kick off meeting city of pensacola april 18, 2011

12
Kick Off Meeting City of Pensacola April 18, 2011

Upload: harold-gordon

Post on 17-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Kick Off Meeting

City of PensacolaApril 18, 2011

• Study Purpose• Determine the best solution for replacement of the existing

bridges and secure FHWA approval of the location and concept design

• Basis for performing the replacement bridge study• Lack of modern safety provisions• No facilities for bikes and pedestrians• Does not meet current navigation requirements• Deteriorating conditions indicate that bridges are structurally

obsolete• Determine the requirements to meet increasing traffic

demands

Project Development &

Environment Study

Planning

Preliminary Design

Final Design

Right-of-Way/ Acquisition

Construction

• Candidate Projects Based on Preliminary Analysis and determination of need

• Prioritize Projects• Funding Options/Availability Reviewed/Programming

• Develop Preliminary Alternatives• Assessment of Potential Environmental & Community

Impacts • Substantial Public Involvement Initiatives• Preferred Alternative(s) advance to Preliminary Engineering

• Develop up to 30% Design Plans• Additional Public Outreach• Agency Coordination

• Proceed through Design, 60, 90 % plans

• Permitting Process• Final Cost Estimates

• Proceed with acquisition of necessary property

Project Development & Environment Study

• Evaluate Current Conditions – Data Collection

• Environmental, Social, Engineering• Forecast Future Needs – Traffic• Evaluate Alternative Corridors & Select One• Develop Alternatives Within Selected

Corridor• Perform Assessments of Potential

Environmental & Community Impacts • Select an Alternative to advance into

Preliminary Engineering

One – On – One

Meetings

Website

pensacolabaybridge.com

Newsletters

Community

Stakeholders

Neighborhood

Associations

Informal Public

Meetings

Special Interest

Groups

Project Advisory

Group (PAG)

Local, State

& Federal

Officials

Local Government

• Throughout the study conduct a comprehensive and continuous Public Involvement Program

Contact US!!

J. Brandon Bruner, PEProject Development EngineerFDOT, District 31074 Highway 90Chipley, FL [email protected]

Dan Kristoff, PEProject ManagerRS&H 10748 Deerwood Park Blvd SouthJacksonville, FL 32256-0597Phone: 904-256-2139 [email protected]

Nick Arnio, PE, PTOEDeputy Project ManagerRS&H1701 Hermitage Blvd., Suite 101Tallahassee, FL  32308Phone: 850-558-2800 [email protected]

www.PensacolaBayBridge.com

Kick Off Meeting

City of PensacolaApril 18, 2011