joint bay,bakool wash assessment report · g) provision of subsidy, fast moving spares and rapid...
TRANSCRIPT
Joint Bay,Bakool WASH Assessment Report
1.1 Executive Summary
This is a WASH joint assessment report jointly by WASH partners working in Bay and Bakool
regions. The purpose of the WASH assessment was to find out the extent and evolution of
WASH situation in Bay and Bakool regions following limited interventions in the area and
based on the findings come up with priority areas of intervention and recommend appropriate
response options.
1.2 Background
WASH gaps are enormous in Bay and Bakool regions due to slow intervention in many areas
exacerbated by the absence of humanitarian agencies in the area. WASH cluster partners in the
area are trying to bring into rapid change towards WASH effectiveness in target areas.
The assessment begun on 15th
to 20th
of July in both regions, WASH partners in the two regions
voluntarily participated in the assessment, SYPD provided WASH assessment guidelines, and
materials (books, pens and envelops), other partners provided transport in accessible areas in Bay
region moving in groups. Also members shared assessment guidelines through email in Bakool
to reduce risks of travelling with documents as it was secure and timesaving.
The joint assessment aimed at identifying WASH gaps, potential areas of intervention both in
long and short term.
1.3 Objectives:
To identify major WASH gaps in the area
Identify any overlap of WASH activities by agencies
To identify both community and IDPs priority needs
To provide a shared overview of WASH situation in all affected areas of the regions
To identify immediate humanitarian needs that were not addressed
To understand recovery needs of affected IDPs and the vulnerable people
1.4 Methodology
The assessment entailed observation and village visit whereby communities including the IDPs
were given an opportunity to air their priority needs. WASH assessment tools were also used.
1.5 Findings
Accesses to latrines in these regions are minimal, hygiene and sanitation is very substantial.
Huge number of population in the areas defecates openly causing environmental health
problems. Available water sources in the area require massive rehabilitation of which most of
them have dried up, households are currently trekking water for domestic uses. This minimizes
access to enough water for household use. Households interviewed in assessed community areas
reported that they can only collect 30lts of water down from 80lts collected during normal times.
This translates to about 4lts per person per day which is 3 times less than the minimum sphere
standards. Over half of the shallow wells have indicated deteriorating water quality and are
projected to dry up due to lack of seasonal replenishment of the aquifers. The region is not
endowed with boreholes due to the high level of under investment in utilization of underground
water may be because of high number of settlements in the area or may be because of other
factors that were beyond the assessment scope. The main water sources in the villages assessed
were communal water catchment which requires recurrent de-silting to increase the capacity.
Inadequate health facilities is also a worrying concern and health facilities are limited in the area,
Most of the IDPS reside in Makeshifts posing protection risks to them. Children have no access
to basic education.
1.5.4 Key findings
When village leaders in the assessment villages asked; is access to water restricted in your
village? Ninety percent of the respondent said water accessibility is restricted. This is so because
the main water sources are water catchments which are not permanent water sources and require
restricted uses of water.
On the other hand the physical observation of the water catchments indicated that almost all the
water catchments dried up.
A question on water sources was asked the interviewed member of the community which
was; where does the village get its water from? Villages explained that their main water
source is communal water catchments dug by the communities. The volumes of these water
catchments are reduced due to silt concentration and they dry up so quickly. One of the target
villages testified that their water source is shallow wells which in relation to water catchments it
semi-permanent water sources and thus they have relatively better water accessibility although
water quality also remains in question.
To assess the longevity of water availability in the water sources of the year a question like
what is the average number of months when water is available in the catchments/wells in
the year? According to the respondents 70% of the assessed villages access water from their
water sources only 6 months average. This is so because the volume and water holding capacity
of their water catchments is less than they require. 20% of the villages access water from their
water catchments between 9 months while they cannot also access water from these sources
more than 9 months in case of rain failures. However, one of the villages using shallow wells as
their water source indicated that they access water all the time because shallow wells are either
permanent or semi-permanent water source.
What are the causes and impacts of lack of access to water?
The causes attributed to water scarcity in these villages vary with villages and respondents.
Some of them responded claim that it is due to lack of permanent rain failure while other
attributed to rain failure and some others attributing to water facilities drying up faster than they
should. The impact of lack of water was obvious with almost all the people interviewed and
100% of the respondents mentioned the impact of lack of water in their area as follows:
Displacement of households
Water related diseases including diarrhea, skin diseases and others
Community based conflict over scarce resources
Lack of land preparation hence crop failure
 Ninety percent of them said the water sources range from 3 to 9 kilometer from the main
villages posing water accessibility distance to women and girls. On the other hand this also puts
them on risk of possible rapes and other violations. Women and girls walk long distances to
collect water either using their back or donkeys to carry water.
When a question on water protection reading “is the water source protected or not protected
was asked the response was: almost all the villages asserted that their water sources are
protected from animal and human accessibility. This indicates the quality of water is very much
unsafe. Water protection is not something the communities understood.
On the other hand the assessment findings indicate that at least 90% of the available water
sources are used by human for domestic water requirement and watering animals in a very
unsafe ways. The communal water catchments with reduced capacity which are not protected
from both human and animals accessing water directly elude and minimize water accessibility
during the drier seasons and rain failure times.
The assessment target villages were all rural agro-pastoral villages where rural poverty is
significantly prevalent. Access to and knowledge of water treatment and purification of water is
minimal if any. When a question on water purification was asked 100% of the respondents said
water is rarely purified. Contaminated water from unprotected water sources are directly
consumed by people in these villages and chances of water related diseases are very high
especially during rain failures and droughts due to minimum accessibility of water. The water
treatment question asked and the graphical presentation are as follows.
What are the causes and impacts of lack of access to water? The causes attributed to water
scarcity in these villages vary with villages and respondents. Some of them responded claim that
it is due to lack of permanent rain failure while other attributed to rain failure and some others
attributing to water facilities drying up faster than they should. The impact of lack of water was
obvious with almost all the people interviewed and 100% of the respondents mentioned the
impact of lack of water in their area as follows:
Displacement of households
Water related diseases including diarrhea, skin diseases and others
Community based conflict over scarce resources
Lack of land preparation hence crop failure
When a question on households accessibility to latrines was asked it was clearly coming out
from the assessment that almost 80% of the households in these villages had no access to proper
human excreta disposal. Open defecation is the main way people use both children and adults
taking advantage of the few bushes around the settlements and villages. These posses a lot of
environmental and aesthetical pressure on these settlements. The very few latrines available are
poorly maintained. According to the respondents only 15% of the people in these villages’ access
latrines while the rest 85% have no access to latrines.
How many people are there per latrine? The few available latrines are over utilized and poorly
maintained. According to the sphere standards each latrine should be used by not more than 5
households and should be well maintained. However the reverse is the situation in the assessed
villages. The few latrines available are over used especially by old people like women. It is also
observed that women are very much affected by this phenomenon because of their shyness. The
issue of latrines maintenance seems to be more serious than availability because of poor
maintenance and possible causes of diseases.
In all the assessed villages there are no any solid waste management systems. The used tool was
a comprehensive village profile assessment tool and as a result investigation on solid waste
management systems was part of it. It was quite evident that solid waste disposal systems has
never been used in these villages and these could be associated with either these villages have
little solid waste production and the few available could have been managed at household levels
or knowledge of solid waste management capacity to do so are limited. Whichever could be the
reason solid waste management is not operational at all and may not be easy to initiate it in these
villages either. What is the system for solid waste disposal?
When a question on what is your proposed action? Was asked the community elders mentioned
their current and future need of water and latrines. Over 90% of the respondents said they will
propose rehabilitation of the existing water catchments digging latrines while others also said
rehabilitation of existing latrines and digging new water facilities could have been added
advantage as they said. The below graph represents the views of the respondents
1.6 Â Recommendation
The assessment made the following recommendations:
a) WASH remains the highest priority need of communities. WASH provision in Bay and
Bakool should be continued, well-coordinated and expanded to ensure that the needs of
the affected population are met Nutrition interventions in order to support children <5
should be included to reduce nutritional situation in Bay and Bakool.
b) Emergency sanitation and hygiene responses should be expanded - less than 30% of sites
assessed had functional latrines resulting in a high risk of disease including cholera.
Interventions should consider security issues in using latrines mentioned.
c) Emergency shelter (SPHERE standard plastic sheeting and fixings) should be provided
for displaced families and those residing in damaged houses.
d) Provision of temporary learning centers to address the reduction in school attendance due
to displacement and other domestic violence.
e) Protection concerns should be addressed: Participatory and community mobilization
approaches to deliver relief and recovery interventions should be employed to facilitate
this.
f) It is recommended to de-prioritize water trucking to displacement sites (as most have NO
water supplies) and buying water is too costly
g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving
human and livestock population to enhance reliability and reduce cost on water fees or
waver as appropriate
h) Support to IDPs and vulnerable households with water fees vouchers for the next three
months or water trucking as appropriate.
i) Enhance disinfection of shallow wells and support to IDPs and poor households to
acquire water treatment and filters at level as well as water quality monitoring.
Recovery needs
a) Rehabilitation of water sources and latrines in areas of IDPs and host communities.
b) Shelter reconstruction/repair considering “build back better”, and disaster resilience.
c) Food security and livelihoods support will be needed.
Specified below is Joint assessment participants and their location of the assessment
S/N
o
Organiz
ation
Region District Visited
Location/V
illage
Populat
ion
Water
Source
s
Bore
hole
Unprotec
ted
shallow
wells
Shallow
with
hand
pumps
Rainwater
catchment
protecte
d
Spring
Unprotecte
d Spring
Functioning Conditio
n
Needs
1
A
RHO Bakol Rabdhure Town 29, 100 12 2 7 3 0 0 0 Yes poor Diggin
g
Rehab
ilitatio
n
Chlori
nation
B RHO Bakol ,, Imilow 2761 6 0 4 2 0 0 0 Yes poor Rehab
ilitatio
n
Chlori
nation
C RHO ,, ,, Quracle 1453 2 0 2 0 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
D RHO ,, ,, Habow 487 3 0 3 0 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
E ,, ,, ,, Lehelow 259 2 0 2 0 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
F ,, ,, ,, Eldhere 541 3 0 2 1 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
G ,, ,, ,, Washaqo 3123 10 1 5 3 1 0 0 Yes poor Rehab
ilitatio
n
Chlorination
H ,, ,, ,, Dhurrey 2985 4 0 2 0 1 0 0 Yes poor Rehab
ilitatio
n
Chlorination
I ,, ,, ,, Harhodey 1234 6 0 2 3 1 Yes poor Rehab
ilitatio
n
Chlorination
J ,, ,, ,, Yed 5760 7 0 3 2 1 0 0 Yes poor Rehab
ilitatio
n
Chlorination
K ,, ,, ,, Ato 4690 5 0 3 2 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
L ,, ,, ,, Sh/Abdalla 1120 2 0 2 0 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
M ,, ,, ,, Sedexbuuro
d
490 3 0 2 3 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
N ,, ,, ,, Iskarix 874 2 0 1 1 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
O ,, ,, ,, Warmarodh
i
238 2 0 2 0 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
P ,, ,, ,, Bodan 2479 5 0 1 4 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
Q ,, ,, ,, Isdhorta 2130 4 0 3 1 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
R ,, ,, ,, Wardhujile
y
982 3 0 1 2 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
S ,, ,, ,, Wabgirad 786 2 0 2 0 0 0 0 Yes poor Rehab
ilitatio
n
Chlori
nation
T ,, ,, ,, Buurbasle 320 3 0 3 0 0 0 0 Yes poor Rehab
ilitatio
n
Chlorination
2
A
DCDG Bakol Huddur Huddur 22500 559 3 197 20 94 155 0 Yes Low
yield &
Collapse
Rehabilitation
Chlorination
Construction
B ,, Bakol Huddur Garasweyn
e
11500 48 1 18 0 20 0 0 Yes Low
yield,
Collapse
dry
Rehabilitation
Chlorination
Construction
3
a
SCWR
W
Bakol El-Berde Buradey 5000 6 0 0 1 5 0 0 Yes Low
yield
Dry
Rehabilitation
Chlorination
Construction
b ,, ,, ,, Abeesaale 7500 16 3 0 5 8 0 0 Yes Low
yield
Rehabilitation
Chlorination
Dry Construction
c ,, ,, ,, Town 44958 12 2 0 5 5 0 0 Yes Low
Yield
Rehabilitation
Chlorination
Construction
4
a
HAAD
O
Bakol Huddur Doonful 1752 5 0 5 0 0 0 0 yes Some
collapsed
Rehabilitation
Chlorination
Construction
b HAAD
O
,, ,, Yowkooyo
w
1050 40 0 0 0 40 0 0 yes 10 Dry Rehabilitation
c ,, ,, ,, Abal 1518 71 1 0 0 70 0 0 yes 20 dry Rehabilitation
Chlorination
Construction
d ,, ,, ,, Abagbeeda
y
1200 26 0 0 0 26 0 0 yes 6 dry Rehabilitation
Chlorination
Construction
e ,, ,, ,, Bandardiir 2500 4 0 4 0 0 0 0 yes 1
unfucnti
on
Rehabilitation
Chlorination
Construction
6 SOYID Bakol Elbarde Town 5992 10 0 7 0 3 0 0 yes 2 dry Rehabilitation
Chlorination
Construction
7 HARS
O
Bakol Rabdhure Town 4000 26 1 0 25 0 0 0 yes Low
yield
Rehabilitation
Chlorination
Construction
8
a
SDIO Bakol Tieglow Town 96782 34 1 23 10 0 0 0 Yes Rehabilitation
Chlorination
Construction
b ,, ,, ,, Biyoley 1440 1 1 0 0 0 0 0 Yes - Rehabilitation
Chlorination
Construction
c ,, ,, ,, Dhinawe 1560 1 0 0 0 1 0 0 yes Dry Rehabilitation
Chlorination
Construction
9
A
SOYV
G
Bay Baidoa Deynunay 4680 1 1 0 0 0 0 0 yes - Rehabilitation
Chlorination
Construction
b ,, ,, ,, ADC2
camp
2520 1 0 0 0 0 0 0 yes dry Rehabilitation
Chlorination
Construction
c SOYV
G
Bay Baidoa Tawakal 870 1 0 1 0 0 0 0 yes good Provision of
water system
d ,, ,, ,, ADC1
camp
2016 1 1 0 0 0 0 0 yes good
e ,, ,, ,, Bula,Enjer
o
1200 2 0 0 0 2 0 0 1 dry poor Digging and
Rehabilitation
10
A
ORDO Bay Baidoa Bonkay 1170 3 3 0 0 0 0 0 3 function good -
b ,, ,, ,, Habare 4320 3 0 3 0 0 0 0 yes - Rehabilitation
c ,, ,, ,, Qasab 2
Camp
708 1 1 0 0 0 0 0 yes -
d ,, ,, ,, Salamey
camp
888 1 1 0 0 0 0 0 yes -
e ,, ,, ,, Bulajadid 2256 2 0 0 0 0 0 2 yes Contami
nated
Construction
11
a
BWMC Bay Baidoa Shalbuur 1500 1 0 0 0 1 0 0 yes Contami
nated
Rehabilitation &
Protection
b ,, ,, ,, Barwaqo 750 3 0 3 0 0 0 0 yes poor Rehabilitation
and
camp Construction
c ,, ,, ,, Qasab 1
camp
750 1 1 0 0 0 0 0 yes good -
d ,, ,, ,, Siliga 1680 1 1 0 0 0 0 0 yes - -
e ,, ,, ,, Malaqda 1944 1 0 0 0 1 0 0 yes Contami
nated
Rehabilitation
12
a
SYPD ,, ,, Hanano 2
camp
2760 2 2 0 0 0 0 0 yes - -
b ,, ,, ,, Salamey
Idale camp
2400 1 1 0 0 0 0 0 yes good IDP need water
piping system
c ,, ,, ,, Ala,amin
camp
930 2 2 0 0 0 0 0 yes good Far distance
from the IDPs
d ,, ,, ,, Bulagudud 2700 2 0 0 0 2 0 0 1 dry Poor Digging &
Rehabilitation
e ,, ,,, ,, Aros ibar 1680 2 0 0 0 2 0 0 Bout to dry contamin
ated
Digging &
Rehabilitation
13
A
DAYA
H
Bay Berdale October 3600 22 1 20 1 0 0 0 yes Cacity
reduction
&
silting
Rehabiliation
and
Construction
B ,, ,, ,, Horseed 2400 2 1 0 0 1 0 0 yes Cacity
reduction
Digging
Rehabilitation
c ,, ,, ,, Morawarab
a
3000 4 0 0 0 4 0 0 yes Contami
nated
Digging &
Rehabilitation
d ,, ,, ,, Bula IIdow 900 3 1 0 0 2 0 0 NO 2
catchme
nt dry
Digging &
Rehabilitation
14
a
TAWA
KAL
Bay Bardale Boorama 1200 4 0 0 0 4 0 0 yes Contami
nated
Digging &
Rehabilitation
b ,, ,, ,, Toosweyne 3810 4 2 0 0 2 0 0 yes poor Digging &
Rehabilitation
c ,, ,, ,, Baqay 2280 3 1 0 0 2 0 0 2 Catchment poor Digging &
Horgoylow dry Rehabilitation
15 SYPD Bay Berdale Waberi 4200 66 1 65 0 0 0 0 35 Functions poor Rehabilitation
Construction
and silting
b SYPD ,, ,, Ahmed
Gurey
4800 4 1 0 3 0 0 0 2
functioning
poor Rehabilitation
Construction
and silting
c ,, ,, ,, Tuutis 528 5 0 2 0 3 0 0 yes 2 dry Digging and
Rehabilitation
16
A
PASOS Bay B/Hakaba H/wadag 4000 3 0 0 0 3 0 0 yes Good - Rehabilitation
b ,, ,, ,, Dubey 10800 3 0 0 0 3 0 0 yes good -
c ,, ,, ,, Sool 1200 1 0 0 0 1 0 0 yes good - Rehabilitation
d ,, ,, ,, Waberi 5000 3 0 0 0 3 0 0 yes
e ,, ,, ,, Wadajir 3000 3 0 0 0 3 0 0 yes
17
A
BTSC Bay Bakol Masarre 4020 52 0 52 0 0 0 0 50
functioning
poor - Rehabilitation
b ,, ,, ,, Alin 2880 4 0 0 0 4 0 0 2
functioning
Rehabilitation
c ,, ,, ,, Gelgelow 11160 6 0 0 0 2 0 4 yes Contamn
ated
Rehabilitation
Construction
and silting
d ,, ,, ,, Oodan 3900 2 0 0 0 2 0 0 1 dry Contamn
ated
Rehabilitation
Construction
and silting
e Godka
Kabagoode
16200 9 0 7 0 2 0 0 yes Polluted
Low
yield
Digging and
Rehabilitation
18
A
G/HOP
E
Bay B/Hakaba Ideeda 2160 8 0 0 0 0 0 6 yes contamin
ated
- Rehabilitation
B ,, ,, ,,, Barkadle 7200 3 0 0 0 3 0 0 2
functioning
- Rehabilitation
Constructions
c ,, ,, ,, Orow 3600 3 0 0 0 3 0 0 1
functioning
- Rehabilitation
d ,, ,,, ,, Jame,o 1800 2 0 0 0 2 0 0 1
functioning
- Digging and
Rehabilitation
e ,, ,, ,, Baale 1530 2 0 0 0 2 0 0 1
functioning
- - Rehabilitation
19 BARD
O
Bay B/Hakaba Waberi 4657 4 0 0 0 4 0 0 Functioning - Rehabilitation
Constructions
,, ,, ,, Hawlwadag 2952 4 0 0 0 4 0 0 Functioning - Rehabilitation
BARD
O
Bay B/Hakaba Isneeb 102 4 0 0 0 4 0 0 Functioning - Rehabilitation
Constructions
,, ,, ,, Masusow 120 3 0 0 0 3 0 0 2
Functioning
- - Rehabilitation
,, ,, ,, Awyay 270 2 0 0 0 2 0 0 1 dry - -
20
a
SYPD Bay B/Hakaba Wadajir 1320 4 0 0 0 4 0 0 Functioning
1
Rest
contamin
ated
Rehabilitation
b ,, ,, ,, Korow 504 2 0 0 0 2 0 0 1Dry poor Rehabilation
c SYPD Bay B/Hakaba Da,arta 252 3 0 0 0 3 0 0 2 Dry
d SYPD Bay B/Hakaba Urweyne 600 2 0 1 0 2 0 0 Low yield
conataminat
ed
poor Chlorination
Rehabilitation
e ,, ,, ,, Lowmanka
r
720 2 0 1 0 1 0 0 Functioning Poor Rehabilitation
F SYPD Bay B/Hakaba Shibelle 390 0 0 0 0 0 0 0 0 0 0
G ,, ,, ,, Makade
Osma
90 1 0 0 0 1 0 0 Functioning poor Rehabilitation
H ,, ,, ,, Makade
M/Hasano
90 0 0 0 0 0 0 0 0 0 Rehabilitation
Chlorination
w Rehabilitation
I ,, ,, ,, Makada
I/Hasanow
48 0 0 0 0 0 0 0 0 0 Rehabilitation
Constructions
J ,, ,, ,, Bula jadid 480 0 0 0 0 0 0 0 0 0 - Rehabilitation
K ,, ,, ,, Gerdumal 540 1 0 0 0 1 0 0 Functioning contamin
ated
Rehabilitation
Constructions
L SYPD Bay B/Hakaba Bukur Eber 240 0 0 0 0 0 0 0 0 0 - Rehabilitation
M SYPD Bay B/Hakaba Rahoole 360 50 0 50 0 0 0 0 0 10
functioni
ng
Rehabilitation
Constructions
21 INTER
SOS
Bay Baidoa Sharif
gamey
2142 1 1 0 0 0 0 0 Functioning good - Rehabilitation
REASD Bay Bakol Baladul
min camp
1092 5 2 2 1 0 0 0 Functioning lowyield Rehabilitation
22 ADA Bay Baidoa Bula,usley
2
camp
2292 1 1 0 0 0 0 0 Functioning - Rehabilitation
Constructions
23 DMO Bay Baidoa Abo,Ashar
ow
Camp
2430 1 0 0 1 0 0 0 Functioning - - Rehabilitation
24 BWEC Bay Baidoa Tawhid
camp
3078 1 1 0 0 0 0 0 Rehabilitation
Constructions
25 DORD
A
Bay Baidoa Wadajir
camp
582 1 0 1 0 0 0 0 - Rehabilitation
26 COOPI Bay Baidoa ADC 2
camp
606 1 0 1 0 0 0 0 Functioning Rehabilitation
Constructions
27 BWDN Bay Baidoa Wadajir 2
camps
900 12 0 12 0 0 0 0 Functioning - Rehabilitation
28 ADO Wadajir
3
570 1 1 0 0 0 0 0 Rehabilitation
Constructions
29 AYDO Bay Baidoa Wadajir
4
600 1 1 0 0 0 0 0 - Rehabilitation
30
a
DCDG Bay Qansahdh
ere
Esow 3000 41 1 15 0 25 0 0 Functioning
15
catchment,
5
unprotected
Low
yield
poor
Rehabilitation
Construction
Chlorination
b DCDG ,, Q/dhere Ufurow 9000 188 2 40 0 121 0 0 Bore hole 1
7 shallow
wells
85 Dry
Silted
poor Rehabilitation
Construction
Digging
chlorination
31 READ
O
Bay Dinsor Dinsor 29000 22 2 0 10 10 0 0 Bore 1
8 shallow
wells
6 catchments
poor Rehabilitation
Construction
Digging
Chlorination
32
a
AL-
FATHI
Bay Baidoa Kormari
camp
1500 4 0 0 4 0 0 0 2 Low
yield
Digging
b ,, ,, ,, Horseed 1326 3 0 0 3 0 0 0 1 - Rehabilitation
33
A
BASD
O
Bay Baidoa Barhanoy 420 7 0 7 0 0 0 0 3 Low
yield
Digging
b ,, ,, ,, Yasiin 342 6 1 5 0 0 0 0 3
34
A
DARE
DO
Bay Baidoa B/Hadama 6242 45 0 45 0 0 0 0 18 poor Rehabilitation
Construction
Digging
Chlorination
b ,, ,, ,, Wadajir 774 7 0 0 7 0 0 0 2 Rehabilitation
Constructions
35
A
TAWA
KAL
Bay Baidoa 11 Janayo 618 5 0 0 5 0 0 0 3 - Rehabilitation
b ,, ,, ,, S/Qasabka 365 7 0 0 7 0 0 0 2 Rehabilitation
Constructions
36
A
AL-
NAIM
Bay Baidoa Awdinle 4296 6 1 3 0 2 0 0 2 - Rehabilitation
b ,, ,, ,, H/Barbaar 8059 14 1 6 3 4 0 0 8 Rehabilitation
Constructions
37
A
Kuwoja Bay Baidoa Mursal 3000 19 1 12 6 0 0 0 9 poor - Rehabilitation
B ,, ,, ,, B/Usley 2 354 6 0 4 2 0 0 0 3 Rehabilitation
Constructions
C ,, ,, ,, A/Asharo 765 12 0 8 4 0 0 0 7 - Rehabilitation
38
A
SDIO Bay Dinsoor Dinsoor 14610 25 0 15 3 7 0 0 25 Salinity,
low yield
polituted
Digging
Chlorination
Rehabilitation
b ,, ,, ,, Gurban 7698 7 2 0 0 5 0 0 6 Poor Rehabilitation
c ,, ,, Q/Dhere Awjiki 900 6 0 3 0 3 0 0 4 Dry,Cont
aminated
Rehabilitation
Construction
39
a
DHO Bay Disoor Kurman 3450 1 0 0 0 1 0 0 1 Silted Deepening
b ,, ,, ,, Rahoole 5232 2 0 0 0 2 0 0 1 Silted Deepening
c ,, ,, ,, Yaqbarawe 2346 1 0 0 0 1 0 0 1 Silted Digging
40
a
ADRO Bay Q/dhere Bulafurad 1250 4 1 0 0 3 0 0 1 Dry,silte
d
Digging and
rehbilitation
b ADRO Bay Q/dhere Koronbood 1075 5 1 0 0 3 0 1 5 Low
yield,
Digging and
Rehabilitation
Dry
Polluted
c ,, ,, ,, Q/dhere 5550 9 4 0 0 5 0 0 4 Dry,1
b/hole
unfuncti
onal
Digging and
Rehabilitation
d ,, ,, ,, Aabey 1330 8 1 0 0 4 0 3 8 Poor Digging and
Rehabilitation
41
a
DCG Bay Baidoa Tawakal
camp
780 1 0 1 0 0 0 0 1 Contami
nated
Rehabilitation
b ,, ,, ,, Manaas 1500 4 0 0 1 2 1 0 2 Rehabilitation
c Goorisane 1800 2 0 0 0 2 0 0 1 Dry Rehabilitation
d ,, ,, ,, B/Barako 3000 5 1 0 0 4 0 0 2 Dry,silte
d
Digging and
Rehabilitation
e ,, ,, ,, Idale 1200 2 0 0 0 2 0 0 1 Deeping Digging and
Rehabilitation
f ,, ,, ,, Hagarka 2400 2 0 0 0 2 0 0 1 Poor Digging and
Rehabilitation
g ,, ,, ,, R/Adey 3300 3 0 1 0 2 0 0 2 Contami
nated
Digging and
Rehabilitation
h ,, ,, ,, B/Madino 1500 3 0 1 0 2 0 0 1 Low
yield,
Dry
Polluted
Digging and
Rehabilitation
i ,, ,, ,, Dhuur 900 4 0 2 0 2 0 0 2 Silted Digging and
Rehabilitation
j ,, ,, ,, Botis 1080 2 0 1 0 1 0 0 1 Dry Digging and
Rehabilitation
k ,, ,, ,, Sabiye 120 1 0 0 0 1 0 0 1 Poor Digging and
Rehabilitation
L ,, ,, ,, Sarmanta 360 2 0 0 0 2 0 0 1 Polluted Digging and
Rehabilitation
M ,, ,, ,, Qalan 780 3 0 1 0 2 0 0 1 Dry Digging and
Rehabilitation
N ,, ,, ,, Berhanoy
camp
768 2 1 1 0 0 0 0 2 Silted Digging and
Rehabilitation
O ,, ,, ,, Alla-amin
camp
690 1 0 0 0 0 0 0 1 Dry,
Silted
Digging and
Rehabilitation
42 DARE
DO
Bakool wajid Kurto 2160 2 0 0 0 0 0 0 1 Poor Digging and
Rehabilitation
A ,, ,, ,, Goobalo 2400 2 0 0 0 0 0 0 1 Contami
nated
Digging and
Rehabilitation
B ,, ,, ,, gomoriyal 1680 3 0 0 0 1 0 0 1 Low
yield,
Dry
Polluted
Digging and
Rehabilitation
C ,, ,, ,, Bur-Aday 1170 1 0 0 0 0 o o 1 Good Digging and
Rehabilitation
43 wwc Bakol Wajid Garsaley 2700 1 0 0 0 1 0 0 1 Poor Digging and
Rehabilitation
A ,, ,, ,, wajid 4680 250 0 250 0 0 0 0 15 Low
yield,
Dry
Polluted
Digging and
Rehabilitation
B ,, ,, ,, Elbon 3900 10 0 10 0 0 0 0 4 Contami
nated
Digging and
Rehabilitation
44 SYPD Bakol Wajid Towsiley 1500 1 0 0 0 1 0 0 11 silted Digging and
Rehabilitation
A ,, ,, ,, Burdhuxule 3804 2 0 0 0 2 0 0 1 Good Digging and
Rehabilitation
B ,, ,, ,, Geliyo 1500 6 0 3 0 3 0 0 2 Dry Digging and
Rehabilitation
45 HARD
O
Bay q/dhere Durey
Eymid
1440 6 2 1 0 3 0 0 3 silted Digging and
Rehabilitation
B ,, ,, ,, Kor-ubot 1140 5 1 o 0 4 0 0 2 Good Digging and
Rehabilitation
B ,, ,, ,, Aabey 702 4 1 0 0 3 0 0 2 Dry Digging and
Rehabilitation
C ,, ,, ,, Barbare 4500 7 2 3 0 2 0 0 3 contamin
ate
Digging and
Rehabilitation
E ,, ,, ,, q/dhere
Town
5700 9 2 6 0 0 0 0 3 Dry Digging and
Rehabilitation
46
A
MARD
O
Bakol Huddur B/Majiin 2600 12 0 5 0 7 0 0 8 Rehabilitation
Digging
Chlorination
B ,, ,, ,, Madawarab
e
3500 20 0 5 0 7 4 4 9 Rehabilitation
Digging
Chlorination
C ,, ,, ,, El-Amaari 2550 12 0 5 0 7 0 0 5 Rehabilitation
Digging
Chlorination
d ,, ,, ,, Buulow 1650 10 0 5 3 0 2 0 4 Rehabilitation
Digging
Chlorination
47
A
GRRN Bakool Tieglow Town 96,782 189 1 134 53 2 0 0 25 Rehabilitation
Digging
Chlorination
B ,, ,, ,, Biyoley 1696 20 2 7 8 3 0 0 1
C GRRN Bakool Tieglow Elgaras 3120 6 2 0 0 4 0 0 3
D ,, ,, ,, Wasilo 2549 1 1 0 0 2 0 0
E GRRN Bakool Tieglow Waranyey 2732 30 0 19 10 1 0 0 1 Rehabilitation
Digging
Chlorination
F ,, ,, ,, Haruun 1879 43 0 38 5 0 0 0 5 Rehabilitation
Constructions
G ,, ,, ,, Dhanawe 2983 100 0 89 10 1 0 0 - Rehabilitation
H GRRN Bakool Tieglow Madaa 2109 32 0 28 2 2 0 0 Rehabilitation
Constructions
I ,, ,, ,, Missir 1987 38 0 38 0 0 0 0 - Rehabilitation
J ,, ,, ,, Abaqle 1876 18 0 17 1 0 0 0 3 Rehabilitation
Digging
Chlorination
K GRRN Bakool Tieglow Balowka 2144 8 0 6 2 0 0 0 Rehabilitation
Constructions
L ,, ,, ,, Yaqo 720 0 0 0 0 0 0 1 - Rehabilitation
M ,, ,, ,, Burdho 891 0 0 0 0 0 0 4 2
N GRRN Bakool Tieglow Dhukubo 676 0 0 0 0 0 0 3 Rehabilitation
Digging
Chlorination
O ,, ,, ,, Heydle 532 0 0 0 0 0 0 1 Rehabilitation
Constructions
P ,, ,, ,, Irmanqare 238 0 0 0 0 0 0 1 - Rehabilitation
Q GRRN Bakool Tieglow Dubbo 432 0 0 0 0 0 0 2 Rehabilitation
Constructions
48 BOHD
O
Bay Baidoa Bonkay 3252 2 1 0 0 1 0 0 - Rehabilitation
,, ,, ,, Geldhere 1800 2 0 2 0 0 0 0
BOHD
O
Bay Baidoa Munabur 120 1 0 1 0 0 0 0 dry Rehabilitation
Digging
Chlorination
,, ,, ,, Bulanasib 312 1 0 0 0 1 0 0
BOHD
O
Bay Baidoa Ooro 288 1 0 0 0 1 0 0
49 SYPD Bakol Elbarde Town 44,958 3 1 1 0 1 0 0 dry poor Rehabilitation
Digging
Chlorination
50
A
SYPD Bay Baidoa Daynuun
ey
1920 2 Water
catchment
B ,, ,, ,, Buulo
Unsiyow
1080 Digging
Construction of
Shallow wells
C ,, ,, ,, Garangar
asle
600 Rehabilitation of
shallow wells
D ,, ,, ,, Dhamaajo 600 Chlorination
Rehabilitations
E ,, ,, ,, Balow 690 Water
catchment
F Diyad 900 Digging
Construction of
Shallow wells
G ,, ,, ,, Buulo
Raran
540 Rehabilitation of
shallow wells
H ,, ,, ,, Burcaash 900 Chlorination
Rehabilitations
I ,, ,, ,, Hanshilole 660 Water
catchment
J ,, ,, ,, Dambal
Ure
960 Digging
Construction of
Shallow wells
K ,, ,, ,, Dhambaalk
a
900 Rehabilitation of
shallow wells
L ,, ,, ,, Korow -
rooge
1200 Chlorination
Rehabilitations
M ,, ,, ,, Bula adid 960 Water
catchment
N ,, ,, ,, Kunyi-
Warabe
480 Digging
Construction of
Shallow wells
O ,, ,, ,, Banyale
Buurfule
360 Rehabilitation of
shallow wells
P ,, ,, ,, Banyaala-
Gaalmado
wli
900 Chlorination
Rehabilitations
Q ,, ,, ,, Banyaala-
Banka
600 Rehabilitation
Construction
Water
catchments
R ,, ,, ,, Banyaala-
Idmoole
420 Water
catchment
S ,, , ,, Low-
Gadud
1200 Rehabilitation of
water
catchments