July 2014. Debbie Cooke. DEMAND RESOURCE ADMINISTRATION. Process Update July 2014. Demand Response Scheduled & Forced Curtailments. Background. Enhancements to the DR baseline calculations became effective June 1, 2014 - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/1.jpg)
JULY 2014
Debbie CookeDEMAND RESOURCE ADMINISTRATION
Process Update July 2014
Demand Response Scheduled & Forced Curtailments
![Page 2: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/2.jpg)
Background
• Enhancements to the DR baseline calculations became effective June 1, 2014
• Allows scheduled and forced curtailments of Real-Time Demand Response and Real-Time Emergency Generation assets– DR assets can preserve their baseline by submitting unadjusted
baseline values during intervals of a forced or scheduled curtailment
• As of July 15, ISO New England has received approximately 50 curtailment requests
2
![Page 3: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/3.jpg)
• Discussed at April DRWG:
• But what about?
Process
3
Pre-Curtailment (Scheduled)Post-
Curtailment
![Page 4: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/4.jpg)
Modification and Cancellation Guidelines
• Scheduled curtailments only– Forced curtailments are submitted after the fact, so
modifications/cancellations are unnecessary
• Modification: A later curtailment start date (same end date) or earlier end date (same start date)
– A change that results in a totally different date range will be treated as a cancellation and a new curtailment request
• Cancellation: Entire curtailment changed or removed
• Submitted through a service note
• Notification should be prior to start date of scheduled curtailment
4
![Page 5: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/5.jpg)
Reminders – Scheduled Curtailments
• For days during the scheduled curtailment:– Do not submit Day Ahead Offers for any days during the curtailment
and remove any existing offers that may be carried forward– Adjust Resource availability
• DRMUI, Navigation > Hourly Resource Availability
• Submit Unadjusted Baseline values for all intervals during the curtailment unless there’s a dispatch pursuant to MR-1, III.13 (OP-4 or audit)– Submit actual meter data during OP-4/audit dispatch intervals
5
![Page 6: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/6.jpg)
Reminders – Forced Curtailments
• For days with an anticipated forced curtailment:– Do not submit Day Ahead Offers and remove any existing offers that may
be carried forward for Operating Days with an anticipated forced curtailment
– Adjust Resource availability• DRMUI, Navigation > Hourly Resource Availability
– Submit Unadjusted Baseline values for all intervals during the curtailment unless:
• there’s a dispatch pursuant to MR-1, III.13 (OP-4 or audit), or• the asset had cleared day-ahead or become eligible in real-time
pursuant to MR-1, Appendix E1 on a day with an unanticipated forced curtailment
• Submit actual meter data during those intervals
6
![Page 7: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/7.jpg)
• Curtailments are per asset, not facility
• Other assets at the facility should submit meter data during the curtailment
Unadjusted Baseline Data Submittal
7
Asset Baseline Type Data SubmittalTotal Facility Load(TFL)
UBL submitted on the load channel
Facility Metered Load(FML)
UBL submitted on the load channel
Distributed Generation(DG)
UBL submitted on the generation channel
![Page 8: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/8.jpg)
What about Facilities With Distributed Gen or Multiple Assets Behind the Same Retail Meter?
• Questions received regarding the impact on performance if:– A Distributed Generation asset is dispatched during a curtailment– A facility with multiple assets behind the same retail meter is dispatched
• M-MVDR and MR-1 modified to allow metering at the RDP for an asset comprised of both generation and load
– Existing assets at a facility can be aggregated into one– Metered demand at the RDP is used to compute the baseline and
determine asset performance
8MR-1, III.8A.4.4
![Page 9: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/9.jpg)
Recap – Scheduled CurtailmentsMarket Participant Responsibilities
9
Requirement Timing ProcessNotification Assets with MIC < 5
MW: 7 calendar days
Assets >= 5 MW: 15 calendar days
Submit Scheduled/Forced Curtailment Form via Service Note
Meter Data Curtailment Period No MR-1, III.13 Event during Curtailment Period:• Unadjusted Baseline values calculated for first
day of curtailment as data correction via DRMUIMR-1, III.13 Event during Curtailment Period:• Actual meter data for event intervals• Unadjusted Baseline from first day of curtailment
for all non-event intervals via DRMUI
Demand Reduction Offers
Curtailment Period Prohibited from submitting offers for an Operating Day with a scheduled curtailment
MR-1, III.8A.5; App. E1
![Page 10: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/10.jpg)
Recap – Forced CurtailmentsMarket Participant Responsibilities
10
Requirement Timing ProcessNotification Prior to Data
Reconciliation Deadline for the month
Submit Scheduled/Forced Curtailment Form via Service Note
Meter Data Curtailment Period No MR-1, III.13 Event during Curtailment Period: Unadjusted Baseline values calculated for first day of curtailment via DRMUINo MR-1, III.13 Event during Curtailment Period, or unanticipated and DA Cleared/RT Eligible :• Actual meter data for event intervals• Unadjusted Baseline from first day of curtailment
for all non-event intervals via DRMUI
Demand Reduction Offers
Curtailment Period Prohibited from submitting offers for an Operating Day with a known forced curtailment
MR-1, III.8A.5; App. E1
![Page 11: July 2014](https://reader035.vdocuments.us/reader035/viewer/2022062721/56813650550346895d9dd2a8/html5/thumbnails/11.jpg)
11