kamal (1)
TRANSCRIPT
-
7/31/2019 Kamal (1)
1/50
A
INDUSTRIAL TRAINING REPORT
ON
SURATGARH THERMAL POWER PLANT
(05.06.2012-05.07.2012)
SUBMITED IN PARTIAL FULFILLMENT
FOR THE AWARD OF THE DEGREE OF
BACHELOR OF TECHNOLOGY
(RAJASTHAN TECHNICAL UNIVERSITY,KOTA)
IN
ELECTRICAL ENGINEERING
SESSION (2012-2013)
SUBMITTED TO: SUBMITTED BY:
Ekta Sharma Kamlesh Palsaniya
HOD of Electrical department EE & 7th sem.
G.I.T 09EGJEE028
DEPARTMENT OF ELECTRICAL ENGINEERING
GLOBAL INSTITUTE OF TECHNOLOGY
ITS PARK RIICO SITAPURA, JAIPUR-302022
-
7/31/2019 Kamal (1)
2/50
ChaptersChapters Page no.Page no.
# ACKNOWLEDGEMENT I
# ABSTRACT II
# MATTER OF TRAINING IIIMATTER OF TRAINING III
LIST OF CONTENTSCONTENTS
1. INTRODUCTION 1
2. SITE SELECTION 2
3. COAL HANDLING PLANT 53.1 Coal Feeders 5
3.1.1 Drag Link coal feeder 6
4. ASH HANDLING PLANT 8
5. DUST EXTRACTION SYSTEM 9
5.1 Electrostatic Preceptors 9
5.2 Description 10
5.3 Electrical System 11
5.4 Interlocking System 11
6. THERMAL POWER GENERATION 126.1Boiler 12
6.2 Electrostatic Precipitator 13
6.3Turbine 13
6.4 Condenser 13
6.5 Deaerater 13
6.6 Boiler feed pump 14
6.7 Generator 14
6.8 HP-LP Bypass System 15
7. REGENERATIVE SYSTEM OF 250 MW UNIT 18
8. TURBO GENERATOR 19
8.1 Stator frame 19
8.2 Stator core 20
8.3 Stator bars 22
8.4 Stator windings 23
8.5 Terminal bushings 24
8.6 Bearings 24
8.7 Ventilation system 24
8.8 Measurement of bearing temperature 26
-
7/31/2019 Kamal (1)
3/50
9. ROTOR 27
9.1 Rotor windings 28
9.2 Bearings 28
9.3 Slip rings 299.4 Bush gear assembly 29
9.5 Drying of windings 30
10. COOLING SYSTEMS 31
10.1 General 31
10.2 Hydrogen Dryers 32
10.3 Hydrogen filling systems 32
11. EXCITATION SYSTEM 33
11.1 Functions of excitation system 33
11.2 Types of excitation system 33
11.3 Static excitation system 34
11.4 Rectifier transformer 35
11.5 Thyristor converter 35
11.5.1 Automatic voltage controls 35
11.6 field suppression system 36
11.7 Advantages of static excitation system 37
11.8 Operation 37
11.8.1 Synchronizing 37
11.8.2 Machine connected on infinite bus 38
12. TRANSFORMER 3812.1 Station transformer 38
12.2 Unit auxiliary transformer 39
12.3 Unit station transformer 40
12.4 Unit service transformer 40
13 DIFFERENT EQUIPMENTS AND BUS SCHEMES 41
13.1 Bus scheme 41
13.2 Bus system 41
13.3 Sf6 gas C.B. 42
13.4 Isolators 43
13.5 Change over schemes 43
13.6 Bus coupler to main breaker 44
13.7 Synchronization of generator to grid 44
13.8 Current transformers 45
13.9 Lightning arresters 45
13.10 Capacitive voltage transformer 45
13.11 Battery 220V DC 45
13.12 Earth shielding 46
-
7/31/2019 Kamal (1)
4/50
14. POWER LINE CARIEER COMMUNICATION 47
15. DATA SHEET & SPECIFICATIONS 49
16. ABOUT AVR 51
#References 53
Table List
Tables Page
11.1 Type of cooling for station transformer 38
11.2 Voltage at no load 39
11.1 Specifications of sf6 gas circuit breakers 50
Figure List
Figures Page
Figure 2.1 Plant overview 4
Figure 3.1 Coal handling plant 7
Figure 5.1 Feed water system 16
Figure 5.2 Air & FG system 17
Figure 7.1 Turbine Generator overview 21
Figure 13.1 Overview of PLCC 47
Figure 13.2 block diagram of PLCC 48
-
7/31/2019 Kamal (1)
5/50
ACKNOWLEDGEMENT
This is opportunity to express my heartfelt words for the people who were part of this training
in numerous ways, people who gave me unending support right from beginning of the training.
I am grateful to training incharge Mr. H.K. Tomar, Xen. STPS for giving guidelines to make
the project successful.
I want to give sincere thanks to the Prof. C. M. Arora, Technical Director of Global Technical
Campus and Dr. Renu Joshi, Director of Global Institute of Technology for her valuable
support.
I extend my thanks to Mrs. Ekta Sharma, Head of the Department of Electrical Engineering
for her cooperation and guidance.
Kamlesh Palsaniya
VII Sem.
09GJEE028
CHAPTER 1
-
7/31/2019 Kamal (1)
6/50
INTRODUCTION
1.1 SURATGARH SUPER THERMAL POWER STATION
STPS is situated near village Thukrana about 27 km South East of Suratgarh town is Sri
Ganganagar District. Suratgarh was considered an ideal location for setting up a thermal power
station in the state having regards to the availability of land, water, transmission network
proximity to broad gauge railway and being an important load centre for North West Rajasthan.
The techno-economic clearance for the prefect was issued by CEA in June 1991 the planning
commission accorded investment sanction for the project in Nov. 91 for a total estimated cost
of Rs. 1253.31 cores on prices prevailing in Sept. 1990. the updated cost of the project is
estimate at Rs. 2300 cores of including IDC
1.2 NEED FOR POWER STATION :-
Rajasthan is the second largest in the country. About 30% Population lives in
village which are local point of development while Rajasthan mineral resources are immense.
But its resources for power station generation not immensurable with the requirement more
over the state government has drawn up a ruler of electrification program with a large demand
on agricultural load with rapid adoption & modern method of agricultural and industrialization
of towns. The mode of living of people in rural and urban areas as changing rapidly with
requirement of more power.
CHAPTER 2
SELECTION OF SITE FOR STEAM POWER PLANTS
-
7/31/2019 Kamal (1)
7/50
INTRODUCTION:-
This is necessary to choose the location of plant. Generally
almost power plants are located where all requirements should be fulfilled like
as following
2.1. SUPPLY OF WATER:-
A large quantity of water is required in steam power plants. It is required:
(I) It raises the steam in the boiler.
(II) For cooling purposes such as in condensers.
(III) As a carrying medium such as in disposal of ash.
(IV) For drinking purposes.
The efficiency of direct cooled plant is about 0.5% higher than that of the plant in which
cooling towers are used. This means a saving of about Rs. 7.5 lacs per year in fuel cot for a
2000 MW station
2.2 REQUIREMENT OF LAND:-
The land is required not only for setting up of the plant but also for other purposes such
as staff colonies, coal storage, ash disposal etc. cost of land adds to the final cost of the plant.
So it should be available at a reasonable cost. Land should be of good bearing capacity since it
has to withstand about 7 Kg. Per Sq. Cm. Moreover, land should be reasonably level.
2.3 TRANSPORTATION FACILITY:-
The land and rail connections should be proper and capable of taking heavy and over
dimensioned loads of machines etc. To carry coal, oil etc. which are daily requirements, we
need these transport linkages.
2.4 LABOUR SUPPLIES:-
Skilled and unskilled laborers should be available rates near the site the plant.
2.5 ASH DISPOSAL:-Ash is the main waste product of the steam power plant. Hence
some suitable means for disposal of ash should be applied. Ash can be purchased by building
contractors, cement manufacturers or it can be used for brick making near the plant site.
Otherwise wasteland should be available near the plant site for disposal of ash.
-
7/31/2019 Kamal (1)
8/50
-
7/31/2019 Kamal (1)
9/50
Fig. 2.1 Plant OverviewFig. 2.1 Plant Overview
CHAPTER 3CHAPTER 3
COAL HANDLING PLANTCOAL HANDLING PLANT
Wagon tippler has rated unloading capacity of twelve box wagon per hour, including
shunting and spotting time of haulage equipment.
For vibrating feeders of capacity 350 tons/hr. each have been provided feeding unloads
coal. A steel hopper has been provided in crusher house to receive coal and distribute it through
manually operated rack and pinion gate to three vibrating screens of 675 t/hr. capacity each
coal above 200 mm size passes on granules for crushing and reduction in size. Coal below 20
mm size passes granular and discharged on to crushed coal conveyor belt.
Following permutation and combination of operation are possible with installed system.
To transfer all crushed coal received from crusher house to live storage pipe. To transfer part of
received crushed coal to plant and to balance to storage yard. To deliver the raw coal bunkers
-
7/31/2019 Kamal (1)
10/50
part and received crushed coal mixed with balanced coal from the live storage pipe. To transfer
the plant crushed coal at 750 T/hr from the reclaim live pile and simultaneously stock and s/
road. the vibrating ones as stated above can be obtained by the use of flap gates which are
installed on various chute and two vibrating feeders, installed on tower. The coal carried on
various conveyers shall be main monitored to ensure proper loading and distributing weightless
and vibrating feeders.
3.1 COAL FEEDERS
Coal feeders deliver the cola from the bunkers to the mill. Since the amount of coal delivered
determines the output of the mill, if follows that the cola flow, through the feeder has to be
controlled. This is normally achieved either by control of feeder speed or by control of the
position of a scraper knife or plough.
3.1.1 Drag Link Coal Feeders:-
In this type of cola feeder, the coal leaves the bottom of the bunker through a large
outlet hopper which is connected directly to the feeder casing. The cola falls on the feeder top
plate and is dragged along by the conveyor chain to the point where the top plate ends. The
depth of the cola bed is controlled by the height regulating gate. At the end of the top plate the
cola falls down between the stands of the chains to the Point of discharge at the mill inlet coal
delivery chute. The rate of coal feeds controlled by variable speed motor drive.
-
7/31/2019 Kamal (1)
11/50
.
-
7/31/2019 Kamal (1)
12/50
Fig.3.1 Coal Handling Plant
CHAPTER 4CHAPTER 4
DUST EXTRACTION PLANTDUST EXTRACTION PLANT
-
7/31/2019 Kamal (1)
13/50
In plant the methods used for the removal of dust from gases are ELECTROSTATIC
PRECIPITATOR which uses electrical forces to remove the dust from the gas stream.
4.1 Electrostatic Precipitators
Working Principle:- The principles upon which an electrostatic precipitator operates are thatthe dust laden gases pass into a chamber where the individual particles of dust are given an
electric charge by absorption of free ions from a high voltage d.c. ionizing field. Electric forces
cause a steam of ions to pass from the discharge electrodes to the collecting electrodes and the
particles of dust entrained in the gas are deflected out o the gas steam into the collecting
surfaces where they are retained, either by electrical or molecular attraction. They are removed
by an intermittent blow usually referred to as rapping, this causes the dust particles to drop into
dust hoppers situated below the collecting electrodes.
There are four different steps in the process of precipitation
1. Ionization of gases and charging of dust particles.
2. Migration of the particle to the collector.
3. Deposition of charged particles on the collecting surface.
4. Dislodging of particles from the collecting surface.
Performance Criteria:
The performance of the electrostatic precipitator depends on several factors among which the
prominent are:
Characteristics of dust:
a) Particle size distribution
b) Dust loading
c) Chemical composition
d) Electrical resistively
e) Adhesive/cohesive properties
Characteristics of gases :
a) Temperature.
b) Chemical composition
c) Moisture content
d) Quantity to be handled
e) pressure
-
7/31/2019 Kamal (1)
14/50
4.2 Description:-
The electrostatic precipitator essentially consists of two sets of electrodes, one in
the from of thin wires called discharge or emitting electrodes and other set called collecting
electrodes in the from of pipes or plates. The emitting electrodes are placed in the centre of pipeor midway between two plates and are connected usually to negative polarity of high voltage
d.c. source if the order if 25-100 kv. The collecting electrodes are connected to the positive
polarity of the source and grounded.
The major fundamental parts of the electrostatic precipitator consist of the following:-
1. Casing
2. Hoppers
3. Has distributor screen
4. Collecting System
5. Emitting system
6. Rapping mechanism for collecting system
7. Rapping mechanism for emitting system
8. Insulator housing
4.3 Electrical System:-
For optimum functional efficiency of the precipitator, the supply voltage cloud
is maintained near the flash over level between the precipitator electrodes. This can be achieved
by an electronic control system which rises the output voltage to flash over level and reduces it
automatically by a small amount in the event of a flash over.
4.4 Interlocking System:
This system is designed for the safety of the personnel and protection of
equipment during the operation and maintenance. This system will not operate unless the
instructions are followed sequentially.
The system consists of rotary switches interlocks and key exchange boxes. The exchange
boxes are located in control room and at prominent places on the precipitator casing.
CHAPTER 5
THERMAL POWER GENERATION
-
7/31/2019 Kamal (1)
15/50
Steam and water undergo various phases of Carnot Cycle in the Boiler, Turbine and other
equipments during this process.
In Thermal Power Station, fossil coal is used as fuel for steam generation in the Boiler.
Steam so generated is utilised in Steam Turbine to generate mechanical energy for rotating the
Generator for producing electric power.
5.1 BOILER:-
Steam is generated by burning very fine pulverised coal in the Boiler. Initially in the
furnace the coal is burned with the help of oil. But afterwards oil support is withdrawn, when
the furnace temperature reaches to 1150c.
The heat generated by the combustion of coal is absorbed by water (De-mineralised) in the
boiler tubes where it gains sensible heat and latent heat. Air required for combustion of coal
consists of primary air, which transports pulverised coal in the mills to furnace and secondary
air. PA fans supply primary air and SA fans supply secondary air. Flue gases generated in the
process of combustion are removed from the furnace by ID fans and dispersed in the
atmosphere through 220 M high chimney.
Water heated up in the boiler tubes is converted into steam at saturation temperature and
further heated up in the superheater tubes to a temperature of 540 degree C and 149 KG/CM2.
5.2 ELECTROSTATIC PRECIPITATOR:-
Combustion products i.e. flue gases and ash passes through electrostatic precipitator before ID
fans and chimney for separation of ash from flue gases. Electrostatic precipitator has large no
of electrodes charged at voltage of 30 KV. Due to electrostatic force ash particles are attracted
and impinge upon the electrode thus separates ash from flue gases.
5.3 TURBINE:-
The superheated steam when enters the turbine passes through the blades ofturbine creates a couple of force and makes the turbine to rotate. Thus thermal energy is
converted into mechanical energy.
Steam is first entered in HP Turbine; after doing work in HP Turbine,
temperature & pressure of steam gets reduced. This steam is sent to the Boiler for re-
heating in the Re-Heater tubes where the temperature of the steam is raised and it is further
entered in the IP Turbine and LP Turbine. Steam coming out of turbine is at a very low
pressure (vacuum) and temperature (50 degree C).
-
7/31/2019 Kamal (1)
16/50
5.4 CONDENSER:-
Steam at exhaust of turbine is condensed by its latent heat. Cooling water of
lower temperature is passed through tubes in the condenser. Steam in the condensersurrounding these tubes reject latent heat to cooling water and gets condensed into water
called condensate which is accumulated in the hot well.
5.5 DEAERATER:-
Condensate from hot well is pumped to de aerator by condensate extraction
pump. Functions of de aerator are: -
1. Removal of dissolved air/oxygen in boiler water.
2. Chemical dosing for maintaining quality of boiler water.3. Regenerative heating of feed water for increasing its temperature and efficiency of
plant.
4. Storage of feed water in water/steam cycle.
5.6 BOILER FEED PUMP:-
It is a very important equipment of power station boiler feed pump pumps water from
de aerator to boiler at very high pressure of about 190KG /CM2. In this process feed water is
passed through high pressure heaters where its heating is done by steam taken turbine toincrease the efficiency of plant.
5.7 GENERATOR:-
Mechanical energy is converted into electric power the stator windings of
generator by the interaction of rotating magnetic field. Rotating magnetic field is created by
field windings mounted on rotor shaft with the help of excitation system. When the shaft is
rotated at 3000 RPM by the coupled turbine electric power is generated at a voltage 16.5
KV and 50 HZ frequency. Generator is filled with hydrogen gas for cooling its windingwhich in turn is cooled by circulating water. The voltage of such generated electricity is
step up to 220kv or 400kv through transformer and power transmitted to Ratangarh GSS for
Northern Grid, and different areas of Rajasthan.6.0 million units energy is generated in 250
MW unit in a single day, out of this about ten percent is consumed in unit itself for running
its auxiliary equipments like pumps, fans etc. about 3300 metric tons of coal is consumed in
one 250 MW unit in one day.
-
7/31/2019 Kamal (1)
17/50
5.8 HP-LP BYPASS SYSTEM
This bypass system has been provided to allow the steam generator to build up, during
start-up, matching steam parameter with the tribune. The steam generated is dumped into the
condenser, thus avoiding loss of boiler water. This system enables starting of he unit of sliding
parameters and also facilitates hot restarting of the unit. In the event of loss of load on the
turbine, the bypass system disposes the steam produced by; the boiler automatically to he
condenser without affecting the boiler operation.
The bypass system had two sections: HP & LP. The HP-Bypass system diverts the
steam before main steam valve to he cold reheat CRH line. HP Bypass system also reduces the
rated steam parameters of the incoming steam from the superheated to the steam condition
expected in the CRH line (i.e. steam temp. and pressure after HP turbine exhaust).
The LP Bypass diverts the incoming steam from hot reheat line before intercepting
valves to he condenser after reducing the HRH steam parameters to the conditions
approximately to that of LP steam turbine exhaust steam.
HP Bypass station is utilised for the following tasks:
1. To establish flow at the outlet of superheated for raising boiler parameters during starts up.
2. To maintain or controls steam pressure at pre-set value in main steam line during start up.
3. To warm up the steam lines.
4. To control steam temperature down of HP bypass at the reset value
LP Bypass station is utilised for the following tasks:
1. Control of steam pressure after reheater.
Establish flow of steam from reheat lines to condenser by its opening, proportional to the
opening of HP bypass valves.
-
7/31/2019 Kamal (1)
18/50
-
7/31/2019 Kamal (1)
19/50
Fig. 5.1 Feed Water SystemFig. 5.1 Feed Water System
-
7/31/2019 Kamal (1)
20/50
-
7/31/2019 Kamal (1)
21/50
Fig.5.2 Air & FG SystemFig.5.2 Air & FG System
CHAPTER 6
Regenerative system of 250 MW units
And Ash handling plant
The regenerative system of the turbine consists of four low-pressure heaters, two gland
coolers, one deaerator and three high-pressure heaters. The condense is drawn by condensate
pumps from the hot well of condenser and is pumped to the deaerator through gland coolers
and low pressure heaters where it is progressively heated up by the steam extracted from seals
and bled points of the turbine. The drain of condensate steam on LP heaters No. 2,3 and 4 flows
in cascade and is ultimately pumped into the main condenasate line after heater No.2 or flows
to condenser. The feed water after being deaerated in the deraerator is drawn buy the boiler
feed pump and pumped to boiler through high pressure heaters where it is heated up by the bled
steam from the turbine. The drain of condensed steam of HP heaters flows in cascade and under
normal load conditions flows to the deaerator.
6.1 ASH HANDLING PLANT6.1 ASH HANDLING PLANT
The ash handling system provide for continuous collection of bottom ash from the
furnace hearth and its intermittent removal by hydro ejectors to a common slurry sump. It also
-
7/31/2019 Kamal (1)
22/50
provides for removal of fly ash to the common slurry sump. Each boiler is provided with ash
precipitator for collecting the fly ash from the flue gases with high efficiency of collection to
minimize the dust mains and to reduce the wear of induced draft fan. The fly ash separated
from flue gases in the ash precipitator is collected in hoppers at the bottom from where it is
mixed with water to form slurry and disposed off to pumping area by means of hydro ash
pumps. Bottom ash from the boiler furnace is passed through slag crushers and then slurred to
the slurry chamber at the suction of the ash disposal pumps. These are high pressure and low
pressure pumps for this purpose. At a time one pump is working and other two are stand by.
From the ash disposal pump house ash slurry is pumped through pipe lines to the ash dump
area within about 1.5 km away from the ash disposal pump house. Too separate discharge lines
are provided one for each unit but only one line is used. The ash slurry from the two units is
taken in one discharge line through electrically operated valves
CHAPTER 7
TURBO GENERATORTURBO GENERATOR
INTRODUCTION:- Turbo generator manefactured by BHEL in Co-Operate with
most modern design concept and constructional features which ensures reliability, easy and
constructional and operational economicity.
The generator stator is a tight construction, supporting and enclosing the stator wdgs,
core and hydrogen coolers. Cooling medium hydrogen is contained within a frame and
circulated by fans mounted at either ends of rotor. The Generator is driven by directly cpupiedsteam turbine at a speed of 3000 r.p.m. The generator is designed for continuous operation at
rated O/P.
Temp. detector and other devices installed or connected within the M/c, permit the
measrement of wdgs, teeth core, and hydrogen temp. hydrogen pressure and purity in M/C
under the conditions.
-
7/31/2019 Kamal (1)
23/50
The Source of excitation to rotor wdgs is thyristorised D.C. supply. The Ausiliary
equipment supplied with M/C superrises and enables the control of hydrogen pressure and
purity, shaft sealing lubricating oils.
There is a provision for cooling water in order to maintain a constant temp. of coolant
(hydrogen) which controls the temp. of wdg., core etc as per loads.
7.1 STATOR FRAME :-
The stator frame of welded steel frame construction which gives sufficient
strength and rigidity necessary to minimise the vibrations and to with stand thermal gas
pressure. Heavy end shields enclose the enels of frame and from mountings of generator
bearings and radial shaft seals. The frame is qub divided by ribs and axial members to form
duct from which the cooling gas passes to and from the radial ducts in the core and in
recirculated through internally mounted coolers. All the gas ducts are designed so a s to reduce
balanced distribution of hydrogen to all parts of the core. The stator, constructed in a single
piece, houses the core and wdge. The horizontally mounted water cooled gas cooler being so
arranged that it may be cleaned on the water side without opening the M/c to atmosphere.
All welded joints exposed to hydrogen will be specially prepared to prevent
leakages. The complete frame is subjected to hydroulic test at a pressure of 7 atm.
-
7/31/2019 Kamal (1)
24/50
Fig. 7.1 Turbo Generator Overview
-
7/31/2019 Kamal (1)
25/50
7.2 STATOTOR - CORESTATOTOR - CORE
It is built up of special sheet steel laminations and whose assembly is supported by the
guide bass. The mothod of construction insure that the core is firmly supported at a large no ofpoints on its periphery. The laminations of high quality silicon steel which combines high
permeability with low hysteresis and ealdy current losses. After stamping each lamination is
varnished. The laminations are varnished on both sides with two coals.
The segment of insulating material is inserted at frequent interval to provide additional
insulation. The laminations are stamped out with accurately fine cimbination of ties.
Laminations are essambled on guide bass of group separated by radial ducts to provide
ventilation passage. The ventilation elucts are disposed so as to discribute the gas evenly over
the core and in partialarly to give adequate support to teeths. At frequent intervals during
stacking the assembled laminations are passed together in powerful hydrolic press to ensure
tight core which is finally held between heavy clamping plates which are of non magnetic steel.
Use of non-magnetic steel reduces. Consielenably the heating of end iron. Clamping to the
foothed region of the core is provided by pressing figures of non-magnetic steel which are
welded to inner point phery of the clamping plate.
In order to reduce the losses in the end packets special dampers are provided at either
end of core. Mostly dampers are provided to prevent hunting in AC Machines.
7.3 STATOR BARS7.3 STATOR BARS
Stator bars are manufactured as half bars. Each stator half coil is composed of altrnate
strips of double glass covered and bars copper, transposed in straight portion of Robill
method So that each strips occupees every radial portion in the bar. For an equal length along
the bar. They are made in strips to reduce skin effect. The wdgs overhead is in involute shape.
The overhang portion of the bar is divided into four quadrants & insulated. Their arrangement
reduces additions losses due to (self inducing) damping currents which otherwise be present
due to self inducing non-uniform flux distribution in the coil slots. The main insulation for the
bar sinsists of resin rich mica losed thermosating epoxy. This has excellent electrical and
mechanical properties and does not require any impregnation. Its moisture absoption tendency
-
7/31/2019 Kamal (1)
26/50
is very low and behaviour of mica is far superivor than any other conventional tape insulation
systems.
Semiconductor coating is also applied to a part of overhangs with a straight
overlap of conductive coal in the straight portion, to prevent corona discharge.The strip will be
transposed in side of reduce eddy currents to minimum. Conductor material is electrolytic
copper connections brozed with free flouting silver alloy to obtain joints which are both
mechanically and electrically sound.
7.4 STATOR WINDINGS
Stator wdgs are double star layers. Lap wound co phase short pitch type. The top and
bottom are brazed and insulated at either and to formturn. Several such turns form a phase.
Phases are connected to form a double star wdg. The end wdg formed on involute shaped ends,
is indined towards M/C axis by 20*, thus form a basket wdg. With total induced conical angle
of 40*. Due to this stray load losses in the stator ends to Zero.
The arrangement of complete star wdg. Electrical ckt. is viewed from turbine
end of generator and rotor wdgs. Slot numbering is clock wise from turbine end. The top bar in
slot no 1 is identified by the thick line. End wdgs will be seaered against movement of short
circuit by both axial and pheripherical bracing. The later consist of hardened glass
laminated blocks inserted between adjacent coil sides in coil overhangs, so that with the coils,
they form a continuous rigid ring. Glass cord or top is used for lashing the packing of blocks.
The complete assembly is secured by high tensile brass blots. The wdgs. Is designed to with
stand short circuit stresses. The exposed portion of wdgs are finally given coated. Insulation of
individual bars and stator wdgs at various stages is tested with applied high voltages AC of 50
HZ.
7.5 TERMINAL BUSHING7.5 TERMINAL BUSHING
Six output leads (3 long, 3 short) have been brought out at bottom of casing ont
he exciter side. External connection are to be made to 3 shorten terminals, which are phase
terminals. The large terminals are of neutral and a current x-mar is inserted. The conductor of
generator terminal bushings having hollow copper tube with copper brazed at
-
7/31/2019 Kamal (1)
27/50
the end to avoid the leakage of hydrogen. Hollow portion enables the bushings to be hydrogen
cooled. Ends of bushings are silver plated. Middle portion of bushing is adequately insulated
and have a circular flang for bolting the stator casing, Gaskets are provided between the flange
of terminal bushings and castings, to make it absolutely gas tight.
7.6 BEARINGS :-
Generator bearings have electrical seats and consists of steel bodies with removable
steel pads. The bearings are formed for forced lubrication of oil at a pressure of 2-3 atm. From
the same pump that supplied oil to the turbine, bearings and governer gears. There is a
provision to ensure and measure the rator bearing temp. by inserting a resistance thermometer
in oil pockets.
7.7 VENTILATION SYSTEM :-
The machine is desgned with ventialtion system having 2 atm. Rated hydrogen
pressure circulation on hydrogen is ensured by two axial fans mounted in either side of the
rotor. The stator is designed for radial ventilation by stem. The end stator core packets and core
clampings plates and intensively cooled by hydrogen through special ventilation circuit. Rotor
wdg. Is provided with a direct radial ventilation system.. Design of ventilation system is so as
to ensure almost univorm temp of rotor wdg. And stator core.
Rated load operating temp. are well within the limits corresponding to class B operation.
Continuous Mounting of active parts temp. of hydrogen in generators, embedded resistance
temp. Detectors are provided as:-
(i) RESISTANCE
A resistance temp detector (R.T.D) is a pt. Resistance element operation of R.T.D os based
on the principal of electrical resistance of metallic conductor, varies linearly with temp.
(ii) APPLICATIONS
R.T.D. and its associated equipments are designed for use with generator to determine temp. at
various parts and places. The equipment consists of two parts.
-
7/31/2019 Kamal (1)
28/50
(iii) The switch board equipments which usually includes a temp. Indicating meter, test
resistors transfer switch and leads. Machine equipments which usually includes the temp.
R.T.D., leads and terminal block with grounding connections, leads from R.T.D. are
brought out to the terminal board by cables through a conduit to protect them from physicaldamage and from contact with high voltage coils.
Such resistance detectors in stator teeth with seven spactors 7 RTDs between
the coil side in the stator slots with 7 spacers and 3 RTD are there in the stator core with 3
spacers.
The location of temp. detectors are in three phases i.e. in the centre of M/C, in each region of
machine and midway between them. The detectors in the stator slots are distributed unitormly
in all three phases. Measurement of temp. in hydrogen cooling water for hydrogen coolers and
metals is as :-
Six R.T.D.s are provided, on at the inlet of each of 6 individual hydrogen
coolers elements for measurement of temp. of hot hydrogen, dimilarly 6 R.T.D.s are provided,
one at outlet of each of six individual cooler elements. One R.T.D. along with one spacer is
provided in the lower part of stator frams for measurement and signalisation of hot hydrogen.. 6
R.T.D.s are provided one at the outlet of six individual cooler elements for measurement of
cooling water at the outlet of hydrogen cooler elements.
7.8 MEASURMENT OF BEARING TEMPERATURE :-
Two resistance detector are provided in the bearings shelves of turbogenerator
for measurement and signatisation of the bearing metal cap.
All the resistance eletectors are provided in bearing shelves of turbogenerator.
Temperature detectors have resistance of 100 at C. The terminals of detectors are brought out
to a common terminal board located on the stator frame.
HYDORGEN COOLERS:-
Three hydrogen coolers, each comprising of two individual units are
horizontally mounted inside the stator frame. The inlet and outlet of cooling water from both
sides of M/C i.e. from the non-driving side as well as turbine side. The clearing of individual
cooler element can be carried out from both ends of generator even during operation. The
-
7/31/2019 Kamal (1)
29/50
assembly of individual cooler elements in the stator frame is however carried out only from the
non driving side.
CHAPTER 8
ROTOR
INTRODUCTION:-
Rotor shaft conststs of co single piece alloy steel fonging of high mechanical
and magnetic propertics performance test includes :-
(i) Tensile test on specimen piece.
(ii) Surface exmination
(iii) Sulphur print test.
(iv) Magnetic Crack detection.
(v) Visual examination of the bore.
(vi) Ultra sonic examination.
Slots are milled on the rotor forging to receive the rotor ludg. Transverse slots
are machined in the pole taces of the rotor to equalise the moment of inertla in the direct and
quadratelre axis of the rotor with a view of minimising the double frequency vibration of the
rotor. The fully based rotor is dynamically balanced and subjected to 120% over speed test at
the work balancing tunnels so as to ensure reliable operation.
8.1 ROTOR WINDINGS :-
The rotor wdgs. Of direct coil type and consists of parallel strips of very high
conductivily silver bearing copper, bent on edge to form coils.
The coil are placed in statin impregnated glass, laminated short shells, using glass strip
interterm insulation and will be brazed at the ends to form a continuous wdgs.
The complete wdgs. Will be baked at high temp. and pressed to size by heavy steel
damping rings. When the wdgs have cooled, the insulation at the tap of the slot portions will be
seaved by heavy dove tail wedges of non-magnetic materials.
-
7/31/2019 Kamal (1)
30/50
The cooling medium hydrogen gas will be brought in direct contact with copper by
means of radial slots in embadded portion.
Lateral movement of the coil overhang is provented by treated glass spacess insrted in
between the coils and the solid ring. The formation and description of the spacers is such as to
leave ample space for ventilation.
8.2 BEARINGS:-
The bearing are self-aligned and sonsists of split steel shells linked with spacial bearing
metal having very low co-efficent of friction. The bore is machid to an elliptical shape so as to
increase the mechanical stability of rotor.
The bearings are pressure lubricated from the turbine oil supply. Special precautions are taken
to prevent oil and oil vapor form the shaft seals and bearing along the shaft.
The circulation of shaft current liable the damage. The bearomg surface is
prevented by insulation so placed that the bearings, seals & necessary pipes are indined from
the frame.
8.3 SLIP RINGS :-
The slip rings are made of forged steel. They are located on the either side of the
generetor shift the slip ring towards the exciter side is to be given a the polarity and towards of
retaining side is to be given a - ve polarity Initially. They have helical grooves and skewed hole
in the body for cooling purpose by air.
Calibrated mica is first built up to required thickness on the shaft where slip
rings are to be located. The slip rings are insulated from the rotor shaft. Excitation current is
supplied to the rotor wdg. Through the slip rings which are connected through semi circuilar
steel excitation leads. The excitation leads are connected to the wdg. On one end and to the
slip rings on the other end with insulated (terminals) studs passing through the radial holes in
the rotor shaft. The terminal studs at both the ends of the excitation leads are fitted gas cat seals
to prevent leakage.
8.4 BUSH GEAR ASSEMBLY:-
-
7/31/2019 Kamal (1)
31/50
Generator bushes are made from the various compositions of natural graphite and
binding materials. They have a low co-efficient of friction and are self lubricating. The brushes
are provided with a double flexible copper leads or pigtails. A pelical spring is mounted rapidly
over each bush so that pressure is applied on the centre line of bush. A metal cap is rivetted to
the brash bead and is provided with a hole to maintain the position of the spring plug. Several
brush holder, each carrying on brush in radial position are fixed to a silver-plated copper studs
mounted on the collecting arm concentric with each slip rings. The collecting arm is made out
of a Copper (Cu.) Strip.
8.5 DRYING OF WINDINGS :-
Generator stator bars are insulated with mica- insulation which is homogeneousin nature and practically impervious to moisture,and reduces time required to draught.
The insulation resistance of the stator phases wdg. against earth and with
reference to other phases under hot conditions shall not be less than the value of
mathematically obtained.
Rin = U / (S / 100 + 1000) M Ohm.
U - Rated Wdg voltage under test.
Rin - Insulation resistance under hot conditions.
S- Rated output of turbo generator.
The insulation resistance of entire excitation system ckt in hot conditions must not fall below
0.5 M Ohm. The insulation resistance in calculated as per the formula -
Rin = Rv ( U 1 + U 2 / U - 1 )
Rin - Insulation resistence of exciation
Rv - Internal resistance of volt meter
V1 - Voltage measured between the slip ring & shaft /
earth (volts)
V2 - Voltage measured between (-)ive slipring & shaft earth (volts)
-
7/31/2019 Kamal (1)
32/50
When starting the drying process, the winding. Insulation resistance will usually
decrease when the drying process becomes effective, the insulation resistance will gradually
increase.
CHAPTER 9
COOLING SYSTEM
9.1 INTRODUCTION: -
In S.T.P.S hydrogen cooling system is employed for generator cooling. Hydrogen is
used for cooling medium primarily because of its superior coding properties and its low
density. Thermal conductivity of hydrogen is 7.3 times of air. It has also higher transfer co-
efficient. Its ability to transfer heat through forced convection is about 50% better than air.
Density of hydrogen is approximately 7/14 of the air ata given temp. and pressure. This reduces
the windage losses in a high speed machine like turbo-generator.
Increasing the hydrogen pressure within the machine improve its capacity to
absorb and remote heat. Relative cooling properties of air and hydrogen are given below as
shown on the next page.
Elimination of fire risk because hydrogen witllnt support combution.
(i) Corona discharge is not harmful to insulation since oxidation is not possible.
(ii) Smooth operation of machine in view of vertical elimination of windage noise and the
use of heavy gas tight enclousers and hence an elirt proby casing.
At pressure 0.035 atm. Of hydrogen heat carrying capacity is 1. But at 2.0 atm
of hydrogen heat carrying capacity is 2.95.
To over come the serious possibility of hydrogen explosion with in the machine
and to ensure the safety of operation purity of hydrogen on the gen. Casing must be maintained
-
7/31/2019 Kamal (1)
33/50
as high as possible. The purity of hydrogen should be 98% pr above but should not be less than
98%. In case of hydrogen purity drops below 98%, an alarm is provided.
9.2 HYDROGEN DRYERS :-
Two no. of dryers are provided to absorb the moisture in the hydrogen in the gererator.
Moisture in this gas is absorbed by silica gel in te dryer as the absorbed gas passes through it.
The saturation of silica get is indicated by its change in colour from blue to pink. The silica gel
is reactivated by heating. By suitable change over from drier to the other on uninterrupted
drying is achieved.
9.3 HYDROGEN FILLING SYSTEM :-
The filling operation is carried out in two steps:
(i) Scavanging the air by carbon dioxide and
(ii) Expelling the CO2 with hydrogen.
Before filling the hydrogen at a pressure of 2 atm. In the machine it is necessary
to store :
(a) At least 18 cylinders of 20 kg CO2 each i.e. 360 kg of CO2 and
(b) 48 cylinders of hydrogen.
-
7/31/2019 Kamal (1)
34/50
CHAPTER 10
EXCITATION SYSTEM
The electric power generators required direct current excited magnets for its
fielf system. The excitation system must be reliable, stable in operation and must response
quickly to excitation current requirements. When excitation system response is controlled by a
fast acting regulators, it is chiefly dependent on exciter.
Exciter supply is given from X-mer and is than rectified.
10.1 FUNCTION OF EXCIATION SYSTEM: -
The main function of exciation system is to supply required excitation current at rated load
condition of turbo generator. It should be able to adjust the field current of the generator either
by normal control or automatic control so that for all operation & between no load and rated
load. The terminal voltage of the system machine is maintained at its value.
The excitation system makes contribution improving power system stability
limit for transient conditions and also for steady state conditons. The excitation system that are
effective from the stand-point if stability are commonly termed quick response system and have
following principal features.
Exciter of quiet response and high cealing voltages of not less than 1.4 times the
rated field voltage and nominal exciter response of minimum 0.5.
10.2 TYPES OF EXCITATION SYSTEM :-
There have been many developments in excitation system designs. There have been a
continuous reach among the disigns and the use alike from improving the excitation system
performance. The ultimate is to achieve on ideal in value (rate) of response stability in
reliability, accuracy etc.
The modern excitation system adopted presently on B.H.E.L. made turbo-
generators.
-
7/31/2019 Kamal (1)
35/50
(i) Conventional D.C. Excitation System.
(ii) Brushes Excitation System.
(iii) Stafic Excitation System.
10.3 STATIC EXCITATION SYSTEM:-
In S.T.P.S. static excitation system is provided. If mainly consists of the
following:
(i) Rectifier X-mer
(ii) 6 Nos. of Thyristor converters
(iii) An automatic voltage regulator (AVR)
(iv) Field syppression equipment
(v) Field flashing equipment.
GENERAL ARRANGEMENT :-
In the excitation system the power required for exciation of generation are
tapped from 11 KV bus-ducts through a step down rectifier X-mer. After rectification inthermistor, convertor, the DC power is fed to the generator field wdg through a field breaker.
The AVR controls the O/P from thyristor convortor by adjusting the firing angle depending
upon generation voltages.
The field flashing system facilitates inital built up of the generator voltage from
the static AC or DC supply.
10.4 RECTIFIER X-MER:-This X - mer step down the bus voltage 11 KV to 640 and has a rating of 1360 KVA. It
is dry type, naturally cooled X-mer with resin cast Coils. It is porvided with how-ever current
relays and two temp. sensors.
10.5 THYRISTOR CONVERTOR:-
-
7/31/2019 Kamal (1)
36/50
The thyristor convertors are housed in thyrert panel and are intended for controlled
rectification of A.C. imput power. 6 Thyristors convertors are comected in parallel each rated
for continuous current O/P of 20% of the rated capacity i.e. 20% of the reserve.
Each thyristor convertor consists of 6 thyristor connected in a 3 - Phase, full
wave, 6 - pulse - dridge from and they are cooled by fans provided with a fuse for protection
against short ckt.
10.5.1 AUTOMATIC VOLTAGE CONTROLS :-
This AVR is a transistorised thyristor controlled equipment with very fast response. The
AVR is also having a provision of Stator and rotor currents limits and load angle limits for
optimum utilization of lagging and leading reactive capacities of generator.
The principal features demanded by modern AVR equipments are as follows :-
a) Maintenance of constant voltage so to permit efficient operation of connected machine
and applications.
b) To control the relative load between a parallel running machine to the best advantager
of the system.
c) To rise the exitation power by the machine as it tends to best advantage of the system,
swing away from the system subsequent to a fault so as to increase the instantaneous
power flowing and there by rise the transient stability limit of the system.
10.6 FIELD SUPRESSION EQUIPMENT :-
The field suppression equipments consists of a field breaker with a discharge
resistors. The field breakers has 4 main breaking contacts and two discharge contacts
which close before main contact break..
10.7 ADVANTAGES OF STATIC EXCITATION SYSTEM :-
1- Very fast response.
2- Extremely reliable in view of static components
3- Low maintenance cost
4- High efficiency
-
7/31/2019 Kamal (1)
37/50
5- Fast field supression through field and discharge resistance as well as through
thyristor bridge, feeding the generator field.
10.8 OPERATION:-After bringing the speed to operating speed say 3000 r.p.m., the voltage is slowly buit up with
the help of excitation system. This action is taken for synchronising the generator with grid.
10.8 SYNCHRONISING : -
For syncronising the generator to the grid system 5 conditions of equality have to be
satisfied. These are :-
(i) Voltage
(ii) Frequency
(iii) Phase displacement
(iv) Phase sequence
(v) Wave form.
Wave form and phase sequence of the generator are determined at the design
and commissioning stages but voltage, frequency and phase displacement have to be set up
by the operator during each connection of synchronising of the generator.
10.8.2MACHINE CONNECTED ON INFINITE BUS :-
While separating a M/c in parallel with grid we will have two conditions :-
(i) Any increase in the power input of the generator increase its share of electrical loads.
(ii) Any excitation in the excitation of generator increase its share of relative load.
-
7/31/2019 Kamal (1)
38/50
CHAPTER 11CHAPTER 11
TRANSFORMERSTRANSFORMERS
Transformer is a static device which transfer electric power from one circuit to another circuitTransformer is a static device which transfer electric power from one circuit to another circuit
without changing frequency.without changing frequency.
11.1STATION TRANSFORMERSTATION TRANSFORMER
When the unit is to be started, power supplied to the auxiliaries is taken from the station
transformer. The rating of the station transformer is 50 MVA. It takes power from the grid at
220 kV and steps it down to 6.6 kV. At the time of starting all the auxiliaries are supplied from
the station transformer. When the generator is synchronized and starts producing power, about
80% of the load is shifted on to the unit auxiliary transformer. The load that requires
uninterrupted supply is left connected on the station transformer.
There are 5 S.Ts in the plant. One for each stage.
Type of cooling ONAN ONAF
MVA rating
H.V.
L.V.
40
26
50
31.05
Current (line)
H.V.
L.V.
105
3351
131
4189
Table 11.1Table 11.1
Voltage (at no load)Voltage (at no load)
H.V. side L.V. side
220 KV 6.9 KV
Table 11.2
Vector group YNyno
Mass of Oil -24400 Kg.
-
7/31/2019 Kamal (1)
39/50
Untanking mass- 8000Kg.
Volume of oil- 27150 litre.
Frequency -50Hz
11.2 UNIT AUXILIARY TRANSFORMERUNIT AUXILIARY TRANSFORMEREach unit has two unit auxiliary transformers. When the unit starts generating
electricity these transformers are energized and then supplies power to the auxiliaries. Before
starting of the unit, UAT bus is connected to the station bus. Auxiliaries of one unit takes about
20MW of power. UAT is connected between the generator and the GT. A tapping is taken from
the power coming from the generator to the GT. UAT relieves GT from extra load of about 20
MW which is to be supplied to the auxiliaries via GT and ST thus increasing the efficiency. It
is a step down transformer, which steps down the voltage from 16.5 kV to 6.9kV. The rating of
UAT is 20 MVA. UAT bus supplies only those auxiliaries, which are not necessary to be
energized in case of sudden tripping of generator.
11.3 UNIT STATION TRANSFORMER11.3 UNIT STATION TRANSFORMER
It is a step down transformer, which is connected to the station bus. It steps down the
voltage from 6.6 kV to 0.433 kV it is used to supply the low voltage auxiliaries.
11.4UNIT SERVICE TRANSFORMER11.4UNIT SERVICE TRANSFORMER
It is also a 66 kV/ 415 V transformers which is used to supply the auxiliaries connected
to the unit secondary switchgear bus.
-
7/31/2019 Kamal (1)
40/50
CHAPTER 12CHAPTER 12
DIFFERENT EQUIPMENTS AND BUS SCHEMESDIFFERENT EQUIPMENTS AND BUS SCHEMES
12.1 BUS SCHEME:-
Main Function Of The Stations Is To Receive The Energy And Transmit It At The
Required Voltage Level With The Facility Of Switching.
At STPS Following Are The Bays:-
Bus Coupler 1
Sog -1
Sog -2
Generator Transformer -1
Ratangarh -1
Station Transformer -1
Bus Sectionalizer
Ratangarh 2
Bus Tie
Generator Transformer-2
Interlinking-1
Station Transformer-2
Interlinking -2
Station Transformer-3
Station Transformer-4
Station Transformer-5
12.2 BUS SYSTEM:-
There Are Mainly Three Buses
Main Bus-1
Main Bus-2
Transfer Bus
-
7/31/2019 Kamal (1)
41/50
Material of bus bar- Tarantull Al conductor with a capacity of 2400 amperes. Bus coupler-1 can
be used as GT breaker for unit 1, 2 and 3. Only one bus coupler can be used as a GT breaker at
a time.
12.3 SF6 GAS CIRCUIT BREAKERS12.3 SF6 GAS CIRCUIT BREAKERSIn this type of breaker quenching of arc is done by SF6 gas. The opening and closing of
the circuit breaker is done by air.
TYPE DESIGNATIONTYPE DESIGNATION
E : S F 6 Gas Insulation
L : Generation
F : Out Door Design
SL : Breaker Construction
4 : Code BIL Rated Voltage 4 245 / 460 / 1050 kv
1 : No. of chamber
The high voltage circuit breaker type ELF SL 4-1 comprises 3 breaker poles , a
common control cubicle and a pneumatic unit ( compressed air plant)
a breaker pole consists of :-
- SUPPORT (FRAME) - 40000
- POLE COLUMN - 41309 N
- PNEUMATIC ACTUATOR ( PKA)- 90200
The actuator is operated with compressed air.
A pneumatic unit (97200), an air receiver and a unit compressor is installed to
supply the compressed air. the compressed air stored in the air receiver is distributor to
the three actuator via pipe line.
The common control cubicle (96000), which is installed separately contains all
control devices and most of the monitoring instrumentation with the exception of the
density monitor 98005 mounted on the middle breaker pole. The pressure switches are
installed in the control cubicle. all three poles columns are filled with insulating gas and
interconnected by means of pipe lines. the gas is monitored by a density monitor 98005
( temp. compensated pressure monitor )
If all the poles of the circuit breaker do not close simultaneously then the pole
discrepancy relay will operate and trip the breaker. Also at the time of tripping, if all the
-
7/31/2019 Kamal (1)
42/50
breakers do not trip simultaneously, then again the tripping command through the pole
discrepancy relay will initiate to trip the breaker and annunciation will appear in the sub
station control room and the UCB.
12.4 ISOLATORS:-12.4 ISOLATORS:-Isolators are used to make or break the circuit on no load. They should never be
operated on load. The isolators installed in the sub station have a capacity of 1250 amperes.
They are double end break type, motor operated and can be operated from local as well as
remote.
1. Tightening of the jumper clamps
2. Tightening of electrical connections
3. Cleaning of male female connections
4. Checking of fuses and replacement there F.
5. Checking of operation of isolators
12.5 CHANGE OVER SCHEMES (BUS TIE SYSTEM)CHANGE OVER SCHEMES (BUS TIE SYSTEM)
When main breaker is in service (on load change over):
Ensure Transfer bus is free (check any temporary earthing)
Charge the transfer by closing bus coupler isolator and circuit breaker.
Put the switches provided on bus coupler on generator control cum desk panel.
Charge the transfer bus by closing isolator d of GT.
Check the isolator of GT through which it has been already connected to the bus.
Close the isolator e,f, & g of tie Bus.
By using synchronizing trolley close the circuit breaker b1
12.6 BUS COUPLER TO MAIN BREAKER12.6 BUS COUPLER TO MAIN BREAKER
Close the isolator 1 & 3 of GT.
Close the breaker a 1 of GT
Close the isolator 5,7 & breaker b 1
After this work close the isolator 9, 10
By using synchronizing Troley, close the bus coupler breaker c1
-
7/31/2019 Kamal (1)
43/50
12.7 SYNCHRONIZATIONOF THE GENERATOR TO THE GRID12.7 SYNCHRONIZATIONOF THE GENERATOR TO THE GRID
(Generator breaker is used)
With The Main Bus1. Close the isolator with the bus selection
2. Close the isolator on both sides of the generator breaker.
3. On Generator control desk panel(GCDP)
a. Put the switch NIT in normal position.
b. Put the synchroscope ON.
c. Measure the voltage and speed matching. Conditions will be included by
checking the synchronizing lamp on GCDP and close the generator breaker.
IMPORTANCE OF THE TRANSFER BUS
Transfer bus is normally free and is used to facilitate repairing job of other breakers by
transferring load on transfer bus.
12.8 CURRENT TRANSFORMERS:-
1. Checking of oil level.
2. Checking of oil and leakage
3. Tightening of jumper clamps
4. Tightening of electrical terminal secondary connection
12.9 LIGHTNING ARRESTERS:-
1. Tightening of jumper connections
2. Tightening of earthing connections
3. Checking of counter reading
4. Checking of porcelain part
5. Checking of grading current
12.10 CAPACITIVE VOLTAGE TRANSFORMER:-
1. Checking of oil level and leakage
2. Tightening of HT jumper clamps.
-
7/31/2019 Kamal (1)
44/50
3. Tightening of secondary terminal connections
12.11 BATTERY 220V DC:-
1. Cleaning of battery terminals
2. Tightening of battery terminal connections3. Recording of specific gravity and voltage of each cell.
13.12 EARTH SHIELDING :-
It is a mesh of wire upon the tower. Its main purpose is to protect the substation
equipment from direct lightning strokes. Metallic body of each equipment is properly earthed.
The earthing resistance of any switch yard is about 0.2 ohm. Before the building up of the sub
station earthing material of G. I. wire is buried in the ground whose depth depends upon themoisture content of ground. Earthing electrodes are provided at various points. This increases
the number of parallel provided at various points. This increases the number of parallel paths
and hence resistance of earth decreases.
-
7/31/2019 Kamal (1)
45/50
CHAPTER 13CHAPTER 13
POWER LINE CARRIER COMMUNICATIONPOWER LINE CARRIER COMMUNICATION
This is a technique in which power lines are used as communication lines by which we
can make contact with other substation
The range of frequency used for communication is 300 KHz to 500 kHz.
Fig.13.1 Overview of PLCC
WORKING
The voice frequency if converted into electrical signal. These signals are super imposed
on a carrier frequency and transmitted on the line through a coupling capacitor. At the receiving
end wave trap does not allow the modulated signal to enter the power circuit where as the
coupling capacitor provides a low resistance path to this signal. This signal is then given to the
line matching unit. In the LMU this frequency is matched and after wards filtration of signal is
done. The signal is demodulated and again converted into the voice signal, which is available at
phone receiver.
SENDING ENDCOUPLING
CAPCITOR
6V
OUTPUT
EARTHED
600 OHMSRECEIVING END
WAVE TRAP
PLCCLMU
-
7/31/2019 Kamal (1)
46/50
Fig . 13.2 block diagram
MEMEORY
DISPLAY
CONTROLER
123
COMMON
CONTROLER
MICRO
PROCESSOR
8085
DIGIT
EL TO
CONT
ANAL
OG
INPUT
DIGITAL INPUT
DIGITAL
OUTPUT
ANALOG INPUT
ANALOG
-
7/31/2019 Kamal (1)
47/50
CHAPTER 14
DATA SHEET & SPECIFICATIONS
(Common for Units I, II, III, IV and V)
GENERATOR
Apparent power 294MVA
Active Power 250 MW
Current 10290 Amps.
Voltage 16.5 kV+/- 825V
Speed 3000 rpm
Power Factor 0.85
Hydrogen Pr. 3.0 bar
Rated Field Current 2386 Amps.
BRUSHLESS EXCITER
BHEL
Active Power 1350 kW
Rated Current 3200 Amps.
Voltage 420 Volt
Speed 3000 rpm
PILOT EXCITOR
Apparent Power 35 kVA
Current 105 Amps
Voltage 220+/-22 V
-
7/31/2019 Kamal (1)
48/50
Speed 3000 rpm
Frequency 400 Hz
RECTIFIER WHEEL
Number of Fuses per Rectifier Wheel =30
Fuse Rating 750V/400 Amp
No. of Wheels 2
SPECIFICATIONS OF SF6 GAS CIRUIT BREAKERS
CIRUIT BREAKERS FOR 220 KV 400KV
Rated lightning impulse with stand voltage 1050 kvp 1425 kvp
Rated short circuit breaking current 17 ka 17 ka
Rated operating pressure of air 15 kg / cm 2 15.5 kg / cm2
First pole to clear factor 1.5 1.3
Rated voltage 245 kv 420kv
Rated current 200A 200A
Rated closing circuit voltage 220 V DC 220 V DC
Rated opening circuit voltage 220 V DC 220 V DC
Rated voltage, frequency 415 V AC 50 Hz 415 V AC 50 HzRated line charging breaking current 125 A 600 A
Table 14.1Table 14.1
CHAPTER 15CHAPTER 15
ABOUT AVR
AVR regulates the terminal Voltage of Generator by direct control of the Main Exciter field
current using Thyristor converter.
-
7/31/2019 Kamal (1)
49/50
AVR is configured as two independent closed loop control systems :
1. Auto
2. Manual
Auto Channel
It controls the generator terminal voltage and is kept normally ON during operation.
To regulate the effect of the Generator reactive current on the Voltage.
To regulate the effect of the Generator active current on the Voltage.
To regulate PF , MVAR of Generator.
To limit V/Hz , max. field current , inductive stator current , capacitive stator current , load
angle , minimum field current .
To dampen active power oscillation.(PSS)
To provide soft start of generator.
Manual Channel
It regulates the Exciter field current.
It serves as backup channel in case of malfunction in Auto channel.
It is basically used for testing and commissioning.
Tracking Feature
Both channels are equipped with tracking feature so that the inactive channel always generates
the same control variable as the active channel under steady state operation. This ensures
smooth switch over Auto to Manual or vice-versa.
CHAPTER 16CHAPTER 16
REFERENCESREFERENCES
P.S. Bhimbra, electrical machinery pp 238-242, 540-557, 852-868, seventh editionP.S. Bhimbra, electrical machinery pp 238-242, 540-557, 852-868, seventh edition
20042004
-
7/31/2019 Kamal (1)
50/50
B.R. Gupta,generation of electrical energy pp 80-89, 105-125, 246-260, First EditionB.R. Gupta,generation of electrical energy pp 80-89, 105-125, 246-260, First Edition
19931993
C.L. Wadhwa,electrical power system pp 173-187, 392-407, 500-504 fourth editionC.L. Wadhwa,electrical power system pp 173-187, 392-407, 500-504 fourth edition
20052005
B.L. Theraja, electrical technologypp 1304-1311 volume second twenty third editionB.L. Theraja, electrical technologypp 1304-1311 volume second twenty third edition
20022002
Various html address are:-Various html address are:-
1.1. http://en.wikipedia.org/wiki/thermalhttp://en.wikipedia.org/wiki/thermal power_stationpower_station
2.2. http://www.s-k.com/pr_vac.htm?sitrackingid=664330http://www.s-k.com/pr_vac.htm?sitrackingid=664330
3 http://www.cheresources.som/ejectors.shtmlhttp://www.cheresources.som/ejectors.shtml
http://en.wikipedia.org/wiki/thermalhttp://en.wikipedia.org/wiki/thermalhttp://www.s-k.com/pr_vac.htm?sitrackingid=664330http://www.s-k.com/pr_vac.htm?sitrackingid=664330http://www.cheresources.som/ejectors.shtmlhttp://www.cheresources.som/ejectors.shtmlhttp://en.wikipedia.org/wiki/thermalhttp://www.s-k.com/pr_vac.htm?sitrackingid=664330http://www.cheresources.som/ejectors.shtml