Joe Nestler, P.E.Bureau of State Highway Programs
Division of Transportation Investment Management
WTBA / WisDOT Contractor Engineer Conference
January 30, 2013
FY-2013State Highway Program Update
2
A Look Back at
State Fiscal Year 2012:
3
FY 12 Program Recap
State And Federal Funding Met Expectations Federal Funding Within 1% Of Estimate
$22 Million Less In Base Obligation Authority
$28 Million In “Redistribution” Funds Covered The Gap
State Revenue Collections A Bit Above EstimateMotor Fuel Collections Within 0.12% Of Forecast
Cost Estimates Were Pretty Accurate Too
Let Savings Of 2.7%
Savings Exceeded 10% In Each Of The Preceding 3 Years
4
$1027M $4M Maintenance/Operations
Final FY 12 LET Level
$1023M Base Improvement Program M
illion
s
[SHR, Majors, SE Freeways, Local Programs]
Goal: $1003 to $1033
Monthly Let Goal Percentages
0%
5%
10%
15%
20%
25%
% of Annual Total
5
~ 60% of annual goal
Final FY 12 Monthly Lets
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
Goal FY 126
% of Annual $
Projects Per Quarter Show Progress
% of Annual Projects
8
State Fiscal Year 2013
Estimates & Projections:
2013
State Fiscal Year 2013 EstimatesChapter 20 Funding for State and Local Highway Programs
~ $1,517,000,000
State Highway Rehabilitation ($826M)
Major Highway Projects Program ($371M)
SEFWY-Megaprojects Program ($188M)
Local Highway Program ($90M)
Local Bridge Program ($42M)
Includes SFY-13 Federal Funds Estimate of $670M
10
Projected FY 13 LET Level
$1044- $1074
$1040-$1070 Improvement Program
Million
s
$4 Maintenance & Operations
$60 Dresbach Bridge (MnDOT Let)
11
Let Level Caveats
Federal FY 13 Funding
State Motor Fuel And Registration Revenues
12
History Of Lets [Excluding Maintenance/Operations]
Millions
13
History Of Construction CostsIndex 1990=100
14
History Of Lets [Constant $, Excluding Maintenance/Operations]
Millions
15
FY 13 Project Quantities Targets
16