kingston capital projects list
TRANSCRIPT
-
7/28/2019 Kingston Capital Projects List
1/5
Capital Project List
Project Priorities marked in RED (A) indicate that those Projects are already underway
Project Priorities marked in BLACK (A/B/C) indicate that those Projects are under considerationProject Priorities unmarked indicate that those Projects require further discussion or investigation
Category Project Name Description Justification Remarks Cost Priority
Recreation
Rondout Recreation Center HVAC
Replace existing 40 year-old boiler and make
necessary repairs to Air Conditioning system
with controls
Existing boiler is 40 years old and inefficient,
air conditioning system is inadequate,
precluding usage during hot weather
A Community Development
Project for 2013/14$100,000 A
Kingston Point Park PavilionInstall new septic tank, pump chamber with
pumps and force main to North Street Sewer
These sewer improvements are part of a DEC
Estuary Grant previously scheduled for
completion last year; a time extension was
granted through September, 2014
Reimbursible to 75%, Need to
coordinate with DPW forinstallation
$10,000 A
Rondout Lighthouse
Rondout LighthouseProvide sewer and water service to the
Rondout LighthouseEconomic Development $400,000
City Hall
City Hall Tower RehabilitationContinue rehabilitation of City Hall Tower and
the Council Chambers
Long-term stabilization of the structure withrepairs to Lunets damaged by water
penetration
$450,000 A
City Hall Emergency Generator Install new Natural Gas Emergency GeneratorProvide for city-wide communications during
loss of power
Bid - Awaiting Award; Funded
under separate Bond$75,000 A
Transportation
Abeel Street Reconstruction
Realign and reconstruct Abeel Street from
Broadway to Dock Street (FHWA Project)
FHWA Project reimbursement of
$4,120,000 (95% reimbursable)$206,000 A
Washington Avenue Signals Upgrade
Upgrade the traffic signals at Wahington
Avenue intersections with North Front Street
and Schwenk Drive (FHWA Project)
FHWA Project reimbursement of
$339,568 (95% reimbursable)
$16,979 A
Greenkill Avenue Bridge ReplacementReplace the Greenkill Avenue Bridge (FHWA
Project)
FHWA Project reimbursement of
$3,600,000 (95% reimbursable)$180,000 A
Broadway Sidewalk Replacement at
City Hall
No local match, will complete work already
started by DPW, eliminates hazards
$100,000 Local (100%
reimbursable)$0 A
Uptown Parking Garage Stairway
Rehabilitation
Repair / replace existing concrete stairs from
North Front Street to at-grade lot below$50,000 A
Rt. 9W & Rt. 32 Intersection
Signalization
Replace controllers, signal heads, cable towers
and sensors; Install pedestrian crossings and
count-down signals
Controll equipment is failing, signal heads do
not conform to size requirements, cable towers
do not allow for raising the signal heads to the
required elevation, traffic loop detection is non-functional; pedestrian crossings and
signalization is non-existent
Maintenance of this intersection is
a City responsibility
$300,000 A
Washington Avenue ResurfacingMill and Fill from Lucas Avenue to Boulevard
(30' W x 4750' L = 15,800 SY)
Preservation, Continuity with previous work
between Lucas and North Front and
anticipated work at Tannery Brook crossing
The paved surface was last
reconstructed about 20 years ago
(CHIPs)
$160,000
-
7/28/2019 Kingston Capital Projects List
2/5
Resurfacing and Striping of the North
Front Street Parking Lots (2) and
Broadway Lot
Resurface and stripe the surface parking lots
The existing lots are in very poor condition;
restriping will provide for better circulation;
improved lighting will enhance safety; Parking
Permit dispenser will provide a mechanism to
defray improvement costs and futuremaintenance
project has been discussed for
several years and has been on our
list of "things to do"
$250,000 A
Safe Routes to SchoolsSidewalk and Street Crossing Improvements
Grant
Provide for enhanced access and safety to
major school "walking" routes
FHWA Project (100%
Reimbursable)$0 A
WWTP
Hurricane Sandy - FEMA
Reimbursement
Reimbursement from FEMA upon completion
of repairs, upgrades and hazard mitigation
Upgrades to current standards may facilitate
other improvements including Blowers,
Filters, Emergency Generator
Currenty Project Work worksheets
detailing the proposed work totals
nearly $3,000,000 at 89%
reimburement rate
$330,000 A
Digester Concrete Repairs Concrete surface repairs at Digesters Encumbered 2013 expenseBid Awarded TO PIM Corporation
for $71,785, encombrance$71,785 A
Secondary Bar Rack Replace Secondary Bar ScreenExisting Bar Screen is at the end of its life
expectancy$125,000 B
Primary Tanks Flights and Drives Replace $50,000 C
Primary Tanks Concrete RepairsConcrete surface repairs (49 Yrs) at Primary
TanksDeteriorating concrete surfaces $100,000 B
Primary Sludge Centrifugal Pumps (4) Replace aging pumps (41 Yrs) Pumps run continuously at capacity FEMA? $160,000 C
Plant-Water Hydrants Replace aging plant-water hydrants (10 Each) Existing hydrants are 41 years old some areout of service
$25,000 C
Control-House BoilerReplace aging boiler, consolidate with Main
Building boiler and Pelletizer Heat Exchanger
New, consolidated boilers with heat exchanger
recovery will provide greater energy efficiency
with a pay-back estimated to be 7 years
Main-Building BoilerReplace aging boiler, consolidate with Control-
House boiler and Pelletizer Heat Exchanger
New, consolidated boilers with heat exchanger
recovery will provide greater energy efficiency
with a pay-back estimated to be 7 years
Settled Sewage Pumps DischargePiping and Mag-Meter
Replace 14" Dia. Piping with 18" Dia. PipingIncreased pipe size will reduce piping headlossess and result in higher flow capacity to
meet 2X requirement
Regulatory / Energy Efficiency /Possibly NYSERDA Grant
$250,000 A
Aeration Blower Filters and
Controllers with VFDs
Remove and replace existing filter ystems and
VFD controllers
Existing controllers are 20 years old and
subject to failure, also provide for
commonality with Turbo-Blowers
Energy Efficiency (7 Year
Payback)$16,000 A
500 Kw Natural Gas Emergency
Generator
Replace the existing 300 Kw Diesel
Emergency Generator
Currently two generators are required to
provide sufficient electrical power to operate
the WWTP, consolidating to one generator
would reduce owning/operating costs, andcould be coordinated with all other electrical
upgrades
Diesel @ $100,000
Natural Gas @ $200,000
This work may be able to becoordinated with FEMA
Reimbursements
$200,000 A
Stormwater
AAeration Blowers
Energy Efficiency (7 Year
Payback)
Energy Efficiency (7 Year
Payback)
$50,000
$570,000Replace existing blowers with turbo blowers
C
-
7/28/2019 Kingston Capital Projects List
3/5
Kingston Plaza Levee Re-CertificationLoss of approximately $??M in assessed
valuation
$75,000 for Project Assessment,
meeting with Congressman
Gibson's Office scheduled for
April 15
$75,000 A
Twaalfskill Creek Outlet Sediment
RemovalRemove sediment by means of HydroVac
Sediment build-up partially blocks outflow,
reducing culvert capacity
DPW Project / Equipment Rental
and Material costs only$50,000 A
Twaalfskill Creek Repairs Repair / Replace Gabion Basket Walls FEMA reimbursement $125,000 A
Jacobs Valley Storm Sewer
ReplacementReplace existing RCP
Existing pipe is collapsed and causes the
Broadway Underpass to flood periodically as
well as Summer Street and a portion of
Wiltwyck Cemetery; the Wiltwyck Cemetery
has put the City on Notice.
CSX will also be replacing the box
culvert under the tracks and
embankment between the
Cemetery and the DPW Wilbur
Ave Annex.
$675,000 A
Hurley Avenue Drainage
Improvements (see Andy)
Improve drainage of Hurley Avenue in the
vacinity of #224 Hurley Ave. to NYS Thruway
Solve drainage problem at #224 and also
provide needed street drainage
DPW Project / Equipment Rental
and Material costs only $20,000 B
Hurley Avenue Drainage
Improvements (see Andy)
Improve drainage of Hurley Avenue in the
vacinity of #135 Hurley Ave.
The existing storm drain is only 15" Dia CMP,
a 30" Dia drain is required to adequately
eliminate flooding
A claim has been filed by #135
Hurley Ave for flooding$200,000 B
Roosevelt Park drainage Extension of existing storm sewers Localized flooding / Inflow to sanitary sewer DPW Project / material costs only $100,000 B
Mid-Town Stormwater Connections
(Pilot Project)
Provide stormwater connections at sidewalk
for downspout and sump pump drainage
Remove I/I by providing stormwater
onnections where alternative street
connections are cost prohibitive
A"Green Infrastructure" Project to
provide convenient stormwater
connections to property owners
where density and physical
features make it feasible
$50,000 C
Main Street Brook / Tannery Brook
Watershed Development
Develop watershed improvements for the
control of flood waters (requires coordinated
effort with the Town of Ulster)
Flooding along the Tannery Brook and Main
Street Brook result from uncontrolled runoff
from Town of Ulster properties
Currently working on the Tidal
Rondout watershed Management
Plan which will provide a segway
into possible controls and
cooperative effort with the Town
of Ulster. A $250,000 Grant @
75% Reimbursable utilizing In-
Kind Services
$62,500 A
Amy Court Drainage (see Andy)
Replace existing undersized drainage pipe
(21") with that specified in subdivision plans
(24")
The existing undersized pipe restricts drainage
system capacity, resulting in localized flooding
at the Amy Court Couldesac (S. John Peters)
DPW Project / material costs only $50,000 A
Twin Ponds Outlet Improvements (see
Andy)
Stabilize and armour the Lower Pond
embankment, develop stabilized emergency
overflow and pond outlet pipe discharge
Twin Ponds accepts and manages stormwater
drainage from the Town of Ulster and portions
of Linderman Avenue, enhancements at the
Upper Pond Drain and Lower Pond Outlet will
protect downstream properties from flooding
An existing agreement provided
for new outlet controls and
protection at the Lower Pond,
improvements to the embankment
and drainage channel were to be
accomplished by DPW
$20,000 A
Sanitary
Washington Avenue Tunnel Repairs
Reline the Stormwater Comparment with Link-
Pipe and Slipline the Sanitary Sewer with
HDPE
Sink Holes in Washington Avenue, private
property damage and reduced volitile organics
on a mass basis at the WWTP
Sliplining and related Tunnel and
invert repairs "upstream" are
ongoing, Stormwater repairs
completed
$1,880,000 A
EDA Grant - Washington Avenue
Tunnel
Work includes soil stabilization in the
Washington Avenue corridor, piping of the
Tannery Brook and restoration of surfaces
Sink Holes in Washington Avenue, private
property damage and reduced volitile organics
on a mass basis at the WWTP
$1.4M Grant, 80% reimbursable $280,000 A
-
7/28/2019 Kingston Capital Projects List
4/5
Grand Street and Broadway SewerReplace 100 year + concrete horse-collar
sanitary sewer, separate stormwater.
The Grand Street and Broadway concrete
sewers have failed four times in the past four
years, three times under emergency conditions,
emergency repairs are very expensive
Emergency closures to Broadway
are very disruptive to the public
and business interests
$765,000 A
Flatbush Avenue and Foxhall Avenue
Sewer Replacement
Replace existing undersized sewers with
geometric issues (slope, configuration)
The relocation of STAVO and Wolf Tech will
add significant flow to a sewer with
inadequate capacity.
STAVO and Wolf Tech are
relocating under an economic
development initiative
$940,000 B
Washington Avenue TunnelA "planning-level" design for future use in the
event of a Tunnel collapse
Provide information for use in reaction to a
possible future emergency (by-pass pumping
rates / connections / detours / design
alternatives)
What-If senarios $25,000 A
Abeel Street Sewer ReplacementSeparate sewers near Block Park that are
tributary to the Block Park Pump Station
Elliminate significant I/I to the Pump Station,
and "regular" overflows
The Block Park Pump Station is
hydraulically overwhelmed at
times during wet weather events
$165,000 A
Ponckhockie Street SewerInstall new sanitary sewer to service the homes
on Ponckhockie Street
There is currently no sanitary sewer on the
dead-end portion of Ponckhonkie Street,
individual laterals discharge through
backyards and across other private property to
connections on Gill Street, Abruyn and East
Strand
We've already begun looking into
this project, and have dyed-out one
home. A Community Development
Project for 2013/14
$100,000 A
CSOs
Sediment Removal at Wilber
Pretreatment Pump StationRemoved sediment, dewater and dispose
These tanks were cleaned several years ago
and need to be done on a bi-annual basis to
ensure proper operation of the system.
$50,000 A
Hunter Street CSO Separation Separate sewers to de-commission the CSO
Remove regulatory and maintenance burden
on DPW, improve water quality of the
Rondout Creek. Eliminate need to comply
with SPRTKA at this location
$400,000
SPRTKA Sewage Pollution Right to Know ActLaw requires public notification of sewer
overflows
Pending development of regulation
by DEC$100,000
Broadway CSO ImprovementsCSO Regulator improvements for
maintenanceAccess is difficult $50,000 C
Hasbrouck Regulator Upgrades Phase I of LTCP Implementation Subject of approval by NYSDECBid - Awaiting Award; Funded
under separate Bond
$328,272 A
Pump Stations
North Street, Frog Alley, North Street
and Harding Ave Pump Station
Improvements
Replace pumps and increase wet well capacityPump Stations are hydraulically overloaded
during periods of wet weather$400,000 A
DPW
Transfer Station CanapiesBid Awarded to Carey
Construction for $65,000$65,000 A
Wilber Complex improvements Construct equipment sheds and wash bays
Heated storage is required for Sweeper and
VacTruck, Wash Bays needed for vehicle
cleaning, "Drying Bed" needed to dewater
VacTruck waste
$300,000 A
Brush Dump ClosureClose brush dump located on Wiltwyck
Cemetery Property
Design submitted to DEC two years ago, City
under Notice of Violation
Awaiting DEC Approval of
Closure Plan$200,000
-
7/28/2019 Kingston Capital Projects List
5/5
Dedicated Vac Truck Crew for Catch
Basin Cleaning
Utilize existing back-up Vac Truck for the
routine cleaning of catch basins city-wide
The Esopus Creek was just designated as
"Impaired", which will result in increase
scrutinity of adjacent municipalities and their
compliance with MS4 regulations
Costs reflect estimated repairs to
equipment$20,000 A
PRIORITY A SPENDING
(Previously Committed)$3,605,536
PRIORITY A SPENDING $4,556,000
PRIORITY B SPENDING $1,465,000
PRIORITY C SPENDING $485,000