joint bay,bakool wash assessment report · g) provision of subsidy, fast moving spares and rapid...

26
Joint Bay,Bakool WASH Assessment Report 1.1 Executive Summary This is a WASH joint assessment report jointly by WASH partners working in Bay and Bakool regions. The purpose of the WASH assessment was to find out the extent and evolution of WASH situation in Bay and Bakool regions following limited interventions in the area and based on the findings come up with priority areas of intervention and recommend appropriate response options. 1.2 Background WASH gaps are enormous in Bay and Bakool regions due to slow intervention in many areas exacerbated by the absence of humanitarian agencies in the area. WASH cluster partners in the area are trying to bring into rapid change towards WASH effectiveness in target areas. The assessment begun on 15 th to 20 th of July in both regions, WASH partners in the two regions voluntarily participated in the assessment, SYPD provided WASH assessment guidelines, and materials (books, pens and envelops), other partners provided transport in accessible areas in Bay region moving in groups. Also members shared assessment guidelines through email in Bakool to reduce risks of travelling with documents as it was secure and timesaving. The joint assessment aimed at identifying WASH gaps, potential areas of intervention both in long and short term. 1.3 Objectives: To identify major WASH gaps in the area Identify any overlap of WASH activities by agencies To identify both community and IDPs priority needs To provide a shared overview of WASH situation in all affected areas of the regions To identify immediate humanitarian needs that were not addressed To understand recovery needs of affected IDPs and the vulnerable people 1.4 Methodology The assessment entailed observation and village visit whereby communities including the IDPs were given an opportunity to air their priority needs. WASH assessment tools were also used. 1.5 Findings

Upload: others

Post on 21-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

Joint Bay,Bakool WASH Assessment Report

1.1 Executive Summary

This is a WASH joint assessment report jointly by WASH partners working in Bay and Bakool

regions. The purpose of the WASH assessment was to find out the extent and evolution of

WASH situation in Bay and Bakool regions following limited interventions in the area and

based on the findings come up with priority areas of intervention and recommend appropriate

response options.

1.2 Background

WASH gaps are enormous in Bay and Bakool regions due to slow intervention in many areas

exacerbated by the absence of humanitarian agencies in the area. WASH cluster partners in the

area are trying to bring into rapid change towards WASH effectiveness in target areas.

The assessment begun on 15th

to 20th

of July in both regions, WASH partners in the two regions

voluntarily participated in the assessment, SYPD provided WASH assessment guidelines, and

materials (books, pens and envelops), other partners provided transport in accessible areas in Bay

region moving in groups. Also members shared assessment guidelines through email in Bakool

to reduce risks of travelling with documents as it was secure and timesaving.

The joint assessment aimed at identifying WASH gaps, potential areas of intervention both in

long and short term.

1.3 Objectives:

To identify major WASH gaps in the area

Identify any overlap of WASH activities by agencies

To identify both community and IDPs priority needs

To provide a shared overview of WASH situation in all affected areas of the regions

To identify immediate humanitarian needs that were not addressed

To understand recovery needs of affected IDPs and the vulnerable people

1.4 Methodology

The assessment entailed observation and village visit whereby communities including the IDPs

were given an opportunity to air their priority needs. WASH assessment tools were also used.

1.5 Findings

Page 2: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

Accesses to latrines in these regions are minimal, hygiene and sanitation is very substantial.

Huge number of population in the areas defecates openly causing environmental health

problems. Available water sources in the area require massive rehabilitation of which most of

them have dried up, households are currently trekking water for domestic uses. This minimizes

access to enough water for household use. Households interviewed in assessed community areas

reported that they can only collect 30lts of water down from 80lts collected during normal times.

This translates to about 4lts per person per day which is 3 times less than the minimum sphere

standards. Over half of the shallow wells have indicated deteriorating water quality and are

projected to dry up due to lack of seasonal replenishment of the aquifers. The region is not

endowed with boreholes due to the high level of under investment in utilization of underground

water may be because of high number of settlements in the area or may be because of other

factors that were beyond the assessment scope. The main water sources in the villages assessed

were communal water catchment which requires recurrent de-silting to increase the capacity.

Inadequate health facilities is also a worrying concern and health facilities are limited in the area,

Most of the IDPS reside in Makeshifts posing protection risks to them. Children have no access

to basic education.

1.5.4 Key findings

When village leaders in the assessment villages asked; is access to water restricted in your

village? Ninety percent of the respondent said water accessibility is restricted. This is so because

the main water sources are water catchments which are not permanent water sources and require

restricted uses of water.

On the other hand the physical observation of the water catchments indicated that almost all the

water catchments dried up.

A question on water sources was asked the interviewed member of the community which

was; where does the village get its water from? Villages explained that their main water

source is communal water catchments dug by the communities. The volumes of these water

catchments are reduced due to silt concentration and they dry up so quickly. One of the target

villages testified that their water source is shallow wells which in relation to water catchments it

semi-permanent water sources and thus they have relatively better water accessibility although

water quality also remains in question.

To assess the longevity of water availability in the water sources of the year a question like

what is the average number of months when water is available in the catchments/wells in

the year? According to the respondents 70% of the assessed villages access water from their

water sources only 6 months average. This is so because the volume and water holding capacity

of their water catchments is less than they require. 20% of the villages access water from their

water catchments between 9 months while they cannot also access water from these sources

more than 9 months in case of rain failures. However, one of the villages using shallow wells as

Page 3: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

their water source indicated that they access water all the time because shallow wells are either

permanent or semi-permanent water source.

What are the causes and impacts of lack of access to water?

The causes attributed to water scarcity in these villages vary with villages and respondents.

Some of them responded claim that it is due to lack of permanent rain failure while other

attributed to rain failure and some others attributing to water facilities drying up faster than they

should. The impact of lack of water was obvious with almost all the people interviewed and

100% of the respondents mentioned the impact of lack of water in their area as follows:

Displacement of households

Water related diseases including diarrhea, skin diseases and others

Community based conflict over scarce resources

Lack of land preparation hence crop failure

 Ninety percent of them said the water sources range from 3 to 9 kilometer from the main

villages posing water accessibility distance to women and girls. On the other hand this also puts

them on risk of possible rapes and other violations. Women and girls walk long distances to

collect water either using their back or donkeys to carry water.

When a question on water protection reading “is the water source protected or not protected

was asked the response was: almost all the villages asserted that their water sources are

protected from animal and human accessibility. This indicates the quality of water is very much

Page 4: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

unsafe. Water protection is not something the communities understood.

On the other hand the assessment findings indicate that at least 90% of the available water

sources are used by human for domestic water requirement and watering animals in a very

unsafe ways. The communal water catchments with reduced capacity which are not protected

from both human and animals accessing water directly elude and minimize water accessibility

during the drier seasons and rain failure times.

The assessment target villages were all rural agro-pastoral villages where rural poverty is

significantly prevalent. Access to and knowledge of water treatment and purification of water is

minimal if any. When a question on water purification was asked 100% of the respondents said

water is rarely purified. Contaminated water from unprotected water sources are directly

consumed by people in these villages and chances of water related diseases are very high

especially during rain failures and droughts due to minimum accessibility of water. The water

treatment question asked and the graphical presentation are as follows.

Page 5: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

What are the causes and impacts of lack of access to water? The causes attributed to water

scarcity in these villages vary with villages and respondents. Some of them responded claim that

it is due to lack of permanent rain failure while other attributed to rain failure and some others

attributing to water facilities drying up faster than they should. The impact of lack of water was

obvious with almost all the people interviewed and 100% of the respondents mentioned the

impact of lack of water in their area as follows:

Displacement of households

Water related diseases including diarrhea, skin diseases and others

Community based conflict over scarce resources

Lack of land preparation hence crop failure

When a question on households accessibility to latrines was asked it was clearly coming out

from the assessment that almost 80% of the households in these villages had no access to proper

human excreta disposal. Open defecation is the main way people use both children and adults

taking advantage of the few bushes around the settlements and villages. These posses a lot of

environmental and aesthetical pressure on these settlements. The very few latrines available are

poorly maintained. According to the respondents only 15% of the people in these villages’ access

latrines while the rest 85% have no access to latrines.

How many people are there per latrine? The few available latrines are over utilized and poorly

maintained. According to the sphere standards each latrine should be used by not more than 5

households and should be well maintained. However the reverse is the situation in the assessed

villages. The few latrines available are over used especially by old people like women. It is also

observed that women are very much affected by this phenomenon because of their shyness. The

issue of latrines maintenance seems to be more serious than availability because of poor

maintenance and possible causes of diseases.

In all the assessed villages there are no any solid waste management systems. The used tool was

a comprehensive village profile assessment tool and as a result investigation on solid waste

management systems was part of it. It was quite evident that solid waste disposal systems has

never been used in these villages and these could be associated with either these villages have

little solid waste production and the few available could have been managed at household levels

or knowledge of solid waste management capacity to do so are limited. Whichever could be the

reason solid waste management is not operational at all and may not be easy to initiate it in these

villages either. What is the system for solid waste disposal?

Page 6: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

When a question on what is your proposed action? Was asked the community elders mentioned

their current and future need of water and latrines. Over 90% of the respondents said they will

propose rehabilitation of the existing water catchments digging latrines while others also said

rehabilitation of existing latrines and digging new water facilities could have been added

advantage as they said. The below graph represents the views of the respondents

1.6 Â Recommendation

The assessment made the following recommendations:

a) WASH remains the highest priority need of communities. WASH provision in Bay and

Bakool should be continued, well-coordinated and expanded to ensure that the needs of

the affected population are met Nutrition interventions in order to support children <5

should be included to reduce nutritional situation in Bay and Bakool.

b) Emergency sanitation and hygiene responses should be expanded - less than 30% of sites

assessed had functional latrines resulting in a high risk of disease including cholera.

Interventions should consider security issues in using latrines mentioned.

c) Emergency shelter (SPHERE standard plastic sheeting and fixings) should be provided

for displaced families and those residing in damaged houses.

d) Provision of temporary learning centers to address the reduction in school attendance due

to displacement and other domestic violence.

Page 7: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

e) Protection concerns should be addressed: Participatory and community mobilization

approaches to deliver relief and recovery interventions should be employed to facilitate

this.

f) It is recommended to de-prioritize water trucking to displacement sites (as most have NO

water supplies) and buying water is too costly

g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving

human and livestock population to enhance reliability and reduce cost on water fees or

waver as appropriate

h) Support to IDPs and vulnerable households with water fees vouchers for the next three

months or water trucking as appropriate.

i) Enhance disinfection of shallow wells and support to IDPs and poor households to

acquire water treatment and filters at level as well as water quality monitoring.

Recovery needs

a) Rehabilitation of water sources and latrines in areas of IDPs and host communities.

b) Shelter reconstruction/repair considering “build back better”, and disaster resilience.

c) Food security and livelihoods support will be needed.

Specified below is Joint assessment participants and their location of the assessment

Page 8: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

S/N

o

Organiz

ation

Region District Visited

Location/V

illage

Populat

ion

Water

Source

s

Bore

hole

Unprotec

ted

shallow

wells

Shallow

with

hand

pumps

Rainwater

catchment

protecte

d

Spring

Unprotecte

d Spring

Functioning Conditio

n

Needs

1

A

RHO Bakol Rabdhure Town 29, 100 12 2 7 3 0 0 0 Yes poor Diggin

g

Rehab

ilitatio

n

Chlori

nation

B RHO Bakol ,, Imilow 2761 6 0 4 2 0 0 0 Yes poor Rehab

ilitatio

n

Chlori

nation

C RHO ,, ,, Quracle 1453 2 0 2 0 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

D RHO ,, ,, Habow 487 3 0 3 0 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

E ,, ,, ,, Lehelow 259 2 0 2 0 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

F ,, ,, ,, Eldhere 541 3 0 2 1 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

G ,, ,, ,, Washaqo 3123 10 1 5 3 1 0 0 Yes poor Rehab

ilitatio

Page 9: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

n

Chlorination

H ,, ,, ,, Dhurrey 2985 4 0 2 0 1 0 0 Yes poor Rehab

ilitatio

n

Chlorination

I ,, ,, ,, Harhodey 1234 6 0 2 3 1 Yes poor Rehab

ilitatio

n

Chlorination

J ,, ,, ,, Yed 5760 7 0 3 2 1 0 0 Yes poor Rehab

ilitatio

n

Chlorination

K ,, ,, ,, Ato 4690 5 0 3 2 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

L ,, ,, ,, Sh/Abdalla 1120 2 0 2 0 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

M ,, ,, ,, Sedexbuuro

d

490 3 0 2 3 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

N ,, ,, ,, Iskarix 874 2 0 1 1 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

O ,, ,, ,, Warmarodh

i

238 2 0 2 0 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

Page 10: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

P ,, ,, ,, Bodan 2479 5 0 1 4 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

Q ,, ,, ,, Isdhorta 2130 4 0 3 1 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

R ,, ,, ,, Wardhujile

y

982 3 0 1 2 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

S ,, ,, ,, Wabgirad 786 2 0 2 0 0 0 0 Yes poor Rehab

ilitatio

n

Chlori

nation

T ,, ,, ,, Buurbasle 320 3 0 3 0 0 0 0 Yes poor Rehab

ilitatio

n

Chlorination

2

A

DCDG Bakol Huddur Huddur 22500 559 3 197 20 94 155 0 Yes Low

yield &

Collapse

Rehabilitation

Chlorination

Construction

B ,, Bakol Huddur Garasweyn

e

11500 48 1 18 0 20 0 0 Yes Low

yield,

Collapse

dry

Rehabilitation

Chlorination

Construction

3

a

SCWR

W

Bakol El-Berde Buradey 5000 6 0 0 1 5 0 0 Yes Low

yield

Dry

Rehabilitation

Chlorination

Construction

b ,, ,, ,, Abeesaale 7500 16 3 0 5 8 0 0 Yes Low

yield

Rehabilitation

Chlorination

Page 11: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

Dry Construction

c ,, ,, ,, Town 44958 12 2 0 5 5 0 0 Yes Low

Yield

Rehabilitation

Chlorination

Construction

4

a

HAAD

O

Bakol Huddur Doonful 1752 5 0 5 0 0 0 0 yes Some

collapsed

Rehabilitation

Chlorination

Construction

b HAAD

O

,, ,, Yowkooyo

w

1050 40 0 0 0 40 0 0 yes 10 Dry Rehabilitation

c ,, ,, ,, Abal 1518 71 1 0 0 70 0 0 yes 20 dry Rehabilitation

Chlorination

Construction

d ,, ,, ,, Abagbeeda

y

1200 26 0 0 0 26 0 0 yes 6 dry Rehabilitation

Chlorination

Construction

e ,, ,, ,, Bandardiir 2500 4 0 4 0 0 0 0 yes 1

unfucnti

on

Rehabilitation

Chlorination

Construction

6 SOYID Bakol Elbarde Town 5992 10 0 7 0 3 0 0 yes 2 dry Rehabilitation

Chlorination

Construction

7 HARS

O

Bakol Rabdhure Town 4000 26 1 0 25 0 0 0 yes Low

yield

Rehabilitation

Chlorination

Construction

8

a

SDIO Bakol Tieglow Town 96782 34 1 23 10 0 0 0 Yes Rehabilitation

Chlorination

Construction

b ,, ,, ,, Biyoley 1440 1 1 0 0 0 0 0 Yes - Rehabilitation

Page 12: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

Chlorination

Construction

c ,, ,, ,, Dhinawe 1560 1 0 0 0 1 0 0 yes Dry Rehabilitation

Chlorination

Construction

9

A

SOYV

G

Bay Baidoa Deynunay 4680 1 1 0 0 0 0 0 yes - Rehabilitation

Chlorination

Construction

b ,, ,, ,, ADC2

camp

2520 1 0 0 0 0 0 0 yes dry Rehabilitation

Chlorination

Construction

c SOYV

G

Bay Baidoa Tawakal 870 1 0 1 0 0 0 0 yes good Provision of

water system

d ,, ,, ,, ADC1

camp

2016 1 1 0 0 0 0 0 yes good

e ,, ,, ,, Bula,Enjer

o

1200 2 0 0 0 2 0 0 1 dry poor Digging and

Rehabilitation

10

A

ORDO Bay Baidoa Bonkay 1170 3 3 0 0 0 0 0 3 function good -

b ,, ,, ,, Habare 4320 3 0 3 0 0 0 0 yes - Rehabilitation

c ,, ,, ,, Qasab 2

Camp

708 1 1 0 0 0 0 0 yes -

d ,, ,, ,, Salamey

camp

888 1 1 0 0 0 0 0 yes -

e ,, ,, ,, Bulajadid 2256 2 0 0 0 0 0 2 yes Contami

nated

Construction

11

a

BWMC Bay Baidoa Shalbuur 1500 1 0 0 0 1 0 0 yes Contami

nated

Rehabilitation &

Protection

b ,, ,, ,, Barwaqo 750 3 0 3 0 0 0 0 yes poor Rehabilitation

and

Page 13: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

camp Construction

c ,, ,, ,, Qasab 1

camp

750 1 1 0 0 0 0 0 yes good -

d ,, ,, ,, Siliga 1680 1 1 0 0 0 0 0 yes - -

e ,, ,, ,, Malaqda 1944 1 0 0 0 1 0 0 yes Contami

nated

Rehabilitation

12

a

SYPD ,, ,, Hanano 2

camp

2760 2 2 0 0 0 0 0 yes - -

b ,, ,, ,, Salamey

Idale camp

2400 1 1 0 0 0 0 0 yes good IDP need water

piping system

c ,, ,, ,, Ala,amin

camp

930 2 2 0 0 0 0 0 yes good Far distance

from the IDPs

d ,, ,, ,, Bulagudud 2700 2 0 0 0 2 0 0 1 dry Poor Digging &

Rehabilitation

e ,, ,,, ,, Aros ibar 1680 2 0 0 0 2 0 0 Bout to dry contamin

ated

Digging &

Rehabilitation

13

A

DAYA

H

Bay Berdale October 3600 22 1 20 1 0 0 0 yes Cacity

reduction

&

silting

Rehabiliation

and

Construction

B ,, ,, ,, Horseed 2400 2 1 0 0 1 0 0 yes Cacity

reduction

Digging

Rehabilitation

c ,, ,, ,, Morawarab

a

3000 4 0 0 0 4 0 0 yes Contami

nated

Digging &

Rehabilitation

d ,, ,, ,, Bula IIdow 900 3 1 0 0 2 0 0 NO 2

catchme

nt dry

Digging &

Rehabilitation

14

a

TAWA

KAL

Bay Bardale Boorama 1200 4 0 0 0 4 0 0 yes Contami

nated

Digging &

Rehabilitation

b ,, ,, ,, Toosweyne 3810 4 2 0 0 2 0 0 yes poor Digging &

Rehabilitation

c ,, ,, ,, Baqay 2280 3 1 0 0 2 0 0 2 Catchment poor Digging &

Page 14: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

Horgoylow dry Rehabilitation

15 SYPD Bay Berdale Waberi 4200 66 1 65 0 0 0 0 35 Functions poor Rehabilitation

Construction

and silting

b SYPD ,, ,, Ahmed

Gurey

4800 4 1 0 3 0 0 0 2

functioning

poor Rehabilitation

Construction

and silting

c ,, ,, ,, Tuutis 528 5 0 2 0 3 0 0 yes 2 dry Digging and

Rehabilitation

16

A

PASOS Bay B/Hakaba H/wadag 4000 3 0 0 0 3 0 0 yes Good - Rehabilitation

b ,, ,, ,, Dubey 10800 3 0 0 0 3 0 0 yes good -

c ,, ,, ,, Sool 1200 1 0 0 0 1 0 0 yes good - Rehabilitation

d ,, ,, ,, Waberi 5000 3 0 0 0 3 0 0 yes

e ,, ,, ,, Wadajir 3000 3 0 0 0 3 0 0 yes

17

A

BTSC Bay Bakol Masarre 4020 52 0 52 0 0 0 0 50

functioning

poor - Rehabilitation

b ,, ,, ,, Alin 2880 4 0 0 0 4 0 0 2

functioning

Rehabilitation

c ,, ,, ,, Gelgelow 11160 6 0 0 0 2 0 4 yes Contamn

ated

Rehabilitation

Construction

and silting

d ,, ,, ,, Oodan 3900 2 0 0 0 2 0 0 1 dry Contamn

ated

Rehabilitation

Construction

and silting

e Godka

Kabagoode

16200 9 0 7 0 2 0 0 yes Polluted

Low

yield

Digging and

Rehabilitation

18

A

G/HOP

E

Bay B/Hakaba Ideeda 2160 8 0 0 0 0 0 6 yes contamin

ated

- Rehabilitation

Page 15: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

B ,, ,, ,,, Barkadle 7200 3 0 0 0 3 0 0 2

functioning

- Rehabilitation

Constructions

c ,, ,, ,, Orow 3600 3 0 0 0 3 0 0 1

functioning

- Rehabilitation

d ,, ,,, ,, Jame,o 1800 2 0 0 0 2 0 0 1

functioning

- Digging and

Rehabilitation

e ,, ,, ,, Baale 1530 2 0 0 0 2 0 0 1

functioning

- - Rehabilitation

19 BARD

O

Bay B/Hakaba Waberi 4657 4 0 0 0 4 0 0 Functioning - Rehabilitation

Constructions

,, ,, ,, Hawlwadag 2952 4 0 0 0 4 0 0 Functioning - Rehabilitation

BARD

O

Bay B/Hakaba Isneeb 102 4 0 0 0 4 0 0 Functioning - Rehabilitation

Constructions

,, ,, ,, Masusow 120 3 0 0 0 3 0 0 2

Functioning

- - Rehabilitation

,, ,, ,, Awyay 270 2 0 0 0 2 0 0 1 dry - -

20

a

SYPD Bay B/Hakaba Wadajir 1320 4 0 0 0 4 0 0 Functioning

1

Rest

contamin

ated

Rehabilitation

b ,, ,, ,, Korow 504 2 0 0 0 2 0 0 1Dry poor Rehabilation

c SYPD Bay B/Hakaba Da,arta 252 3 0 0 0 3 0 0 2 Dry

d SYPD Bay B/Hakaba Urweyne 600 2 0 1 0 2 0 0 Low yield

conataminat

ed

poor Chlorination

Rehabilitation

e ,, ,, ,, Lowmanka

r

720 2 0 1 0 1 0 0 Functioning Poor Rehabilitation

F SYPD Bay B/Hakaba Shibelle 390 0 0 0 0 0 0 0 0 0 0

G ,, ,, ,, Makade

Osma

90 1 0 0 0 1 0 0 Functioning poor Rehabilitation

H ,, ,, ,, Makade

M/Hasano

90 0 0 0 0 0 0 0 0 0 Rehabilitation

Chlorination

Page 16: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

w Rehabilitation

I ,, ,, ,, Makada

I/Hasanow

48 0 0 0 0 0 0 0 0 0 Rehabilitation

Constructions

J ,, ,, ,, Bula jadid 480 0 0 0 0 0 0 0 0 0 - Rehabilitation

K ,, ,, ,, Gerdumal 540 1 0 0 0 1 0 0 Functioning contamin

ated

Rehabilitation

Constructions

L SYPD Bay B/Hakaba Bukur Eber 240 0 0 0 0 0 0 0 0 0 - Rehabilitation

M SYPD Bay B/Hakaba Rahoole 360 50 0 50 0 0 0 0 0 10

functioni

ng

Rehabilitation

Constructions

21 INTER

SOS

Bay Baidoa Sharif

gamey

2142 1 1 0 0 0 0 0 Functioning good - Rehabilitation

REASD Bay Bakol Baladul

min camp

1092 5 2 2 1 0 0 0 Functioning lowyield Rehabilitation

22 ADA Bay Baidoa Bula,usley

2

camp

2292 1 1 0 0 0 0 0 Functioning - Rehabilitation

Constructions

23 DMO Bay Baidoa Abo,Ashar

ow

Camp

2430 1 0 0 1 0 0 0 Functioning - - Rehabilitation

24 BWEC Bay Baidoa Tawhid

camp

3078 1 1 0 0 0 0 0 Rehabilitation

Constructions

25 DORD

A

Bay Baidoa Wadajir

camp

582 1 0 1 0 0 0 0 - Rehabilitation

26 COOPI Bay Baidoa ADC 2

camp

606 1 0 1 0 0 0 0 Functioning Rehabilitation

Constructions

27 BWDN Bay Baidoa Wadajir 2

camps

900 12 0 12 0 0 0 0 Functioning - Rehabilitation

28 ADO Wadajir

3

570 1 1 0 0 0 0 0 Rehabilitation

Constructions

Page 17: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

29 AYDO Bay Baidoa Wadajir

4

600 1 1 0 0 0 0 0 - Rehabilitation

30

a

DCDG Bay Qansahdh

ere

Esow 3000 41 1 15 0 25 0 0 Functioning

15

catchment,

5

unprotected

Low

yield

poor

Rehabilitation

Construction

Chlorination

b DCDG ,, Q/dhere Ufurow 9000 188 2 40 0 121 0 0 Bore hole 1

7 shallow

wells

85 Dry

Silted

poor Rehabilitation

Construction

Digging

chlorination

31 READ

O

Bay Dinsor Dinsor 29000 22 2 0 10 10 0 0 Bore 1

8 shallow

wells

6 catchments

poor Rehabilitation

Construction

Digging

Chlorination

32

a

AL-

FATHI

Bay Baidoa Kormari

camp

1500 4 0 0 4 0 0 0 2 Low

yield

Digging

b ,, ,, ,, Horseed 1326 3 0 0 3 0 0 0 1 - Rehabilitation

33

A

BASD

O

Bay Baidoa Barhanoy 420 7 0 7 0 0 0 0 3 Low

yield

Digging

b ,, ,, ,, Yasiin 342 6 1 5 0 0 0 0 3

34

A

DARE

DO

Bay Baidoa B/Hadama 6242 45 0 45 0 0 0 0 18 poor Rehabilitation

Construction

Digging

Chlorination

b ,, ,, ,, Wadajir 774 7 0 0 7 0 0 0 2 Rehabilitation

Page 18: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

Constructions

35

A

TAWA

KAL

Bay Baidoa 11 Janayo 618 5 0 0 5 0 0 0 3 - Rehabilitation

b ,, ,, ,, S/Qasabka 365 7 0 0 7 0 0 0 2 Rehabilitation

Constructions

36

A

AL-

NAIM

Bay Baidoa Awdinle 4296 6 1 3 0 2 0 0 2 - Rehabilitation

b ,, ,, ,, H/Barbaar 8059 14 1 6 3 4 0 0 8 Rehabilitation

Constructions

37

A

Kuwoja Bay Baidoa Mursal 3000 19 1 12 6 0 0 0 9 poor - Rehabilitation

B ,, ,, ,, B/Usley 2 354 6 0 4 2 0 0 0 3 Rehabilitation

Constructions

C ,, ,, ,, A/Asharo 765 12 0 8 4 0 0 0 7 - Rehabilitation

38

A

SDIO Bay Dinsoor Dinsoor 14610 25 0 15 3 7 0 0 25 Salinity,

low yield

polituted

Digging

Chlorination

Rehabilitation

b ,, ,, ,, Gurban 7698 7 2 0 0 5 0 0 6 Poor Rehabilitation

c ,, ,, Q/Dhere Awjiki 900 6 0 3 0 3 0 0 4 Dry,Cont

aminated

Rehabilitation

Construction

39

a

DHO Bay Disoor Kurman 3450 1 0 0 0 1 0 0 1 Silted Deepening

b ,, ,, ,, Rahoole 5232 2 0 0 0 2 0 0 1 Silted Deepening

c ,, ,, ,, Yaqbarawe 2346 1 0 0 0 1 0 0 1 Silted Digging

40

a

ADRO Bay Q/dhere Bulafurad 1250 4 1 0 0 3 0 0 1 Dry,silte

d

Digging and

rehbilitation

b ADRO Bay Q/dhere Koronbood 1075 5 1 0 0 3 0 1 5 Low

yield,

Digging and

Rehabilitation

Page 19: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

Dry

Polluted

c ,, ,, ,, Q/dhere 5550 9 4 0 0 5 0 0 4 Dry,1

b/hole

unfuncti

onal

Digging and

Rehabilitation

d ,, ,, ,, Aabey 1330 8 1 0 0 4 0 3 8 Poor Digging and

Rehabilitation

41

a

DCG Bay Baidoa Tawakal

camp

780 1 0 1 0 0 0 0 1 Contami

nated

Rehabilitation

b ,, ,, ,, Manaas 1500 4 0 0 1 2 1 0 2 Rehabilitation

c Goorisane 1800 2 0 0 0 2 0 0 1 Dry Rehabilitation

d ,, ,, ,, B/Barako 3000 5 1 0 0 4 0 0 2 Dry,silte

d

Digging and

Rehabilitation

e ,, ,, ,, Idale 1200 2 0 0 0 2 0 0 1 Deeping Digging and

Rehabilitation

f ,, ,, ,, Hagarka 2400 2 0 0 0 2 0 0 1 Poor Digging and

Rehabilitation

g ,, ,, ,, R/Adey 3300 3 0 1 0 2 0 0 2 Contami

nated

Digging and

Rehabilitation

h ,, ,, ,, B/Madino 1500 3 0 1 0 2 0 0 1 Low

yield,

Dry

Polluted

Digging and

Rehabilitation

i ,, ,, ,, Dhuur 900 4 0 2 0 2 0 0 2 Silted Digging and

Rehabilitation

j ,, ,, ,, Botis 1080 2 0 1 0 1 0 0 1 Dry Digging and

Rehabilitation

k ,, ,, ,, Sabiye 120 1 0 0 0 1 0 0 1 Poor Digging and

Rehabilitation

L ,, ,, ,, Sarmanta 360 2 0 0 0 2 0 0 1 Polluted Digging and

Rehabilitation

M ,, ,, ,, Qalan 780 3 0 1 0 2 0 0 1 Dry Digging and

Page 20: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

Rehabilitation

N ,, ,, ,, Berhanoy

camp

768 2 1 1 0 0 0 0 2 Silted Digging and

Rehabilitation

O ,, ,, ,, Alla-amin

camp

690 1 0 0 0 0 0 0 1 Dry,

Silted

Digging and

Rehabilitation

42 DARE

DO

Bakool wajid Kurto 2160 2 0 0 0 0 0 0 1 Poor Digging and

Rehabilitation

A ,, ,, ,, Goobalo 2400 2 0 0 0 0 0 0 1 Contami

nated

Digging and

Rehabilitation

B ,, ,, ,, gomoriyal 1680 3 0 0 0 1 0 0 1 Low

yield,

Dry

Polluted

Digging and

Rehabilitation

C ,, ,, ,, Bur-Aday 1170 1 0 0 0 0 o o 1 Good Digging and

Rehabilitation

43 wwc Bakol Wajid Garsaley 2700 1 0 0 0 1 0 0 1 Poor Digging and

Rehabilitation

A ,, ,, ,, wajid 4680 250 0 250 0 0 0 0 15 Low

yield,

Dry

Polluted

Digging and

Rehabilitation

B ,, ,, ,, Elbon 3900 10 0 10 0 0 0 0 4 Contami

nated

Digging and

Rehabilitation

44 SYPD Bakol Wajid Towsiley 1500 1 0 0 0 1 0 0 11 silted Digging and

Rehabilitation

A ,, ,, ,, Burdhuxule 3804 2 0 0 0 2 0 0 1 Good Digging and

Rehabilitation

B ,, ,, ,, Geliyo 1500 6 0 3 0 3 0 0 2 Dry Digging and

Rehabilitation

45 HARD

O

Bay q/dhere Durey

Eymid

1440 6 2 1 0 3 0 0 3 silted Digging and

Rehabilitation

B ,, ,, ,, Kor-ubot 1140 5 1 o 0 4 0 0 2 Good Digging and

Rehabilitation

Page 21: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

B ,, ,, ,, Aabey 702 4 1 0 0 3 0 0 2 Dry Digging and

Rehabilitation

C ,, ,, ,, Barbare 4500 7 2 3 0 2 0 0 3 contamin

ate

Digging and

Rehabilitation

E ,, ,, ,, q/dhere

Town

5700 9 2 6 0 0 0 0 3 Dry Digging and

Rehabilitation

46

A

MARD

O

Bakol Huddur B/Majiin 2600 12 0 5 0 7 0 0 8 Rehabilitation

Digging

Chlorination

B ,, ,, ,, Madawarab

e

3500 20 0 5 0 7 4 4 9 Rehabilitation

Digging

Chlorination

C ,, ,, ,, El-Amaari 2550 12 0 5 0 7 0 0 5 Rehabilitation

Digging

Chlorination

d ,, ,, ,, Buulow 1650 10 0 5 3 0 2 0 4 Rehabilitation

Digging

Chlorination

47

A

GRRN Bakool Tieglow Town 96,782 189 1 134 53 2 0 0 25 Rehabilitation

Digging

Chlorination

B ,, ,, ,, Biyoley 1696 20 2 7 8 3 0 0 1

C GRRN Bakool Tieglow Elgaras 3120 6 2 0 0 4 0 0 3

D ,, ,, ,, Wasilo 2549 1 1 0 0 2 0 0

E GRRN Bakool Tieglow Waranyey 2732 30 0 19 10 1 0 0 1 Rehabilitation

Digging

Chlorination

F ,, ,, ,, Haruun 1879 43 0 38 5 0 0 0 5 Rehabilitation

Constructions

Page 22: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

G ,, ,, ,, Dhanawe 2983 100 0 89 10 1 0 0 - Rehabilitation

H GRRN Bakool Tieglow Madaa 2109 32 0 28 2 2 0 0 Rehabilitation

Constructions

I ,, ,, ,, Missir 1987 38 0 38 0 0 0 0 - Rehabilitation

J ,, ,, ,, Abaqle 1876 18 0 17 1 0 0 0 3 Rehabilitation

Digging

Chlorination

K GRRN Bakool Tieglow Balowka 2144 8 0 6 2 0 0 0 Rehabilitation

Constructions

L ,, ,, ,, Yaqo 720 0 0 0 0 0 0 1 - Rehabilitation

M ,, ,, ,, Burdho 891 0 0 0 0 0 0 4 2

N GRRN Bakool Tieglow Dhukubo 676 0 0 0 0 0 0 3 Rehabilitation

Digging

Chlorination

O ,, ,, ,, Heydle 532 0 0 0 0 0 0 1 Rehabilitation

Constructions

P ,, ,, ,, Irmanqare 238 0 0 0 0 0 0 1 - Rehabilitation

Q GRRN Bakool Tieglow Dubbo 432 0 0 0 0 0 0 2 Rehabilitation

Constructions

48 BOHD

O

Bay Baidoa Bonkay 3252 2 1 0 0 1 0 0 - Rehabilitation

,, ,, ,, Geldhere 1800 2 0 2 0 0 0 0

BOHD

O

Bay Baidoa Munabur 120 1 0 1 0 0 0 0 dry Rehabilitation

Digging

Chlorination

,, ,, ,, Bulanasib 312 1 0 0 0 1 0 0

BOHD

O

Bay Baidoa Ooro 288 1 0 0 0 1 0 0

Page 23: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

49 SYPD Bakol Elbarde Town 44,958 3 1 1 0 1 0 0 dry poor Rehabilitation

Digging

Chlorination

50

A

SYPD Bay Baidoa Daynuun

ey

1920 2 Water

catchment

B ,, ,, ,, Buulo

Unsiyow

1080 Digging

Construction of

Shallow wells

C ,, ,, ,, Garangar

asle

600 Rehabilitation of

shallow wells

D ,, ,, ,, Dhamaajo 600 Chlorination

Rehabilitations

E ,, ,, ,, Balow 690 Water

catchment

F Diyad 900 Digging

Construction of

Shallow wells

G ,, ,, ,, Buulo

Raran

540 Rehabilitation of

shallow wells

H ,, ,, ,, Burcaash 900 Chlorination

Rehabilitations

I ,, ,, ,, Hanshilole 660 Water

catchment

J ,, ,, ,, Dambal

Ure

960 Digging

Construction of

Shallow wells

K ,, ,, ,, Dhambaalk

a

900 Rehabilitation of

shallow wells

L ,, ,, ,, Korow -

rooge

1200 Chlorination

Rehabilitations

Page 24: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability

M ,, ,, ,, Bula adid 960 Water

catchment

N ,, ,, ,, Kunyi-

Warabe

480 Digging

Construction of

Shallow wells

O ,, ,, ,, Banyale

Buurfule

360 Rehabilitation of

shallow wells

P ,, ,, ,, Banyaala-

Gaalmado

wli

900 Chlorination

Rehabilitations

Q ,, ,, ,, Banyaala-

Banka

600 Rehabilitation

Construction

Water

catchments

R ,, ,, ,, Banyaala-

Idmoole

420 Water

catchment

S ,, , ,, Low-

Gadud

1200 Rehabilitation of

water

catchments

Page 25: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability
Page 26: Joint Bay,Bakool WASH Assessment Report · g) Provision of subsidy, fast moving spares and rapid repair of critical boreholes serving human and livestock population to enhance reliability