kam kotia case study - abandoned · pdf file• nit dry cover & dam upgrade 7,341 k...
TRANSCRIPT
KAM KOTIACASE STUDY
A Pragmatic Approachto a Big $ Problem
Dick Cowan/John RobertsonMinistry of Northern Development and Mines
Sudbury, Ontario
Orphaned/Abandoned Mines WorkshopWinnipeg, Manitoba
June 26, 2001
WHAT IS KAM KOTIA?• Kam Kotia is a former CU/ZN mine near
Timmins, Ontario• There are about 6 million tonnes of
unmanaged acid generating tailings coveringmore than 500 ha
• Environmental impacts are locally significant– acidic leachate– dusting– aesthetics– physical safety
MINING HISTORY• Principle exploration 1926-1928,
exploration shaft• Mining * 1943-1944 - 169,000 tonnes
open pit• Mining 1961-1972 - 5,840,000 tonnes,
mainly underground• Production 6.6 MT @ 1.1% Cu,
1.17% Zn, 0.10 oz/TAg* Mining in 1943-1944 carried out on behalf of Wartime Metals
Corporation, a Federal Government Agency. Cu sold to MetalsReserve Company. Washington, which paid operating costs androyalty.
OWNERSHIP HISTORY• Patented 1932 - Kam Kotia Porcupine
Mines Limited (82.5% owned by HollingerConsolidated Gold Mines Limited)
• Transferred 1966, Violamac Mines Limited -Kam Kota Mines Limited
• Transferred 1975, Robison Mines Limited• Surface rights forfeit to Crown, January
1988• Mining rights forfeit to Crown, March 1988
TAILINGS DEPOSITION<1961 270,000 tonnes in unconfirmed
area north of mill
1961 170,000 tonnes in SUT
1961-67 2.73 MT deposited in NUT area
1967 OWRC required construction ofdams to create NIT
1967 1.5 MT deposited in open pit
1968-1972 1.4 MT deposited in NIT
HYDROLOGY
• North and East seeps drain NUT, E1/2 ofNIT and N1/2 plant site � KamiskotiaRiver pH 2-3
• South seep drains SUT, S1/ of NIT andplant site to Little Kamiskotia River �Kamiskotia Lake
2000 CONSULTANT REVIEW• Reviewed site chemistry & hazards,
previous reports & pre-MENDrehabilitation proposals
• Proposed various options for each projectarea using modern technologyapproaches
• Completedrisk/benefit/advantage/disbenefit analysis
• Recommended approach
ORDER OF MAGNITUDE COST ESTIMATES
• Phase I Study $130 k
• Evaluation & Engineering 875 k
• Relocate SUT tails & Reclaim 2,377 k
• Collect seepage, construct & operate
treatment plant 8,040 k
• Consolidate NUT tails 10,764 k
• NIT dry cover & dam upgrade 7,341 k
• Rehab plant site area 2,300 k
Total before contingency $31, 827,000
With contingency + $40 million
KAM KOTIA STEERINGCOMMITTEE
• Ministry of Northern Development andMines (lead)
• Ministry of Environment• Ministry of Natural Resources• Northwatch
* Committee agrees to a financially manageable(?)approach which will significantly reduce leachaterelease and consequences.
FUNDING ISSUES• Does the benefit justify the cost?• $40 million?• Minister initially agrees to $3 million
expenditure• Following Phase I evaluation Minister
agrees to $9 million after SteeringCommittee recommendations and muchdeliberation
CURRENT PROGRAM
• Designed to reduce impacts onmanageable? $$$
• To be completed 2001-2003 (1st quarter)• Represents a compromise between
improving environmental effects vs.letting it sit!