jw marriott revised
DESCRIPTION
ProgrammeTRANSCRIPT
![Page 1: JW Marriott Revised](https://reader038.vdocuments.us/reader038/viewer/2022100509/55cf9af3550346d033a42657/html5/thumbnails/1.jpg)
Activity ID Activity Name OriginalDuration
Early Start Early Finish
JW Marriot, Deira - InteJW Marriot, Deira - Interior fit out works - Floor by Floor Program Phase 1 -1 384 24-Nov-13 12-Dec-14
Pre construction woPre construction works 166 24-Nov-13 08-May-14
GeneralGeneral 1 24-Nov-13 24-Nov-13A1000 Work order confirmation 1 24-Nov-13 24-Nov-13
Samples, shopSamples, shop drawings, procurement 131 25-Nov-13 04-Apr-14A1010 No shop drawing submission ( Production based on Mock - Up) 1 25-Nov-13 25-Nov-13A1020 Lighting specification / drawings submission 10 26-Nov-13 05-Dec-13A1040 Overseas procurement 130 26-Nov-13 04-Apr-14A1030 Approval for lighting specs 3 06-Dec-13 08-Dec-13
Joinery producJoinery production works 165 25-Nov-13 08-May-14A1050 Material procurement for joinery items 25 25-Nov-13 19-Dec-13A1060 Joinery production 120 20-Dec-13 18-Apr-14A1070 Painting works 120 09-Jan-14 08-May-14
Construction WorksConstruction Works 254 03-Apr-14 12-Dec-14
GenaralGenaral 7 03-Apr-14 09-Apr-14A1200 Site mobilization 7 03-Apr-14 09-Apr-14
6th Floor (28 ro6th Floor (28 rooms) 38 10-Apr-14 17-May-14A1210 Removal of existing fittings & fitures 3 10-Apr-14 12-Apr-14A1220 Removal of existing carpet 2 13-Apr-14 14-Apr-14A1230 Strip out existing finishes & making good to receive new finishes 7 14-Apr-14 20-Apr-14A1240 Masonry works ( Mosaic tiles) 6 16-Apr-14 21-Apr-14A1250 Fit out works ( Wall paper, Painting, Repainting skirting, Sanitary repolishing etc 12 18-Apr-14 29-Apr-14A1260 Joinery installation 7 24-Apr-14 30-Apr-14A1270 FF & E Installation 10 27-Apr-14 06-May-14A1280 Snagging & cleaning 6 05-May-14 10-May-14A1290 Completion of the floor 0 10-May-14A1750 Client inspection, testing, commissioning & handover 7 11-May-14 17-May-14
5th Floor (26 ro5th Floor (26 rooms) 35 18-May-14 21-Jun-14A1300 Removal of existing fittings & fitures 3 18-May-14 20-May-14A1310 Removal of existing carpet 2 21-May-14 22-May-14A1320 Strip out existing finishes & making good to receive new finishes 7 22-May-14 28-May-14A1330 Masonry works ( Mosaic tiles) 6 24-May-14 29-May-14A1340 Fit out works ( Wall paper, Painting, Repainting skirting, Sanitary repolishing etc 14 26-May-14 08-Jun-14A1350 Joinery installation 10 01-Jun-14 10-Jun-14A1360 FF & E Installation 12 03-Jun-14 14-Jun-14A1370 Snagging & cleaning 6 09-Jun-14 14-Jun-14A1380 Completion of the floor 0 14-Jun-14A1760 Client inspection, testing, commissioning & handover 7 15-Jun-14 21-Jun-14
4th Floor (44 ro4th Floor (44 rooms) 45 22-Jun-14 05-Aug-14A1390 Removal of existing fittings & fitures 4 22-Jun-14 25-Jun-14A1400 Removal of existing carpet 2 26-Jun-14 27-Jun-14
0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1D J F March April May June July August S O N D J
2014 2015
Work order confirmation
o shop drawing submission ( Production based on Mock - Up)Lighting specification / drawings submission
Overseas procurementApproval for lighting specs
Material procurement for joinery itemsJoinery production
Painting works
Site mobilization
Removal of existing fittings & fituresRemoval of existing carpet
Strip out existing finishes & making good to receive new finishesMasonry works ( Mosaic tiles)
Fit out works ( Wall paper, Painting, Repainting skirting, Sanitary repolishJoinery installation
FF & E InstallationSnagging & cleaning
Client inspection, testing, commissioning & handover
Removal of existing fittings & fituresRemoval of existing carpet
Strip out existing finishes & making good to receive new finishesMasonry works ( Mosaic tiles)
Fit out works ( Wall paper, Painting, Repainting skirting, SanitaJoinery installationFF & E InstallationSnagging & cleaning
Client inspection, testing, commissioning & handover
Removal of existing fittings & fituresRemoval of existing carpet
Project Start: 24-Nov-13
Date: 11-Nov-13
Actual WorkRemaining WorkCritical Remaining Work
JW Marriot, Deira - Interior fit out works - Floor by Floor Program Phase 1 -1
Page 1 of 2
Date Revision Checked Approved
![Page 2: JW Marriott Revised](https://reader038.vdocuments.us/reader038/viewer/2022100509/55cf9af3550346d033a42657/html5/thumbnails/2.jpg)
Activity ID Activity Name OriginalDuration
Early Start Early Finish
A1410 Strip out existing finishes & making good to receive new finishes 12 27-Jun-14 08-Jul-14A1420 Masonry works ( Mosaic tiles) 12 29-Jun-14 10-Jul-14A1430 Fit out works ( Wall paper, Painting, Repainting skirting, Sanitary repolishing etc 16 02-Jul-14 17-Jul-14A1440 Joinery installation 14 08-Jul-14 21-Jul-14A1450 FF & E Installation 14 14-Jul-14 27-Jul-14A1460 Snagging & cleaning 8 22-Jul-14 29-Jul-14A1470 Completion of the floor 0 29-Jul-14A1770 Client inspection, testing, commissioning & handover 7 30-Jul-14 05-Aug-14
3rd Floor (42 ro3rd Floor (42 rooms) 45 06-Aug-14 19-Sep-14A1480 Removal of existing fittings & fitures 4 06-Aug-14 09-Aug-14A1490 Removal of existing carpet 2 10-Aug-14 11-Aug-14A1500 Strip out existing finishes & making good to receive new finishes 12 11-Aug-14 22-Aug-14A1510 Masonry works ( Mosaic tiles) 12 13-Aug-14 24-Aug-14A1520 Fit out works ( Wall paper, Painting, Repainting skirting, Sanitary repolishing etc 15 18-Aug-14 01-Sep-14A1530 Joinery installation 13 25-Aug-14 06-Sep-14A1540 FF & E Installation 13 29-Aug-14 10-Sep-14A1550 Snagging & cleaning 8 05-Sep-14 12-Sep-14A1560 Completion of the floor 0 12-Sep-14A1780 Client inspection, testing, commissioning & handover 7 13-Sep-14 19-Sep-14
2nd Floor (40 r2nd Floor (40 rooms) 42 20-Sep-14 31-Oct-14A1570 Removal of existing fittings & fitures 4 20-Sep-14 23-Sep-14A1580 Removal of existing carpet 2 24-Sep-14 25-Sep-14A1590 Strip out existing finishes & making good to receive new finishes 12 25-Sep-14 06-Oct-14A1600 Masonry works ( Mosaic tiles) 12 27-Sep-14 08-Oct-14A1610 Fit out works ( Wall paper, Painting, Repainting skirting, Sanitary repolishing etc 15 01-Oct-14 15-Oct-14A1620 Joinery installation 13 07-Oct-14 19-Oct-14A1630 FF & E Installation 13 11-Oct-14 23-Oct-14A1640 Snagging & cleaning 8 17-Oct-14 24-Oct-14A1650 Completion of the floor 0 24-Oct-14A1790 Client inspection, testing, commissioning & handover 7 25-Oct-14 31-Oct-14
1st Floor (40 ro1st Floor (40 rooms) 42 01-Nov-14 12-Dec-14A1660 Removal of existing fittings & fitures 4 01-Nov-14 04-Nov-14A1670 Removal of existing carpet 2 05-Nov-14 06-Nov-14A1680 Strip out existing finishes & making good to receive new finishes 12 06-Nov-14 17-Nov-14A1690 Masonry works ( Mosaic tiles) 12 08-Nov-14 19-Nov-14A1700 Fit out works ( Wall paper, Painting, Repainting skirting, Sanitary repolishing etc 15 12-Nov-14 26-Nov-14A1710 Joinery installation 13 18-Nov-14 30-Nov-14A1720 FF & E Installation 13 22-Nov-14 04-Dec-14A1730 Snagging & cleaning 8 28-Nov-14 05-Dec-14A1740 Completion of the floor 0 05-Dec-14A1800 Client inspection, testing, commissioning & handover 7 06-Dec-14 12-Dec-14
0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1D J F March April May June July August S O N D J
2014 2015
Strip out existing finishes & making good to receive neMasonry works ( Mosaic tiles)
Fit out works ( Wall paper, Painting, Repainting skirJoinery installation
FF & E InstallationSnagging & cleaning
Client inspection, testing, commissioning & han
Removal of existing fittings & fituresRemoval of existing carpet
Strip out existing finishes & making good Masonry works ( Mosaic tiles)
Fit out works ( Wall paper, Painting, RJoinery installationFF & E InstallationSnagging & cleaning
Client inspection, testing, commiss
Removal of existing fittings & fituRemoval of existing carpet
Strip out existing finishes & mMasonry works ( Mosaic tiles
Fit out works ( Wall paper,Joinery installationFF & E InstallationSnagging & cleaning
Client inspection, testin
Removal of existing fRemoval of existing
Strip out existing Masonry works (
Fit out works ( Joinery installaFF & E InstaSnagging &
Client insp
Project Start: 24-Nov-13
Date: 11-Nov-13
Actual WorkRemaining WorkCritical Remaining Work
JW Marriot, Deira - Interior fit out works - Floor by Floor Program Phase 1 -1
Page 2 of 2
Date Revision Checked Approved