kpc_productivity improvement 2014
TRANSCRIPT
-
8/10/2019 KPC_Productivity Improvement 2014
1/37
Integrated Improvement Initiatives and
Strategic decisions during the challenging
situation of low coal prices
Presented by : Gede Ngurah Ambara*Mgr Business Performance ImprovementKPC
Novotel Hotel Balikpapan, Indonesia
2-3 September 2014
*e-mail : [email protected] : +62 (549) 52 1501
Kalimantan Coal Market
Overview of PT Kaltim Prima Coal Operation Challenging time : main driving factors for changes Stretching work-load (production) to reduce cost Improving Overall Effectiveness of Equipment Improve operators and mechanic discipline Sustainability of improvement initiatives Future Challenge of continuous improvement
The Outline Summary
mailto:[email protected]:[email protected] -
8/10/2019 KPC_Productivity Improvement 2014
2/37
PT KaltimPrimaCoalVision
Indonesias leading coal producer for global needs
delivering optimum values to all stakeholders
Missions
Fostering a culture that considers health, safety
and environment in everything we do, maintaining
good corporate governance and promoting good
corporate citizenship, providing an environment
for learning to achieve excellence and improvelivelihood, Optimizing value for all stakeholders,
and carrying out best practice in management
and operations to deliver consistent high quality
product and performance
-
8/10/2019 KPC_Productivity Improvement 2014
3/37
Location and Project Summary
-
8/10/2019 KPC_Productivity Improvement 2014
4/37
Sangatta Coal Deposit
Sangatta coal deposit occurrs in Balikpapan formation, withi
Kutai Basin during Miocene age : located 20 km from the coast
uncontaminated organic deposits with low ash and sulphur. The
deposit was subjected by a geological intrusion called Pinang
Dome. These pressures and temperature elevated the coal t
higher rank than its age would normally suggest.
Coal occurs in nine principal seams to the west of the Pinang Dome with thicknesses vary from
0.5 to 15 meters, with most in the range 2.4 to 6.5 meters. Seam dips normally varies between
3 and 20. The overburden consist of incompetent mudstones, siltstones and sandstones.
-
8/10/2019 KPC_Productivity Improvement 2014
5/37
Exploration , Drilling & Geotechnical Monitoring
-
8/10/2019 KPC_Productivity Improvement 2014
6/37
Soil Handling, Drill Blast, OB Removal & Coal Mining
-
8/10/2019 KPC_Productivity Improvement 2014
7/37
KPC Fleets and Production
Mobile-Heavy Equipment are 974 machines. KPC Daily production:
Explosives usage : 487 tonnes AN , Fuel consumption : 1,200,000 litres ,
Overburden removal : 1,450,000 bcm , Coal mined : 135,000 tonnes
Trucks Units CapacityLiebherr T282 31 360 tonnes
Hitachi EH 4500/5000 129 282 tonnes
Caterpillar 789 94 185 tonnes
Caterpillar 785 55 135 tonnes
Komatsu HD785 52 100 tonnes
Caterpillar 777 14 80 tonnes
Shovels Units Capacity
Liebherr R9800 3 45 m3
Liebherr 996 18 32 to 33 m3
Hitachi EX3600 11 23 to 24 m3
Hitachi EX 3500 6 22 m3
Hitachi EX 2500 4 15 16 m3
Liebherr 984C 4 5 8 m3
-
8/10/2019 KPC_Productivity Improvement 2014
8/37
CPP Stockpiles
8 stock piles (Prima.Pinang & Melawan Brand)Total capacity > 300 kt
-
8/10/2019 KPC_Productivity Improvement 2014
9/37
13 Km Dual OLC with speed 8.68 m/scapacity Max 9,000 tonnes per hour
Overland Conveyor
-
8/10/2019 KPC_Productivity Improvement 2014
10/37
Coal Transport & Loading Facilities (Sangatta)
KPC has complete facilities to provide full coal mining and transportation solutions
Coal Transportationto Loading Port
13 km Overland Conveyor
Average capacity : 4,200 tph Coal delivered in approximately
25 minutes
Port Stockpile
Total Stockpile capacity of 2.5 Mt
Stacker capacity of 4,200 tph
Reclaim capacity of 7,500
9,000 tph
Ship Loading
Private International Port
2 km Jetty 17.2 m draft deep water berth at low tide
Load vessels up to 220,000 dwt.
Loading rate of 7,500 tph with one (1) legand up to 9,000 tph for 2 ship loading
-
8/10/2019 KPC_Productivity Improvement 2014
11/37
111
Port Stockpile
7,500 tph for 1 Ship Loader
9,000 tph for 2 Ship Loaders
The facility can handle cape SizeShip (vessel) up to 200 kt with
approx 20-25 hours
-
8/10/2019 KPC_Productivity Improvement 2014
12/37
11
Coal Trans-shipment Facilities
Tanjung Bara Barge Loading
New 1000 tph facility commissioned
Barges loaded to vessel at Tanjung Baraanchorage
1 km sailing distance from barge to vessel
Lubuk Tutung Barge Loading
2000 tph facility (1000 tph ROM crushing)
Barges loaded to vessel at Lubuk Tutung
anchorage or at FTS
Floating Transfer Station (FTS)
1000 tph floating loading facility
Load up to Capesize vessels
Stationed at Lubuk Tutung (Bengalon)
1
-
8/10/2019 KPC_Productivity Improvement 2014
13/37
1
Challenging time : main driving factors for changes
Recent Years and Current Situation
KPC has been smoothly moved from 8 to 12 hours/shift roster toward end of year 2012. By doing this KPChas hindered the requirement to get additional man-power requirement of more than 800 operators.Meanwhile the expansion project continues, KPC and the other coal mined companies has been heavilyimpacted by continual decrease of coal price which due to prolonged economic crisis hit Europe, andslowing down of China and India economic which limits their coal import demand, and Excess coal supplyfrom North America. During one year by the end of year 2013, KPC Coal Average Selling Price has droppedmore than 12 USD.
The uncertainty of when the coal price will back to normal continues even until nowdays, with main workforce of 5000 employees, and in total of 23,000 including contractors, KPC faced dilemmatic situation,rather than doing rationalization of employees, KPC has started to implement several strategic decisionssome of the main ones are :
Substantially reduce the production by standing down 10 big diggers and more than hundreds of trucks. Started a new project of Improvement synergizing two main divisions : mining operation division (MOD)
and Mining Support Division (MSD) to focus on increasing the overall effectiveness of equipment (OEE) Deliberately sending the excess operators to a semi-military training to improve their discipline, moral
and work attitudes Develop additional work forces to focus on sustaining improvement initiatives at MOD and MSD.
-
8/10/2019 KPC_Productivity Improvement 2014
14/37
1
Reduce Production: parking up some of the main equipment
Deliberately Parked-up equipment (reducing work-load)
Year 2012 has been the peak of overburden removal production of KPC Pits, after that KPC has deliberatelyreduce the overburden production by means of parking-up about 10 big diggers and hundred of trucks.
But in the same time the coal mined has been increasing, by means of reducing the strip ratio. The overallstrip ratio (SR) in year 2012 was 11.7, subsequently reducing to 9.8 by the end of year 2014. Theoverburden cost removal constitute about 80% of total mining cost, by doing this strategy, KPC has beensignificantly lowering the unit cost of production ($/tonnes).
This parking up strategy has been subsequently implemented since early days of year 2013 and continuesuntil current time. To support the smoothness of this strategy, KPC management are ensuring that :A specific guide-lines/procedures of Park-up are being closely implemented and monitoredProcedure to re-activate any machine to be followed up carefullyA Roster/schedule of parking-up the machines is updated regularly to suit to recent/current dynamicsituation of coal mining activities, i.e : a significant change on overburden cycle-time which affect toincreasing number of waiting on trucks or trucks queue times.Integrate the park-up and re-activate the fleet with other procedures which may be impacted to, forinstances the SOP of Match Factor which relate to Fuel Efficiency project
-
8/10/2019 KPC_Productivity Improvement 2014
15/37
1
Reduce Production: parking up some of the main equipment
-
8/10/2019 KPC_Productivity Improvement 2014
16/37
1
Liebherr T282360 T = 32 Units
New Project : Improving Overall Effectiveness of Equipment (OEE)
Improving Overall Effectiveness of Equipment (OEE)
Through careful study, and benchmarking to similar companies, initiated on early year 2012 and with the
help with external consultant, it was found that KPC assets have not yet sweated , the overall effectivenessof equipment which were overall availability, usage and utilization were still relatively low compared toworld best practice. Further study also revealed that within digger-truck systems, the diggers capacitieswere in excess, while the trucks performances were the bottle-neck which needed to be enhanced .
Since mid of year 2012, a new project called Membara Project was established. This project aimed atimproving overall effectiveness of equipment (OEE) particularly it was first focusing on improving the OEEof overburden trucks. During first pass off Membara Project, the improvement initiatives to improve the
OEE were focused at two main division i.e. : Mining Operation Division (MOD) which has work force over3000 personnel, and Mining Support Division which maintain the mining fleet which supported by about1100 personnel. In MOD, Membara Project was focusing at improving OB trucks utilization on the biggestpit at that time, i.e. : Pit Bintang, while at MSD the focus was how to improve the physical availability of OBtrucks. At the end of year 2012, in MSD, after completing the project on OB trucks, the initiatives were thenrolled out to Improving Big Diggers and Support Equipment (dozer, grader) availability.
The first pass of Membara Project completed on mid of 2013, which then continued to 2ndpass which focus
on Cycle Time Project and Improvement on Drill and Blast.
The challenge for Membara Projects which are typical for other improvement initiatives is how to make allimprovement initiatives sustained not only during project but keep continues in the future until the life ofmine.
-
8/10/2019 KPC_Productivity Improvement 2014
17/37
1
Liebherr T282360 T = 32 Units
Frame-work of Membara Project
Mindsetsand
capabilities(MC)
Managementinfrastructure
(MI)
Managementinfrastructure maturity
"The formal structures, processes and systems
through which human and organizational
resources are managed and optimized to
achieve shared goals"
Performance management Organization design Continuous improvement infrastructure
Effective review mechanisms
Technical systems maturity
"The most efficient way
physical assets andresources are configured and
optimized to create value
and minimize losses"
OEE improvement Reducing lost time of
un-critical activities
Improving PhysicalAvailability (PA) of
trucks
Fleet dispatch Truck cycle time
management
Maintenance planningand execution
Mindsets and capabilitiesmaturity
"The way people think, feel and conduct themselves in the
workplace, both individually and collectively
Management training Frontline engagement Effective feedback
Membara framework focuses onimplementing new initiatives andensuring their sustainability, toachieve its goal
Notes: Impr oving OEE in
previous term is relat ively
s imi lar to improv ing overal l
uti l i zation of the equipm ent, i.e.
Util ization (KPC) = PA x Usage
Th G l f OEE I t
-
8/10/2019 KPC_Productivity Improvement 2014
18/37
1
Liebherr T282360 T = 32 Units
The Goal of OEE Improvement
A goal of attaining 63% OEEwith a stretch plan of 69%
OEE
All ops delays
System delays
Noncriticaldelays
Critical delays
Availabletime
BM2
PM1
Total
85
65
Current OEE Potential future
89
71
Availability
Utilization
57 63
Availability%
Utilization%
OEE%
Improvements
Improve availabilityfrom 85% to 89%
Improve MTTR Improve MTBF
Defectelimination
Bettercomunicationwith MOD
Improve utilizationfrom 65% to 71%
Improved shiftchange
Reduce nooperator
Reduce mealand pray delays Reduce time for
recovery afterrains
Improve haulroads
Improved availability
and efficiency resulting in
Improved OEE of 63%(stretch target 69%)
MC
MI
M b P j t i t t MOD MSD
-
8/10/2019 KPC_Productivity Improvement 2014
19/37
1
Liebherr T282360 T = 32 Units
Membara Project improvement process at MOD-MSD
Involving many line teams
and create official SOP
documents; these can
change after better insight
from implementation
Intensive Field Observationand involving line teams in
refining concept of initiatives
and lock changes by
creating official SOPs and
Change Managementdocuments
Also involving all neccesarystake holders : MOD-MSDstaff, Dispatch, Contractors,and OEMs
Multiple iterations on the SOPdocument were conductedwith all stakeholders to
ensure buy-in
Improving OB Truck OEE : the Initiatives development
-
8/10/2019 KPC_Productivity Improvement 2014
20/37
1
Improving OB Truck OEE : the Initiatives development
After multiple idea
generation session in
MSD, MOD and dispatch
a KPC Membara
operating model evolved
and new initiatives weredefined
Category
Manag-ement
Infrastruct
ure
Robust performance management system introduced that includes appropriate incentive systems andperformance dialogues
Refined organization structure that is aligned towards goal of the organization
Setup a Membara PMO team that will drive continuous improvement at KPC
Mindset &capabilities
Frontline engagement program to create awareness and generate momentum
Capability building curriculum targeted for Membara change managers and initiative champions
Specific technical training programs for operators, supervisors and mechanics
Reduced repair diagnostics time: Clear SOP on truck repair for operators Introduce new diagnosticians team Contractor management
Reduced repair preparation time: Portable in-car toolbox Mini ware-houses in pits In-pit hose fabricator
Reduced repair complete confirmation time
Reduced repair time: SMED for priority ideas
Defect elimination initiatives
New equipment strategy
Reduced repair response time: Staggered shifts for MSD
Improved workmanship
Technicalsystems
Improved hauling: Improved road maintenance Improved road construction and design
Improved loading: Refined loading SOPs and methods Defining optimal loading factors Matching shovel to truck body sizes
Improved dumping practices: Refine dumping SOPs
Improved shift change practices Newly defined shift change process and SOP
Reduction in time for meal and pray
Improved recovery from stops practices
Optimal interfaces between departments: MOD - MSD
Improve dispatch process and equipmentconfiguration
Improve end to end mine planning andexecution process
Make long term strategic mine planassumptions robust
Planning and dispatch (Mineplanning and Mine optimiza-tion)
Equipment availability (MSD- Haul trucks) Equipment utilization (MOD)A CB
Improving Utilization of MOD OB trucks
-
8/10/2019 KPC_Productivity Improvement 2014
21/37
2
Liebherr T282360 T = 32 Units
Improving Utilization of MOD OB trucks
Part of OB Trucks OEE Improvement at Mining Operation Division Areas is how to improve the utilizationof these Trucks. During Membara Projects and continues to recent time and to be sustained in the future,
there are 4 main areas focus of improving the utilization, that are :1.Shift Change process2.Meal and Pray Delay3.Wet Road Delays (Quick Start-up /Recovery after Rain : QSuar)4.No Operator Delay5.Improving Hauling (to reduce cycle time)These four main improvement initiatives at Mining Operation Division within Membara Project are knownas Ready MOD Project
Meal Pray
Shift Change
No Operator
Recovery from rain
Improve Hauling
Improving Shift Change Process
-
8/10/2019 KPC_Productivity Improvement 2014
22/37
2
Improving Shift Change Process
ImpactSolutionSituation
Baseline
Mar 2013
High shift change delaypre-implementation due
to: Operators take longtime in muster area
Operators take longto handover at shiftchange area
4.2
J
11.9
HT
17.4
BIG
6.9
1. Minimize operator time in muster area Operators spend minimal time in
muster area due to fingerprinting andupfront unit assignment
2. Clear truck assignment
Unit status and operator assignmentupdated before start of shift anddisplayed in muster area
3. Increase supervisor control in musterarea and shift change area
Supervisors are assigned to monitormuster area and shift change area
Clear responsibility to ensure operatorsget into trucks quickly
4. Hot handovers
Hot handover procedure implementedfor safe and efficient hand-over oftrucks from one operator to the next
initiatives implemented across all 3 pits Time lost reduced by 50% - 80%, equals to
0.25% to 1% of OEE
4.64.2
JHT
2.5
BIG
3.4
Initiatives Prioritization matrix
f Schedule PPE distribution
h Set up board to display truck location andoperator assignment in the muster area
i clear guidelines & target time for equip. handover
c Install siren in the muster area for efficiently
b Re-inforce supervisor authority
j Assign supervisor during shift change
a Remove benches from the muster area
d Effective safety briefing in manhaul/ muster area
e Develop & follow stdard format for safety briefing
g Clear assignment of transport for each panel
k Build shift change bays to accommodate trucks
l Build additional shift change area close to panels
m Road patrol to ensure trucks not slow down
Im-
pact
Ease of implementation
a
d
e
b ch
i j
f
m
g
kl
-
8/10/2019 KPC_Productivity Improvement 2014
23/37
2
Liebherr T282360 T = 32 Units
Shift Change : Remove Benches& Reinforce Supervisors Authority
Muster area processes
Benches in the muster area have been removedso that the operators moved quickly Supervisor uniform and equipment reflects theauthority and role he should have
Yellow PPE and different colored safety helmetmark the supervisor as different and gives himadditional authority responsibility (e.g., army rank)
Communication device is a must in order to beable to provide real time answers to problems
Light lamp allows supervisor to direct vehiclesinto the shift change area during the night
PPE distribution is scheduled once a fortnight orevery week in order to prevent inefficient process
Efficient attendance recording using fingerprint(applies only in selected pits)
Removing benches and reinforcing supervisors authority help expediting process in muster area
Improving Meal Pray Process
-
8/10/2019 KPC_Productivity Improvement 2014
24/37
2
Liebherr T282360 T = 32 Units
Improving Meal Pray Process
Impact
33.3
PitJHT
46.2
35.9
10.3
BIGPitJ
37.3
26.2
11.0
HT
22.9
14.4
8.5
BIG
27.1
17.7
9.4
1. Staggered Meal and Praybreaks
Optimal schedule withstaggered breaks with eachback-up operator covering
more trucks than previously
2. Shadow crew enforcement
Shadow crew is enforcedworking according to shift
and new working hours from6 to 6 to improve shift change
3. Back-up allocation and
visibility
Operators from breakdownunits utilized as back-ups and
allocated optimally
4. Revised roles and responsi-bilities
Specially created pondoksupervisors manage back-up
process in the pondoksupported by dispatch
5. Hot handovers
Hot handover procedureimplemented for safe and
efficient handover of trucksfrom one operator to the next
SolutionSituation
Apr-Jun1 Sep- Feb2
High meal pray delayobserved pre-
implementation due tounregulated break time and
poor back-up allocation
33.3
14.2
PitJ4
8.7
5.5
HT3
13.9
8.8
5.1
BIG
13.7
7.9
5.8
Apr 2013
Pray
Meal
Meal Pray Initiative wasimplemented across all 3pits in MarApr 2013
Good impact from theinitiative has been seenwith the delay reduced tobelow budget figures inall 3 pits
H:\Personal\Harold Ong\Indonesia\PGN\IPO\Legal DD Presentation.ppt - May 20 2003 - 23:24 /2
Staggered Meal pray using a floating back up system
-
8/10/2019 KPC_Productivity Improvement 2014
25/37
22
Staggered Meal pray using a floating back-up system
Key design decisions in staggering meal and pray breaks
Principles Benefits
5-6 configuration canmeet the constraint on
spread of break variation possible to implement
this configuration for alltrucks at a 3.72 manningratio
Details of implementation
1 back-up operatordeployed for every 5
trucks for maximumcoverage at availablemanning ratio withinacceptable break window
3Break
schedule
Saving in time lost due topray delay. Forexample,in the day shift,in addition to meal, the 2breaks cover Dzuhur andAshar prayers
Cycle time loss due toadditional travel topondok are reduced
Optimal schedule withstaggered breaks areimplemented
2 x 30 mins duringday shift
1 x 1 hr during thenight shift
Savingcycle time due toreduction in handovers
Equal working hours forall operators
All operators man oneequipment after the otheras back-ups instead of
using designated back-up operators
Floatingback-up
system
2
5:6
configura-tion
1
New pondok supervisor roles have beencreated to provide additional manpowerfor managing Meal pray process
H:\Personal\Harold Ong\Indonesia\PGN\IPO\Legal DD Presentation.ppt - May 20 2003 - 23:24 /2
Staggered Meal pray (continue)
-
8/10/2019 KPC_Productivity Improvement 2014
26/37
22
Advantages of fixed back-up system
Advantages of floating back-up systemProblem of operatorsrefusing to man trucks inpoor condition can be
avoided
Complexity of kimpermanagement can be
reduced by designating
mutli-kimpered operatorsas back-up
Easy to implement as itsclose to current practice
Feeling of equipmentownership by primaryoperators, potentiallyreducing maintenance
issues
Elimination of cycle timeloss due to back-ups
returning after each breakslot to pondok (~ 5
mins/truck)
Potential opportunity ofidentifying operators whodont maintain trucks in
good condition as theycan be reported by others
Staggered Meal pray (continue)
Due to the saving incycle time, floatingsystem for back-upsis preferred over thefixed system
Meal Pray Delay : min/avail.unit/shift
Improving Physical Availability component initiatives
-
8/10/2019 KPC_Productivity Improvement 2014
27/37
2
Liebherr T282360 T = 32 Units
Improving Physical Availability component initiatives
Diagnostics time
Repair time
Confirmationtime
Response time
Preparation time
Planningimprovements
Opportunitymaintenance
Equipmentstrategy
IncreaseMTBF
IncreasePhysical
Availabilityof Trucks
ReduceMTTR
Focus area Components
Defectelimination
1
2
1a
1b
1c
1d
1e
2a
2b
2c
2d
9 areas of focus forImproving Physical
Availability of OBTrucks
We can break down
Physical Availabilityinto 9 components
To ensurecomprehensiveness,we should generateinitiatives around allthese components
PA = 1(MTTR/MTBF)
Reduce Response Time (Improve MTTR of OB Trucks)
-
8/10/2019 KPC_Productivity Improvement 2014
28/37
2
Liebherr T282360 T = 32 Units
Reduce Response Time (Improve MTTR of OB Trucks)
Ideas implemented to reduce staff
unproductivity during shiftchangeover
After, we have reduced this unproductivetime by up to 25%
New shift change processBefore, mechanics dont work for a
full 65 minutes after shift change
Total 65
Prayer 24
PPE preparation 5
Other discussions 6
Discussion andjob distribution
7
Daily PA update 2
Fatigue Control 2
Safety talk 5
Travel time fromworkshop 14
44
5
Total
Discussion andjob distribution
2PPE preparation
Daily PA update 2
Fatigue Control 2
Safety Talk 4
Prayer 15
Travel time fromworkshop
14
Al l d iscussions done outdoors,
reducing unn ecessary activi t ies
(remo val of s hoes, irrelevant
d iscussions)
21 mins reduction inmechanics
unproductivity
Staggered
praying from
the start
Improve Shift Change and no labor-mechanic available
-
8/10/2019 KPC_Productivity Improvement 2014
29/37
2
Liebherr T282360 T = 32 Units
p o e S t C a ge a d o abo ec a c a a ab e
Prayer rooms set up at Maintenance Inpit Bases toreduce time needed to start-up during over shift period
Up to 15minutes iswasted every
beginning ofshift due topraying inbatches
Small prayerrooms arebottleneckfor fasterstart-up time
Prayer rooms are ready and in use
Total of 2 prayer rooms areprepared: at In-Pit Maintenancebases
New SOP for truck repair location has significantlyreduced no labour available category in our MTTR
much easier now to
superv ise my m echanics-Supervisor
We have bet ter access
to parts and supp ort
equipment
44
66
(AugSept)
-33%
Baseline(AprJune)
No labour available Inpit
Maintenance BintangNew SOP for truck
repair location wasimplemented
Truck operatorsnow know thatthey alwaysneed to go to pitbase except for:
Engineproblems
Brakeproblems
Steeringproblems
Safety belt
Previously, truckoperators areunsure ifoperating thetruck will makecondition worse
now we are easier
finding the trucks
Improve Repair Time (MTTR) : SMED analysis
-
8/10/2019 KPC_Productivity Improvement 2014
30/37
2
Liebherr T282360 T = 32 Units
Improve Repair Time (MTTR) : SMED analysis
Description
Video-takingand baselining
Duration
1-3 days
3-4 weeks total
Video analysisand creation of
newprocedures
3-4 days
Trial of newprocedures
1-3 days
Evaluation oftrial
3-4 days
Creating newservice sheetsand standard
jobs
2 days
Video taking following each of the mechanics on duty Categorization of tasks and baselining total time
required for the job
Analysis of video based on externalization,parallelization, tweaking sequences, and removinginternal waste
Identification of new tools and support equipmentsneeded
Mechanics training for new processes Live trial of new processes on the ground (videotaped)
Re-evaluation of trial, refinement of time taken based onsecond observation
Re-evaluation of new tools and support equipmentsneeded
Standardization of new processes and documentationin standard jobs and service sheets
Improve Repair Time (MTTR) : SMED example Result
-
8/10/2019 KPC_Productivity Improvement 2014
31/37
3
Liebherr T282360 T = 32 Units
p p ( ) pIdeas and new toolsCAT 789 250 hours service
Impact 1/2
Compressor Trolley
Oil filter with bottle samples
Compartment
2 ladders with air filter platform
Stocks of nipples & hoses
Double punch
Operator chair
20 m air hose
Additional tools and facilities needed
Inform operator beforehand, mechanic to drive to end of pitbase with operator waiting
2
Merge electrical, steering and AETA checks5
Do both air filter replacement in parallel (2 ladders, 2mechanics)
6
Oil condition to be checked in parallel7
Ideas
Create inventory for top 10 defective parts10
Mechanics to do light checks while parking to bay4
Mechanics to do steering check while driving to bay8
Create space in ladder to keep old air filter9
Use slide hammer to increase oil flow11
Prepare a trolley and keep it close to truck ready with filter oil13
Put aside old air filter only after the truck has left12
Trolley should contain empty bottles for engine oil sample14
Just before parking we should lift the body up, inspect, andthen park instead of doing at the end
3
1 Ask technicians to handover truck at the entrance of pit base
Process/sequenc-
ingtweaks
Paralleli-zation
Better
supporttools
Externali-zation
Air fi l ter already
placed on top of the
customized ladder
New container and
better oi l draining
too l
The Result of Improvement of OB Trucks OEE
-
8/10/2019 KPC_Productivity Improvement 2014
32/37
3
Liebherr T282360 T = 32 Units
p
The OEE of OB Trucks has been steadily improving from the base-line of about 55%, in current days it isnow more than 65%. Since the completed project of Membara Phase-2 (May-13), for about one year, anaccumulative total cost saving of about 48 million dollars has been generated coming from theimprovement of the OEE of Overburden Trucks at KPC
Improve Operators & Mechanic Discipline through PKU
-
8/10/2019 KPC_Productivity Improvement 2014
33/37
3
Liebherr T282360 T = 32 Units
p p p g
Starting early month of year 2013 until the end of year, more than 2400 operators, mechanic and supervisorswere being sent to military training program called PKUprogram at the Army training center at Cilodong,West Java. This programs aims at improving their moral, discipline and team-work which induce to
better effectiveness and efficiency of work. This Training program were subsequently scheduled into 8batches . On each batch, they were about 300 employees participated. The period of training was about 3weeks.
KPC used the momentum/opportunity of overflowoperators during parking of many equipment bysubsequently sending the work forces to this militarytraining program
Semi Military Training (PKU) Results
-
8/10/2019 KPC_Productivity Improvement 2014
34/37
3
Liebherr T282360 T = 32 Units
y g ( )
Untung Suhartanto : A Refueling Superintendent, used to smoke a lots (addicted toit), after PKU program he smoke no more, after he dicipline himself during 3 weeks
military training at Cilodong
Many operators testified that their discipline at works and team work has increased
significantly after PKU program
How to Sustaining KPU result ?
1. A mandatory for each supervisor to conduct apel siaga of their subordinates(operators/mechanic) at the scheduled roster
2. Conduct a survey feed back from the alumni of PKU
3. Sport Competition among PKU alumni held regularly4. Conduct a Workshop for Supervisors regarding the PKU result and benefit5. Always endorsing at every occasion for all workforces to implement the 7 Values of the
company : Excellence, Integrity, Transparency, Agility, Empowerment, Team Work & Care
More operators and mechanic were eventually quitted to smoke, furthermore KPCmanagement has been endorsing and proclaiming that by early of year 2015, all KPCwork sites, not only in the office building but also outside at mining site, at workshop
and the vicinity, on the work areas no body is allowed to smoke.
Sustainability of Improvement : Develop new structure
-
8/10/2019 KPC_Productivity Improvement 2014
35/37
3
Liebherr T282360 T = 32 Units
Sustainability is a classical issue facing by every improvement initiatives, in order to sustain the process and results
of improvement initiatives, KPC executives deliberately has developed new structure on MOD and MSD which
called Continuous Improvement (CI) Lead and CI-specialist. Structurally these CI-Lead and CI Specialist are
reported to GM MOD and MSD, but horizontally they are on close coordination with existing Business PerformanceImprovement Division (BPID) which has been established since 2008.
Additionally to strengthen the culture of improvement in the company, the COO of KPC since Q4 2013, has been
given a strong direction that for any promotion from supervisor level to higher position (superintendent), beside that
the candidate should be seconded first at Safety Division, he or she should also be seconded at BPID to be directly
assigned to project improvement tasks within at least 6 months.
Continuous Improvement (CI) Academy Projects
-
8/10/2019 KPC_Productivity Improvement 2014
36/37
3
Liebherr T282360 T = 32 Units
BATCH-1 : Nov 2013 - May 2014
CI Academy Divisi Asal Mentor-Co Mentor Project Task Potential Saving ( million dollars)
1 Sumarjono MOD -MO Anwar-Ambara Queuing Project 0.2
2 Iswanto MOD- HT Anwar-Deni Improve Shift Change (additonal load during s.change) Intangible
3 Denastry MOD-BIG Anwar-Ambara Improve Payload T282 1.6
4 M Yanuar Hidayat CPHD Ambara-U.Suhartanto Improve Payload EH4500 3.0
5 Zulfikar S MOD-PitJ Anwar-Ambara Fuel Efficiency Project Part -4 3.6
6 Bachtiar Hidayat MSD Chairal S- U.Suhartanto OB truck (planning isiatif, inpit hose fab.) + SMK Intangible
7 Sahirul Alim MSD Ilham S-Marzel P.Excavator , support equipment, Defect Elimination of
Cat789&EH4500 Intangible
Total Projects 8.4
BATCH-1 : August 2014 - Feb 2015
CI Academy Divisi Asal Mentor Project Task
1 Adi Setyo Utomo MSD Untung S Mews Performance Improvement
2 Raymond Lasor Bosar Ritonga MSD Untung S WO Closure and Labor Costing
3 Irwansyah MSD Untung S Land Cruisher PA Improvement
4 Muhammad Kurniawan MOD Ramli Denas + Anwar Improve Productivity of R9800
5 Hermanto MOD Deni apriadi + Anwar Improved produksi MS Rehab
6 Galuh Boyo Munanto HSES Kris Pranoto+Ambara Water Quality Improvement
7 Wahyu Wardana HSES Kris Pranoto+Ambara Rehabilitation Quality Improvement
Future Challenges
-
8/10/2019 KPC_Productivity Improvement 2014
37/37
3
Liebherr T282360 T = 32 Units
Will take time to achieve a real Culture of Continuous Improvement
Long term goal ofcontinues improvement ishow to make improvement
become day-to-day practice
of doing business of everyindividual in the company
END of Presentation