j.m. wright ths – stamford renovation timelines and costs
DESCRIPTION
J.M. Wright THS – Stamford Renovation Timelines and Costs. ARCHITECT: Bianco Giolitto Weston. What secondary programs are being considered?. Culinary Arts Carpentry Electrical Automotive Facilities Management Tourism/Hotel/Hospitality Plumbing and Heating Health Technology. - PowerPoint PPT PresentationTRANSCRIPT
J.M. Wright THS – StamfordRenovation Timelines and Costs
ARCHITECT: Bianco Giolitto Weston
What secondary programs are being considered?
1. Culinary Arts2. Carpentry3. Electrical4. Automotive5. Facilities Management6. Tourism/Hotel/Hospitality7. Plumbing and Heating8. Health Technology
What other programsmight be considered
in the future?
1. Early Child Care2. Financial Management3. Licensed Practical Nurse4. Media Productions
Scope of Renovation Project
• Renovation of approximately 196,667 square feet of the existing structure and replacement of all mechanical systems, windows, and roofing.
• Public Act 09-6 authorizes $90,230,942 for the renovation project at J.M. Wright THS. Funding for LEED Gold certification included in this authorization.
What is LEED?
• LEED stands for Leadership in Energy and Environmental Design and is the Green Building Rating System.
Renovation Timelines
• June 2010: State Board of Education approves ad hoc committee’s recommendations;
• July 2010: The Departments of Education and Public Works (DPW) are provided “green light” to proceed with redesign;
• August 2010: DPW approves amendments to architect’s contract based on new program design;
Renovation Timelines• September 2010: DPW issues amended design
contract;
• September 2010 – September 2011: Architect meets with district staff including trade and academic consultants to review design drawings, incorporates changes, completes design plans, and bids project.
Renovation Timelines
• December 2011: DPW selects construction firm and issues construction contract;
• January 2012: Renovations begin with an estimated timeline for completion of two years (24 months);
Renovation Timelines
• Spring 2014: Renovations completed, principal and other key staff hired, and new equipment is delivered and installed;
Enrollment Timelines
• August 2014: Initial freshman class of 144 students accepted (8 trades with 18 students each);
Enrollment Timelines• August 2015: a new freshman class of 144 - 165
students accepted bringing total enrollment to 288 - 309;
• August 2016: a new freshman class of 144 – 165 students accepted resulting in total enrollment of 432 – 453;
• August 2017: a new freshman class of 144 – 165 students accepted resulting in total enrollment not to exceed 576 secondary students;
Cost Projections• Construction: $90 million (includes $7M Equip)• Operating costs:
– FY 2014: $1.1M– FY 2015: $3.3M (total $4.4M)– FY 2016: $2.6M (total $7.0M)– FY 2017: $3.3M (total $10.3M)– FY 2018: $3.1M (total $13.4M)
• Staffing requirements:– FY 2014: 15– FY 2015: 32 (total 47)– FY 2016: 23 (total 70)– FY 2017: 8 (total 78)– FY 2018: 5 (total 83)
Cost Projections
• Capital funding:– FY 2014: $55,000*– FY 2015: $450,000*– FY 2016: $0– FY 2017: $0– FY 2018: $0
*Above the $7.1 million included in the renovation project
Other Issues for Future Discussions
• Ability to hire, train, and retain high quality staff due to unique issues associated with Fairfield County including:
– High cost of living– Transportation issues– Competitive wages