jersey future hospital - government of jersey and wellbeing... · 8 conclusion ... basement - the...
TRANSCRIPT
JERSEY FUTURE HOSPITAL
ENVIRONMENTAL IMPACT STATEMENT ADDENDUM
DATE 24th July 2018
Environmental Impact Statement Addendum 1-1
Contents
1 INTRODUCTION ......................................................................................................... 1
2 DESCRIPTION OF CHANGES TO PLANNING APPLICATION .................................. 1
3 SCOPE OF EISA ......................................................................................................... 4
4 HERITAGE .................................................................................................................. 5
5 WASTE ........................................................................................................................ 6
6 TOWNSCAPE AND VISUAL IMPACT ........................................................................ 7
7 CORRECTIONS TO ERRORS IN EIS NOISE AND VIBRATION CHAPTER ............ 13
8 CONCLUSION ........................................................................................................... 14
APPENDIX A ...................................................................................................................... 15
Environmental Impact Statement Addendum 1
1 Introduction
1.1 The Environmental Impact Statement (EIS) for the proposed Jersey Future Hospital was
submitted in support of planning application PP/2018/0507 on 13th April 2018. Since this
time, a number of changes to the parameter envelope and design principles submitted
have been introduced which results in the need to provide additional information for
consideration alongside the submitted application.
1.2 This Environmental Impact Statement Addendum (ESIA) sets out what these changes
are, identifying whether this results in any changes to the assessment outcomes. It
should be read in conjunction with the original EIS that was submitted alongside the
planning application PP/2018/0507.
1.3 The Planning and Building (Environmental Impact) (Jersey) Order 2006 does not make
provisions for providing additional information and updating the EIS prior to planning
decisions being made. In this instance therefore, in line with best practice, the procedure
required under the UK Town and Country (Environmental Impact Assessment)
Regulations 2017 have been followed which set out in Part 5 (25) how further information
or evidence should be provided and publicised.
2 Description of changes to planning application
2.1 The changes to the design result from revision to the parameter envelope and as a result
of the design principles that were submitted in July 2018. These are described in Table
2-1 along with a brief justification for this change. These design changes are also
updated within the Design and Access Statement which has also been resubmitted in
July 2018.
2.2 The proposed amendments do not change the quantum of development or the phasing
of development.
Table 2-1 Design changes
Design Change Justification
Main Building, Block B - The roofline
edge of the JFH ward block elements
(Volume B2) where adjacent to the rear of
the Granite Block has been reduced in
height by 2m (to 32m).
The reduction in height allows for a more
gradual increase in height between the
Granite Block and Block B. When viewed from
the opposite side of Gloucester Street (eastern
side), less than a full floor height is now visible
Environmental Impact Statement Addendum 2
Design Change Justification
above the Granite Block parapet (17.20
datum).
Basement - The current layouts utilise
60% of the basement area shown within
the parameter plan PL101 S2P06.
In order to calculate the volume of waste
materials that would be generated from
excavation of the basement it has been
assumed that 60% of the basement area is
developable. This represents 7,500m2.
Westaway Court – the height of this
building has been modified so that the
block fronting Elizabeth Place has
increased in height to 13.20m (from
12.90m) and the block fronting Savile
Street has increased in maximum height
to 9.00m (from 8.70m) with a slightly lower
frontage facing Savile Street 5.60m. The
overall footprint remains the same.
Reductions in frontage height were sought to
lessen the visual effect experienced along
Savile Street and Elizabeth Place.
Transport proposals – a number of
minor changes to the transport proposals
include:
2.3 The changes to the transport and access
proposals have been made for the following
reasons:
Optimisation of the internal areas and
clinical adjacencies;
Reinforcement of a clear and legible
circulation diagram, achieving grade
separation between ground floors staff
focused areas and first floor public areas
with the hospital; and
External benefits including the provision of
additional “active frontage” on Kensington
Place.
2.4
Phase 1B
Proposed service block has been
relocated from the north of Patriotic
Street MSCP to the southwest of The
Parade behind St Elmos and Edward
Place.
Hearse bay for the mortuary is
proposed adjacent to the Newgate
Street/ Kensington Place junction
Kensington Place is kept one-way
between the junctions with Newgate
Street (extended) and Kensington
Street
Environmental Impact Statement Addendum 3
Design Change Justification
Pedestrian access from Kensington
Place in to Block A has been removed
Phase 2 Final State
Drop-off facility on The Parade is
reduce in size and Patient Transport
Services will use an extended layby
on Newgate Street.
2.5 In addition, a couple of errors were identified in the EIS Chapter 6 (Noise and Vibration).
These are identified and rectified in Section 7 of this EIS Addendum.
EIS Figure updates
2.6 All parameter plans have been updated and resubmitted for consideration with the
planning application. The changes that have been made to the parameter plans are
listed in Appendix A of this EISA. Some of the Figures that were submitted as Volume
III of the ESIA in April 2018 were copies of the parameter plans, therefore these Figures
have also required updating as have Figures relating to the transport assessment and
the revised visualisations which have been needed following the design changes post
April 2018.
2.7 The EIS Figures which have been updated are listed below and are included in Appendix
A. Where these relate to updated parameter plans these are also identified (in brackets):
Figure 3.1 – Building Heights Parameter Plan (PL103-S2.P06);
Figure 3.2 – Building Frontages Parameter Plan (PL102-S2.P06);
Figure 3.3 Ground Floor, Public Realm and Pedestrians Parameter Plan (JFH-
HSL-M1-ZZ-DR-A-PL104-S2.P06)
Figure 3.4 Phasing Plan Parameter Plan - (JFH-HSL-M1-ZZ-DR-A-PL106-
S2.P05);
Figure 7.1 Phase 1A Overview of Proposals
Figure 7.2 Phase 1B Overview of Proposals
Environmental Impact Statement Addendum 4
Figure 7.3 Phase 2 Overview of Proposals
Figure 15.5 - Photosheets_150dpi_1 of 2
Figure 15.5 - Photosheets_150dpi_2 of 2
3 Scope of EISA
3.1 The changes that have been proposed have been reviewed and topic specialists have
identified whether there is a potential for these changes to result in changes to their
original findings as set out in Chapters 5-16 of the EIS. This is summarised in Table X
below and where changes to assessment outcomes were identified as likely, further
assessment has been carried out and reported.
Table 3-1 EISA scope
EIS Topic Scoped
into
EISA?
Justification
Air quality x Changes do not alter findings from the EIS.
Noise & vibration x Changes do not alter findings from the EIS
Traffic x A Transport Technical Note has been prepared to be
submitted with the updated design details. This reports on
the changes to the design as they relate to transport issues
and confirms that there are no anticipated changes to the
Traffic Impact Assessment / construction routing.
Therefore, the changes do not alter the findings from the
EIS.
Biodiversity x Changes do not alter findings from the EIS
Geology,
hydrogeology and
contamination
x Changes do not alter findings from the EIS
Water resources x Changes do not alter findings from the EIS
Environmental Impact Statement Addendum 5
EIS Topic Scoped
into
EISA?
Justification
Heritage The reduction in height of certain elements of Block B and
Westaway requires reassessment of the views afforded to
and from heritage assets.
Waste The proposed design changes, in particular the
confirmation of the main building basement layout requires
the volume of excavated waste to be assessed to
determine whether this changes the significance levels
assigned in the EIS.
Wind x The changes to the height of Block B and Westaway are
unlikely to result in any changes to the findings from the EIS
Socioeconomics x Changes do not alter findings from the EIS
TVIA The changes to the height Westaway may result in changes
to the magnitude of impact and have been reassessed
within the EISA.
4 Heritage
4.1 In relation to the Granite Block, it is proposed to reduce the height of Block B in the zone
closest to the rear façade from 34m to 32m and to secure this through a design principle
that would be guaranteed by a planning condition. This will significantly reduce the
visibility of Block B to ensure that less than a full floor height is visible above the Granite
Block parapet, and to secure this through a design principle. in views from the opposite
side of Gloucester Street, to the point where the impact on the setting of the Granite
Block – as viewed from Gloucester Street - will be slight. This represents an impact of
less significance than was identified in the EIS.
Figure 1 below shows the sight lines from Gloucester Street demonstrating that less
than a full floor height would be visible.
Environmental Impact Statement Addendum 6
Figure 1 Section showing reduction in height behind Granite Block (less than full floor
height visible)
4.2 In relation to the changes proposed for Westaway, the parameter envelope has been
refined so that there are now four defined building heights (17.9m, 13.2m, 9m and 5.6m).
The height of development in the zone adjacent to Savile Street has been reduced to
5.6m and the development at the corner of Savile Street and Elizabeth Place now
incorporates a set-back. As a result, the scale of the new development has an improved
relationship to the domestic scale of these streets, and the impact on listed assets at 24
Savile Street and 14 Elizabeth Place is reduced from moderate to minor.
5 Waste
5.1 For the purposes of construction waste impacts 60% of the basement area of the Main
Building (7,500m2) has been assumed as the extent of basement within this zone.
Based on this assumption, the comparison of the new waste generation volumes with
those assessed in the EIS are set out in Table 4-1 below.
Table 5-1 Estimated Excavation Waste – comparison with EIS data and July 2018 designs
Year Estimated Excavation Waste (EIS) Contingency
New Estimated Excavation Waste (July 2018)
New Contingency
Total Excavation waste (EIS) New Total
Excavation Waste
Volume (m3) Volume (m3) Volume (m3) Volume (m3) Volume (m3) Volume (m3)
2019 30,163 3,016 26726 2,673
33,179 29,399
2022 18,139 1,814 27440 2,744 19,953 30,184
2025 2,955 296 1966 197 3,251 2,163
Total 51,257 5,126 56132 5,613
56,383 61,745
Environmental Impact Statement Addendum 7
5.2 The figures above show that there is estimated to be an increase in excavation waste
volumes of approximately 9.5% from those identified in the EIS. Whilst this represents
an increase, these changes in waste volumes do not result in changes to the overall
predicted significance of effect.
6 Townscape and Visual Impact
Volumetric Amendment to Block B
6.1 The proposed reduction in the height of Block B to 32m to the rear of the Granite Block
will have the effect of decreasing the perceived height of the hospital roofline as seen
from Gloucester Street. This will mitigate its impact on these views and on the setting
of the Granite Block; the degree of mitigation will vary depending on viewing position.
Revised versions of the relevant visualizations are to be prepared to confirm whether
this amendment will have any implications for the magnitude of effects predicted in the
TVIA.
Amended Massing of Westaway Court Building
6.2 The findings of the TVIA (EIS Chapter 15) should be assumed to remain valid unless
varied by this document. It is supported by a supplementary version of the
visualizations, six of which have been amended to take account of the changes; these
relate to Viewpoints 11, 21, 23, 24, 25 and 26.
Approach
6.3 The re-assessment has comprised the following steps:
The revised massing model was reviewed and relevant views identified;
Amended versions of the visualizations were prepared for these views;
The assessment of these views, as set out in EIS Table 15.4, was re-visited; and
Any implications for the predicted effects were identified.
6.4 Only six views were considered to merit re-modelling. These comprise one longer-
distance view (Viewpoint 11) and five close-range views (Viewpoints 21, 23, 24, 25 and
26). Although Westaway Court is glimpsed in one or two other views, its influence is
minimal and these were not considered to require remodelling. No further desktop
research or fieldwork has been carried out.
Environmental Impact Statement Addendum 8
Implications for the Assessment Views
6.5 An amended version of the relevant views from Table 15.4 is attached. The changes
are as follows:
The descriptive text has been updated to more accurately reflect what is shown in
the views.
The magnitude of change is considered to remain the same for five of the views.
This is because, even with the amended modelling, the overall scale of the
proposed building, and thereby its relationship both to the existing building and to
its immediate context, remain broadly similar to the previous proposal.
The magnitude of change is considered to be reduced from high to medium for one
view: Viewpoint 25 (Savile Street). This is because the massing of the building has
been stepped back, so that its perceived height is similar to that of the existing four-
storey building and lower than that of the existing tower block. Whilst the
composition of the view will still change – particularly in terms of the larger footprint
and loss of trees – the refined massing allows the magnitude of impact to be
reduced by one order of magnitude.
Implications for the Predicted Effects
6.6 As indicated on the Table 5-1 (which is an extract from EIS Table 15.4), the reduced
magnitude of change affects two categories of receptor: pedestrians and residents in
Savile Street. The effects on these receptors are thereby predicted to decrease as
follows:
Pedestrians: from Moderate to Slight; and
Residents: from Substantial to Moderate to Substantial.
6.7 There would be no change in the significance of these effects; the effects on pedestrians
are not considered to be significant, whilst the effects on local residents are considered
to remain significant (but of reduced magnitude) in amenity terms.
6.8 The TVIA concluded that the effects on some residents in Savile Street would be
adverse. This was mainly due to the foreshortening and partial obstruction of views that
would result from the introduction of a building of substantial scale and larger footprint.
Whilst these sources of impact would remain, they have been mitigated by the revised
modelling. When considered in combination with the benefits of removing the existing
tower block and parking, together with the opportunity to create a building of
Environmental Impact Statement Addendum 9
demonstrable design quality, it is possible that some of these effects could now be
neutral (but still significant).
6.9 The revised modelling will also ameliorate the effect on the streetscape of Savile Street,
which already has a somewhat unbalanced character, due to the juxtaposition of
Westaway Court with the two-storey dwellings opposite. However, the overall effect at
character area level is considered to remain unchanged at medium.
6.10 There would be no implications for the cumulative effects.
Environmental Impact Statement Addendum 10
Table 5-1 (extract from EIS Table 15.4): Evaluation of Effects on Assessment Views and Associated Receptors Extract to show the Impact of the Revised Westaway Court Proposals on Selected Views
VP Description and Magnitude of Change to View Receptors Sensitivity Receptor-Specific
Magnitude of
Change
Significance of Effect
11 The “1980s block”, the chimney and the tower block at Westaway Court would be removed.
On the main hospital site, Blocks A and B are seen to extend to the right and to sit above the prevailing height of surrounding buildings. However, they are perceived to be about half the height of the chimney and about 25% lower than the “1980s block”. They do not breach the skyline (unlike the chimney and “1980s block”).
The development extends partly across the view towards Mont de la Ville, but would not obstruct the view of Fort Regent.
The development at Westaway Court is seen to be significantly lower than the existing tower block, but would extend further laterally and above the prevailing height of surrounding buildings. The visible height of St Thomas’ Church is slightly reduced, but would not be obstructed.
Magnitude of Change to View: Medium
Urban Character Area: Town Edges
and Slopes
High Medium Moderate to Substantial
Iconic Landmark: St Thomas’s Church High Low Moderate
Iconic Landmark: Fort Regent High Low Moderate
Major Local Landmark: Unlisted
Hospital Buildings
Low Very High Moderate to Substantial
Visual receptors: Road users Very Low Medium Slight
Visual receptors: Pedestrians Low Medium Slight to Moderate
Visual receptors: Residents on
Westmount Road
High Medium Moderate to Substantial
Visual receptors: Users of People’s
Park
High Medium Moderate to Substantial
21 The existing buildings at Westaway Court are replaced by a block that is perceived to be of greater scale (twice the height of the adjoining Maison du
Urban Character Area: The Parade
and Esplanade
Medium Low Slight to Moderate
Important Urban Space: Parade
Gardens
Medium Medium Moderate
Environmental Impact Statement Addendum 11
Pape building), but slightly lower than the existing tower block.
Magnitude of Change: Medium
Visual receptors: Users of Parade
Gardens
Medium Medium Moderate
Major Local Landmark: Unlisted
Hospital Buildings
Low Very High Moderate to Substantial
Important Urban Space: Parade
Gardens
Medium High Moderate to Substantial
Visual receptors: Users of Parade
Gardens
Medium High Moderate to Substantial
23 The existing buildings at Westaway Court are replaced by a block of demonstrably greater height and extent, which is perceived to be taller than the existing tower block and obstructs slightly more of the view towards Elizabeth Place.
Magnitude of Change: Medium
Urban Character Area: The Parade
and Esplanade
Medium Medium Moderate
Important Urban Space: Parade
Gardens
Medium Medium Moderate
Visual receptors: Users of Parade
Gardens
Medium Medium Moderate
24 The existing buildings at Westaway Court are replaced by a block of demonstrably greater height and extent, which is perceived to be up to 50% taller and extends further along both facades.
Magnitude of Change: Medium
Urban Character Area: The Parade
and Esplanade
Medium Medium Moderate
Visual receptors: Road users Very Low Low Negligible to Slight
Visual receptors: Pedestrians Low Medium Slight
Visual receptors: Residents in
Elizabeth Place
High Medium Moderate to Substantial
25 The existing buildings at Westaway Court are replaced by a block of demonstrably larger footprint. Its height is perceived to be broadly similar to that of the existing 4-storey block and lower than that of the existing tower block. The two mature trees within the site would be removed and the view towards Elizabeth Place obstructed.
Magnitude of Change: Medium
Urban Character Area: The Parade
and Esplanade
Medium Medium Moderate
Visual receptors: Pedestrians Low Medium Slight
Visual receptors: Residents in Savile
Street
High Medium Moderate
Environmental Impact Statement Addendum 12
26 The buildings at Westaway Court are replaced by a block of demonstrably larger footprint that is perceived to be taller than the existing 4-storey block. The glimpse of the “1980s block” to the right would be lost, together with the view towards Parade Gardens and the two mature trees within the site.
Magnitude of Change: High
Urban Character Area: The Parade
and Esplanade
Medium Medium Moderate
Visual receptors: Road users Very Low High Slight to Moderate
Visual receptors: Pedestrians Low High Moderate
Visual receptors: Residents in Rouge
Bouillon and Elizabeth Place
High High Substantial
Environmental Impact Statement Addendum 13
7 Corrections to errors in EIS Noise and Vibration Chapter
7.1 In EIS Chapter 6 Noise and Vibration, a number of errors and omissions have been
identified which are highlighted below.
7.2 Paragraph 6.86 of the EIS reported that noise from construction traffic using Kensington
Place would exceed the assessment criterion for daytime construction noise and lead to
a significant adverse effect. This was incorrect and due to a calculation error. The
correct construction traffic noise levels were included in Appendix C-4, Table 5, but
these are not reflected in paragraph 6.86, which should have stated that the traffic noise
levels would be below the criterion and consequently there is not a significant effect
identified.
7.3 Paragraph 6.89 of the EIA refers to construction traffic along Lewis Street. It should have
stated ‘traffic during construction’, referring to the re-routing of non-construction traffic
along Lewis Street during the works. Construction traffic will not use Lewis Street.
7.4 Table 6.18 within the EIS presents the predicted construction noise levels during Phase
1A. The predictions for the receptors on Newgate Street and Patriotic Street, and for
those around Westaway Court were omitted. The following table should be read in place
of Table 6.18 of the EIS.
7.5 EIS Paragraph 6.129 should read that the residual effect of construction noise is not
significant at all receptors for phases 1A and 1B. During phase 2 however, the effect is
NSR (see Figure 6.5)
Approx. distance to site centre
(m)
Assumed stage* activity noise level (dBLAeq,T)
1 2 3 4
A 33 73 75 75 63
B 18 79 81 81 69
C 22 77 79 79 68
D 25 76 78 78 67
E 25 76 75 75 67
F 22 77 76 76 68
I 52 68 70 70 58
J 40 71 73 73 61
K 26 76 77 77 66
L 33 73 75 75 64
*Construction stages defined in paragraph 6.92
Environmental Impact Statement Addendum 14
significant at receptor H. The assessment summary matrix also should reflect this
change.
8 Conclusion
8.1 This EISA has set out the changes proposed in relation to the parameter envelope and
design principles submitted for planning application PP/2018/0507 on 13th April 2018
and identified whether these changes are likely to result in any changes to the
environmental assessment that was undertaken and reported within the EIS.
8.2 With the exception of waste, heritage and LVIA all environmental topics were scoped
out based on the conclusion that the proposed changes would not change the
conclusions presented in the EIS.
8.3 The assessment of effects related to heritage and LVIA concludes that the proposed
changes will result in ameliorated effects. The volumes of waste have been identified
as being approximately 9.5% more than was identified in the EIS, but this does not
change the level of impact significance identified which remains as significant.
Environmental Impact Statement Addendum 15
Appendix A
Updated parameter plans
All parameter plans have been updated to include updated contact information. Table
A1-1 identifies which parameter plans have been updated to reflect design revisions.
Table A0-1 Parameter plan updates
Parameter
plan
Revision Changes
PL021 S2.P02 Granite Block ridge height reduced based on updated site
information
PL101 S2.P06 Basement footprint and key annotation added to sheet
Westaway Court parcel footprint / dimensions updated
Site underlay updated to reflect proposed road layout at
The Parade
PL102 S2.P06 Frontages updated to align to current internal clinical
planning / departmental adjacencies
Westaway Court: Elizabeth Place, Savile Street, laneway
made secondary frontage
Westaway Court parcel footprint / dimensions updated
Site underlay updated to reflect proposed road layout at
The Parade
PL103 S2.P06 Zones of disruption graphic and key annotation added to
break Block B skyline massing
Westaway Court parcel footprint / dimensions updated
Westaway Court heights updated to revised parameter
envelope (overall height remains +17.90 relative to
Westaway Court project datum)
Environmental Impact Statement Addendum 16
Site underlay updated to reflect proposed road layout at
The Parade
PL104 S2.P06 Indicative internal routes graphic and key annotation
updated to reflect current internal planning
Key annotations for primary/secondary pedestrian routes
revised to clarify L00/L01 routes
Key annotation for MSCP updated to include 'entry/egress'
Secondary entrance added on Newgate Street to reflect
anticipated Minors Emergency entrance
Public Realm reduced at Edward Place to reflect loading
bay
Primary / secondary ground floor routes amended to reflect
developments in entrance positions
Extent of new public edge treatment adjusted at Edward
Place gable end
Westaway Court parcel footprint / dimensions updated
Westaway Court primary entrance scope amended
Site underlay updated to reflect proposed road layout at
The Parade
PL106 S2.P05 Phase 1B hatch extended to include strip between
Parameter Envelope and Gloucester St
Westaway Court parcel footprint / dimensions updated
Site underlay updated to reflect proposed road layout at
The Parade
PL201 S2.P05 Note added to clarify street name annotations
Zones of disruption graphic and key annotation added to
break Block B skyline massing
Environmental Impact Statement Addendum 17
Non-occupied floor hatch, +29.00 levels, and key
annotation removed
Granite Block ridge height reduced based on updated site
information
PL211 S2.P03 Note added to clarify street name annotations
Parameter massing adjusted to include setback to Savile
Street, increased height to Elizabeth Place, and extended
length to the top floor Parade Gardens mass
PL301 S2.P05 Note added to clarify street name annotations
Non-occupied floor hatch, +29.00 levels, and key
annotation removed
Zones of disruption graphic and key annotation added to
break Block B skyline massing
Basement extents updated in Section CC, key annotation
added to sheet
PL302 S2.P05 Note added to clarify street name annotations
Zones of disruption graphic and key annotation added to
break Block B skyline massing
Basement extents updated in Section FF, key annotation
added to sheet
Kensington Place typo corrected in Sections DD/EE
annotations
PL311 S2P02 Note added to clarify street name annotations
Parameter massing adjusted to include setback to Savile
Street, increased height to Elizabeth Place, and extended
length to the top floor Parade Gardens mass
Indicative width of Savile Street made consistent between
elevation views on sheet
Environmental Impact Statement Addendum 18
Spot elevation heights rounded to two decimal places to
coordinate with Main Hospital sheets
Environmental Impact Statement Addendum 19
Updated Figures from EIS Volume III: Figures
8-20
Environmental Impact Statement | Chapter 1 | Introduction 8-21
THE PARADE
KENSINGTON PLACE
GLOUCESTER STREET
NEW
GATE STREET
PATRIOTIC STREET
ESPLANADE
LEWIS STREET
PEIRSON ROAD
SAND STREET
ST AUBINS ROAD
CHEAPSIDE
PATRIOTIC
PLACE
WESTMOUNT ROAD
+20.60
+15.60
+15.60
+20.60
+15.60+16.70
+13.20+9.00
+17.90
+19.00
SA
VIL
E S
TRE
ET
ELIZA
BETH L
ANE
ELIZA
BETH P
LACE
SAVILE STREET
+15.60
6000
60006000
6000
2380
+10.00
5100
KENSINGTO
N STREET
+14.20(to match existing)
+11.90(to match existing)
+5.60
+34.00
32500
+34.00
A
B
B
SHADES OF GREY SHOW INDICATIVE RELATIVE HEIGHTS WITH THE SHORTER MASSING SHOWN LIGHTEST
NB. ALL LEVELS SHOWN IN BLUE TEXT INDICATE MAXIMUM HEIGHTS FOR THE MAIN HOSPITAL SCHEME. HEIGHTS ARE RELATIVE TO PROJECT DATUM LEVEL 0.00m (GROUND FLOOR DATUM) = JERSEY DATUM LEVEL (+10.00m)
ALL LEVELS SHOWN IN RED TEXT INDICATE MAXIMUM HEIGHTS FOR THE WESTAWAY SCHEME. HEIGHTS ARE RELATIVE TO PROJECT DATUM LEVEL 0.00m (GROUND FLOOR DATUM) = JERSEY DATUM LEVEL (+12.00m)
• +15.60 HEIGHTS TO PODIUM DO NOT INCLUDE FOR BALUSTRADING TO PUBLICLY ACCESSIBLE ROOF ZONES. THE PARAMETER CONSTRAINTS FOR BALUSTRADING TO THESE AREAS ARE DEFINED IN THE PARAMETER SECTION DRAWINGS.
• THE MAXIMUM BUILDING HEIGHTS AS SHOWN ON THIS DRAWING EXCLUDE THE HEIGHTS OF ANY PROTECTIVE HANDRAILS, HARNESSING EQUIPMENT ETC REQUIRED FOR ACCESS AND MAINTENANCE TO ROOFS.
+20.00
+20.00
ZONE OF DISRUPTION A - ZONE WITHIN WHICH A CHANGE IN HEIGHT WILL BE INSERTED TO BREAK ROOFLINE TO WARD BLOCK ELEMENTS AND A PLAN INDENTATION AND / OR CHANGE IN MATERIALS INSERTED TO PROVIDE RELIEF / SHADOWING TO THIS SKYLINE ELEVATION
ZONE OF DISRUPTION B - ZONE WITHIN WHICH A PLAN INDENTATION AND / OR CHANGE IN MATERIALS WILL BE INSERTED TO PROVIDE RELIEF / SHADOWING TO THIS SKYLINE ELEVATION
ZONE WHERE REDUCTION IN PARAMETER VOLUME IS APPLIED TO REDUCE HEIGHT OF BUILDING BEHIND GRANITE BLOCK
OUTLINE OF PROPOSED FUTURE HOSPITAL DEVELOPMENT
0
1:750
15 30 60
HASSELL Limited CN 75458191 CURTAIN PLACELONDONEC2A 3AN UNITED [email protected] +44 207 490 7669
HASSELL
CONSULTANT
PROJECT
CLIENT
Original Sheet Size A1 - 841 x 594mm
DRAWING TITLE
SCALE @ A1 APPROVED
STATUS
PROJECT# - ORIGIN. - ZONE - LEVEL - TYPE - ROLE - DRAWING# - STATUS+REV
NOTES
1. DO NOT SCALE DRAWINGS. WRITTEN DIMENSIONS GOVERN.
2. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE.
3. ALL DIMENSIONS SHALL BE VERIFIED ON SITE BEFORE PROCEEDING
WITH THE WORK. HASSELL SHALL BE NOTIFIED IN WRITING OF ANY DISCREPANCIES.
4. THIS DRAWING MUST BE READ IN CONJUNCTION WITH ALL RELEVANT
CONTRACTS, SPECIFICATIONS AND DRAWINGS.
THIS DRAWING IS AN UNCONTROLLED COPY. UNLESS NOTED OTHERWISE.
© COPYRIGHT OF THIS DRAWING IS VESTED IN HASSELL.
2018 HASSELL. LTD.
ORIGINATOR PROJECT #
012145
REVIEWED
23/07
/2018
21:44
:15C:
\_Rev
itPr
ojects
\1807
20_J
FH-H
SL-M
1-ZZ
-M3-
A-BU
ILD_P
R_Ou
tlineP
lannin
g_RE
V_HA
RWX.
rvt
1 : 750
JERSEY FUTURE HOSPITAL (JFH)
THE PARADE, ST HELIER, JERSEYJE1_3QS
CL
FIGURE 3.1 - PARAMETER PLAN 03 - BUILDINGHEIGHTS
FOR INFORMATION
DEPARTMENT FOR INFRASTRUCTURE
JFH-HSL-M1-ZZ-DR-A-PL103-S2.P06
WH
REV DESCRIPTION DATE
S2.P01 FIRST ISSUE 02/03/18
S2.P02 SECOND ISSUE 17/03/18
S2.P03 UPDATED BOUNDARY, PARAMETEREXTENT
24/03/18
S2.P04 UPDATED BOUNDARY 04/04/18
S2.P05 OUTLINE PLANNING APPLICATION ISSUE 11/04/18
S2.P06 OUTLINE PLANNING APPLICATION ISSUEREVISED
23/07/18
THE PARADE
KENSINGTON PLACE
GLOUCESTER STREET
NEW
GATE STREET
PATRIOTIC STREET
ESPLANADE
LEWIS STREET
PEIRSON ROAD
SAND STREET
ST AUBINS ROAD
CHEAPSIDE
PATRIOTIC
PLACE
WESTMOUNT ROAD
SA
VIL
E S
TRE
ET
ELIZA
BETH L
ANE
ELIZA
BETH P
LACE
SAVILE STREET
KENSINGTO
N STREET
OUTLINE OF PROPOSED FUTURE HOSPITAL DEVELOPMENT
PARAMETER EXTENTS
PRIMARY FRONTAGE - ZONE FOR PRIMARY HOSPITAL ENTRANCE AND ACTIVE FRONTAGES
SECONDARY FRONTAGE - ZONE WHERE OCCUPIED FLOORS AND SECONDARY ENTRANCES ARE PREDOMINANTLY LOCATED (DOES NOT EXCLUDE LIMITED LOUVRES FOR AIR INTAKE / EXHAUST OR PLANT ROOM ACCESS LOCATIONS)
TERTIARY FRONTAGE - ZONE WHERE CONCEALED ELEVATIONS ALLOW FOR PLANT / LOUVRES / SERVICE ACCESS
PROPOSED ACCESS TO NEWGATE STREET AT GROUND FLOOR ONLY
0
1:750
15 30 60
HASSELL Limited CN 75458191 CURTAIN PLACELONDONEC2A 3AN UNITED [email protected] +44 207 490 7669
HASSELL
CONSULTANT
PROJECT
CLIENT
Original Sheet Size A1 - 841 x 594mm
DRAWING TITLE
SCALE @ A1 APPROVED
STATUS
PROJECT# - ORIGIN. - ZONE - LEVEL - TYPE - ROLE - DRAWING# - STATUS+REV
NOTES
1. DO NOT SCALE DRAWINGS. WRITTEN DIMENSIONS GOVERN.
2. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE.
3. ALL DIMENSIONS SHALL BE VERIFIED ON SITE BEFORE PROCEEDING
WITH THE WORK. HASSELL SHALL BE NOTIFIED IN WRITING OF ANY DISCREPANCIES.
4. THIS DRAWING MUST BE READ IN CONJUNCTION WITH ALL RELEVANT
CONTRACTS, SPECIFICATIONS AND DRAWINGS.
THIS DRAWING IS AN UNCONTROLLED COPY. UNLESS NOTED OTHERWISE.
© COPYRIGHT OF THIS DRAWING IS VESTED IN HASSELL.
2018 HASSELL. LTD.
ORIGINATOR PROJECT #
012145
REVIEWED
23/07
/2018
21:44
:00C:
\_Rev
itPr
ojects
\1807
20_J
FH-H
SL-M
1-ZZ
-M3-
A-BU
ILD_P
R_Ou
tlineP
lannin
g_RE
V_HA
RWX.
rvt
1 : 750
JERSEY FUTURE HOSPITAL (JFH)
THE PARADE, ST HELIER, JERSEYJE1_3QS
CL
FIGURE 3.2PARAMETER PLAN 02 - BUILDINGFRONTAGES
FOR INFORMATION
DEPARTMENT FOR INFRASTRUCTURE
JFH-HSL-M1-ZZ-DR-A-PL102-S2.P06
WH
REV DESCRIPTION DATE
S2.P01 FIRST ISSUE 02/03/18
S2.P02 SECOND ISSUE 17/03/18
S2.P03 UPDATED BOUNDARY, PARAMETEREXTENT
24/03/18
S2.P04 UPDATED BOUNDARY 04/04/18
S2.P05 OUTLINE PLANNING APPLICATION ISSUE 11/04/18
S2.P06 OUTLINE PLANNING APPLICATION ISSUEREVISED
23/07/18
THE PARADE
KENSINGTON PLACE
GLOUCESTER STREET
NEW
GATE STREET
PATRIOTIC STREET
ESPLANADE
LEWIS STREET
PEIRSON ROAD
SAND STREET
ST AUBINS ROAD
CHEAPSIDE
PATRIOTIC
PLACE
WESTMOUNT ROAD
SA
VIL
E S
TRE
ET
ELIZA
BETH L
ANE
ELIZA
BETH P
LACE
SAVILE STREET
KENSINGTO
N STREET
OUTLINE OF PROPOSED FUTURE HOSPITAL DEVELOPMENT
NEW PUBLIC REALM ZONE
NEW PRIMARY PEDESTRIAN ROUTES (GROUND FLOOR)
NEW SECONDARY PEDESTRIAN ROUTES (GROUND FLOOR)
PRIMARY PEDESTRIAN ENTRANCE TO BE LOCATED WITHIN ZONE SHOWN (GROUND FLOOR)
NEW PRIMARY PEDESTRIAN ROUTES (LEVEL 01)
SECONDARY PEDESTRIAN ENTRANCE TO BE LOCATED WITHIN ZONE SHOWN (GROUND FLOOR)
SECONDARY ENTRANCE (USED AS INTERIM ENTRY DURING PHASE 2)
INDICATIVE INTERNAL PEDESTRIAN ROUTES (PUBLIC / STAFF)
PATRIOTIC STREET MSCP ENTRANCE / EGRESS
NEW PUBLIC EDGE TREATMENT
PROPOSED ACCESS TO NEWGATE STREET AT GROUND FLOOR ONLY
PRIMARY PEDESTRIAN ENTRANCE TO BE LOCATED WITHIN ZONE SHOWN (LEVEL 01)
0
1:750
15 30 60
HASSELL Limited CN 75458191 CURTAIN PLACELONDONEC2A 3AN UNITED [email protected] +44 207 490 7669
HASSELL
CONSULTANT
PROJECT
CLIENT
Original Sheet Size A1 - 841 x 594mm
DRAWING TITLE
SCALE @ A1 APPROVED
STATUS
PROJECT# - ORIGIN. - ZONE - LEVEL - TYPE - ROLE - DRAWING# - STATUS+REV
NOTES
1. DO NOT SCALE DRAWINGS. WRITTEN DIMENSIONS GOVERN.
2. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE.
3. ALL DIMENSIONS SHALL BE VERIFIED ON SITE BEFORE PROCEEDING
WITH THE WORK. HASSELL SHALL BE NOTIFIED IN WRITING OF ANY DISCREPANCIES.
4. THIS DRAWING MUST BE READ IN CONJUNCTION WITH ALL RELEVANT
CONTRACTS, SPECIFICATIONS AND DRAWINGS.
THIS DRAWING IS AN UNCONTROLLED COPY. UNLESS NOTED OTHERWISE.
© COPYRIGHT OF THIS DRAWING IS VESTED IN HASSELL.
2018 HASSELL. LTD.
ORIGINATOR PROJECT #
012145
REVIEWED
23/07
/2018
21:44
:34C:
\_Rev
itPr
ojects
\1807
20_J
FH-H
SL-M
1-ZZ
-M3-
A-BU
ILD_P
R_Ou
tlineP
lannin
g_RE
V_HA
RWX.
rvt
1 : 750
JERSEY FUTURE HOSPITAL (JFH)
THE PARADE, ST HELIER, JERSEYJE1_3QS
CL
FIGURE 3.3 -PARAMETER PLAN 04 - GROUNDFLOOR PUBLIC REALM ANDPEDESTRIANS
FOR INFORMATION
DEPARTMENT FOR INFRASTRUCTURE
JFH-HSL-M1-ZZ-DR-A-PL104-S2.P06
WH
REV DESCRIPTION DATE
S2.P01 FIRST ISSUE 02/03/18
S2.P02 SECOND ISSUE 17/03/18
S2.P03 UPDATED BOUNDARY, PARAMETEREXTENT
24/03/18
S2.P04 UPDATED BOUNDARY 04/04/18
S2.P05 OUTLINE PLANNING APPLICATION ISSUE 11/04/18
S2.P06 OUTLINE PLANNING APPLICATION ISSUEREVISED
23/07/18
OUTLINE OF PROPOSED FUTURE HOSPITAL DEVELOPMENT
THE PARADE
KENSINGTON PLACE
GLOUCESTER STREET
NEW
GATE STREET
PATRIOTIC STREET
ESPLANADE
LEWIS STREET
PEIRSON ROAD
SAND STREET
ST AUBINS ROAD
CHEAPSIDE
PATRIOTIC
PLACE
WESTMOUNT ROAD
PHASE 1B PHASE 2
PHASE 1A
PHASE 1A
PHASE 1A
SA
VIL
E S
TRE
ET
ELIZA
BETH L
ANE
ELIZA
BETH P
LACE
SAVILE STREET
KENSINGTO
N STREET
INTERIMDROPOFF
PHASE 1A
PHASE 1B
PHASE 2
INTERIM DROP-OFF
0
1:750
15 30 60
HASSELL Limited CN 75458191 CURTAIN PLACELONDONEC2A 3AN UNITED [email protected] +44 207 490 7669
HASSELL
CONSULTANT
PROJECT
CLIENT
Original Sheet Size A1 - 841 x 594mm
DRAWING TITLE
SCALE @ A1 APPROVED
STATUS
PROJECT# - ORIGIN. - ZONE - LEVEL - TYPE - ROLE - DRAWING# - STATUS+REV
NOTES
1. DO NOT SCALE DRAWINGS. WRITTEN DIMENSIONS GOVERN.
2. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE.
3. ALL DIMENSIONS SHALL BE VERIFIED ON SITE BEFORE PROCEEDING
WITH THE WORK. HASSELL SHALL BE NOTIFIED IN WRITING OF ANY DISCREPANCIES.
4. THIS DRAWING MUST BE READ IN CONJUNCTION WITH ALL RELEVANT
CONTRACTS, SPECIFICATIONS AND DRAWINGS.
THIS DRAWING IS AN UNCONTROLLED COPY. UNLESS NOTED OTHERWISE.
© COPYRIGHT OF THIS DRAWING IS VESTED IN HASSELL.
2018 HASSELL. LTD.
ORIGINATOR PROJECT #
012145
REVIEWED
23/07
/2018
21:44
:59C:
\_Rev
itPr
ojects
\1807
20_J
FH-H
SL-M
1-ZZ
-M3-
A-BU
ILD_P
R_Ou
tlineP
lannin
g_RE
V_HA
RWX.
rvt
1 : 750
JERSEY FUTURE HOSPITAL (JFH)
THE PARADE, ST HELIER, JERSEYJE1_3QS
CL
FIGURE 3.4PARAMETER PLAN 06 - PHASING
FOR INFORMATION
DEPARTMENT FOR INFRASTRUCTURE
JFH-HSL-M1-ZZ-DR-A-PL106-S2.P05
WH
REV DESCRIPTION DATE
S2.P01 FIRST ISSUE 17/03/18
S2.P02 UPDATED BOUNDARY, PARAMETEREXTENT
24/03/18
S2.P03 UPDATED BOUNDARY 04/04/18
S2.P04 OUTLINE PLANNING APPLICATION ISSUE 11/04/18
S2.P05 OUTLINE PLANNING APPLICATION ISSUEREVISED
23/07/18
Cheapside
Cheapside
Kensington Street
Kensington Street
Lewis Street
Lewis Street
A3
Job Title
Client
4 Pierhead Street
Cardiff CF10 4QP
Tel +44 29 2047 3727 Fax +44 29 2047 2277
www.arup.com
Issue Date By Chkd Appd
© Arup
Job No
237035-00
Drawing No Issue
03
Approval
JFH-ARP-ZZ-XX-DR-Y-1003
Scale at A3
NTS
Suitability
Role
Civil
ParadeGardensParade
Gardens
Legend
Operational Hospital
Junction Works
Plant
Demolition & Construction Site
01 BOS23-03-2018
Issued For Approval
AW BP
Department for Infrastructure
Jersey Future Hospital
Figure 1: Overview of ProposalsPhase 1A
02 BOS10-04-2018 AW BP
Kensington Place
Kensington Place
The Parade
The Parade
Gloucester Street
Gloucester Street
St Aubins Road
St Aubins Road
Granite Block
Plant
BP03 MK18-07-2018 AW
Patriotic Street
MSCP
JerseyGeneralHospital
Block A
Direction of Traffic
Service Road
Ambulance Access
WestawayCourt
!°
Newgate Street
Newgate Street
People’sPark
People’sPark
Peirson Road
Peirson Road
The ParadeThe Parade
Union StreetUnion Street
York Street
York Street
Elizab
eth Plac
e
Elizab
eth Plac
e
Savile StreetSavile Street
Patriotic Street
Patriotic Street
Patriotic Place
Patriotic Place
Ambulance access retained
Motocycle access only
Barrier to MSCP access removed to avoid queuing on Kensington Place
MSCP access
Construction vehicles only
Proposed alteration to junction
Proposed junction improvement scheme
Residential parking on Kensington Place to be temporarily relocated (potentially to People’s Park)
Service road between JGH and Block A will removed to enable construction
Phased road closure of Kensington Place and buildouts removed to enable construction
MSCP egress relocated from Newgate Street to Patriotic Street
Proposed works to Patriotic Street MSCP including an additional half deck, improvements to core and a pedestrian link to Block A
Direction of one-way traffic reversed to enable the closure of Kensington Place. Potential for 20mph speed limit to be introduced for the duration of the closure
Plant relocated to Granite Block forecourt to enable demolition of the energy centre. Staff parking relocated to a public car park
Proposed alterations the to pedestrian refuge island to accomondate construction vehicles
Figure 7.1: Overview of ProposalsPhase 1A
Cheapside
Cheapside
Kensington Street
Kensington Street
Lewis Street
Lewis Street
A3
Job Title
Client
4 Pierhead Street
Cardiff CF10 4QP
Tel +44 29 2047 3727 Fax +44 29 2047 2277
www.arup.com
Issue Date By Chkd Appd
© Arup
Job No
237035-00
Drawing No Issue
03
Approval
Scale at A3
NTS
Suitability
Role
Civil
ParadeGardensParade
Gardens
Legend
Operational Hospital
Junction Improvements
Hospital Allocated Parking
Plant
Demolition & Construction Site
01 BOS23-03-2018
Issued For Approval
PA PT
Department for Infrastructure
Jersey Future Hospital
Figure 2: Overview of ProposalsPhase 1B
02 BOS10-04-2018 PA PTKensington Place
Kensington Place
The Parade
The Parade
Gloucester Street
Gloucester Street
St Aubin’s Road
St Aubin’s Road
Granite Block
Plant
Proposed alterations the to pedestrian refuge isalnd as per Phase 1A
Patriotic Street
MSCP
JerseyGeneralHospital
Block B(under construction)
Block A
Direction of Traffic
Service Road
Ambulance AccessWestaway
Court
!°
Newgate Street
Newgate Street
Patriotic Place
Patriotic Place
People’sPark
People’sPark
Peirson Road
Peirson Road
The ParadeThe Parade
Union StreetUnion Street
York Street
York Street
Elizab
eth Plac
e
Elizab
eth Plac
e
Savile StreetSavile Street
Patriotic Street
Patriotic Street
Motorcycle Parking
Proposed improvement scheme including the provision of a signalised pedestrian crossings on Savile Street
Public short-stay parking to be allocated for Patient Transport Services
Proposed service block with access/egress from Kensington Place
Public short-stay parking to be allocated for patient drop-off
Ambulance access retained
Two-way running of Patriotic Pace
Alterations to MSCP accesses to enable closure of Newgate Street
Pedestrian link proposed between Block A and the MSCP
Access to the rear of properties fronting Edward Place retained
MSCP accesses
Staff cycle parking relocated in to Patriotic Street MSCP
Hospital parking relocated to Patriotic Street MSCP
Phased closure of Newgate Street
Removal of three short-stay parking spaces and the relocation of three doctors parking spaces in to Patriotic Street MSCP
Proposed signalisation of Gloucester Street/ Seaton Place/Patriotic Place junction to enable two-way running of Patriotic Place. Signalised pedestrian crossings proposed as part of the temporary junction arrangement JFH-ARP-ZZ-XX-DR-Y-1004
Junction Improvement Scheme as per Phase 1A
BP03 MK18-07-2018 AW
Proposed access to the mortuary from Kensington Place
Figure 7.2: Overview of ProposalsPhase 1B
Cheapside
Cheapside
Cheapside
Kensington Street
Kensington Street
Kensington Street
Lewis Street
Lewis Street
Lewis Street
A3
Job Title
Client
4 Pierhead Street Cardiff CF10 4QP Tel +44 29 2047 3727 Fax +44 29 2047 2277www.arup.com
Issue Date By Chkd Appd
© Arup
Job No
237035-00
Drawing No Issue
03
Approval
Scale at A3
NTS
Suitability
Role
Civil
ParadeGardensParadeGardensParadeGardens
Legend
Operational Hospital
Junction ImprovementsAmbulance Only Lane
01 BOS23-03-2018
Issued For Approval
AW BP
Department for Infrastructure
Jersey Future Hospital
Figure 3: Overview of ProposalsPhase 2 Final State
JFH-ARP-ZZ-XX-DR-Y-1001
02 BOS10-04-2018 AW BP
BP
Kensington Place
Kensington Place
The Parade
The Parade
Gloucester Street
Gloucester Street
Gloucester Street
aceace
The Paraded
The Parade
Granite Block
Patriotic Street
MSCP
Block B
Block C
Block A
Direction of Traffic
Service RoadAmbulance Access
WestawayCourt
!°
Newgate Street
Newgate Street
Newgate Street
People’sPark
People’sPark
People’sPark
Peirson Road
Peirson Road
Peirson Road
The ParadeThe ParadeThe Parade
Union StreetUnion StreetUnion Street
York Street
York Street
York Street
Elizab
eth Plac
e
Elizab
eth Plac
e
Elizab
eth Plac
e
Savile StreetSavile StreetSavile Street
Patriotic Street
Patriotic Street
Patriotic Street Patriotic Place
Patriotic Place
Patriotic Place
Junction improvement scheme as per Phase 1A
Proposed improvement scheme including the provision of a pedestrian crossing as per Phase 1B
Motorcycle Parking
Block C provides the main entrance in to Jersey Future Hospital
Proposed drop-off for patients and taxis
On-street parking on The Parade removed alongside proposed improvements to public realm
Pedestrian crossing to be reinstated to previous dimensions
Staff cycle parking proposed in the basement of Block B and adjacent to the Granite Block
Proposed junction improvement scheme including a signalised pedestrian crossing
Proposed junction improvment scheme including signalised pedestrian crossings
Newgate Street proposed to be two-way running (ambulance only north-westbound)
MSCP accesses reinstated on Patriotic Street
Ambulance bay relocated to Newgate Street
Proposed extension to Newgate Street for ambulances only
Build-outs on Kensington Place reinstated
Proposed layby for Patient Transport Services
03 MK18-07-2018 AW
Figure 7.3: Overview of ProposalsPhase 2 Final State