jelena fedurko_how is ccpm differnt_10 tocpa_feb 2013_india_22 feb 2014_fin

31
10 th International Conference of the TOC Practitioners Alliance - TOCPA Copyright © 2014 by Oded Cohen & Jelena Fedurko www.tocpractice.com Feb 21-22, 2014 Noida, India 10 th International Conference of the TOC Practitioners Alliance - TOCPA www.tocpractice.com In which way CCPM is different? Jelena Fedurko TOC Strategic Solutions, Estonia 22 February, 2014

Upload: jelena-fedurko

Post on 07-Sep-2015

13 views

Category:

Documents


1 download

DESCRIPTION

Jelena Fedurko_How is CCPM differnt_10 TOCPA_Feb 2013_India_22 Feb 2014_FIN

TRANSCRIPT

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Feb 21-22, 2014 Noida, India

    10th International Conference of the

    TOC Practitioners Alliance - TOCPAwww.tocpractice.com

    In which way CCPM

    is different?

    Jelena FedurkoTOC Strategic Solutions, Estonia22 February, 2014

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Jelena has 14 years of TOC experience as atrainer and consultant providing support in TOCimplementations in the areas of peoplemanagement, production, supply chain, projectmanagement.Jelena has worked in Japan, Poland, Turkey, Italy,Russia, Ukraine, India, China, Chile, Colombia,Mexico and other countries throughout the world.Jelena is the author of the books Behind theCloud Enhancing logical thinking and ThroughClouds to Solutions. The books present newdevelopments in the area of working withassumptions, UDEs and UDE Clouds.Together with Oded Cohen Jelena has co-authored the book TOC Fundamentals, recentlypublished in Russian.She has authored numerous articles on TOCconcepts and implementation, and hascontributed to and edited several TOC books. [email protected]

    www.toc-strategicsolutions.com

    Jelena Fedurko

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Main types of constraints of a commercial system:

    Capacity Constraint a system has a resource which cannot provide capacity that

    the systems demands within the required span of time.

    Market Constraint the amount of customers orders is not sufficient to sustain the

    required growth of the system.

    Time Constraint the response time of the system to the requirement of the market

    is too long to the extent that it jeopardizes the systems ability to meet its current

    commitment to its customers as well as the ability of winning new business.

    What is the constraint of the project management?When does the system create value for the goal of making more money?

    At the completion of the project benefits are generated and money invested is

    starting to be returned! The shorter is the time to complete the project the better!

    Conclusion: Projects have the TIME constraint.

    1. The realization that every systems performance is governed by

    the constraint.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Step 1. Identify (choose) the systems constraint.

    In projects it is TIME the longest chain of dependant tasks.

    The dependency is not only logical but also resource dependency.

    Step 2. Decide how to exploit the systems constraint.

    In projects it done through planning of the acceptable and realistic

    duration of the project to bring financial benefits.

    Step 3. Subordinate everything else to the above decision.

    Ensuring that the plan is

    realistic

    absorbs inevitable fluctuations in the execution phase, and

    protected against disruptions.

    WE DO NOT REPLAN!!

    2. Following 5 Focusing Steps of TOC.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Step 4. Elevate the systems constraint.

    Making more projects with the same resources in the same

    period of time.

    Step 5. If the constraint is broken go back to step one but do

    not allow Inertia to cause the systems constraint. Ensuring that the system will NOT create

    Capacity constraint

    Market constraint

    Cash constraint (a Capacity constraint type)

    2. Following 5 Focusing Steps of TOC.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Current and harmful practice

    We have seen project plans that include over a thousand tasks with durations

    from 2 hours to several weeks.

    One director of a big construction company once boasted that every project

    manager in their company must follow in detail and make decisions for up to

    SEVENTY open tasks on several construction sites EVERY DAY including daily

    personal visits to several sites.

    What is the quality of detailed following and making decisions in this case?

    How many minutes can be spent for each one of 70 open tasks? On average it

    makes reviewing 9 open tasks an hour less than 7 minutes per task. It is if the

    project manager sits in his office and just opens the files. What about the time

    that is needed to visit the construction site and physically move from the area of

    one task to another?

    TOC Rule not more than 300-400 tasks even in a very big project.

    3. Having manageable number of tasks in the plan.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Current and harmful practice Top managements appoints the best expert in the subject of the project to be the

    project manager to ensure that s/he will be able to understand every task in order to

    better oversee it.

    TOC Rule Project Manager is responsible for maintaining and speeding up the FLOW of

    tasks from resource to resource.

    The responsibility of understanding every task and ensuring that it is performed by the

    qualified resource and the content and way of working on it are appropriate is the

    responsibility of the Resource Manager. OR

    A top manager of a VERY high level of authority Vice President for Operations/

    Director of Product Development/ Creative Director, etc. is officially appointed as the

    Project Manager for an important project.

    TOC Recommendation such highly positioned top managers could be Program Directors

    but should NOT be given the role of Project Managers.

    4. The Project Manager is a MANAGER, NOT an Expert in the subject

    matter of tasks, and not a Vice President.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    5. The project plan MUST have FIXED START DATE AND FIXED

    COMPLETION DATE aggressive but realistic.

    The PRIME objective of CCPM and the Prime Measurement for projects

    completing project ON TIME.

    Why?

    The project brings benefits only AFTER completion.

    Having fixed start date and project completion due date is also a technical

    requirement for the CCPM mechanics to work.

    This raises a frequent question WHAT IS THE END OF MY PROJECT?

    Especially if the project is treated by a company as an Investment project

    - New equipment

    - New production facility

    - New technology

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    5. The project plan MUST have FIXED START DATE AND FIXED

    COMPLETION DATE aggressive but realistic

    WHEN IS THE END OF MY PROJECT?

    Purchasing new equipment (especially dedicated for a specific

    type of product food industry) what is the project end?

    When the equipment is installed and produced the first batch?

    When the equipment moved to mass production?

    When the product for which this equipment was bought has

    finished its market life cycle?

    Building a new commercial facility what is the project end?

    When the construction is completed?

    When all premises are sublet to tenants?

    Another frequent question: Shouldnt the end of the project be

    tied to the return on investment?

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    5. The project plan MUST have FIXED START DATE AND FIXED

    COMPLETION DATE aggressive but realistic

    And there is also another frequent question:

    WHAT IS THE START OF MY PROJECT?

    Is the starting point a decision to investigate an idea?

    Is the starting point planning?

    Is the stating point the start of the first task (start of the

    execution)?

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    W16

    B10 M16

    C20

    G10

    M12

    FinishLetter andColour = Resource

    6. The project plan is built ONLY with the relationship Finish to Start.

    The end of each task has a tangible deliverable without which

    the next task CANNOT START.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    6. The project plan is built ONLY with the relationship Finish to Start.

    Why is there the requirement Finish to Start?

    To allow for the mechanics of PROJECTING the behaviour of the

    chain in the execution phase to work.

    28d

    T2-10d T3-16d

    T6-20d

    T1-10dBUFFER 50% of the chain

    28d

    T2-10d T3-16d

    T6-20d

    T1-17d

    BUFFER IS NOT A CUSHION

    BUT MANAGEMENT

    MECHANISM!

    Task 1 started and in Day 3 the resource reports that the task faces a difficulty and it will

    take not 7 days to complete, but 14.

    The chain went into the buffer for 7 days

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    To allow for the mechanics of PROJECTING the behaviour of the chain in the execution phase to work.

    28d

    T2-10d T3-16d

    T6-20d

    T1-17d

    Day 3: Task 1 started and in Day 3 the resource reports that the task faces a difficulty and it will take not

    7 days to complete, but 14. New estimated total task duration is: 3 days (passed) +14 days (projected)

    =17 days new estimated total duration of Task1. Estimated duration in the project plan was 10 days.

    The chain went

    into the buffer

    for 7 days

    28d

    T2-10d T3-16d

    T6-20d

    T1-12dThe chain moved

    backwards and

    now is only 2 days

    in the buffer

    Day 6: After the recovery actions on Task 1 the task resource reports that now it will take 6 days

    more to complete: 6 days passed+6 days more = total 12 days (instead of estimated 10).

    Amount of work in days increased protection decreased

    We decreased the amount of work and increased protection

    In which way CCPM is different?

    6. The project plan is built ONLY with the relationship Finish to Start.

    Why is there the requirement Finish to Start?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Why is the TOC projection mechanism not going to be helpful for managing the

    project if the connection is anything different from Finish to Start?

    Construction 6 months

    Supply 4 months

    6. The project plan is built ONLY with the relationship Finish to Start.

    Construction 6 months

    Supply 4.5 months

    Increase in Task Supply is 2 weeks. So

    what? How does this increase in

    duration reflect on the START of Task

    Construction?

    And how often is it discovered that there is delay in supply only WHEN Construction

    actually cannot start because the materials are LATE?

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Construction 6 months

    Supply 4 months

    We may hear an argument: it is enough if the supplier ships us of the materials

    that we may start the Task Construction. Then the relationship is like that:

    Construction 6 months

    Supply

    the rest - 3 months

    Supply

    first 1/4 mater.

    - 1 month

    If the 1/4 of

    materials come

    with the 2 week

    delay:

    Construction 6 months

    Supply

    the rest - 3 months

    Supply

    first 1/4 mater.

    - 1 month

    Or supply can still finish

    within the initial

    estimation

    In which way CCPM is different?

    6. The project plan is built ONLY with the relationship Finish to Start.

    Why is there the requirement Finish to Start?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    7. For every task in the project plan we put the estimation of task

    duration that has ONLY 50% probability to be completed within the

    estimated time or earlier.

    Bad multitasking Students syndrome Parkinsons Law

    Tasks contain a lot of safety! Why? Because of the behaviour of managers: in the planning phase managers ask for estimations,in execution they treat estimations as justified commitments.

    Natural behaviour of people to protect themselves by putting safety into the estimation.

    What impacts conventional estimations of task duration?P

    r

    o

    b

    a

    b

    i

    l

    i

    t

    y

    o

    f

    c

    o

    m

    p

    l

    e

    t

    i

    o

    n

    50% 80% TimeDurations of estimations with 80% and more probability to be met

    are twice longer than durations with 50% probability to be met.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Letters Project Numbers Project Shapes ProjectA 1

    B 2 C 3 D 4

    E 5 F 6 G 7 H 8 I 9 J 10

    In which way CCPM is different?

    7. For every task in the project plan we put the estimation of task

    duration that has ONLY 50% probability to be completed within the

    estimated time or earlier.

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Estimation times Impact of Multitasking

    Duration of Project

    Letters

    Duration of Project

    Numbers

    Duration of Project

    Shapes

    Duration of Project

    Letters

    Duration of Project

    Numbers

    Duration of

    Project

    Shapes

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    Critical Chain sorts out the resource contention it takes into

    consideration both logical AND resource dependency.

    W16

    B10 M16C20

    G10

    M12

    Finish

    64 days

    Critical Chain

    W16

    B10 M16

    C20

    G10

    M12

    FinishLetter andColour = Resource

    Critical Path Promise = 56 days

    M16 - Resource contention!

    How realistic is this plan?

    What if the plan had 500 tasks, or even 150 tasks? Could one easily see the

    resource overlap?

    8. The project plan is built based on understanding that the

    Constraint in Projects is the Duration of the longest chain.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    1- Build the project network

    Now the projected completion date of the longest chain is 20.08.2013

    BUT we have resource contention

    8. The project plan is built based on understanding that the

    Constraint in Projects is the Duration of the longest chain.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    2- Level the resources remove resource contention

    The projected completion date of the longest chain moved to 17.09.2013 REALISTIC!

    8. The project plan is built based on understanding that the

    Constraint in Projects is the Duration of the longest chain.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    8. The project plan is built based on understanding that the

    Constraint in Projects is the Duration of the longest chain.

    3 Identify Critical Chain and build resource dependencies

    The projected completion date of the longest chain did not change 17.09.2013

    New dependencies RESOURCE dependencies are inserted.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    9. The individual safety is removed from each task (due to putting in the plan 50% probability estimations) and accumulated in buffers for common CONTROLLED use.

    The projected completion date of the Critical Chain moved to 23.09.2013,

    the realistic and PROTECTED projected end of the project is 02.12.2013

    The buffers protect the Critical Chain from the fluctuations in task durations in the

    execution phase. Project Buffer is added to the end of the Critical Chain, and Feeding

    buffers at the end of each Feeder in the point where the Feeder flows into the

    Critical Chain.

    The TOC Rule the size of the buffer is 50% of the chain at the end of which it is put.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    BUFFERS A frequent reservation that we hear: But Buffers make the duration of the project 50% longer!! VERY WRONG! Compare:

    With 50% durations and buffers the projected completion date for the project is 02.12.2013.

    With 80% durations the projected completion date for the project is 05.02.2014.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    10. CCPM does NOT work on the principle of TASK DUE DATE!

    CCPM works on the principle of Roadrunner- every resource

    finishes the task as soon as possible and passes it to the next

    resource that will be informed in time and will be waiting.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    11. Tasks performers report NOT How Much They Have Completed

    (this is looking backwards) but HOW MANY MORE DAYS IS LEFT

    FOR THEM TO COMPLETE THE TASK according to their fresh

    estimation. This is looking forward!

    TOC

    TODAYTHE PAST THE FUTURE

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    12. DAILY projection of the penetration into the buffers gives early warning that allows to take corrective actions that are not overly expensive and return the project back on its track.

    In the execution phase every day each resource gives the Project

    Manager the estimation HOW MANY DAYS ARE LEFT TO COMPLETE

    THE TASK.

    This data is entered into the system and the system calculates the

    projected penetration to the buffers.

    The projection works on the principle of a train on the rail

    moving forward and backward in time.

    Forward consuming the days from the buffer, Backward

    returning the days in the buffer.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    12. DAILY projection of the penetration into the buffers gives early warning that allows to take corrective actions that are not overly expensive and return the project back on its track.

    Today is 20 May, the resource performing Task C1 (that was supposed to be finished 06 May)

    reports that he still needs 15 days to complete.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    12. DAILY projection of the penetration into the buffers gives early warning that allows to take corrective actions that are not overly expensive and return the project back on its track.

    Today is 21 May, during the day corrective actions were taken (e.g. expert assistance or adding resources ), and by the end of the day he reports that now he needs 2 days to complete.

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    12. DAILY projection of the penetration into the buffers gives early warning that allows to take corrective actions that are not overly expensive and return the project back on its track.

    % Longest Chain Complete

    %

    B

    u

    f

    f

    e

    r

    C

    o

    n

    s

    u

    m

    e

    d

    100%Buffer penetration Report

    In which way CCPM is different?

  • 10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko

    www.tocpractice.com

    13. Gives the top management quick, comprehensive and clearly visualized way of the project portfolio status.

    In which way CCPM is different?

    Each dot is a project.