kingston capital projects list

Upload: daily-freeman

Post on 03-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Kingston Capital Projects List

    1/5

    Capital Project List

    Project Priorities marked in RED (A) indicate that those Projects are already underway

    Project Priorities marked in BLACK (A/B/C) indicate that those Projects are under considerationProject Priorities unmarked indicate that those Projects require further discussion or investigation

    Category Project Name Description Justification Remarks Cost Priority

    Recreation

    Rondout Recreation Center HVAC

    Replace existing 40 year-old boiler and make

    necessary repairs to Air Conditioning system

    with controls

    Existing boiler is 40 years old and inefficient,

    air conditioning system is inadequate,

    precluding usage during hot weather

    A Community Development

    Project for 2013/14$100,000 A

    Kingston Point Park PavilionInstall new septic tank, pump chamber with

    pumps and force main to North Street Sewer

    These sewer improvements are part of a DEC

    Estuary Grant previously scheduled for

    completion last year; a time extension was

    granted through September, 2014

    Reimbursible to 75%, Need to

    coordinate with DPW forinstallation

    $10,000 A

    Rondout Lighthouse

    Rondout LighthouseProvide sewer and water service to the

    Rondout LighthouseEconomic Development $400,000

    City Hall

    City Hall Tower RehabilitationContinue rehabilitation of City Hall Tower and

    the Council Chambers

    Long-term stabilization of the structure withrepairs to Lunets damaged by water

    penetration

    $450,000 A

    City Hall Emergency Generator Install new Natural Gas Emergency GeneratorProvide for city-wide communications during

    loss of power

    Bid - Awaiting Award; Funded

    under separate Bond$75,000 A

    Transportation

    Abeel Street Reconstruction

    Realign and reconstruct Abeel Street from

    Broadway to Dock Street (FHWA Project)

    FHWA Project reimbursement of

    $4,120,000 (95% reimbursable)$206,000 A

    Washington Avenue Signals Upgrade

    Upgrade the traffic signals at Wahington

    Avenue intersections with North Front Street

    and Schwenk Drive (FHWA Project)

    FHWA Project reimbursement of

    $339,568 (95% reimbursable)

    $16,979 A

    Greenkill Avenue Bridge ReplacementReplace the Greenkill Avenue Bridge (FHWA

    Project)

    FHWA Project reimbursement of

    $3,600,000 (95% reimbursable)$180,000 A

    Broadway Sidewalk Replacement at

    City Hall

    No local match, will complete work already

    started by DPW, eliminates hazards

    $100,000 Local (100%

    reimbursable)$0 A

    Uptown Parking Garage Stairway

    Rehabilitation

    Repair / replace existing concrete stairs from

    North Front Street to at-grade lot below$50,000 A

    Rt. 9W & Rt. 32 Intersection

    Signalization

    Replace controllers, signal heads, cable towers

    and sensors; Install pedestrian crossings and

    count-down signals

    Controll equipment is failing, signal heads do

    not conform to size requirements, cable towers

    do not allow for raising the signal heads to the

    required elevation, traffic loop detection is non-functional; pedestrian crossings and

    signalization is non-existent

    Maintenance of this intersection is

    a City responsibility

    $300,000 A

    Washington Avenue ResurfacingMill and Fill from Lucas Avenue to Boulevard

    (30' W x 4750' L = 15,800 SY)

    Preservation, Continuity with previous work

    between Lucas and North Front and

    anticipated work at Tannery Brook crossing

    The paved surface was last

    reconstructed about 20 years ago

    (CHIPs)

    $160,000

  • 7/28/2019 Kingston Capital Projects List

    2/5

    Resurfacing and Striping of the North

    Front Street Parking Lots (2) and

    Broadway Lot

    Resurface and stripe the surface parking lots

    The existing lots are in very poor condition;

    restriping will provide for better circulation;

    improved lighting will enhance safety; Parking

    Permit dispenser will provide a mechanism to

    defray improvement costs and futuremaintenance

    project has been discussed for

    several years and has been on our

    list of "things to do"

    $250,000 A

    Safe Routes to SchoolsSidewalk and Street Crossing Improvements

    Grant

    Provide for enhanced access and safety to

    major school "walking" routes

    FHWA Project (100%

    Reimbursable)$0 A

    WWTP

    Hurricane Sandy - FEMA

    Reimbursement

    Reimbursement from FEMA upon completion

    of repairs, upgrades and hazard mitigation

    Upgrades to current standards may facilitate

    other improvements including Blowers,

    Filters, Emergency Generator

    Currenty Project Work worksheets

    detailing the proposed work totals

    nearly $3,000,000 at 89%

    reimburement rate

    $330,000 A

    Digester Concrete Repairs Concrete surface repairs at Digesters Encumbered 2013 expenseBid Awarded TO PIM Corporation

    for $71,785, encombrance$71,785 A

    Secondary Bar Rack Replace Secondary Bar ScreenExisting Bar Screen is at the end of its life

    expectancy$125,000 B

    Primary Tanks Flights and Drives Replace $50,000 C

    Primary Tanks Concrete RepairsConcrete surface repairs (49 Yrs) at Primary

    TanksDeteriorating concrete surfaces $100,000 B

    Primary Sludge Centrifugal Pumps (4) Replace aging pumps (41 Yrs) Pumps run continuously at capacity FEMA? $160,000 C

    Plant-Water Hydrants Replace aging plant-water hydrants (10 Each) Existing hydrants are 41 years old some areout of service

    $25,000 C

    Control-House BoilerReplace aging boiler, consolidate with Main

    Building boiler and Pelletizer Heat Exchanger

    New, consolidated boilers with heat exchanger

    recovery will provide greater energy efficiency

    with a pay-back estimated to be 7 years

    Main-Building BoilerReplace aging boiler, consolidate with Control-

    House boiler and Pelletizer Heat Exchanger

    New, consolidated boilers with heat exchanger

    recovery will provide greater energy efficiency

    with a pay-back estimated to be 7 years

    Settled Sewage Pumps DischargePiping and Mag-Meter

    Replace 14" Dia. Piping with 18" Dia. PipingIncreased pipe size will reduce piping headlossess and result in higher flow capacity to

    meet 2X requirement

    Regulatory / Energy Efficiency /Possibly NYSERDA Grant

    $250,000 A

    Aeration Blower Filters and

    Controllers with VFDs

    Remove and replace existing filter ystems and

    VFD controllers

    Existing controllers are 20 years old and

    subject to failure, also provide for

    commonality with Turbo-Blowers

    Energy Efficiency (7 Year

    Payback)$16,000 A

    500 Kw Natural Gas Emergency

    Generator

    Replace the existing 300 Kw Diesel

    Emergency Generator

    Currently two generators are required to

    provide sufficient electrical power to operate

    the WWTP, consolidating to one generator

    would reduce owning/operating costs, andcould be coordinated with all other electrical

    upgrades

    Diesel @ $100,000

    Natural Gas @ $200,000

    This work may be able to becoordinated with FEMA

    Reimbursements

    $200,000 A

    Stormwater

    AAeration Blowers

    Energy Efficiency (7 Year

    Payback)

    Energy Efficiency (7 Year

    Payback)

    $50,000

    $570,000Replace existing blowers with turbo blowers

    C

  • 7/28/2019 Kingston Capital Projects List

    3/5

    Kingston Plaza Levee Re-CertificationLoss of approximately $??M in assessed

    valuation

    $75,000 for Project Assessment,

    meeting with Congressman

    Gibson's Office scheduled for

    April 15

    $75,000 A

    Twaalfskill Creek Outlet Sediment

    RemovalRemove sediment by means of HydroVac

    Sediment build-up partially blocks outflow,

    reducing culvert capacity

    DPW Project / Equipment Rental

    and Material costs only$50,000 A

    Twaalfskill Creek Repairs Repair / Replace Gabion Basket Walls FEMA reimbursement $125,000 A

    Jacobs Valley Storm Sewer

    ReplacementReplace existing RCP

    Existing pipe is collapsed and causes the

    Broadway Underpass to flood periodically as

    well as Summer Street and a portion of

    Wiltwyck Cemetery; the Wiltwyck Cemetery

    has put the City on Notice.

    CSX will also be replacing the box

    culvert under the tracks and

    embankment between the

    Cemetery and the DPW Wilbur

    Ave Annex.

    $675,000 A

    Hurley Avenue Drainage

    Improvements (see Andy)

    Improve drainage of Hurley Avenue in the

    vacinity of #224 Hurley Ave. to NYS Thruway

    Solve drainage problem at #224 and also

    provide needed street drainage

    DPW Project / Equipment Rental

    and Material costs only $20,000 B

    Hurley Avenue Drainage

    Improvements (see Andy)

    Improve drainage of Hurley Avenue in the

    vacinity of #135 Hurley Ave.

    The existing storm drain is only 15" Dia CMP,

    a 30" Dia drain is required to adequately

    eliminate flooding

    A claim has been filed by #135

    Hurley Ave for flooding$200,000 B

    Roosevelt Park drainage Extension of existing storm sewers Localized flooding / Inflow to sanitary sewer DPW Project / material costs only $100,000 B

    Mid-Town Stormwater Connections

    (Pilot Project)

    Provide stormwater connections at sidewalk

    for downspout and sump pump drainage

    Remove I/I by providing stormwater

    onnections where alternative street

    connections are cost prohibitive

    A"Green Infrastructure" Project to

    provide convenient stormwater

    connections to property owners

    where density and physical

    features make it feasible

    $50,000 C

    Main Street Brook / Tannery Brook

    Watershed Development

    Develop watershed improvements for the

    control of flood waters (requires coordinated

    effort with the Town of Ulster)

    Flooding along the Tannery Brook and Main

    Street Brook result from uncontrolled runoff

    from Town of Ulster properties

    Currently working on the Tidal

    Rondout watershed Management

    Plan which will provide a segway

    into possible controls and

    cooperative effort with the Town

    of Ulster. A $250,000 Grant @

    75% Reimbursable utilizing In-

    Kind Services

    $62,500 A

    Amy Court Drainage (see Andy)

    Replace existing undersized drainage pipe

    (21") with that specified in subdivision plans

    (24")

    The existing undersized pipe restricts drainage

    system capacity, resulting in localized flooding

    at the Amy Court Couldesac (S. John Peters)

    DPW Project / material costs only $50,000 A

    Twin Ponds Outlet Improvements (see

    Andy)

    Stabilize and armour the Lower Pond

    embankment, develop stabilized emergency

    overflow and pond outlet pipe discharge

    Twin Ponds accepts and manages stormwater

    drainage from the Town of Ulster and portions

    of Linderman Avenue, enhancements at the

    Upper Pond Drain and Lower Pond Outlet will

    protect downstream properties from flooding

    An existing agreement provided

    for new outlet controls and

    protection at the Lower Pond,

    improvements to the embankment

    and drainage channel were to be

    accomplished by DPW

    $20,000 A

    Sanitary

    Washington Avenue Tunnel Repairs

    Reline the Stormwater Comparment with Link-

    Pipe and Slipline the Sanitary Sewer with

    HDPE

    Sink Holes in Washington Avenue, private

    property damage and reduced volitile organics

    on a mass basis at the WWTP

    Sliplining and related Tunnel and

    invert repairs "upstream" are

    ongoing, Stormwater repairs

    completed

    $1,880,000 A

    EDA Grant - Washington Avenue

    Tunnel

    Work includes soil stabilization in the

    Washington Avenue corridor, piping of the

    Tannery Brook and restoration of surfaces

    Sink Holes in Washington Avenue, private

    property damage and reduced volitile organics

    on a mass basis at the WWTP

    $1.4M Grant, 80% reimbursable $280,000 A

  • 7/28/2019 Kingston Capital Projects List

    4/5

    Grand Street and Broadway SewerReplace 100 year + concrete horse-collar

    sanitary sewer, separate stormwater.

    The Grand Street and Broadway concrete

    sewers have failed four times in the past four

    years, three times under emergency conditions,

    emergency repairs are very expensive

    Emergency closures to Broadway

    are very disruptive to the public

    and business interests

    $765,000 A

    Flatbush Avenue and Foxhall Avenue

    Sewer Replacement

    Replace existing undersized sewers with

    geometric issues (slope, configuration)

    The relocation of STAVO and Wolf Tech will

    add significant flow to a sewer with

    inadequate capacity.

    STAVO and Wolf Tech are

    relocating under an economic

    development initiative

    $940,000 B

    Washington Avenue TunnelA "planning-level" design for future use in the

    event of a Tunnel collapse

    Provide information for use in reaction to a

    possible future emergency (by-pass pumping

    rates / connections / detours / design

    alternatives)

    What-If senarios $25,000 A

    Abeel Street Sewer ReplacementSeparate sewers near Block Park that are

    tributary to the Block Park Pump Station

    Elliminate significant I/I to the Pump Station,

    and "regular" overflows

    The Block Park Pump Station is

    hydraulically overwhelmed at

    times during wet weather events

    $165,000 A

    Ponckhockie Street SewerInstall new sanitary sewer to service the homes

    on Ponckhockie Street

    There is currently no sanitary sewer on the

    dead-end portion of Ponckhonkie Street,

    individual laterals discharge through

    backyards and across other private property to

    connections on Gill Street, Abruyn and East

    Strand

    We've already begun looking into

    this project, and have dyed-out one

    home. A Community Development

    Project for 2013/14

    $100,000 A

    CSOs

    Sediment Removal at Wilber

    Pretreatment Pump StationRemoved sediment, dewater and dispose

    These tanks were cleaned several years ago

    and need to be done on a bi-annual basis to

    ensure proper operation of the system.

    $50,000 A

    Hunter Street CSO Separation Separate sewers to de-commission the CSO

    Remove regulatory and maintenance burden

    on DPW, improve water quality of the

    Rondout Creek. Eliminate need to comply

    with SPRTKA at this location

    $400,000

    SPRTKA Sewage Pollution Right to Know ActLaw requires public notification of sewer

    overflows

    Pending development of regulation

    by DEC$100,000

    Broadway CSO ImprovementsCSO Regulator improvements for

    maintenanceAccess is difficult $50,000 C

    Hasbrouck Regulator Upgrades Phase I of LTCP Implementation Subject of approval by NYSDECBid - Awaiting Award; Funded

    under separate Bond

    $328,272 A

    Pump Stations

    North Street, Frog Alley, North Street

    and Harding Ave Pump Station

    Improvements

    Replace pumps and increase wet well capacityPump Stations are hydraulically overloaded

    during periods of wet weather$400,000 A

    DPW

    Transfer Station CanapiesBid Awarded to Carey

    Construction for $65,000$65,000 A

    Wilber Complex improvements Construct equipment sheds and wash bays

    Heated storage is required for Sweeper and

    VacTruck, Wash Bays needed for vehicle

    cleaning, "Drying Bed" needed to dewater

    VacTruck waste

    $300,000 A

    Brush Dump ClosureClose brush dump located on Wiltwyck

    Cemetery Property

    Design submitted to DEC two years ago, City

    under Notice of Violation

    Awaiting DEC Approval of

    Closure Plan$200,000

  • 7/28/2019 Kingston Capital Projects List

    5/5

    Dedicated Vac Truck Crew for Catch

    Basin Cleaning

    Utilize existing back-up Vac Truck for the

    routine cleaning of catch basins city-wide

    The Esopus Creek was just designated as

    "Impaired", which will result in increase

    scrutinity of adjacent municipalities and their

    compliance with MS4 regulations

    Costs reflect estimated repairs to

    equipment$20,000 A

    PRIORITY A SPENDING

    (Previously Committed)$3,605,536

    PRIORITY A SPENDING $4,556,000

    PRIORITY B SPENDING $1,465,000

    PRIORITY C SPENDING $485,000