jelena fedurko_how is ccpm differnt_10 tocpa_feb 2013_india_22 feb 2014_fin
DESCRIPTION
Jelena Fedurko_How is CCPM differnt_10 TOCPA_Feb 2013_India_22 Feb 2014_FINTRANSCRIPT
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Feb 21-22, 2014 Noida, India
10th International Conference of the
TOC Practitioners Alliance - TOCPAwww.tocpractice.com
In which way CCPM
is different?
Jelena FedurkoTOC Strategic Solutions, Estonia22 February, 2014
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Jelena has 14 years of TOC experience as atrainer and consultant providing support in TOCimplementations in the areas of peoplemanagement, production, supply chain, projectmanagement.Jelena has worked in Japan, Poland, Turkey, Italy,Russia, Ukraine, India, China, Chile, Colombia,Mexico and other countries throughout the world.Jelena is the author of the books Behind theCloud Enhancing logical thinking and ThroughClouds to Solutions. The books present newdevelopments in the area of working withassumptions, UDEs and UDE Clouds.Together with Oded Cohen Jelena has co-authored the book TOC Fundamentals, recentlypublished in Russian.She has authored numerous articles on TOCconcepts and implementation, and hascontributed to and edited several TOC books. [email protected]
www.toc-strategicsolutions.com
Jelena Fedurko
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Main types of constraints of a commercial system:
Capacity Constraint a system has a resource which cannot provide capacity that
the systems demands within the required span of time.
Market Constraint the amount of customers orders is not sufficient to sustain the
required growth of the system.
Time Constraint the response time of the system to the requirement of the market
is too long to the extent that it jeopardizes the systems ability to meet its current
commitment to its customers as well as the ability of winning new business.
What is the constraint of the project management?When does the system create value for the goal of making more money?
At the completion of the project benefits are generated and money invested is
starting to be returned! The shorter is the time to complete the project the better!
Conclusion: Projects have the TIME constraint.
1. The realization that every systems performance is governed by
the constraint.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Step 1. Identify (choose) the systems constraint.
In projects it is TIME the longest chain of dependant tasks.
The dependency is not only logical but also resource dependency.
Step 2. Decide how to exploit the systems constraint.
In projects it done through planning of the acceptable and realistic
duration of the project to bring financial benefits.
Step 3. Subordinate everything else to the above decision.
Ensuring that the plan is
realistic
absorbs inevitable fluctuations in the execution phase, and
protected against disruptions.
WE DO NOT REPLAN!!
2. Following 5 Focusing Steps of TOC.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Step 4. Elevate the systems constraint.
Making more projects with the same resources in the same
period of time.
Step 5. If the constraint is broken go back to step one but do
not allow Inertia to cause the systems constraint. Ensuring that the system will NOT create
Capacity constraint
Market constraint
Cash constraint (a Capacity constraint type)
2. Following 5 Focusing Steps of TOC.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Current and harmful practice
We have seen project plans that include over a thousand tasks with durations
from 2 hours to several weeks.
One director of a big construction company once boasted that every project
manager in their company must follow in detail and make decisions for up to
SEVENTY open tasks on several construction sites EVERY DAY including daily
personal visits to several sites.
What is the quality of detailed following and making decisions in this case?
How many minutes can be spent for each one of 70 open tasks? On average it
makes reviewing 9 open tasks an hour less than 7 minutes per task. It is if the
project manager sits in his office and just opens the files. What about the time
that is needed to visit the construction site and physically move from the area of
one task to another?
TOC Rule not more than 300-400 tasks even in a very big project.
3. Having manageable number of tasks in the plan.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Current and harmful practice Top managements appoints the best expert in the subject of the project to be the
project manager to ensure that s/he will be able to understand every task in order to
better oversee it.
TOC Rule Project Manager is responsible for maintaining and speeding up the FLOW of
tasks from resource to resource.
The responsibility of understanding every task and ensuring that it is performed by the
qualified resource and the content and way of working on it are appropriate is the
responsibility of the Resource Manager. OR
A top manager of a VERY high level of authority Vice President for Operations/
Director of Product Development/ Creative Director, etc. is officially appointed as the
Project Manager for an important project.
TOC Recommendation such highly positioned top managers could be Program Directors
but should NOT be given the role of Project Managers.
4. The Project Manager is a MANAGER, NOT an Expert in the subject
matter of tasks, and not a Vice President.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
5. The project plan MUST have FIXED START DATE AND FIXED
COMPLETION DATE aggressive but realistic.
The PRIME objective of CCPM and the Prime Measurement for projects
completing project ON TIME.
Why?
The project brings benefits only AFTER completion.
Having fixed start date and project completion due date is also a technical
requirement for the CCPM mechanics to work.
This raises a frequent question WHAT IS THE END OF MY PROJECT?
Especially if the project is treated by a company as an Investment project
- New equipment
- New production facility
- New technology
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
5. The project plan MUST have FIXED START DATE AND FIXED
COMPLETION DATE aggressive but realistic
WHEN IS THE END OF MY PROJECT?
Purchasing new equipment (especially dedicated for a specific
type of product food industry) what is the project end?
When the equipment is installed and produced the first batch?
When the equipment moved to mass production?
When the product for which this equipment was bought has
finished its market life cycle?
Building a new commercial facility what is the project end?
When the construction is completed?
When all premises are sublet to tenants?
Another frequent question: Shouldnt the end of the project be
tied to the return on investment?
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
5. The project plan MUST have FIXED START DATE AND FIXED
COMPLETION DATE aggressive but realistic
And there is also another frequent question:
WHAT IS THE START OF MY PROJECT?
Is the starting point a decision to investigate an idea?
Is the starting point planning?
Is the stating point the start of the first task (start of the
execution)?
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
W16
B10 M16
C20
G10
M12
FinishLetter andColour = Resource
6. The project plan is built ONLY with the relationship Finish to Start.
The end of each task has a tangible deliverable without which
the next task CANNOT START.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
6. The project plan is built ONLY with the relationship Finish to Start.
Why is there the requirement Finish to Start?
To allow for the mechanics of PROJECTING the behaviour of the
chain in the execution phase to work.
28d
T2-10d T3-16d
T6-20d
T1-10dBUFFER 50% of the chain
28d
T2-10d T3-16d
T6-20d
T1-17d
BUFFER IS NOT A CUSHION
BUT MANAGEMENT
MECHANISM!
Task 1 started and in Day 3 the resource reports that the task faces a difficulty and it will
take not 7 days to complete, but 14.
The chain went into the buffer for 7 days
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
To allow for the mechanics of PROJECTING the behaviour of the chain in the execution phase to work.
28d
T2-10d T3-16d
T6-20d
T1-17d
Day 3: Task 1 started and in Day 3 the resource reports that the task faces a difficulty and it will take not
7 days to complete, but 14. New estimated total task duration is: 3 days (passed) +14 days (projected)
=17 days new estimated total duration of Task1. Estimated duration in the project plan was 10 days.
The chain went
into the buffer
for 7 days
28d
T2-10d T3-16d
T6-20d
T1-12dThe chain moved
backwards and
now is only 2 days
in the buffer
Day 6: After the recovery actions on Task 1 the task resource reports that now it will take 6 days
more to complete: 6 days passed+6 days more = total 12 days (instead of estimated 10).
Amount of work in days increased protection decreased
We decreased the amount of work and increased protection
In which way CCPM is different?
6. The project plan is built ONLY with the relationship Finish to Start.
Why is there the requirement Finish to Start?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Why is the TOC projection mechanism not going to be helpful for managing the
project if the connection is anything different from Finish to Start?
Construction 6 months
Supply 4 months
6. The project plan is built ONLY with the relationship Finish to Start.
Construction 6 months
Supply 4.5 months
Increase in Task Supply is 2 weeks. So
what? How does this increase in
duration reflect on the START of Task
Construction?
And how often is it discovered that there is delay in supply only WHEN Construction
actually cannot start because the materials are LATE?
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Construction 6 months
Supply 4 months
We may hear an argument: it is enough if the supplier ships us of the materials
that we may start the Task Construction. Then the relationship is like that:
Construction 6 months
Supply
the rest - 3 months
Supply
first 1/4 mater.
- 1 month
If the 1/4 of
materials come
with the 2 week
delay:
Construction 6 months
Supply
the rest - 3 months
Supply
first 1/4 mater.
- 1 month
Or supply can still finish
within the initial
estimation
In which way CCPM is different?
6. The project plan is built ONLY with the relationship Finish to Start.
Why is there the requirement Finish to Start?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
7. For every task in the project plan we put the estimation of task
duration that has ONLY 50% probability to be completed within the
estimated time or earlier.
Bad multitasking Students syndrome Parkinsons Law
Tasks contain a lot of safety! Why? Because of the behaviour of managers: in the planning phase managers ask for estimations,in execution they treat estimations as justified commitments.
Natural behaviour of people to protect themselves by putting safety into the estimation.
What impacts conventional estimations of task duration?P
r
o
b
a
b
i
l
i
t
y
o
f
c
o
m
p
l
e
t
i
o
n
50% 80% TimeDurations of estimations with 80% and more probability to be met
are twice longer than durations with 50% probability to be met.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Letters Project Numbers Project Shapes ProjectA 1
B 2 C 3 D 4
E 5 F 6 G 7 H 8 I 9 J 10
In which way CCPM is different?
7. For every task in the project plan we put the estimation of task
duration that has ONLY 50% probability to be completed within the
estimated time or earlier.
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Estimation times Impact of Multitasking
Duration of Project
Letters
Duration of Project
Numbers
Duration of Project
Shapes
Duration of Project
Letters
Duration of Project
Numbers
Duration of
Project
Shapes
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
Critical Chain sorts out the resource contention it takes into
consideration both logical AND resource dependency.
W16
B10 M16C20
G10
M12
Finish
64 days
Critical Chain
W16
B10 M16
C20
G10
M12
FinishLetter andColour = Resource
Critical Path Promise = 56 days
M16 - Resource contention!
How realistic is this plan?
What if the plan had 500 tasks, or even 150 tasks? Could one easily see the
resource overlap?
8. The project plan is built based on understanding that the
Constraint in Projects is the Duration of the longest chain.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
1- Build the project network
Now the projected completion date of the longest chain is 20.08.2013
BUT we have resource contention
8. The project plan is built based on understanding that the
Constraint in Projects is the Duration of the longest chain.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
2- Level the resources remove resource contention
The projected completion date of the longest chain moved to 17.09.2013 REALISTIC!
8. The project plan is built based on understanding that the
Constraint in Projects is the Duration of the longest chain.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
8. The project plan is built based on understanding that the
Constraint in Projects is the Duration of the longest chain.
3 Identify Critical Chain and build resource dependencies
The projected completion date of the longest chain did not change 17.09.2013
New dependencies RESOURCE dependencies are inserted.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
9. The individual safety is removed from each task (due to putting in the plan 50% probability estimations) and accumulated in buffers for common CONTROLLED use.
The projected completion date of the Critical Chain moved to 23.09.2013,
the realistic and PROTECTED projected end of the project is 02.12.2013
The buffers protect the Critical Chain from the fluctuations in task durations in the
execution phase. Project Buffer is added to the end of the Critical Chain, and Feeding
buffers at the end of each Feeder in the point where the Feeder flows into the
Critical Chain.
The TOC Rule the size of the buffer is 50% of the chain at the end of which it is put.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
BUFFERS A frequent reservation that we hear: But Buffers make the duration of the project 50% longer!! VERY WRONG! Compare:
With 50% durations and buffers the projected completion date for the project is 02.12.2013.
With 80% durations the projected completion date for the project is 05.02.2014.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
10. CCPM does NOT work on the principle of TASK DUE DATE!
CCPM works on the principle of Roadrunner- every resource
finishes the task as soon as possible and passes it to the next
resource that will be informed in time and will be waiting.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
11. Tasks performers report NOT How Much They Have Completed
(this is looking backwards) but HOW MANY MORE DAYS IS LEFT
FOR THEM TO COMPLETE THE TASK according to their fresh
estimation. This is looking forward!
TOC
TODAYTHE PAST THE FUTURE
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
12. DAILY projection of the penetration into the buffers gives early warning that allows to take corrective actions that are not overly expensive and return the project back on its track.
In the execution phase every day each resource gives the Project
Manager the estimation HOW MANY DAYS ARE LEFT TO COMPLETE
THE TASK.
This data is entered into the system and the system calculates the
projected penetration to the buffers.
The projection works on the principle of a train on the rail
moving forward and backward in time.
Forward consuming the days from the buffer, Backward
returning the days in the buffer.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
12. DAILY projection of the penetration into the buffers gives early warning that allows to take corrective actions that are not overly expensive and return the project back on its track.
Today is 20 May, the resource performing Task C1 (that was supposed to be finished 06 May)
reports that he still needs 15 days to complete.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
12. DAILY projection of the penetration into the buffers gives early warning that allows to take corrective actions that are not overly expensive and return the project back on its track.
Today is 21 May, during the day corrective actions were taken (e.g. expert assistance or adding resources ), and by the end of the day he reports that now he needs 2 days to complete.
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
12. DAILY projection of the penetration into the buffers gives early warning that allows to take corrective actions that are not overly expensive and return the project back on its track.
% Longest Chain Complete
%
B
u
f
f
e
r
C
o
n
s
u
m
e
d
100%Buffer penetration Report
In which way CCPM is different?
-
10th International Conference of the TOC Practitioners Alliance - TOCPACopyright 2014 by Oded Cohen & Jelena Fedurko
www.tocpractice.com
13. Gives the top management quick, comprehensive and clearly visualized way of the project portfolio status.
In which way CCPM is different?
Each dot is a project.