josÉ cabrera npp dismantling and decommissioning project · josÉ cabrera npp dismantling and...
TRANSCRIPT
3
José Cabrera NPP D&D Project
SITUATION
SPAIN
Madrid
Almonacid de Zorita
(Guadalajara)
Guadalajara. José Cabrera NPP Dismantling -Project length: 2010-2016 -Reactor type: PWR Reactor -Status: Preparatory activities / Conventional dismantling
4
José Cabrera NPP D&D Project
OBJECTIVES
Complete dismantling of the nuclear (first time in Spain)
Proper management of the resulting materials
1
2
1
2
Dismantling is the best way for controlling the risk at any NPP after operation
5
José Cabrera NPP D&D Project
DECOMMISSIONING VISION
Inputs Outputs Transformation process
+ + RESOURCES MATERIALS
1
2 3 4
5 6
DISMANTLING is not only DEMOLITION, but an INDUSTRIAL
PROCESS
1 2 3 4 5 6
8
José Cabrera NPP D&D Project
ENRESA`s RESPONSIBILITY
OTHER RESPONSIBILITIES
ENGINEERING &
START UP
COMMERCIAL STAGE
D&D EXECUTION
PROJECT FINAL SHUTDOWN
TRANSITION STAGE
1963
STRATEGY BASIC STUDIES
DOCUMENTATION + EIS
LICENSING
D&D PLANNING
“LANDING” PLAN
2006 1969
SITE RETURN to the OWNER
ELECTRICAL NET DISCONNECTION
NSSS DECONTAMINATION
SPENT FUEL MANAGEMENT
SPENT FUEL CASKS at the ISFI
TRANSFER of RESPONSIBILITY
(Feb, 11, 2010)
LIFE CYCLE
DECOMMISSION
2016 2010
Build up Starting – Jul-65
1st Criticallity – Jun-68
1st Electrical Net Connection – Jul-68
Commercial Status– Oct-69
FIRST NPP IN SPAIN DEVELOPING the SPANISH NUCLEAR INDUSTRY BASE for TRAINING
History
9
José Cabrera NPP D&D Project
Type: Westinghouse - 1-Loop PWR
Net Electrical Power: 160 MWe
Net Thermal Power: 510 MWth
Fuel Elements: 69 – 14x14
Fuel Type: UO2 – enrichment 3,6% (U-235)
Mass UO2 (core) 20,76 t
Control Rod (Banks): 17
Reactor Vessel (Diameter): 2,82 m
Reactor Vessel (Height without Head): 5,87 m
NSSS (Diameter): 70 cm
Containment:
Reinforced concrete + Stainless Steel Head
Spent Fuel Pool:
In Containment
Final cooling:
Tajo River
INSTALLATION MAIN DESIGN DATA
History
10
José Cabrera NPP D&D Project
INSTALLATION MAIN CROSS SECTION
TURBINE HALL – CONTAINMENT BUILDING
History
11
José Cabrera NPP D&D Project
SITE MAP & BUILDINGS
1
2 3
7 6 8
9 13
14
15
16
10
17
18
11
12
5
1.- Reactor 2.- Turbine 3.- Auxiliary Building 4.- Offices 5.- Transformers 6.- Diesel 7.- Evaporator 8.- RadWaste Building 1 9.- Warehouse 10.- General Warehouse 11.- RadWaste Building 2 12.- Release Measurements Zone 13.- Electrical Distribution Area 14.- Discharge Channel 15.- Cooling Towers 16.- Release Material Storage Area 17.- Parking 18.- Radwaste Expedition Area
History
15
José Cabrera NPP D&D Project
43 t
218 t
4.000 t
4.700 t 95.300 t
175 t
MATERIALS MANAGEMENT: EXPECTED QUANTITIES
104.000 tons to manage Only 4% is radiactive All materials have a destination
17
José Cabrera NPP D&D Project
WORK SCHEDULE
The scheduled time of dismantling works is 6 years
ACTIVITY 2010 2011 2013 2012 2014 2015 2016
PREPARATORY ACTIVITIES
RADIOLOGICAL DISMANTLING
Major rad components
Other components
DESCONTAMINATION AND DEMOLITION
MATERIAL MANAGEMENT
EMPLACEMENT RESTORATION
System Discharge
System Modifications
Conditioning Facilities
CONVENTIONAL DISMANTLING
18
José Cabrera NPP D&D Project
PROJECT MAIN ACTIVITIES Cost
(M€ 2003)
-Engineering & Basic Project 34
-Previous Activities after Shutdown + NSSS Decon 5
-Transition Activities (2006-2010) 6
-Dismantling & Decom Execution 29
-Material & Rad Waste Management 11
-Site Restoration 23
-Others 4
(Un-Expected (%)) 20%
SPENT FUEL MANAGEMENT NOT INCLUDED ( ~ 35 M€) TOTAL ~ 135
BUDGET
PROJECT DATA & FEATURES
19
José Cabrera NPP D&D Project
HUMAN RESOURCES
0
50
100
150
200
250
300
Nº
EMP
LEA
DO
S
PERIODO
PERSONNEL EVOLUTION DURING THE PROJECT
ACTIVIDADES EJECUCIÓNPDC
VIGILANCIA YMANTENIMIENTOINSTALACIÓN
INGENIERÍA Y DIRECCIÓNDE OBRA
Estimated peak: 250 workers
21
José Cabrera NPP D&D Project
Characterization
Modifications
Disassemblies
Demolitions
Site restoration
Materials Management
Transfer of ownership
Decommisioning
Statement
DECOMMISSIONING MAIN STEPS
23
José Cabrera NPP D&D Project
MATERIALS RELEASE METHODOLOGY
HISTORICAL OPERATING
DATA
1
RADIOMETRIC STUDIES
2
ACTIVE ZONES
CONVENTIONAL ZONES
ACTIVE PARTS P.D.
CLEAN
CONVENCIONAL COMPONENT P.D.
“IN SITU” RADIOLOGICAL
CONTROL
3
+
RADIOACTIVE WASTE
DESTINATION (Administrative control)
EXIT GATE MONITORS
5
CLEARANCE
4
Disassembly & Preparation of MDC handling
Units
YES
Disassembly & preparation
MTC handling unit
EL CABRIL DISPOSAL FACILITY
TRANSPORT
NO CONDITIONING AND PREPARATION FOR
TRANSPORT
25
José Cabrera NPP D&D Project
MATERIALS MANAGEMENT
Radiological characterization with Box Counter Transfer of handling units
Loading of clered materials Dispatch of cleared materials
DECLASSIFICATION
28
José Cabrera NPP D&D Project
PROJECT PROGRESS (2010-2011)
Towers Electrical Building
Water Intake
Strucuture
Turbine Building
DAB (Dismant. Auxiliay Building)
Reactor Building
Electrical and
Auxiliary Building
Cooling Towers
Diesel Building
Waste Storage
Outdoor Areas
Clearance Area
Preparatory Activities
Electric Systems 100% 100% 90% 100%
Mechanical Syst. / Fire Fight System Conditioning
100% 100%
Ventilation System Adaptation
5% 100% 100%
Support Facilities Adequacy
75% 60% 100%
Support Facilities Equipment
70% (*)
Active Zones Preparation 30% 10%
Conventional Dismantling 100% 100% 100% 100%
Radiological Dismantling
(*) Design / manufacturing activities ongoing
29
José Cabrera NPP D&D Project
PROJECT PHASES
PHASE 0 – REMOVAL of FUEL & PRELIMINARY WORKS
• Post-Shutdown Activities
• Primary System Decontamination
• Update Initial Radiological Characterization
• Update Physical Inventory
• Shutdown-Drain & Isolation of Non Required Systems & Components
• Construction of ITS (Independent Temporary Storage)
• Dry Store Cask Loading (Fuel Pool empty)
30
José Cabrera NPP D&D Project
SPENT FUEL – CASK LOADING
HI-STORM going to the PAD
STORAGE AREA
HI-TRACK – EXIT of CONTAINMENT BUILDING
MPC into the HI-STORM
PHASE 0.- REMOVAL of SPENT FUEL & PRELIMINARY WORKS
31
José Cabrera NPP D&D Project
12 HI-STORM Z CASKS
INDEPENDENT TEMPORARY STORAGE (ITS) FACILITY
PHASE 0.- REMOVAL of SPENT FUEL & PRELIMINARY WORKS
32
José Cabrera NPP D&D Project
BUILDINGS & COMPONENTS – INITIAL RADIOLOGICAL IDENTIFICATION
Samples & Laboratory Measurements
PHASE 0.- REMOVAL of SPENT FUEL & PRELIMINARY WORKS
33
José Cabrera NPP D&D Project
PROJECT PHASES
PHASE 1 – PREPARATORY ACTIVITIES
• Mobilization & Set-up of Site Offices
• Hazardous Material Removal
• Dismantling of Non Radioactive Systems & Areas & Equipments
• Modification & Reconfiguration of Systems & Equipments
• Turbine Hall: Modification + Adaptation
• Tests & Start up Procedures of the New Systems & Facilities
34
José Cabrera NPP D&D Project
Discharge systems
PHASE 1.- PREPARATORY ACTIVITIES
DISCONNECT SYSTEMS & EQUIPMENTS
35
José Cabrera NPP D&D Project
New Electrical Building Power Cells & Cabins
3 kV & 380 V
Electric Supply System Modification
D&D New Principal Transformer
46 kV Equipment
Modification
PHASE 1.- PREPARATORY ACTIVITIES
36
José Cabrera NPP D&D Project
Electric Supply System Modification
PHASE 1.- PREPARATORY ACTIVITIES
38
José Cabrera NPP D&D Project
New Tubes & Modifications
Ventilation System Adaptation
New Controlled Area Ventilation
New Equipments
PHASE 1.- PREPARATORY ACTIVITIES
40
José Cabrera NPP D&D Project
Cooling Towers
Diesel Turbine Building Transformers
Conventional Dismantling of Systems & Buildings
PHASE 1.- PREPARATORY ACTIVITIES
44
José Cabrera NPP D&D Project
Temporary RadW Store CE-2a/b
CE-2a/b Concrete Filling Area
New Areas for Cutting & Decon
CMT Conditioning Area
Temporary RadW Store
TURBINE BUILDING MODIFICATION & ADAPTATION
PHASE 1.- PREPARATORY ACTIVITIES
51
José Cabrera NPP D&D Project
TURBINE BUILDING MODIFICATION AND ADAPTATION
Section of concrete structures with diamond
wire
64
José Cabrera NPP D&D Project
Ventilation System
Adaptation
TURBINE BUILDING MODIFICATION AND ADAPTATION
66
José Cabrera NPP D&D Project
PROJECT PHASES
PHASE 2 – DISMANTLING of MAJOR RAD COMPONENTS
• Radioactive Equipment & Systems – Decontamination + Dismantling
• Reactor Internals Segmentation
• Dismantling of Large Components + NSSS Removal
• Cleareance Survey of Materials (Equipment & Systems)
• Rad Waste Processing, Storage & Disposal
• Conventional Materials Management
67
José Cabrera NPP D&D Project
CORE BARREL LOWER INTERNALS
UPPER INTERNALS
THERMAL SHIELD BAFFLE
REACTOR VESSEL & MAJOR COMPONENTS
FORMERS
REACTOR VESSEL
PHASE 2.- DISMANTLING of MAJOR RAD COMPONENTS
68
José Cabrera NPP D&D Project
Elevation 621,600
Elevation 604,000
+614,700
Transfer Wire Basket
75 tons Crane
35 tons Crane
32 tons New Crane
CE-2a
Reinforced Bell
TRANSPORT AND WASTE PACKAGING
PHASE 2.- DISMANTLING of MAJOR RAD COMPONENTS
77
José Cabrera NPP D&D Project
PROJECT PHASES
PHASE 3 – REMOVE of AUX. INSTALLATIONS,CLEAN & DEMOLITIONS
• Miscellaneous Systems & Equipment Removal
• Radioactive Structures Decontamination
• Post Radiological Characterization
• Cleareance Survey of Materials (Structures & Buildings)
• Demolition & Removal of Structures & Buildings
78
José Cabrera NPP D&D Project
PROJECT PHASES
PHASE 4 – ENVIRONMENTAL RESTORATION • Final Cleanup
• Final Radiological De-License Survey
• Backfill of Cavities
• Site Restoration
• Landscaping
• Close out Report
• Regulatory Approval of De-License Application
• Site Formally De-Licensed
• Return to the Owner