JOSÉ CABRERA NPP DISMANTLING AND

DECOMMISSIONING PROJECT

Manuel Rodríguez Silva

IDN, November 2011

PROJECT GOALS AND VISION

3

José Cabrera NPP D&D Project

SITUATION

SPAIN

Madrid

Almonacid de Zorita

(Guadalajara)

Guadalajara. José Cabrera NPP Dismantling -Project length: 2010-2016 -Reactor type: PWR Reactor -Status: Preparatory activities / Conventional dismantling

4

José Cabrera NPP D&D Project

OBJECTIVES

Complete dismantling of the nuclear (first time in Spain)

Proper management of the resulting materials

1

2

1

2

Dismantling is the best way for controlling the risk at any NPP after operation

5

José Cabrera NPP D&D Project

DECOMMISSIONING VISION

Inputs Outputs Transformation process

+ + RESOURCES MATERIALS

1

2 3 4

5 6

DISMANTLING is not only DEMOLITION, but an INDUSTRIAL

PROCESS

1 2 3 4 5 6

THE INPUTS

7

José Cabrera NPP D&D Project

CONSTRUCTION WORKS

History

8

José Cabrera NPP D&D Project

ENRESA`s RESPONSIBILITY

OTHER RESPONSIBILITIES

ENGINEERING &

START UP

COMMERCIAL STAGE

D&D EXECUTION

PROJECT FINAL SHUTDOWN

TRANSITION STAGE

1963

STRATEGY BASIC STUDIES

DOCUMENTATION + EIS

LICENSING

D&D PLANNING

“LANDING” PLAN

2006 1969

SITE RETURN to the OWNER

ELECTRICAL NET DISCONNECTION

NSSS DECONTAMINATION

SPENT FUEL MANAGEMENT

SPENT FUEL CASKS at the ISFI

TRANSFER of RESPONSIBILITY

(Feb, 11, 2010)

LIFE CYCLE

DECOMMISSION

2016 2010

Build up Starting – Jul-65

1st Criticallity – Jun-68

1st Electrical Net Connection – Jul-68

Commercial Status– Oct-69

FIRST NPP IN SPAIN DEVELOPING the SPANISH NUCLEAR INDUSTRY BASE for TRAINING

History

9

José Cabrera NPP D&D Project

Type: Westinghouse - 1-Loop PWR

Net Electrical Power: 160 MWe

Net Thermal Power: 510 MWth

Fuel Elements: 69 – 14x14

Fuel Type: UO2 – enrichment 3,6% (U-235)

Mass UO2 (core) 20,76 t

Control Rod (Banks): 17

Reactor Vessel (Diameter): 2,82 m

Reactor Vessel (Height without Head): 5,87 m

NSSS (Diameter): 70 cm

Containment:

Reinforced concrete + Stainless Steel Head

Spent Fuel Pool:

In Containment

Final cooling:

Tajo River

INSTALLATION MAIN DESIGN DATA

History

10

José Cabrera NPP D&D Project

INSTALLATION MAIN CROSS SECTION

TURBINE HALL – CONTAINMENT BUILDING

History

11

José Cabrera NPP D&D Project

SITE MAP & BUILDINGS

1

2 3

7 6 8

9 13

14

15

16

10

17

18

11

12

5

1.- Reactor 2.- Turbine 3.- Auxiliary Building 4.- Offices 5.- Transformers 6.- Diesel 7.- Evaporator 8.- RadWaste Building 1 9.- Warehouse 10.- General Warehouse 11.- RadWaste Building 2 12.- Release Measurements Zone 13.- Electrical Distribution Area 14.- Discharge Channel 15.- Cooling Towers 16.- Release Material Storage Area 17.- Parking 18.- Radwaste Expedition Area

History

THE OUTPUTS

13

José Cabrera NPP D&D Project

RELEASED SITE

14

José Cabrera NPP D&D Project

MATERIALS MANAGEMENT

15

José Cabrera NPP D&D Project

43 t

218 t

4.000 t

4.700 t 95.300 t

175 t

MATERIALS MANAGEMENT: EXPECTED QUANTITIES

104.000 tons to manage Only 4% is radiactive All materials have a destination

THE RESOURCES

17

José Cabrera NPP D&D Project

WORK SCHEDULE

The scheduled time of dismantling works is 6 years

ACTIVITY 2010 2011 2013 2012 2014 2015 2016

PREPARATORY ACTIVITIES

RADIOLOGICAL DISMANTLING

Major rad components

Other components

DESCONTAMINATION AND DEMOLITION

MATERIAL MANAGEMENT

EMPLACEMENT RESTORATION

System Discharge

System Modifications

Conditioning Facilities

CONVENTIONAL DISMANTLING

18

José Cabrera NPP D&D Project

PROJECT MAIN ACTIVITIES Cost

(M€ 2003)

-Engineering & Basic Project 34

-Previous Activities after Shutdown + NSSS Decon 5

-Transition Activities (2006-2010) 6

-Dismantling & Decom Execution 29

-Material & Rad Waste Management 11

-Site Restoration 23

-Others 4

(Un-Expected (%)) 20%

SPENT FUEL MANAGEMENT NOT INCLUDED ( ~ 35 M€) TOTAL ~ 135

BUDGET

PROJECT DATA & FEATURES

19

José Cabrera NPP D&D Project

HUMAN RESOURCES

0

50

100

150

200

250

300

EMP

LEA

DO

S

PERIODO

PERSONNEL EVOLUTION DURING THE PROJECT

ACTIVIDADES EJECUCIÓNPDC

VIGILANCIA YMANTENIMIENTOINSTALACIÓN

INGENIERÍA Y DIRECCIÓNDE OBRA

Estimated peak: 250 workers

THE PROCESS

(PROJECT PHASES)

21

José Cabrera NPP D&D Project

Characterization

Modifications

Disassemblies

Demolitions

Site restoration

Materials Management

Transfer of ownership

Decommisioning

Statement

DECOMMISSIONING MAIN STEPS

22

José Cabrera NPP D&D Project

DECOMMISSIONING MAIN STEPS

23

José Cabrera NPP D&D Project

MATERIALS RELEASE METHODOLOGY

HISTORICAL OPERATING

DATA

1

RADIOMETRIC STUDIES

2

ACTIVE ZONES

CONVENTIONAL ZONES

ACTIVE PARTS P.D.

CLEAN

CONVENCIONAL COMPONENT P.D.

“IN SITU” RADIOLOGICAL

CONTROL

3

+

RADIOACTIVE WASTE

DESTINATION (Administrative control)

EXIT GATE MONITORS

5

CLEARANCE

4

Disassembly & Preparation of MDC handling

Units

YES

Disassembly & preparation

MTC handling unit

EL CABRIL DISPOSAL FACILITY

TRANSPORT

NO CONDITIONING AND PREPARATION FOR

TRANSPORT

24

José Cabrera NPP D&D Project

MATERIALS MANAGEMENT

25

José Cabrera NPP D&D Project

MATERIALS MANAGEMENT

Radiological characterization with Box Counter Transfer of handling units

Loading of clered materials Dispatch of cleared materials

DECLASSIFICATION

VIDEO

PROJECT PROGRESS

(UNTIL OCTOBER 2011)

28

José Cabrera NPP D&D Project

PROJECT PROGRESS (2010-2011)

Towers Electrical Building

Water Intake

Strucuture

Turbine Building

DAB (Dismant. Auxiliay Building)

Reactor Building

Electrical and

Auxiliary Building

Cooling Towers

Diesel Building

Waste Storage

Outdoor Areas

Clearance Area

Preparatory Activities

Electric Systems 100% 100% 90% 100%

Mechanical Syst. / Fire Fight System Conditioning

100% 100%

Ventilation System Adaptation

5% 100% 100%

Support Facilities Adequacy

75% 60% 100%

Support Facilities Equipment

70% (*)

Active Zones Preparation 30% 10%

Conventional Dismantling 100% 100% 100% 100%

Radiological Dismantling

(*) Design / manufacturing activities ongoing

29

José Cabrera NPP D&D Project

PROJECT PHASES

PHASE 0 – REMOVAL of FUEL & PRELIMINARY WORKS

• Post-Shutdown Activities

• Primary System Decontamination

• Update Initial Radiological Characterization

• Update Physical Inventory

• Shutdown-Drain & Isolation of Non Required Systems & Components

• Construction of ITS (Independent Temporary Storage)

• Dry Store Cask Loading (Fuel Pool empty)

30

José Cabrera NPP D&D Project

SPENT FUEL – CASK LOADING

HI-STORM going to the PAD

STORAGE AREA

HI-TRACK – EXIT of CONTAINMENT BUILDING

MPC into the HI-STORM

PHASE 0.- REMOVAL of SPENT FUEL & PRELIMINARY WORKS

31

José Cabrera NPP D&D Project

12 HI-STORM Z CASKS

INDEPENDENT TEMPORARY STORAGE (ITS) FACILITY

PHASE 0.- REMOVAL of SPENT FUEL & PRELIMINARY WORKS

32

José Cabrera NPP D&D Project

BUILDINGS & COMPONENTS – INITIAL RADIOLOGICAL IDENTIFICATION

Samples & Laboratory Measurements

PHASE 0.- REMOVAL of SPENT FUEL & PRELIMINARY WORKS

33

José Cabrera NPP D&D Project

PROJECT PHASES

PHASE 1 – PREPARATORY ACTIVITIES

• Mobilization & Set-up of Site Offices

• Hazardous Material Removal

• Dismantling of Non Radioactive Systems & Areas & Equipments

• Modification & Reconfiguration of Systems & Equipments

• Turbine Hall: Modification + Adaptation

• Tests & Start up Procedures of the New Systems & Facilities

34

José Cabrera NPP D&D Project

Discharge systems

PHASE 1.- PREPARATORY ACTIVITIES

DISCONNECT SYSTEMS & EQUIPMENTS

35

José Cabrera NPP D&D Project

New Electrical Building Power Cells & Cabins

3 kV & 380 V

Electric Supply System Modification

D&D New Principal Transformer

46 kV Equipment

Modification

PHASE 1.- PREPARATORY ACTIVITIES

36

José Cabrera NPP D&D Project

Electric Supply System Modification

PHASE 1.- PREPARATORY ACTIVITIES

37

José Cabrera NPP D&D Project

Fire Fight System Conditioning

PHASE 1.- PREPARATORY ACTIVITIES

38

José Cabrera NPP D&D Project

New Tubes & Modifications

Ventilation System Adaptation

New Controlled Area Ventilation

New Equipments

PHASE 1.- PREPARATORY ACTIVITIES

39

José Cabrera NPP D&D Project

Ventilation System Adaptation

PHASE 1.- PREPARATORY ACTIVITIES

40

José Cabrera NPP D&D Project

Cooling Towers

Diesel Turbine Building Transformers

Conventional Dismantling of Systems & Buildings

PHASE 1.- PREPARATORY ACTIVITIES

41

José Cabrera NPP D&D Project

COOLING TOWERS DEMOLITION

42

José Cabrera NPP D&D Project

COMPONENTS DISASSEMBLY IN DIESEL BUILDING

43

José Cabrera NPP D&D Project

DISASSEMBLY OF THE MAIN TRANSFORMER

44

José Cabrera NPP D&D Project

Temporary RadW Store CE-2a/b

CE-2a/b Concrete Filling Area

New Areas for Cutting & Decon

CMT Conditioning Area

Temporary RadW Store

TURBINE BUILDING MODIFICATION & ADAPTATION

PHASE 1.- PREPARATORY ACTIVITIES

45

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

46

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

47

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

48

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

49

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

50

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

51

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

Section of concrete structures with diamond

wire

52

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

53

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

54

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

55

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

56

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

57

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

58

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

59

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

60

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

61

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

62

José Cabrera NPP D&D Project

TURBINE BUILDING MODIFICATION AND ADAPTATION

63

José Cabrera NPP D&D Project

Electrical rewiring

TURBINE BUILDING MODIFICATION AND ADAPTATION

64

José Cabrera NPP D&D Project

Ventilation System

Adaptation

TURBINE BUILDING MODIFICATION AND ADAPTATION

FOLLOWING ACTIVITIES

66

José Cabrera NPP D&D Project

PROJECT PHASES

PHASE 2 – DISMANTLING of MAJOR RAD COMPONENTS

• Radioactive Equipment & Systems – Decontamination + Dismantling

• Reactor Internals Segmentation

• Dismantling of Large Components + NSSS Removal

• Cleareance Survey of Materials (Equipment & Systems)

• Rad Waste Processing, Storage & Disposal

• Conventional Materials Management

67

José Cabrera NPP D&D Project

CORE BARREL LOWER INTERNALS

UPPER INTERNALS

THERMAL SHIELD BAFFLE

REACTOR VESSEL & MAJOR COMPONENTS

FORMERS

REACTOR VESSEL

PHASE 2.- DISMANTLING of MAJOR RAD COMPONENTS

68

José Cabrera NPP D&D Project

Elevation 621,600

Elevation 604,000

+614,700

Transfer Wire Basket

75 tons Crane

35 tons Crane

32 tons New Crane

CE-2a

Reinforced Bell

TRANSPORT AND WASTE PACKAGING

PHASE 2.- DISMANTLING of MAJOR RAD COMPONENTS

69

José Cabrera NPP D&D Project

PREPARATORY WORKS

70

José Cabrera NPP D&D Project

PREPARATORY WORKS

71

José Cabrera NPP D&D Project

PREPARATORY WORKS

José Cabrera NPP Reactor

Cavity

72

José Cabrera NPP D&D Project

PREPARATORY WORKS

Section of concrete structures with diamond wire

73

José Cabrera NPP D&D Project

PREPARATORY WORKS

74

José Cabrera NPP D&D Project

PREPARATORY WORKS

75

José Cabrera NPP D&D Project

PREPARATORY WORKS

76

José Cabrera NPP D&D Project

PREPARATORY WORKS

77

José Cabrera NPP D&D Project

PROJECT PHASES

PHASE 3 – REMOVE of AUX. INSTALLATIONS,CLEAN & DEMOLITIONS

• Miscellaneous Systems & Equipment Removal

• Radioactive Structures Decontamination

• Post Radiological Characterization

• Cleareance Survey of Materials (Structures & Buildings)

• Demolition & Removal of Structures & Buildings

78

José Cabrera NPP D&D Project

PROJECT PHASES

PHASE 4 – ENVIRONMENTAL RESTORATION • Final Cleanup

• Final Radiological De-License Survey

• Backfill of Cavities

• Site Restoration

• Landscaping

• Close out Report

• Regulatory Approval of De-License Application

• Site Formally De-Licensed

• Return to the Owner

79

José Cabrera NPP D&D Project

LANDSCAPING

PHASE 4.- ENVIRONMENTAL RESTORATION

JOSÉ CABRERA 2016

80

José Cabrera NPP D&D Project