Construction Schedule
Name of Proposed Sub-Project : Construction of 0.60 x 0.80 x 100 ln.m drainage canal
Actual Start of Work:
Target Completion Date:
Construction Duration (Calendar Days): 15 Calendar days
Qty Unit Unit Price Amount % WT 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3
0.015 0.015 0.015 0.015 0.015 0.015
0.031 0.031 0.031 0.031 0.031 0.031 0.031 0.031 0.031 0.031 0.031 0.031
0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045
193 ,627 .50 100 .00% 100%
Planned 1.48% 1.48% 1.48% 9.07% 9.07% 9.07% 7.59% 7.59% 7.59% 7.59% 7.59% 7.59% 7.59% 7.59% 7.59
Actual
Planned 1.48% 2.95% 4.43% 13.50% 22.57% 31.65% 39.24% 46.84% 54.43% 62.03% 69.62% 77.22% 84.81% 92.41% 100.00
Actual
Planned
Prepared by:
Location: Brgy. Salvacion, Palo Leyte
0.37
0.09
0.54I II Masonry Works 100 .00
Sr Construction Manager - CRS
% Accomplishment
Cummulative % Accomplishment
Slippage (%)
Ruel B. Bansali
l n.m 1 ,050 .23 105 ,022 .50 54.24%
II Concrete Works 100.00 ln.m 714.45 71,445.00 36.90%
I Excavation 100.00 ln.m 171.60 17,160.00 8.86%
W1 W2 W3
July 4, 2016
July 16, 2016
Item No. Item DescriptionBill of Quantities
ANNEX A page 1 of 1