june 27-july2: remove shield wall (3.5 days, riggers)

2
June 27-July2: Remove Shield Wall (3.5 days, Riggers) June 27 – July 2: Remove Vacuum pipe spool pieces. July 3: Pull East Poletip July 5: Pull West Poletip. Install scaffolding E&W. (Charlie & Steve) June 27 – July 13: Remove SVT RDOs, extender cables, and cabling back to the Racks. Remove EEMC Trigger Cables. June 27 – July 18: Install Rollers and disconnect utilities, and roll STAR to AB and connect utilities. July 20 – Aug. 24: EEMC electronics maintenance. July 19 – 27: Install SVT platform, FTPC West platform, and disconnect end of cone cables, remove FTPCs, and extract cone to platform. July 30 – Aug. 14 : Remove SSD, SVT, all utilities on cone, and reassemble cone. • Aug. 1 – 15: Install Draft STAR Shutdown Schedule/Plan Summer Sunday July 2007 August 2007

Upload: miranda-calvin

Post on 31-Dec-2015

15 views

Category:

Documents


0 download

DESCRIPTION

June 27-July2: Remove Shield Wall (3.5 days, Riggers) June 27 – July 2 : Remove Vacuum pipe spool pieces. July 3: Pull East Poletip July 5: Pull West Poletip. Install scaffolding E&W. (Charlie & Steve) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: June 27-July2:  Remove Shield Wall (3.5 days, Riggers)

• June 27-July2: Remove Shield Wall (3.5 days, Riggers)

• June 27 – July 2: Remove Vacuum pipe spool pieces.

• July 3: Pull East Poletip

• July 5: Pull West Poletip. Install scaffolding E&W. (Charlie & Steve)

•June 27 – July 13: Remove SVT RDOs, extender cables, and cabling back to the Racks. Remove EEMC Trigger Cables.

•June 27 – July 18: Install Rollers and disconnect utilities, and roll STAR to AB and connect utilities.

• July 20 – Aug. 24: EEMC electronics maintenance.

• July 19 – 27: Install SVT platform, FTPC West platform, and disconnect end of cone cables, remove FTPCs, and extract cone to platform.

• July 30 – Aug. 14: Remove SSD, SVT, all utilities on cone, and reassemble cone.

• Aug. 1 – 15: Install new BEMC PMT comm./controls system.

• Aug. 16-21: Reinstall cone, reinstall FTPCs, & remove rails. Remove installation platform.

• Aug. 22 – 27: Disconnect utilities.

• Aug. 28 - 29: Roll STAR back into IR.

• Aug. 30 – Sept. 10: Install Utilities.

Draft STAR Shutdown Schedule/Plan

Summer Sunday

July 2007

August 2007

Page 2: June 27-July2:  Remove Shield Wall (3.5 days, Riggers)

• Sept. 6 – 18: Beam Pipe Bakeout

• Sept. 11th: STAR in IR with utilities connected.

• Sept. 11 – Oct. 12: TPC Electronics maintenance.

• October 1st: TOF Trays arrive at BNL for installation.

• Oct. 15 – 18: SGIS Certification.

• Oct. 17th: West Poletip installed.

• Oct. 24: East Poletip installed.

• Oct. 25 – 30: Magnet testing.

• Nov. 1st: Collider Cooldown Begins.

• Nov. 1 – 2: Install BBCs.

• Nov. 7th: Lose access to IR for Collider Commissioning.

Still Open:

* When/where best to install TOF trays? Best locations 2, 4, 7, & 10:00.

* Details/plan for the TOF water system?

Collider Cooldown Begins

September 2007

October 2007