koodaideri project - mining newspilbara iron company (services) pty ltd level 18, central park...
TRANSCRIPT
Level 18, Central Park 152-158 St Georges Terrace Perth WA 6000 © Copyright 2018 Rio Tinto
www.worleyparsons.com
RIO TINTO PROJECTS
Koodaideri Project Koodaideri Processing Plant Works Approval Application
Licence Amendment Supporting Documentation Works Approval – Pelican Pelican Camp Waste Water Treatment Plant Supporting Documentation
Koodaideri Exploration Pelican Camp – L8562/2011/1
Project No 201012-00702
Document No. KD-9900-H-REP-00005
20 December 2018
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
Koodaideri Project – KD-9900-H-REP-00005
Rev Description Original
Review WorleyParsons
Approval Date
Customer Approval
Date
0 Issued for Use 20-Dec-18 20-Dec-18
D Pearse N Simcock B McLernon J Whitburn
KD-9900-H-REP-00005_0.DOCX
ii
Disclaimer
This report has been prepared on behalf of and for the exclusive use of Rio Tinto Projects, and is subject to and
issued in accordance with the agreement between Rio Tinto Projects and WorleyParsons. WorleyParsons
accepts no liability or responsibility whatsoever for it in respect of any use of or reliance upon this report by any
third party. Copying this report without the permission of Rio Tinto Projects or WorleyParsons is not permitted.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
Works Approval Application Supporting
Documentation
Koodaideri Iron Ore Mine
December 2018
RTIO-HSE-0327750
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
iv
Disclaimer and Limitation
This report has been prepared by Rio Tinto Iron Ore (Rio Tinto), on behalf of Pilbara Iron
Company (Services) Pty Ltd, specifically for the Koodaideri Iron Ore Mine. Neither the report
nor its contents may be referred to without the express approval of Rio Tinto, unless the report
has been released for referral and assessment of proposals.
Document Status
Rev Author Reviewer/s Date Approved for Issue
Signed Date
1 Worley Parsons
Leisa Turner, Sean Savage
20 Dec 2018 20/12/2018
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
iii
TABLE OF CONTENTS
Disclaimer ............................................................................................................................. 2
1 Licensee Information ............................................................................................ 1
1.1 Occupier Details ...................................................................................................... 1
2 Premises Details .................................................................................................... 2
2.1 Prescribed Activity Overview ................................................................................... 2
2.2 Legal Land Description ............................................................................................ 2
2.3 Location and Siting .................................................................................................. 2
2.4 Topography ............................................................................................................. 8
2.5 Water Resources ..................................................................................................... 8
2.6 Hydrogeology .......................................................................................................... 8
2.7 Geology ................................................................................................................... 8
2.8 Fauna ...................................................................................................................... 9
2.9 Vegetation and Flora ............................................................................................... 9
2.10 Stakeholder and Community Consultation ............................................................... 9
3 Prescribed Premises Category ........................................................................... 11
3.1 Current Environmental Protection Act 1986 (Part V) Licences / Works Approvals . 11
3.2 Other Approvals / Licences ................................................................................... 12
4 Process Description ............................................................................................ 14
4.1 Overview ............................................................................................................... 14
4.2 Design and Operation ........................................................................................... 14
4.3 Timescale for Construction / Operation ................................................................. 22
4.4 Commissioning and Reporting ............................................................................... 22
5 Risk Identification and Assessment .................................................................. 23
6 Emission Management ........................................................................................ 27
6.1 Air Emissions (excluding dust) ............................................................................... 27
6.2 Dust Emissions ..................................................................................................... 27
6.3 Noise ..................................................................................................................... 29
6.4 Odour Emissions ................................................................................................... 30
6.5 Light Emissions ..................................................................................................... 31
6.6 Discharge to Water ................................................................................................ 31
6.7 Discharges to Land ............................................................................................... 32
6.8 Hydrocarbon Management .................................................................................... 34
6.9 Solid/Liquid Waste ................................................................................................. 34
6.10 Flora and Fauna .................................................................................................... 35
7 Rehabilitation and Closure ................................................................................. 36
8 Project Costs ....................................................................................................... 36
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
vi
9 Summary of Commitments ................................................................................. 37
A Drawings .............................................................................................................. 40
TABLES
Table 2-1 Coordinates (MGA Zone 50) of the Koodaideri Mine Proposed Prescribed Premise Boundary ............................................................................................................ 6
Table 2-2 Sensitive Land Uses and distance from prescribed activity ................................... 6
Table 2-3 Specified ecosystems ........................................................................................... 7
Table 2-4: Other landscape features, relevant factors or receptors ....................................... 7
Table 3-1 Proposed prescribed premise categories .......................................................... 11
Table 3-2 Prescribed premise category details under Part V licence L8562/2011/1 .......... 11
Table 4-1 Inputs to the process plant .................................................................................. 17
Table 4-2 Outputs from the process plant ........................................................................... 17
Table 5-1: Risk Rating Matrix ............................................................................................. 23
Table 5-2: Consequence Matrix ......................................................................................... 24
Table 5-3: Likelihood Matrix ............................................................................................... 24
Table 5-4: Risk Assessment .............................................................................................. 25
Table 8.7-1: Project Costs ................................................................................................... 36
FIGURES
Figure 2-1: Koodaideri Iron Ore Mine Location ...................................................................... 3
Figure 2-2: Koodaideri Project Location ................................................................................ 4
Figure 2-3: Koodaideri Proposed Prescribed Premises Boundary ......................................... 5
Figure 4-1: Koodaideri Processing Plant Flow Sheet........................................................... 16
Figure 4-2: Koodaideri Primary Crusher .............................................................................. 18
Figure 4-3: Secondary Crushing Facility.............................................................................. 18
Figure 4-4: Product Screening Facility ................................................................................ 19
Figure 4-5: Stockyard Cross-Section ................................................................................... 20
Figure 4-6: Surge bin outlet and charge gates removal method .......................................... 21
APPENDICES
A Drawings .............................................................................................................. 40
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
v
Abbreviations
BWT Below Water Table
CEMP Construction Environmental Management Plan
DWER Department of Water and Environmental Regulation
DMIRS Department of Mines, Industry Regulation and Safety
EPA Environmental Protection Authority
EPBC Act Environment Protection and Biodiversity Conservation Act 1999 (Commonwealth)
EPAS EPA Services (branch of DWER)
HG High-grade
HSEQ Health, Safety, Environment and Quality Management System
km Kilometre
m Metres
PDWSA Public Drinking Water Source Area
PER Public Environmental Review
PLNB Pilbara Leaf-nosed Bat
ROM Run of Mine
SOP Saleable Ore Product
TLO Train Load-out
WFSF Waste Fines Storage Facility WRC Western rail Corridor
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
1
1 Licensee Information
1.1 Occupier Details
The occupier (the Licensee) of the land subject to this works approval application is:
Pilbara Iron Company (Services) Pty Ltd Level 18, Central Park 152-158 St Georges Tce Perth WA 6000 ACN: 107 210 248 The Proponent is Pilbara Iron Company (Services) Pty Ltd, wholly owned subsidiary of Rio Tinto. The proposed works are being undertaken in the Shire of East Pilbara and Shire of Ashburton. The contact person for the licence amendment is as follows: Sean Savage Superintendent, Government Approvals Rio Tinto Level 18, Central Park 152-158 St Georges Terrace Perth WA 6000 Telephone: (0)8 6213 1254 M: (0)467 776 204 Email: [email protected]
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
2
2 Premises Details
2.1 Prescribed Activity Overview
This application is for the proposed construction and commissioning of an iron ore processing
facility comprising a primary crusher, screenhouse, secondary crusher, stockyard, train
loadout and related conveyor and ancillary systems at the Koodaideri Mine site. The
application also includes two mobile crushing and two mobile screening plants to be used
during construction only.
2.2 Legal Land Description
The Koodaideri Iron Ore mine (The Project) and processing facility is located on AML70/00252
(ML252SA) held by Mount Bruce Mining Pty Ltd and the pending Special Rail Licence being
obtained by Hamersley Iron Pty Limited (a subsidiary of Rio Tinto) pursuant to clause 10N(6)
of the Hamersley Range State Agreement. Minor facilities will also be located on pending
L47/00701 held by Mount Bruce Mining Pty Ltd.
Pilbara Iron Company (Services) Pty Ltd (a subsidiary of Rio Tinto) provides extensive
corporate and site services to Rio Tinto owned entities (including Hamersley Iron Pty Limited
and Mount Bruce Mining Pty Ltd) in the Pilbara, including the operation of Rio Tinto mines.
Pilbara Iron Company (Services) Pty Ltd is therefore the licence holder for the Koodaideri
mine.
2.3 Location and Siting
2.3.1 Location Context
The Koodaideri Iron Ore mine is located approximately 110 kilometres (km) northwest of
Newman in the Pilbara region of Western Australia (Figure 2-1).
The premises are located on the northern margins of the Hamersley Range and includes the
level plains immediately north of the range. The Hamersley Range escarpment is aligned in
a west-north-west to east-south-east direction, rising approximately 120 metres (m) above the
plain in the vicinity of the premises site. The proposed processing plant lies approximately 22
km to the east of the Karijini National Park and the Fortescue Marsh is located approximately
7km north of the site (Figure 2-2).
Table 2-1 lists the approximate boundary coordinates of the Koodaideri iron ore proposed
prescribed premise boundary. The proposed processing plant will have a footprint area of
approximately 54 ha within lease AML70/00252 (ML252SA) pending Special Rail Licence and
pending L47/00701 as shown in Figure 2-3. The two mobile crushing and two mobile screening
plants will also be located in the same area.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
3
Figure 2-1: Koodaideri Iron Ore Mine Location
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
4
Figure 2-2: Koodaideri Project Location
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
5
Figure 2-3: Koodaideri Proposed Prescribed Premises Boundary
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
6
Table 2-1 Coordinates (MGA Zone 50) of the Koodaideri Mine Proposed Prescribed Premise Boundary
2.3.2 Sensitive Land Uses
The distances to residential and sensitive receptors are detailed in Table 2-2. The closest
residential area to the premises is the township of Newman 110 km to the south-east, which
had a population of 6,162 in 2014 (Australian Bureau of Statistics, 2016).
The Premises Village is 7.5 km to the south east of the facility and within the Premises
boundary, however as this facility is operated by the Licence Holder the Premises Village is
not considered to be a sensitive land use or receptor.
Table 2-2 Sensitive Land Uses and distance from prescribed activity
Sensitive Land Uses Distance from Prescribed Activity
Closest residential zoned premises is
Marillana Station Homestead
33 km from the eastern edge of the prescribed
premises boundary.
Closest recreation zoned premises Approximately 22 km from the premises to the
eastern boundary of Karijini National Park.
Fortescue Marsh Approximately 8 km north of the premises to the
nearest mapped boundary.
2.3.3 Specified Ecosystems
The distances (within a 30 km radius) to specified ecosystems are shown in Table 2-3.
ID Easting (m) Northing (m)
1 707,332 7,511,974
2 706,744 7,510,695
3 704,841 7,511,566
4 702,359 7,506,423
5 702,521 7,506,347
6 702,434 7,506,168
7 714,549 7,500,559
8 717,148 7,505,934
9 714,713 7,507,048
10 712,570 7,509,684
11 707,332 7,511,974
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
7
Table 2-3 Specified ecosystems
Specified ecosystems Distance from Prescribed Premises
Parks and Wildlife tenure Approximately 22 km from the premises to the eastern
boundary of Karijini National Park.
Public Drinking Water Source
Area (PDWSA)
There are no PDWSAs located within 30 km of the
premises.
RAMSAR wetland – Fortescue
Marsh
Approximately 8km north of the premises to the nearest
mapped boundary.
Geomorphic Wetlands No geomorphic wetlands are located within 30 km of the
premises.
Threatened Ecological
Communities and Priority
Ecological Communities
The premises boundary intersects with the buffer zone of
the Priority 1 Fortescue Marsh Priority Ecological
Community
Declared Rare Flora There are no Declared Rare Flora within the Premises.
Lepidium catapycnon (previously Declared Rare Flora,
now Priority 4) is located adjacent to the Premises.
2.3.4 Other environmental receptors
Environmental receptors relevant to the premises are provided in Table 2-4.
Table 2-4: Other landscape features, relevant factors or receptors
Other receptors or areas of concern Location
Koodaideri Spring Located 4.1 km from the processing plant.
Pilbara Orange Leaf-nosed bat
(Rhinonicteris aurantius)
A colonised adit is located approximately 2.5 km
south west from the primary crusher
Northern quoll (Dasyurus hallacatus) Recorded in the Project Area.
Pilbara Olive python (Liasis olivaceus
barroni)
Recorded in the Project Area.
Trogolofauna Zones Located within the mine pit area and not within
the footprint of the prescribed premises
boundary.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
8
2.4 Topography
The Project mine site is located on the northern margins of the Hamersley Range and includes
the level plains immediately north of the range. The Hamersley Range escarpment is aligned
in a west-north-west to east-south-east direction and rises to approximately 120 m above the
plain level in the vicinity of the Project mine site. The ground level falls towards the Fortescue
River Basin to the north-east. The portion of the Hamersley Range containing the proposed
prescribed premises location is rugged and rocky, giving rise to an irregular network of
ephemeral streams. The plateau containing the ore resources is incised by a series of gullies
that drain into ephemeral creeks on the plains below.
2.5 Water Resources
The mine processing area lies within the Upper Fortescue River catchment. All of the creek
systems within the Upper Fortescue River catchment are ephemeral. Creekline flows are
generated following significant rainfall events, which generally occur between December and
July. Sub-catchments south of the Fortescue River Valley (including the headwaters of the
Fortescue River, Weeli Wolli Creek, and to a lesser extent Coondiner Creek, Mindy Creek and
other smaller creeks) contribute surface water and sediments into the Fortescue Marsh.
The Fortescue Marsh is a nationally and internationally important wetland, and is located to
the north of the Project development area. At its closest, the premises boundary is
approximately 8 km from the mapped boundary of the Fortescue Marsh.
The Koodaideri deposits are intercepted by deeply incised gullies that characterise the
Hamersley Ranges. Surface water drainage occurs within defined water courses during and
immediately following large, extended duration or high intensity rainfall events. High surface
water infiltration is expected to occur within alluvial creek beds on the lower slopes of the
Hamersley Range and adjacent plains. Surface water runoff in the mine processing area
commences via weakly defined tributaries in shallow bedrock/gravelly soils that then drain into
thicker alluvium/colluvium sequences in the incised valley systems. Water courses in the
incised valleys facilitate ephemeral surface water flows typically after large or intense rainfall
events. Smaller rainfall events are likely to generate sub-surface flow in the loosely
consolidated gravelly stream beds. Stream drainage systems gradually multiply and become
shallower due to flat relief as they continue northwards towards the Fortescue Marsh.
2.6 Hydrogeology
Local groundwater is fresh and is approximately 70 m below ground level in the area of the Processing Plant. Water quality is fresh with electrical conductivity between 412 and 420 µS/cm. There are no nearby users of groundwater in the area.
2.7 Geology
The Project area lies within the Hamersley Range which is principally comprised of rocks of
the Brockman Iron Formation. Further north is the broad expanse of the Fortescue Valley,
which was formed by the preferential erosion of the Wittenoom Formation and includes deep
layers of Cainozoic sediments.
The Koodaideri mine area contains martite-geothite mineralisation predominantly within the
Dales Gorge Member of the Brockman Iron Formation, with lesser mineralisation in the Joffre
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
9
Member. A variable thickness hydrated capping overlies the deposits, which is permeated with
numerous cavities. The orebody is underlain by the Mount McRae Shale and Mount Sylvia
Formations.
2.8 Fauna
Several species of conservation significance are found within the overall project development
footprint. Impacts on the Pilbara Leaf-nosed Bat (PLNB), Pilbara Olive Python and Northern
Quoll have been assessed and will be managed through relevant conditions in MS999. In
terms of Short Range Endemics species, large exclusion zones have been implemented to
protect trogolofauna in the Project area in accordance with MS999.
The habitat types present in the Processing Plant development footprint are considered to be
well represented in the local and regional area. The same land systems are found outside the
Development Envelope, including within the nearby KNP.
Koodaideri spring and the K75W adit/cave system are important habitat for Pilbara Leaf-nosed
Bat, Pilbara Olive Python and Northern Quoll and have been designated as development
exclusion zones to minimise the risk of impacting on this important fauna habitat.
2.9 Vegetation and Flora
Vegetation communities within the immediate area consist of mixed Acacia species, Hakea
chordophylla, and Grevillea wickhamii, tall open shrubland over Triodia lanigera, T. pungens
and open hummock grassland.
There are two flora species of elevated conservation value within the overall development
area: Lepidium catapycnon and Synostemon hamersleyensis. The closest of these species to
the processing plant is located 1200 m from the primary crusher. Neither species will be
impacted by the construction or operation of the processing plant and all recorded populations
are protected by development exclusion areas.
The vegetation of the Koodaideri Spring Gorge is of conservation significance as it provides
key habitat for a number of fauna species including the Pilbara Leaf-nosed Bat, Pilbara Olive
Python and Northern Quoll. As required by MS 999 an exclusion zone has been implemented
to protect Koodaideri Spring Gorge and an approved adaptive management plan implemented
to monitor and respond to any changes in the hydrology of Koodaideri spring.
2.10 Stakeholder and Community Consultation
2.10.1 Community Consultation
Rio Tinto has a long-term commitment to working with Pilbara communities. Specific
consultation strategies and initiatives are outlined within the Annual Sustainable Development
Report.
All stakeholders consulted during the preparation of the Public Environmental Review (PER)
were provided with details of the Koodaideri project key characteristics, including mining,
processing and infrastructure requirements, and the environmental studies undertaken. This
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
10
consultation process provided stakeholders with details of the works for this Works Approval
application.
Key government agencies actively consulted with during the preparation of the PER include:
• EPA; • Department of Water and Environmental Regulation (DWER); and • Department of Mines, Industry Regulation and Safety (DMIRS). • Local government organisations (Shires of Ashburton and East Pilbara)
Key non-government stakeholders who were consulted during the preparation of the PER include:
• Youngaleena Aboriginal Community; • Banjima People; • Yindjibarndi People; • Mulga Downs Station; • Mt Florence Station; and • Coolawanyah Station.
Rio Tinto has sought to keep relevant stakeholders up-to-date with studies relating to planned mining activities.
2.10.2 Aboriginal Heritage
The Koodaideri Mine Plant Area is located within the traditional lands of the Banjima People.
The identification and management of cultural heritage within the traditional lands of the
Banjima Traditional owners is in accordance with the principles and practices outlined within
Rio Tinto’s Communities and Social Performance Guidelines, the Rio Tinto Cultural Heritage
Group Procedure.
In relation to this works approval, detailed Aboriginal heritage surveys, both archaeological
and ethnographical, have been undertaken with approved representatives from native title
claimant groups in the proposed development footprint.
There are no heritage sites within the vicinity of the screen house or stockyard. Six aboriginal
heritage sites have been identified within 1 km of the proposed primary crusher. All of the sites
at risk of impact are the subject of a Section 18 application under the Aboriginal Heritage Act
1972. One site is located within the footprint of K58W ROM Pad with another site within 30 m
of the K58W ROM Pad. Two sites are within the design of a heavy vehicle haul road. The
remaining two sites will not be impacted by the proposed works and will be fenced in
accordance with Rio Tinto’s Heritage Site Fencing Procedure (RTIO-HSE-0121790).
.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
11
3 Prescribed Premises Category
The proposed facility is considered to be an activity defined by Schedule 1 of the
Environmental Protection Regulations 1987 (as amended) and detailed below in Table 3-1.
DWER have advised during project scoping discussions that the processing plant should be
constructed and commissioned under a works approval, followed by an amendment to existing
operating licence L8562/2011/1 (Koodaideri Exploration Camp). The mobile crushing and
screening plant will be installed, commissioned and operated under the same works approval
as the activity is required immediately for construction works to commence and involves
minimal commissioning. This approach was discussed and agreed during scoping meetings
with DWER.
The mine plant is expected to process 43 million tonnes per year of iron ore by crushing and
screening coarse ore to a saleable product. The mobile crushing and screening plant is
required during the construction of the mine plant to facilitate earthworks.
Table 3-1 Proposed prescribed premise categories
3.1 Current Environmental Protection Act 1986 (Part V) Licences / Works Approvals
The Licensee currently holds Part V Operating Licence L8562/2011/1 (expiry date
18/03/2030), with categories shown in Table 3-2. The current licence for the Koodaideri
Exploration Camp includes a putrescible landfill, two waste water treatment plants and
associated sprayfields Once works for the mine plant are completed this licence will be
amended to include the operation of the mine plant (Category 5) and ongoing use of mobile
crushing and screening plants (Category 12) as required.
Table 3-2 Prescribed premise category details under Part V licence L8562/2011/1
Category
number
Category Description Category Premises Production or
Design Capacity
5 Processing or beneficiation of metallic or non-metallic ore
>50,000 tonnes per year 43 million tonnes per year
12 Mobile crushing and screening plant.
>50,000 tonnes per year 10 million tonnes per year
Category
number
Category Description Category Premises Production or
Design Capacity
54 Sewage facility 100 cubic metres or more per
day
418.5 cubic metres per day
64 Class II putrescible
landfill site
20 tonnes or more per year 2000 tonnes per year
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
12
3.2 Other Approvals / Licences
3.2.1 Part IV of the Environmental Protection Act 1986
Background
Rio Tinto referred a proposal to the Environmental Protection Authority (EPA) on 28 May 2012
to develop and operate an open pit iron ore mine, rail corridor and associated infrastructure at
the Premises.
The level of assessment was set by the EPA as a PER. The PER was reviewed by the EPA
and the Report and Recommendations of the EPA (EPA Report 1533) were submitted to the
Minister for Environment for approval. Approval was granted through Ministerial Statement
999 on 10 March 2015 for the project to be implemented.
The proposal was also referred to the former Department of Sustainability, Environment,
Water, Population and Communities (DSEWPaC) (now the Department of Environment and
Energy) for consideration under the Commonwealth Environment Protection and Biodiversity
Conservation Act 1999 (EPBC Act) on 5 June 2012. DSEWPaC determined that the proposal
was a ‘controlled action’ and subject to a bilateral assessment coordinated by the Government
of WA. The proposal was approved under the EPBC Act on 9 May 2015 through instrument
reference EPBC 2012/6422.
Ministerial Statement 999
Ministerial approval was granted 10 March 2015 under Ministerial Statement 999 to construct
and operate an iron ore mining area and associated infrastructure at the Premises. This
included the construction and operation of a rail corridor, high voltage power transmission line,
airstrip and accommodation facilities.
Relevant to Part V of the Environmental Protection Act 1986, EPA’s assessment (EPA Report
1533) determined that the impacts from the Project could be adequately managed and issued
Ministerial Statement 999 with conditions to ensure that:
(a) The proposal is implemented in a manner that maintains the Pilbara Leaf-nosed
Bat colony which resides within the K75W adit/cave system;
(b) Troglofauna are protected by excluding mining and infrastructure placement within
a significant portion of troglofauna habitat;
(c) Mine construction and operational activities are carried out in a manner that
minimises impacts to the Northern Quoll;
(d) Mining and infrastructure is sited in a manner that avoids the Declared Rare Flora,
Hamersley Lepidium;
(e) The proposal is implemented so that it does not affect the viability of the Priority 1,
Sauropus sp. Koodaideri detritals; and
(f) Mining activities do not impact the hydrological regime or water quality of the
Koodaideri Spring Gorge.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
13
Conditions relating the management of asbestos related risk are relevant to the construction
of the Rail corridor through the Wittenoom Asbestos Management Area and are not directly
relevant to construction of the mine site processing plant.
3.2.2 Rights in Water and Irrigation Act 1914
The following Licences to Take Groundwater have been issued under the Rights in Water and
Irrigation Act 1914 (RiWI Act) for the Project.
Table 3-3 Koodaideri 5C licences
Licence Number Volume (kL) Expiry Date
GWL 158473(6) 45,000 3 Sept 2023
GWL 164672(7) 95,000 14 Oct 2023
GWL 171847(3) 45,000 15 Sept 2027
GWL 174242 15,000 1 Sept 2023
GWL 177962(3) 212,000 6 Sept 2028
Groundwater abstraction and quality will continue to be managed in accordance with the
existing Groundwater Licences and associated Groundwater Operating Strategies, and any
amendments and new licences as required. An application to increase the abstraction limit for
GWL174242 for water supply purposes is being progressed with the DWER-Water branch.
Bed and banks permits are not required as the Project is being constructed on land that is the
subject of a State Agreement as described in section 3.2.3 below and any potential significant
impact on major drainage lines has been assessed as part of the Part IV environmental
approval process.
3.2.3 State Agreement and Mining Act 1978
The development of the Project is subject to the provisions on the Iron Ore (Mount Bruce) Agreement Act 1972.
Other forms of Mining Act tenure have also been obtained to facilitate supporting
infrastructure. Activities related to this application are purely located on State Agreement Act
tenure ML252SA and pending Miscellaneous Licence L47/00701.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
14
4 Process Description
4.1 Overview
The Koodaideri Iron Ore Mine will produce 43 million tonnes per annum (Mtpa) of Saleable
Ore Product (SOP) as lump and fines from coarse ore feed.
In order to process coarse ore feed into saleable ore product, the Koodaideri processing plant
will include facilities for crushing, screening, stockpiling and loading onto rail transport.
Key inputs to the processing plant include iron ore (high phosphorus Brockman ore – goethite),
diesel fuel, electrical power and process water (obtained from local licensed groundwater
source).
Key outputs include iron ore product (lump and fines), noise, dust, light and greenhouse gas
emissions.
Mobile crushing and screening units will be required to support mine earthworks. When
constructed, the Koodaideri processing plant will operate 24 hours per day, 7 days per week.
The life of mine is expected to be more than 30 years.
Construction of the Koodaideri processing plant is expected to commence in Quarter 1, 2019
and be completed in Quarter 2, 2021. Commissioning is expected to commence in Quarter 1
2021.
4.2 Design and Operation
4.2.1 Plant Layout
The following drawings show the overall site layout and are attached to this document as Appendix B:
KD-0000-F-DRG-00001 Process Plant – Process Flow Diagram
1000-EG-DWG-0003 Overall Site Building Set Out – General Arrangement
1000-EG-DWG-0004 Overall Site Building Set Out (1 of 6)
1000-EG-DWG-0005 Overall Site Building Set Out (2 of 6)
1000-EG-DWG-0006 Overall Site Building Set Out (3 of 6)
1000-EG-DWG-0007 Overall Site Building Set Out (4 of 6)
1000-EG-DWG-0008 Overall Site Building Set Out (5 of 6)
1000-EG-DWG-0009 Overall Site Building Set Out (6 of 6)
4.2.2 Process Flow
The plant flowsheet is shown schematically in Figure 4.1 and in more detail in Appendix B.
Run of Mine (ROM) ore will be delivered by haul truck to a primary gyratory crusher located to
the north west of the K58W pit (as shown in Figure 3.1). The high-grade (HG) primary crushed
ore will be processed through a dry crushing and screening plant to produce HG lump and HG
fines product.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
15
Seven double-deck banana screens will provide the required production throughput and
achieve the required product specifications, which will divide the ore into three streams: lump
product, fines product and oversize material.
Oversize material will be conveyed to the secondary crusher surge bin. The secondary crusher
surge bin will have a total live capacity of 860 tonnes and incorporate two outlet hoppers,
isolation gates and belt feeders, each providing feed to a cone secondary crusher. The design
throughput of each secondary crusher is 3,600 tph.
The fines and lump products from the process plant will be conveyed to their respective fines
and lump stockpiles. Representative samples of each ore stream are taken at six minute
increments and sub-sampled prior to conveying directly to a fully automated laboratory cell.
The laboratory cell will provide the metallurgical and analytical / chemical assays for the
process. The laboratory will also manually process the mine and exploration samples with
laboratory rejects conveyed back to the lump stockyard feed conveyor
Final product will be conveyed and stacked separately onto lump and fine product stockpiles for later reclaiming by a bucket wheel reclaimer to a train load-out (TLO) facility.
The process plant features the construction of the following major facilities:
Primary Crusher apron sized for up to 300 tonne class haul trucks;
Dual truck tipping points and ROM dump hopper of 600 tonne live capacity and discharge surge bin of 600 tonne;
Direct-feed crushing facility complete with dump hopper, gyratory crusher, service crane, rock breaker and discharge apron feeder onto the overland conveyor;
Conveyors feeding a coarse ore fixed stacker;
Primary crushed ore stockpile with 25,000 tonne live storage and reclaim with two apron feeders;
7-bay screening plant with shuttle fed, bins, feeders and screens;
Allowance for a future 8th product screening bay in the design;
Two bay secondary crusher facility with bins, belt feeders and MP1250 type secondary crushers;
Sample plants – cutters, conveyors, and equipment for sampling lump and fines;
Stockyard with two slewing and luffing stackers and a rotary reclaimer; and
Volumetric train load-out.
The major facilities are linked by conveyors capable of providing an average 43 Mtpa SOP. More detail on the major facilities is provided in the following sections.
The processing plant is serviced by air, water, and dust suppression and collection systems.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
16
Figure 4-1: Koodaideri Processing Plant Flow Sheet
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
17
4.2.3 Process Plant Production Capacity
During normal operations the plant will have the capacity to process 43 Mtpa of coarse ore. Table 4-1 summarises the maximum input to the process based on continuous operation for 24 hours.
Table 4-1 Inputs to the process plant
Inputs Rate Unit of Measure
ROM ore 43,000,000 Tonnes / annum
Raw Water 6.15 GL / annum
Table 4.2 summarises the maximum outputs from the process plant.
Table 4-2 Outputs from the process plant
Outputs Rate Unit of Measure
Fines Product 1,600 Tonnes / hour
Lump Product 1,800 Tonnes / hour
4.2.4 Primary Crushing
A dual tip direct-fed primary gyratory crusher will be located on the north-western boundary
of the K58W mine area (Figure 4-2). The primary crushing facility comprises the following
key equipment:
ROM dump hopper;
Maintenance crane;
ROM Bin Rockbreaker;
Primary gyratory crusher assembly;
Primary crusher discharge surge bin
Apron feeder;
Crusher discharge conveyor;
Conveyor weightometer, tramp metal detector and magnet;
Ducted dust collection system;
Primary crusher sump;
Dust suppression, and fire protection system; and
Compressed air system and water services.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
18
A dedicated oil lubrication system for the gyratory crusher will be provided which will also
incorporate the primary crusher’s hydroset hydraulic power pack as it utilises the same oil
reservoir.
Figure 4-2: Koodaideri Primary Crusher
4.2.5 Secondary Crushing
The Secondary Crushing Facility receives oversize material from Product Screening Facility
and re-crushes the material prior to it being conveyed back to the Product Screening Facility
for re-screening. There will be two secondary cone crushers each with a design capacity of
3,300 t/h (wet). Figure 4-3 shows the general arrangement of the secondary crushing facility.
Figure 4-3: Secondary Crushing Facility
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
19
4.2.6 Product Screening
The Product Screening Facility will fed via a shuttle head conveyor to seven feed bins that
report to seven vibrating feeders integrated with the double-deck banana screens. Each
screen design capacity on medium ore is 1,800 tph (wet).The oversize material from the
screening plant will be conveyed to the secondary crushing facility, re-crushed and returned
to the feed bins and rescreened.
The fines and lump products from the process plant will be conveyed to their respective fines
and lump stockpiles. Representative samples of each ore stream are taken at six minute
increments and sub-sampled prior to conveying directly to a fully automated laboratory cell.
Figure 4-4 shows the cross-sectional arrangement of the Product Screening Facility.
Figure 4-4: Product Screening Facility
4.2.7 Stockyard and Reclaimer
The product stockyard will be located north of the process plant and south of the Roy Hill-
Munjina Road. It will consist of two rows of three 200,000-tonne (nominal) SOP longitudinal-
type stockpiles, one row for lump and one row for fines products.
The product stockyard has two slewing and luffing stackers of 5,700 tph capacity, one for fines
and one for lump products. The stockyard will also have a single slewing and luffing boom-
type bucket wheel reclaimer with an average stockpile reclaim capacity of 4,690 m3/h. The
reclaimer will reclaim either lump or fines to the train load-out system.
The stockyard cross sectional arrangement is shown in Figure 4-5 and general Arrangement
is shown in Appendix B. The stockyard will receive ore from the lump and fines stackers and
consists of two excavated canyons approximately 1,000 m in length. Each canyon
accommodates 3 x 200,000-tonne fines SOP stockpiles, and 3 x 200,000-tonne lump SOP
stockpiles.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
20
The stockyard will be serviced by dust suppression water cannons which operate
automatically. The water cannons will be linked to the site weather management systems
and will be automatically activated in sequence based on stockpile height, evaporation rate,
wind speed and wind direction.
.
Figure 4-5: Stockyard Cross-Section
4.2.8 Train Load-Out
The TLO is shown in Figure 4-6 consists of a 1,500 tonne surge bin supplying ore to the train
loading gate. The loading gate will load the ore cars volumetrically and will be capable of
loading lump or fines product at a nominal design rate of 11,500 t/h.
Nominally, product trains will consist of 240 cars with a transport capacity of 29,520 to 30,480
tonnes per train. The system, including the bucket wheel reclaimer and the reclaim conveyor,
is designed to maintain a minimum average loading rate of 9,100 tph for all products and load
a train in 200 minutes (first ore car to last ore car).
An under-rail clean-out vault will be located directly beneath the train load-out bin. Any spillage
from the load-out discharge will be allowed to fall through the grating beneath the rail and into
the tunnel below. A loader will be required to periodically remove the spillage material from
the tunnel.
A load optimisation system is included which utilises volumetric scanning and loaded ore car
track weighers to enable the control system to adjust the mass or ore and profile of the ore
being loaded.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
21
Figure 4-6: Surge bin outlet and charge gates removal method
4.2.9 Mobile Crushing and Screening Plant
As part of the processing plant construction, suitable material is required to be sourced from
adjacent borrow pits. Prospective borrow areas have been identified on AML70/00252
ML252SA and L47/00701 to provide suitable quantities of material for construction
earthworks. This borrow material, in addition to other select cuttings from the processing plant
footprint area, will be processed through a mobile crushing and/ or a mobile screening plant.
The mobile crushing and screening plant components proposed to be used is a Terex Finlay
J1480 Jaw Crusher“and Terex Finlay – Heavy Duty Screen 883”. Basic specifications are
provided in Appendix C. It should be noted that this specific make of plant is subject to change
based on the contractor availability, however if a different make is used, it will be of similar
specification and with the same environmental controls.
The mobile crushing and screening plants will be located within the prescribed premises in
areas previously cleared for the sourcing of borrow material, so no additional clearing will be
required. As borrow material used in the crushing and screening plant is exhausted, the
mobile plant will be transported to the next cleared borrow pit area within the prescribed
premises. This process will continue as required throughout the duration of construction.
The mobile crushing plant works by placing material into the feed hopper via an excavator of
front end loader. The plant is preconfigured for use so the only modification required during
commissioning are the setting of the crusher aperture to deliver product of the required size,
and testing of dust suppression systems. The target particle size (screen setting) is
approximately 40mm. Product material is stockpiled for transport to the relevant construction
site.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
22
4.3 Timescale for Construction / Operation
Based on the current schedule it is expected that construction of the mine processing plant will begin in Quarter 1, 2019 will be completed in Quarter 4, 2021. The facility is expected to be operational for approximately 30 years. Once construction of the processing plant is completed and prior to commissioning, a compliance document detailing compliance with commitments made in this works approval application will be submitted to DWER as per the works approval conditions. The mobile crushing and screening plants will initially be on site for up to 2 years to support the Project construction activities. At the completion of construction work for the processing plant, the mobile facilities (or similar) may be required for other purposes, for example, to provide stemming for blasting purposes.
4.4 Commissioning and Reporting
4.4.1 Processing Plant
Once construction activities are completed at the mine processing plant, commissioning
activities will begin and are expected to be completed by Quarter 1 2022. In general, the basic
scope of commissioning and handover activities for the processing plant can be designated
by the following six stages:
Stage 1: Construction Verification – verify construction completion to design intent.
Stage 2: Pre-commissioning – functional testing of energised equipment.
Stage 3: No-load Commissioning – dynamic testing of operating systems without process
materials.
Stage 4: Load Commissioning – running the facilities with feedstock and incremental load
tuning. Note during this phase the plant will be running under operational conditions and hence
the risk of emissions and means of mitigation are almost identical.
Stage 5: Care custody and Control – operations and maintenance teams will seek to rectify
any operating issues and aim to achieve stable performance from the new plant.
Stage 6: Performance Verification – ramp up production rate and confirm achievement of
designed through-put.
The licensee seeks to undertake all stages of the commissioning under the works approval,
with Stages 1 to 3, including first fill of all lubricants and running of all process plant equipment
(including conveyors, sizers, feeders, crushers, scrubbers, cyclones, and balanced machines)
undertaken prior to submitting a compliance document and application for a licence.
Upon submission of the compliance document, the licensee will undertake Stages 4 to 6, load
commissioning (i.e. ‘wet commissioning’) and performance verification prior to submitting a
commissioning report and submitting an application to obtain a licence to operate.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
23
Stages 4 to 6 are expected to take up to 12 months; hence an 18 month commissioning period
is requested to enable commissioning to occur and an amendment to the existing licence to
operate to be obtained.
4.4.2 Mobile Crushing and Screening Plant
The mobile crushing and screening plants will arrive on site ready for commissioning.
Commissioning entails setting the crusher jam aperture to produce material of the desired size
and installing the screens required to produce materials of the desired size. During
commissioning, dust suppression sprays will be tested to ensure functionality. The
commissioning period will be completed within three months of mobilising the crushing and
screening plant to site.
It is requested that commissioning and operation of the mobile crushing and screening plant
be undertaken under the Works Approval (i.e. without the need to obtain an initial licence
amendment within months of the works approval being obtained).Category 12 for ongoing use
of mobile plant following construction of the processing plant would be added to the operating
licence at the same time as the amendment to add Category 5 (for the processing plant).
5 Risk Identification and Assessment
A risk assessment has been prepared to identify the potential emissions from the proposed
activities and the potential sources, pathways and receptors of those emissions, and proposed
controls to manage potential emissions to determine a risk rating. The risk assessment has
been based on the DWER Guidance Statement: Risk Assessments (released by the then
named Department of Environmental Regulation in 2017) and the Rio Tinto risk assessment
process, based on the following risk rating matrix (Table 5-1):
Table 5-1: Risk Rating Matrix
Consequence
Likelihood Slight Minor Moderate Major Severe
Almost Certain Medium High High Extreme Extreme
Likely Medium Medium High High Extreme
Possible Low Medium Medium High Extreme
Unlikely Low Medium Medium Medium High
Rare Low Low Medium Medium High
Risk = consequence x likelihood
The following criteria (DWER 2017) are used to determine the consequence and likelihood of a risk event occurring (Table 5-2 and Table 5-3).
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
24
Table 5-2: Consequence Matrix
Consequence Consequence description
Environment Health
Severe
On-site impacts: catastrophic
Off-site impacts (local scale): high level
Off-site impacts (wider scale): mid level
Mid to long term or permanent impact to an
area of high conservation value or special
significance
Loss of life
Adverse health effects: high level or
ongoing medical treatment
Local scale impacts: permanent loss of
amenity
Major
On-site impacts: high level
Off-site impacts (local scale): mid level
Off-site impacts (wider scale): low level
Short term impact to an area of high
conservation value or special significance
Adverse health effects: mid-level or
frequent medical treatment
Local scale impacts: high level impact to
amenity
Moderate
On-site impacts: mid level
Off-site impacts local scale: low level
Off-site impacts wider scale: minimal
Adverse health effects: low level or
occasional medical treatment
Local scale impacts: mid-level impact to
amenity
Minor
On-site impacts: low level
Off-site impacts (local scale): minimal
Off-site impacts (wider scale): not detectable
Local scale impacts: low level impact to
amenity
Slight On-site impacts: minimal Local scale impacts: minimal impacts to
amenity
Table 5-3: Likelihood Matrix
Likelihood Likelihood description
Almost certain The risk event is expected to occur in most circumstances.
Likely The risk event will probably occur in most circumstances.
Possible The risk event could occur at some time.
Unlikely The risk event will probably not occur in most circumstances.
Rare The risk event may only occur in exceptional circumstances.
The potential emissions, sources, pathways and receptors that have been identified for the
construction, commissioning and operation of the proposed facilities are outlined in Table 5-4
Risk Assessment. This table also identifies the potential impacts, proposed controls and
associated risk ratings. A detailed risk assessment will be undertaken for any activity which
has been identified as having a ‘Medium’ risk rating or higher (Section 6). Detailed risk
assessment includes:
A description of the potential emissions, sources, pathways and receptors.
Any controls that have been identified for the risk event.
An assessment of the consequence and likelihood.
Risk rating.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
25
Table 5-4: Risk Assessment
Source Potential
Emission Pathway Potential Receptors Potential Impacts Proposed Controls Consequence Likelihood Risk Rating
Detailed Assessment
Required?
Category 5:
Processing of
ore
Category 12:
Screening etc.
of material
Construction of
crushing and
screening
equipment
Dust Air (windborne)
No sensitive land uses in proximity – Fortescue Marsh 8 km away, no residential premises
Vegetation including vegetation adjacent to mining areas
Dust impacts on surrounding
vegetation, including reduced
ability for photosynthesis due to
smothering
Health and amenity: None, given
the distance to the nearest
receptor
Dust suppression (water sprays, water trucks, control
of vehicle movements / restricted speeds)
Rehabilitation of disturbed areas
Minor Rare Low
Risk pathway is low, detailed
assessment is not required.
However, further detail on
controls provided in Section
6.2d
Noise Air (windborne)
Nocturnal native fauna, including
the Pilbara Leaf Nose Bat
(PLNB)
Residential: None, the nearest
receptors are the Koodaideri
Village, offices and mining
operations.
Noise / Vibration impacts on
fauna habitat, including potential
roosting sites for bats
Health and amenity: None, given
the distance to the nearest
receptor
A specific PLNB Environmental Management Plan has
been developed as required under MS999
Environmental Protection (Noise) Regulations 1997
Moderate Possible Medium
No, managed by MS 999. However, further detail on
controls provided in Section
6.3
Light Air Nocturnal native fauna, including
the PLNB
Disruption in PLNB roosting
patterns
Construction activities limited to daytime hours
Lighting limited to the minimum required to maintain
site safety and security.
Directional lighting will be used to minimise stray light
emission.
A specific PLNB Environmental Management Plan has
been developed as required under MS999.
Minor Possible Medium
No, managed by MS 999. However, further detail on
controls provided in Section
6.5
Discharge of
washwater or
process water
potentially
hydrocarbon
contaminated
and / or
sediment
laden
Discharge to Water Surface water bodies
(Fortescue Marsh 8km away)
No pathway to surface waters
due to distance and topography
No planned discharge of water from site
Potentially contaminated waters managed on site via
bunds and surface diversions
Minor Rare Low
Risk pathway is low, detailed
assessment is not required.
However, further detail on
controls provided in Section
6.6
Discharge to Land
Terrestrial ecosystems
Groundwater
Potential contamination of soil
and groundwater due to
presence of iron, hydrocarbons
and chemicals within
stormwater, leaks and spills.
Clean stormwater run-off and potentially sediment
loaded run-off from the plant are separated to the
extent achievable by applying Rio Tinto Standard
specification SS-N102 Sediment Control and
Separation, with the site graded to direct stormwater
away from the process plant.
Any potential hydrocarbon / sediment laden water will
be retained onsite by use of diversions and bunds
Minor Possible Medium Detailed assessment
provided in Section 6.7.
Operation of
crushing and
screening
equipment,
movement of ore
product between
these and the
stockyards via
conveyors.
Dust Air (windborne)
No sensitive land uses in proximity (Fortescue Marsh 8km away)
Vegetation including vegetation adjacent to mining areas
Dust impacts on surrounding
vegetation, including reduced
ability for photosynthesis due to
smothering
Health and amenity: None, given
the distance to the nearest
receptor
Dust suppression on trafficable areas including water
sprays, water trucks, control of vehicle movements /
restricted speeds
ROM dump hopper dust suppression through high
pressure water fogging combined with a water spray
curtain system at the ROM feed hopper and coarse
ore stockpile
Two baghouse dust collection systems
Sprays on conveyor transfer points
Stockyard will have automatic water cannons located
on both sides of the stockpiles at 50 m intervals.
Stacker boom conveyors will be fitted with head-end
sprays and dust shrouds
Conveyors covered except in stockyard
Rehabilitation of disturbed areas
Minor Possible Medium Detailed assessment
provided in Section 6.2.
Noise Air (windborne)
Nocturnal native fauna, including
the PLNB
Residential: None, the nearest
receptors are the Koodaideri
Village, offices and mining
operations.
Interruption of natural PLNB
activities
Health and amenity: None, given
the distance to the nearest
receptor
A specific PLNB Environmental Management Plan has
been developed as required under MS999.
Environmental Protection (Noise) Regulations 1997
Moderate Possible Medium
No, managed by MS 999. However, further detail on
controls provided in Section
6.3
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
26
Source Potential
Emission Pathway Potential Receptors Potential Impacts Proposed Controls Consequence Likelihood Risk Rating
Detailed Assessment
Required?
Light Air Nocturnal native fauna, including
the PLNB
Disruption in PLNB roosting
patterns
Plant lighting design will comply with Australian
standards for safe work.
Lighting design will ensure light is directed to work
areas and minimal light spill occurs.
Walkways and platforms that require permanent
lighting at night will have shrouded lenses and LED’s
with optics that direct lighting only onto walkways and
platforms with minimal “spill” to reduce light spill.
A specific PLNB Environmental Management Plan has
been developed as required under MS999.
Minor Possible Medium
No, managed by MS 999. However, further detail on
controls provided in Section
6.5
Discharge of
washwater or
process water
potentially
hydrocarbon
contaminated
or / sediment
laden
Discharge to Water Surface water bodies
(Fortescue Marsh 8km away)
No pathway to surface waters
due to distance and topography
No planned discharge of water from site
Potentially contaminated waters retained onsite via
bunds and surface diversions
Minor Rare Low
Risk pathway is low, detailed
assessment is not required.
However, further detail on
controls provided in Section
6.6
Discharge to Land Terrestrial ecosystems
Groundwater
Potential contamination of soil
and groundwater due to
presence of iron, hydrocarbons
and chemicals within
stormwater, leaks and spills.
Diversion of clean surface water around the work area
Stormwater will be collected in open drains which then
discharge to sedimentation ponds.
Plant drainage will flow to an earthen sedimentation /
silt pond designed to treat a peak 1:10 year rainfall
event.
Concrete hardstand under main processing areas with
sediment/silt traps
Drive in sumps installed to collect sediment
Oily water separators (centrifugal type) to separate out
hydrocarbons from surface water.
Minor Possible Medium Detailed assessment
provided in Section 6.7.
Non-
prescribed
activity
Hydrocarbon
storage (under
requirement for
licensing).
Discharge of
hydrocarbons /
hydrocarbon
contaminated
water to Land
Discharge to Land Terrestrial ecosystems
Hydrocarbon spills causing soil
contamination, potential
seepage to groundwater
resulting in reduction in water
quality beyond its beneficial /
post closure use and adverse
impacts to the health and
survival of vegetation dependent
upon groundwater
Australian Standard AS1940 - Storage and handling of
flammable and combustible liquids
Storage in bunded areas / secondary containment
Appropriate labelling of storage areas
Provision of spill response equipment
Minor Possible Medium
Detailed assessment and
controls provided in Section
6.8
General
construction /
putrescible waste
during
construction
Solid / Liquid
Waste Discharge to Land
Terrestrial ecosystems /
Surface Water / Groundwater
Seepage of landfill leachate
leading to groundwater
contamination beyond its
beneficial / post-closure use,
and adverse impacts to the
health and survival of vegetation
dependent upon groundwater
Waste material that is suitable for re-use or recycling
will be separated from landfill waste and sent off-site
for treatment or recycling as practicable.
Non-recyclables will be disposed of in approved site
landfill.
Existing landfill conditions on L8562/2011/1
Slight Possible Low
Risk pathway is low, detailed
assessment is not required.
Further detail on controls
provided in Section 6.4
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
27
6 Emission Management
Rio Tinto (WA) has a Health, Safety, Environment and Quality Management System (HSEQ) that ensures environmental controls are developed for key environmental aspects, legal compliance is maintained and continuous improvement is achieved through a formal review process.
6.1 Air Emissions (excluding dust)
There is not expected to be significant air emissions, generated during the construction, commissioning and operation of the mine processing plant and mobile crushing and screening plants.
During construction, commissioning and operations the generation of smoke and gaseous emissions will be limited to the operation of construction machinery including earthmoving machinery, minor temporary power generation and the mobile crushing and screening plants. The mine processing plant will be electrically powered via the high voltage power transmission line.
6.2 Dust Emissions
6.2.1 Description of risk event
Construction – Fixed Crushing / Screening Plant Dust emissions during construction are typically associated with clearing, earthworks and vehicle movement on unsealed roads. There are no sensitive land uses in proximity of the construction activities, with Fortescue Marsh 8 km away and no residential premises within 25 km. Other potential environmental receptors that could be impacted by dust emissions during construction include vegetation adjacent to mining areas. This includes potential for vegetation to have a reduced ability for photosynthesis due to smothering. Operation – Fixed Crushing / Screening Plant Potential dust emissions during the operation of the processing plant are typically point source emissions. Dust emissions are typically generated from a range of point sources including:
ROM area during ore loading and unloading;
ore processing (crushing and screening);
conveyors and conveyor transfer points;
stockpiles where dust lift off from the surface may occur in windy conditions;
stockpiling and reclaiming of ore product; and
frequent light and heavy vehicle movement on unsealed roadways.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
28
6.2.2 Proposed environmental controls
Construction – Fixed Crushing / Screening Plant The dispersed and temporary nature of dust emissions during construction requires a broad range of controls to be applied including:
Water carts will be used during clearing and construction activities and in areas with
frequent vehicle movement on unsealed roads. The application of water increases the
specific mass of the soil particles and to increase bonding between the soil particles,
minimising the dust generated.
In some transport corridors, dust suppressant additives will be applied through water
carts to assist with dust control.
Site clearing and rehabilitation will be managed to ensure that areas are only cleared
as required and progressive rehabilitation is implemented as construction activities are
completed.
Weather forecasts will be monitored to ensure the availability of adequate water carts
if there is a risk of windy conditions.
Dust emissions during construction will be managed in accordance with the Koodaideri Project Construction Environmental Management Plan (CEMP). Operation – Fixed Crushing / Screening Plant The controls for managing dust in the processing plant will include:
ROM dump hopper dust suppression through high pressure water fogging combined
with a water spray curtain system at the ROM feed hopper and coarse ore stockpile.
This control will raise the overall moisture content and minimise dust generation in
downstream processing.
Provision has been made for water spray addition points at the discharge from the
apron feeders, transfer points and at the head end of the primary crusher discharge
conveyor.
Dust extraction: Two dust collectors will be installed, one between the coarse ore
stockpile and secondary crusher, and a second at the screening plant. Dust collectors
are ducted to a typical baghouse dust collection system. Where possible, collected
dust will be processed using an agglomerator with product being discharged back onto
the process system.
Conveyors handling material with a low moisture content will be fitted with spray booths
for dust suppression at most transfer points. This includes the primary crushed ore
conveyor, dry screen feed conveyor, lump stacking conveyor, and fines stacking
conveyor.
All conveyors are covered except in the stockyard to reduce dust lift off.
Drop heights at all conveyor transfer points have been minimised where possible
throughout the process plant design.
The stockyard will be serviced by automatic water cannons on either side of the
stockpiles. The water cannons will be linked to the site weather management systems
and will be automatically activated in sequence based on stockpile height, evaporation
rate, wind speed and wind direction.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
29
Stacker boom conveyors will be fitted with head-end sprays and dust shrouds.
The reclaimer bucket wheel will have dust suppression sprays and conveyor sprays
fitted.
Regular housekeeping will be undertaken to collect and remove material that may
present a potential dust risk from around conveyors and loading/unloading areas.
Water flow rates will be calculated and four hourly moisture samples will be taken from
the product belt to measure moisture content of the ore. This allows adjustments to the
moisture content to minimise dust while not adding too much water to the ore and
creating runoff from the stockpiles.
Monitoring of dust levels will be conducted on a real‐time basis in the processing plant to provide data that can be used to reduce overall dust levels and help adjust moisture management to match feed‐specific requirements. The main focus of this monitoring is to mitigate any potential impact on the health and safety of employees, which has the added benefit of assisting to reduce overall dust generated by the plant. Specific monitoring regarding impact to a specific environmental receptor is not required given the significant distances involved.
All water flows will be recorded in the plant control system. Over time the analytics algorithms will correlate water addition, environmental data, ore properties and dust emission data to arrive at optimal dust suppression strategies.
Mobile Crushing and Screening Plants
Dust emissions from the proposed mobile crushing and screening plants are point source emissions that will be managed through the use of dust suppression sprays. The mobile plant will arrive on site with an installed system of dust suppression sprays that will be plumbed in to a site water supply. Dust from mobile plants shall also be managed by:
Spraying the feed stockpile with water prior to being fed into the screen.
Use of dust suppression on stockpiles as necessary.
Water carts to dampen work areas, access roads and stockpiles to minimise dust lift-
off during storage and handling of borrow and screened material as required.
If fitted, use of hydraulically angle-adjustable stockpiling conveyors to minimise drop
heights.
If fitted, belt sprayers will be employed to dampen crushed material as necessary.
Implementation of the CEMP requires regular documented inspections to be undertaken to ensure the dust suppression system is fully functional during operation.
6.2.3 Residual risk to environment
The licensee believes that with the lack of sensitive receptors in the region and the significant number of proposed controls to be implemented, the risk to the environment from potential dust emissions at Koodaideri is low.
6.3 Noise
Noise emissions during construction will be distributed across the site, predominantly mobile and limited to daylight hours. The main source of noise emissions will be earthmoving and construction machinery and on-site power generation.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
30
During construction noise emissions will be managed under the CEMP. The CEMP controls apply equally to the proposed mobile crushing and screening plant. Controls may include:
• Fitting vehicles and stationary items of equipment with exhaust mufflers;
• Screening or enclosing stationary items of equipment with acoustic enclosures to
reduce operating nose levels.
• Requiring contractors to comply with the Environmental Protection (Noise)
Regulations 1997.
• Construction works must be carried out in accordance with Section 6 of Australian
Standard 2436-1981 “Guide to Noise control on Construction, Maintenance and
Demolition Sites” and the Environmental Protection (Noise) Regulations 1997 (WA)
• A Blast Management Plan must be prepared for all blasting activities and include
an assessment of proximity to sensitive receptors, including nearby communities,
heritage rock shelters and bat cave locations
Once operational the processing plant will operate on a continuous 24 hours per day basis. During mining operations noise sources include:
• Running conveyors – start and stop alarms, rollers, drives and belt interaction
(continuous operation).
• Plant major equipment – primary and secondary crushers, vibrating screens,
stackers, reclaimers and train load out.
• Miscellaneous equipment – air compressors, blowers, transformers (continuous
operation).
• Mobile plant and vehicles – reverse warning alarms and other warning alarms
(irregular).
• ROM Bin Rock Breaker - intermittent use.
There is one sensitive noise receptor being the K75W Adit/Cave system which provides
roosting habitat for a PLNB Colony. The impact on PLNB has been assessed under Part IV
of the Environmental Protection Act 1986 and relevant conditions written into MS 999. A
specific PLNB Environmental Management Plan has been developed by Rio Tinto on the
advice of DWER and approved by the Office of the EPA. This plan includes monitoring for
threshold noise and vibration limits at the entrance to the K75W Adit/Cave system that will
trigger further additional responses.
Noise and vibration are not expected to be significant issues during the construction or
operation of the primary crusher, conveyors and processing plant. The risk related to noise
emissions is low (other than as discussed above regarding PLNBs). The noise emission
profile and risk is well understood and as described above there are significant controls applied
to monitoring and managing noise at Koodaideri.
6.4 Odour Emissions
No significant odour emissions are expected to be produced from the construction or operation of the Koodaideri processing plant or mobile crushing and screening plants.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
31
6.5 Light Emissions
Light emissions during construction of the processing plant are expected to be minimal. Construction activities will not be conducted at night and so night lighting will be limited to the minimum required to maintain site safety and security. Directional lighting will be used to minimise stray light emission.
When constructed and commissioned the processing plant will be operate on a continuous 24 hour basis. Night lighting in and around the processing plant, accommodation areas, offices and workshops is required in accordance with Australian standards for safe work.
The following controls will be implemented to manage light emissions:
• Plant lighting design will comply with Australian standards for safe work.
• Lighting design will be modelled prior to installation to ensure light is directed to
work areas and minimal light spill occurs.
• Walkways and platforms that require permanent lighting at night will have shrouded
lenses and LED’s with optics that direct lighting only onto walkways and platforms
with minimal “spill” to reduce light spill.
All nocturnal native fauna are potentially sensitive receptors to stray light emission. The project impact on Pilbara Leaf Nosed Bats has been assessed under Part IV of the Environmental Protection Act 1986 and relevant conditions written into MS 999. A specific PLNB Environmental Management Plan has been developed by Rio Tinto and approved by the Office of the EPA which includes commitments to limit light spill and to prevent development in PLNB exclusion zones. The risk to the environment related to light emissions (other than as described for the PLNB) at Koodaideri from the processing plant and mobile crushing and screening plant is therefore considered low.
6.6 Discharge to Water
There are no planned discharges to water during construction or operation of the processing plant or the mobile crushing and screening plants.
The closest surface water expression to the processing plant is Koodaideri Spring Gorge, approximately 4 km and up-gradient. The Fortescue Marsh is located approximately 8 km from the premises boundary. Impacts to either Koodaideri Spring Gorge or the Fortescue Marsh are not expected during operation or construction of the processing plant or mobile crushing and screening plants. Controls in addition to those required by MS999 are not considered necessary as the risk to environmental receptors is low.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
32
6.7 Discharges to Land
6.7.1 Description of risk event
Construction – Fixed Crushing / Screening Plant
The potential for contamination of soil and groundwater exists due to the possible presence of
iron, hydrocarbons and chemicals within stormwater, leaks and spills associated with the
construction of the fixed crushing and screening infrastructure.
Local groundwater is fresh and is approximately 70 m below ground level in the area where
the Processing Plant is to be constructed.
Operation – Fixed Crushing / Screening Plant
The potential for contamination of soil and groundwater exists due to the presence of iron,
hydrocarbons and chemicals within stormwater, leaks and spills, associated with the operation
of the fixed crushing and screening infrastructure.
Local groundwater is fresh and is approximately 70 m below ground level in the area of the
Processing Plant.
6.7.2 Proposed environmental controls
Construction – Fixed Crushing / Screening Plant
The environmental controls proposed to mitigate any potential impact on the environment during construction of the fixed crushing and screening infrastructure include:
• Diversion of clean surface water around the work area.
• Secondary containment of all chemical and hydrocarbon storage across the entire
site.
• Approval process prior to mobilising any chemicals to site.
• Drainage sumps to settle out sediments prior to discharge from the plant area.
• No permitted release of any potentially contaminated site water that has not been
checked for hydrocarbon contaminants.
Operation – Fixed Crushing / Screening Plant
The processing area will be constructed to enable the separation of clean stormwater run-off
and potentially sediment laden run-off to the extent achievable by applying Rio Tinto Standard
specification SS-N102 Sediment Control and Separation. The area surrounding the crushing
plant and conveyor transfer points will be compacted structural fill. Stormwater will be collected
in open drains which then discharge to sedimentation ponds. The plant drainage will flow to
an earthen sedimentation / silt pond designed to treat a peak 1:10 year rainfall event. The area
under the primary and secondary crushing plant and conveyor transfer points will be concrete
slab, graded such that washdown water will be collected in concrete sediment/silt traps.
Washdown water from conveyors will be collected in concrete sumps and either removed by
pumping out, or allowed to evaporate depending on climatic conditions and volumes reporting
to sumps. Drive in sumps will be installed around the plant site and all wash down from
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
33
concrete slabs placed under the operating plant will be directed into these sumps. The bulk of
solids will settle in the drive in pits of these sumps while the liquid containing particles will be
pumped into silt traps. Fine solids will settle in these silt traps prior to release of the clean
water. Both the drive in sumps and silt traps will be debogged using bobcats and front end
loaders. Sumps will be installed at the Primary Crusher, Transfer Station TF0101, Transfer
Station TF0313, Transfer Station TF0316, COS, Product Screen Area North, Product Screen
Area South, Secondary Crusher, Secondary Sampling Area, Reclaim Conveyor Drive Station
and the Train Loadout. Sumps are designed to be drive-in to allow removal of sediment. These
are depicted in the drawings provided in Attachment B. No other waste water is expected to
be generated in the crusher/conveyor circuit.
The levee and drain structures installed to prevent the ingress of surface water in to the mining
operations will also be used to contain runoff water from around the plant and other
infrastructure. There are no sensitive receptors that could potentially be impacted by
contaminated surface water in the vicinity of the processing plant infrastructure. The Fortescue
Marsh is approximately 8 km from the facilities and the Koodaideri Spring Gorge is 4km away
and upgradient. Regardless, a range of controls will be implemented to ensure any potential
risk to the environment is minimised including:
• Diversion of clean surface water around the work area.
• Secondary containment of all chemical and hydrocarbon storage across the entire
site.
• Approval process prior to mobilising any chemicals to site.
• Drainage sumps to settle out sediments prior to discharge from the plant area.
• Oily water separators (centrifugal type) to separate out hydrocarbons from surface
water.
• No permitted release of any potentially contaminated site water that has not been
checked for hydrocarbon contaminants.
Mobile Crushing and Screening Plants
There are no contaminated discharges to land expected from the construction and operation of the mobile crushing or screening plants. The plant is mobile and will be located within existing cleared borrow pit areas so that any dust laden water is retained within the confines of the borrow pit. Clean surface water will be diverted around the work area by use of bunding where practicable. Mobile plants shall also be situated in a suitable location such that they are located at least 50 meters from any permanent water body.
6.7.3 Residual risk to environment
The risk to the environment from discharges to land from the processing plant and mobile crushing and screening plant is considered low given the distance to any sensitive receptor (see Table 2-2 and Table 2-3), and the significant controls to be implemented.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
34
6.8 Hydrocarbon Management
Hydrocarbons stored on site during the Project construction will be predominantly diesel fuel, lubricants (new and used oil) and hydraulic fluids. There will typically be up to four 110 kL diesel storage tanks and up to six 55kL diesel storage tanks on site at any one time. A range of minor chemical storage facilities will be located on site typically containing a range of packaged chemicals in 50 litre containers and 220L drums. Hydrocarbons will be stored in the contractor laydown work areas. All bulk hydrocarbon storage will comply with DMIRS licensing requirements. All chemicals and hydrocarbons used during construction will be secondarily contained in bunded storage areas, approved chemical cabinets or dual skinned tanks. All chemicals and hydrocarbons will be managed under the Construction Environmental Management Plan (CEMP) and will be in accordance with Dangerous Goods Safety (Storage and Handling of non–explosive) Regulations 2007 and AS1940:2004 The storage and handling of flammable and combustible liquids. Site environmental management requirements include:
• All storage tanks and transfer points will be above ground and secondarily
contained in accordance with AS1940:2004;
• Vehicle refuelling will occur over compacted, lined earthen pad or a concrete
hardstand area (with the exception of field based machinery refuelling where a drip
tray will be used at the transfer point);
• All piping will be above ground where practicable. Where hydrocarbon piping is
below ground it will be secondary contained and have visual inspection pits for any
leaks in accordance with Rio Tinto standard specifications.
• All tanks will be secondarily contained;
• Substances in small volume packages (nominally 20 litres or less) will be stored in
a self bunded chemical cabinet or in a bunded area;
• Containers and drums may be stored temporarily on self bunded pallets or in a
HDPE lined earthen bund. The capacity of the bunding must be at least 100
percent of the volume of the largest container plus 25 percent of the storage
capacity up 10,000 litres as per AS1940:2004 s4.4.3; and
• Spill kits suitable for the stored material being stored will be co-located with all
chemical storage areas.
6.9 Solid/Liquid Waste
There are no liquid waste by-products generated by the Processing plant during construction or operation. Solid industrial and domestic waste will be generated during the construction and operation of the ore processing area. Waste material that is suitable for re-use or recycling will be separated from landfill waste and sent off-site for treatment or recycling as practicable. Non-recyclables will be disposed of in the licensed site landfill.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
35
All Controlled Waste will be removed from site via an appropriately licensed controlled waste carrier and relevant records including tracking notes maintained on site for audit and inspection purposes. All waste handling procedures will be in accordance with the CEMP during construction and the RTIO Health Safety Environment and Quality (HSEQ) Management System during operations.
6.10 Flora and Fauna
New clearing is required for the construction of the Processing Plant, associated infrastructure
and site access. Ministerial Statement 999 approves up to 7911 ha of clearing for the mine
and Processing Plant Area, with all clearing associated with this proposal being covered by
this approval. Of this 7911 hectares approximately 54 ha will be required for the footprint of
the Processing Plant.
Construction and operation of the Processing Plant and related infrastructure has the potential
to impact on certain conservation significant flora and fauna. In particular MS 999 specifies
conditions relating to the management of impacts on the PLNB, Northern Quoll, certain
Troglofauna zones and two flora species Hamersley Lepidium (Lepidium catapycnon) and
Sauropus sp. Koodaideri detritals now known as Synostemon hamersleyensis.
The Rio Tinto Approval Request and Ground Disturbance permitting process will be used to
directly control all land clearing and ground disturbing activities on site. Issuing permits
involves extensive analysis using GIS data acquired through professional botanical and
ecological surveys. The commencement of work under approved permits requires formal
survey, delineation of clearing limits, direct supervision of land clearing activities, mandatory
land disturbance training and extensive reporting including survey pick and assessment via
GIS applications.
Site specific controls relating to the management of impacts to PLNB committed to in the PLNB
management plan include:
• Implementing the approved PLNB management plan;
• Implementing an exclusion zone around the K75W Adit/cave System to minimise
noise and vibration impacts;
• Implementing exclusion zones around the Koodaideri Spring Gorge Foraging
habitat;
• Undertaking monitoring in accordance with the approved PLNB; and
• Ensuring lighting is designed in accordance with Australian Standards
requirements for plant and some infrastructure.
Site specific controls relating to the management of impacts to Northern Quoll required under
MS 999 include:
• Implementing the approved Northern Quoll Management plan;
• Undertaking surveys to identify Northern quoll habitat, presence and abundance
within the mine plant development envelope;
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
36
• Having the Northern Quoll management plan prepared and approved prior to the
commencement of ground-disturbing activities within 50 metres of the mapped
Northern quoll foraging and denning habitat; and
• Implementing protocols and procedures to monitor Northern Quoll presence and
abundance adjacent to the mine pit within the Mine/Plant Area Development
Envelope during construction and operation.
Additional general site-wide controls relating to fauna management include:
• General personnel and contractors are prohibited from feeding or handling nay
wildlife in the Project area;
• Trained Fauna Handlers will be on site to manage fauna interaction issues;
• A fauna interaction register will be maintained on site;
• All open pits and trenches are required to include fauna egress facilities or
preferably prevent fauna access to the extent possible;
• Water sources (i.e. turkeys nests) will be fenced so that non-native fauna are not
attracted to the area;
• All waste food material is contained in closed bins onsite; and
• Site communications will periodically feature conservation significant fauna to
assist with educating the workforce on fauna management requirements.
7 Rehabilitation and Closure
After construction works are completed, areas that have been cleared and no longer required for operational use will be rehabilitated. On completion of the required mining operations all structures associated with Koodaideri will be removed from the site and the area rehabilitated. The closure of infrastructure and activities the subject of this works approval will follow the approved mine closure plan for the Koodaideri Mine. The closure plan will evolve over time and will be updated regularly as required under Ministerial Statement 999.
8 Project Costs
Costs associated with the construction of the proposed facilities are detailed below:
Table 8.7-1: Project Costs
Project Description Projected Cost $AUD
Primary Crushing, Transfer Station and Conveyors $ 98,977,302
Crushed Ore Conveyor and Storage $ 62,188,758
Secondary Crushing, Screening, Conveyors and Substations $ 198,946,574
Product Sample Station and Conveyors $ 13,388,483
Stockyard, Stackers, Reclaimer and Conveyors $ 189,289,543
Train Load Out $ 26,559,913
Total Cost (excl, GST) $ 589,350,573
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
37
9 Summary of Commitments
Environmental factor
Potential impacts Proposed management Section number
Commitment
Dust emissions
Dust impacts on surrounding vegetation, including reduced ability for photosynthesis due to smothering.
Dust suppression (water
sprays, water trucks, control of
vehicle movements / restricted
speeds)
Rehabilitation of disturbed
areas
6.2.2
Automated water cannons installed in stockyard.
Dust suppression systems installed in mobile crushing and screening
plant.
Water spray addition points at the discharge from the apron feeders,
transfer points and at the head end of the primary crusher discharge
conveyor.
Two dust collectors will be installed, one between the coarse ore stockpile
and secondary crusher, and a second at the screening plant.
Conveyors handling material with a low moisture content will be fitted with
spray booths for dust suppression at most transfer points, including the
primary crushed ore conveyor, dry screen feed conveyor, lump stacking
conveyor, and fines stacking conveyor.
All conveyors are covered except in the stockyard to reduce dust lift off.
The stockyard will be serviced by automatic water cannons on either side
of the stockpiles.
Stacker boom conveyors will be fitted with head-end sprays and dust
shrouds.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
38
Environmental factor
Potential impacts Proposed management Section number
Commitment
Noise emissions Noise / Vibration impacts on fauna habitat, including potential roosting sites for bats
Implement the approved
Pilbara Leaf Nosed Bat
Environmental Management
Plan
6.3
Fitting vehicles and stationary items of equipment with exhaust mufflers;
Screening or enclosing stationary items of equipment with acoustic
enclosures to reduce operating nose levels.
Requiring contractors to comply with the Environmental Protection (Noise)
Regulations 1997.
Construction works must be carried out in accordance with Section 6 of
Australian Standard 2436-1981 “Guide to Noise control on Construction,
Maintenance and Demolition Sites” and the Environmental Protection
(Noise) Regulations 1997 (WA)
Implementation of Blast Management Plans for all blasting activities and
include an assessment of proximity to sensitive receptors, including
nearby communities, heritage rock shelters and bat cave locations
Prevent development in Pilbara Leaf Nosed Bat exclusion zones
Light Emissions Disruption to nocturnal fauna Disruption in PLNB roosting patterns
Implement the approved
Pilbara Leaf Nosed Bat
Environmental Management
Plan
6.5
Plant lighting design will comply with Australian standards for safe work.
Lighting design will ensure light is directed to work areas and minimal light
spill occurs.
Walkways and platforms that require permanent lighting at night will have
shrouded lenses and LED’s with optics that direct lighting only onto
walkways and platforms with minimal “spill” to reduce light spill.
Prevent development in Pilbara Leaf Nosed Bat exclusion zones
Discharge to Land
Potential contamination of soil and groundwater exists due to the possible presence of iron, hydrocarbons and chemicals within stormwater, leaks and spills associated with the construction of the fixed crushing and screening infrastructure.
Secondarily contain storage of
hydrocarbons and other
chemicals.
Separate all clean and
potentially contaminated water
sources.
6.7.2
Diversion of clean surface water around the work area to the extent
achievable by applying Rio Tinto Standard specification SS-N102
Sediment Control and Separation
Secondary containment of all chemical and hydrocarbon storage across
the entire site.
Approval process prior to mobilising any chemicals to site.
Drainage sumps to settle out sediments prior to discharge from the plant
area.
No permitted release of any potentially contaminated site water that has
not been checked for hydrocarbon contaminants.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
39
Environmental factor
Potential impacts Proposed management Section number
Commitment
Hydrocarbon Storage
Potential contamination of soil and groundwater exists due to the possible presence of hydrocarbons within stormwater.
All chemicals and
hydrocarbons used during
construction will be secondarily
contained in bunded storage
areas, approved chemical
cabinets or dual skinned tanks.
6.8
All storage tanks and transfer points will be above ground and secondarily
contained in accordance with AS1940:2004;
Vehicle refuelling will occur over compacted, lined earthen pad or a
concrete hardstand area (with the exception of field based machinery
refuelling where a drip tray will be used at the transfer point);
All piping will be above ground;
All tanks will be secondarily contained;
Substances in small volume packages (nominally 20 litres or less) will be
stored in a self bunded chemical cabinet or in a bunded area;
Containers and drums may be stored temporarily on self bunded pallets
or in a HDPE lined earthen bund. The capacity of the bunding must be at
least 100 percent of the volume of the largest container plus 25 percent of
the storage capacity up 10,000 litres as per AS1940:2004 s4.4.3; and
Spill kits suitable for the stored material being stored will be co-located
with all chemical storage areas.
Specially protected fauna
Land clearing impacts on Northern Quoll and Pilbara Leaf Nosed Bat
Implementation of the Northern
Quoll and Pilbara Leaf Nosed
Bat management Plans
6.10
Implementing the approved PLNB management plan;
Implementing an exclusion zone around the K75W Adit/cave System to
minimise noise and vibration impacts;
Implementing exclusion zones around the Koodaideri Spring Gorge
Foraging habitat;
Undertaking monitoring in accordance with the approved PLNB; and
Ensuring lighting is designed in accordance with Australian Standards
requirements for plant and some infrastructure.
Implementing the approved Northern Quoll Management plan;
Undertaking surveys to identify Northern quoll habitat, presence and
abundance within the mine plant development envelope;
Having the Northern Quoll management plan prepared and approved
prior to the commencement of ground-disturbing activities within 50
metres of the mapped Northern quoll foraging and denning habitat; and
Implementing protocols and procedures to monitor Northern Quoll
presence and abundance adjacent to the mine pit within the Mine/Plant
Area Development Envelope during construction and operation.
Specially protected flora
Land clearing impacts on Hamersley Lepidium (Lepidium catapycnon) and Sauropus sp. Koodaideri detritals now known as Synostemon hamersleyensis
Avoid direct disturbance of
known populations 6.10
Implementation of the Rio Tinto Approval Request and Ground
Disturbance Permitting system.
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
40
Appendices
A Drawings
KD-0000-F-DRG-00001 Process Plant – Process Flow Diagram
1000-EG-DWG-0003 Overall Site Building Set Out – General Arrangement
1000-EG-DWG-0004 Overall Site Building Set Out (1 of 6)
1000-EG-DWG-0005 Overall Site Building Set Out (2 of 6)
1000-EG-DWG-0006 Overall Site Building Set Out (3 of 6)
1000-EG-DWG-0007 Overall Site Building Set Out (4 of 6)
1000-EG-DWG-0008 Overall Site Building Set Out (5 of 6)
1000-EG-DWG-0009 Overall Site Building Set Out (6 of 6)
TEREX J-1840 Jaw Crusher Specification Sheet and Layout
TEREX 883 Mobile Screening Plant Specification Sheet and Layout
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
41
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
42
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
43
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
44
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
45
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
46
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
47
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
48
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
49
TEREX J-1840 Jaw Crusher
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078
RTIO-HSE-0327750
50
TEREX 883 Mobile Screening Plant
DocuSign Envelope ID: 62ED1C2C-A9FF-4707-B31B-CD6786EB587ADocuSign Envelope ID: D48B096D-ED6E-47A6-85A7-F37F96FE3078