june 27-july2: remove shield wall (3.5 days, riggers)
DESCRIPTION
June 27-July2: Remove Shield Wall (3.5 days, Riggers) June 27 – July 2 : Remove Vacuum pipe spool pieces. July 3: Pull East Poletip July 5: Pull West Poletip. Install scaffolding E&W. (Charlie & Steve) - PowerPoint PPT PresentationTRANSCRIPT
• June 27-July2: Remove Shield Wall (3.5 days, Riggers)
• June 27 – July 2: Remove Vacuum pipe spool pieces.
• July 3: Pull East Poletip
• July 5: Pull West Poletip. Install scaffolding E&W. (Charlie & Steve)
•June 27 – July 13: Remove SVT RDOs, extender cables, and cabling back to the Racks. Remove EEMC Trigger Cables.
•June 27 – July 18: Install Rollers and disconnect utilities, and roll STAR to AB and connect utilities.
• July 20 – Aug. 24: EEMC electronics maintenance.
• July 19 – 27: Install SVT platform, FTPC West platform, and disconnect end of cone cables, remove FTPCs, and extract cone to platform.
• July 30 – Aug. 14: Remove SSD, SVT, all utilities on cone, and reassemble cone.
• Aug. 1 – 15: Install new BEMC PMT comm./controls system.
• Aug. 16-21: Reinstall cone, reinstall FTPCs, & remove rails. Remove installation platform.
• Aug. 22 – 27: Disconnect utilities.
• Aug. 28 - 29: Roll STAR back into IR.
• Aug. 30 – Sept. 10: Install Utilities.
Draft STAR Shutdown Schedule/Plan
Summer Sunday
July 2007
August 2007
• Sept. 6 – 18: Beam Pipe Bakeout
• Sept. 11th: STAR in IR with utilities connected.
• Sept. 11 – Oct. 12: TPC Electronics maintenance.
• October 1st: TOF Trays arrive at BNL for installation.
• Oct. 15 – 18: SGIS Certification.
• Oct. 17th: West Poletip installed.
• Oct. 24: East Poletip installed.
• Oct. 25 – 30: Magnet testing.
• Nov. 1st: Collider Cooldown Begins.
• Nov. 1 – 2: Install BBCs.
• Nov. 7th: Lose access to IR for Collider Commissioning.
Still Open:
* When/where best to install TOF trays? Best locations 2, 4, 7, & 10:00.
* Details/plan for the TOF water system?
Collider Cooldown Begins
September 2007
October 2007