well

    flow during

    commissioning,

    potential for spill of

    heavy crude

    Water Quality, Land use,

    Sediments, Plankton, Seabed

    fauns, Fish,/Shellfish, Offshore

    seabirds, Marine mammals,

    Coastal seabirds, Fishing, Tourism

    Crews will be experienced and tr ained in well control techniques and supervised.

    Emergency drills will be held regularly.

    Well design and construction reviewed by an independent well examiner.

    Production isolation valves will be included on the subsea Xmas tree and all safety-

    critical subsea valves will be ROV or diver operable.

    Emergency Response Plans, OPEP and equipment will be in place. Will also includedetails of available capping devices, possible relief well locations and time frames to

    drill a relief well.

    Low to Medium

    NON ROUTINE HAZARDS Production

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Physical presence /

    Seabed disturbance

    Debris dropped at

    sea

    Sediments, seabed fauna, seabed

    infrastructure

    Audits of all equipment brought onto, and taken off, the site.

    Debris is identified during the post work surveys or if dropped objects occur then

    these will be appropriately reported and procedures will be in place to ensure their

    recovery, wherever possible.

    Low

    Atmospheric

    emissions

    Emission of CO2/N2from firefighting

    Atmosphericpollution from

    uncontrolled gas

    release from well

    Air quality A shallow gas survey has been undertaken.

    Crews will be adequately experienced, trained in well control techniques and

    supervised. Emergency drills will be held regularly.

    Well design and construction reviewed by an independent well examiner. Production

    isolation valves will be included on the subsea Xmas tree and all safety-critical

    subsea valves will be ROV or diver operable.Emergency Response Plans and equipment will be in place

    Fire fighting equipment not to be used in exercise scenarios.

    Low

  • 5/28/2018 Kraken Development

    33/440

    EnQuest

    Kraken Field Development Area Environmental Statement

    Doc Ref No: ENQ-KRA-HS-00-STA-0002 xxxi

    NON ROUTINE HAZARDS Production

    Hazard & Effect(s) Environmental receptors Mitigation Measures Residual Impact

    Marine Discharges

    Potential for

    hydrocarbon and

    chemical spills

    during supply,

    bunkering andrefuelling. Loss of

    containment of

    hydrocarbons during

    normal operations

    Water Quality, Land use,

    Sediments, Plankton, Benthic

    communities, Fish, Shellfish,

    Offshore seabirds, Marine

    mammals, Coastal seabirds,

    Fishing, Tourism

    Environmentally critical equipment will be identified and specifically highlighted in

    the FPSO maintenance procedures and plans.

    Crews will be adequately trained, supervised and regularly hold exercises to contain

    and clean up deck spills.

    Where practicable, re-fuelling and transfer of lubricants and other utility fluids will

    be undertaken during daylight and in good weather conditions.

    Non-return valves will be installed on fuel transfer hoses, hoses will be tested and

    inspected as a part of a reg ular maintenance programme.

    Transfer operations will be supervised at all times from both the supply boat and

    FPSO.

    Clean up materials will be available on the FPSO and vessels to manage small deck

    spills

    Low to Medium

    depending upon

    environmental

    receptors (others)

    Low (loss of

    containment

    during normal

    operations)

    Marine Discharges

    Loss of containment

    on the FPSO due to

    ship collision or

    other major event .

    Release of

    hydrocarbons into

    the marine

    environment

    Water Quality, Land use,

    Sediments, Plankton, Seabed

    fauna, Fish/Shellfish, Offshore

    seabirds, Marine mammals,

    Coastal seabirds, Fishing, Tourism

    Liquid storage areas and areas that might be contaminated with oil are segregated

    from other deck areas.

    Permanent drip trays will be located under pr ocess plant, pumps and vessels (on

    grated decks).

    Bunding will be provided around plated areas bene ath equipment with significant

    hydrocarbon inventories.

    On all levels with grated decks any operational tasks requiring breaking of

    hydrocarbon containment will make use of portable drip trays, temporary bundingand other absorbent materials.

    Utility and fuel storage tanks will be equipped with trip and alarm systems and

    procedure will be in place to minimise and prevent spills overfilling these storage

    tanks.

    Special training will be given to personnel with the responsibility for the operation

    of valves, particularly dump valves.

    Routine equipment maintenance programme will be in pla