jeff king northwest power and conservation council portland, or july 17, 2008
DESCRIPTION
Sixth Northwest Conservation & Electric Power Plan Proposed Aeroderivative Combustion Turbine Planning Assumptions. Jeff King Northwest Power and Conservation Council Portland, OR July 17, 2008. Reference plant. - PowerPoint PPT PresentationTRANSCRIPT
Sixth Northwest Conservation & Electric Power Plan
Proposed Aeroderivative Combustion Turbine Planning
AssumptionsJeff King
Northwest Power and Conservation CouncilPortland, OR
July 17, 2008
July 17, 2008 2Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Reference plant Twin 47 MW (nominal) natural gas-fired gas turbine
generators and ancillary equipment, control building and switchyard. Inlet air evaporative cooling. Dry low-emission combustors and SCR for NOx control and CO oxidizing catalyst for CO and VOC control. Located in utility service territory near load center. Characteristics generally based on GE LM6000PD Sprint.
July 17, 2008 3Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Aeroderivative GT applications:
Energy generation Cogeneration (requires heat recovery & integration equipment) Regulating reserve (requires AGC) Load-following (requires AGC) Spinning reserve (requires AGC) Non-spinning reserve Replacement reserve Voltage control (VAR support) (requires clutch) Black start (requires auxilliary diesel generator) Local emergency service
Status: Commercially mature
July 17, 2008 4Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Aeroderivative GT operating characteristics I
5th Plan Proposed
Base rating (net ISO MW, lifecycle average)
2 units @ 46 MW/unit
2 units @ 45 MW/unit
ISO rating less 2% plant losses, less 2%
degradation
Rating at reference PNW locations
PNW Westside (200’)
PNW Eastside (700’)
S. ID (3000’)
E. MT (5500’)
0.99
0.97
0.90
0.82
Minimum load (% rated power) 25% Same
Ramp rate (%/hr) >100% Same Cold start to min. load < 10 min
Minimum run time (hr) 1 hour < 1 hr
Minimum down time (hr) 1 hour < 1 hr
July 17, 2008 5Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Aeroderivative GT operating characteristics II
5th Plan Proposed
Scheduled outage factor 3.6% (10 days/yr ave)
Same GE maintenance schedule: Annual – 7 d 6 yr Hot gas path – 10 d 12 yr Major - 28 d
Equivalent forced outage rate 3.6%/10% ?? NERA is 3.7%. Review GADS
Mean time between failures -- 528 hr GADS GT value ca: 2004. Will review GADS
Mean time to repair 80 hours Same GADS GT value ca: 2004. Will review GADS
Heat rate (HHV, full load, lifecycle ave)
9960 Btu/kWh Same 1% degradation during hot gas path maintenance
interval; 50% retoration; 100 % restoration at Major
Vintage heat rate improvement - 0.5%/yr average Same 5% learning rate
Service life 30 years Same
July 17, 2008 6Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Aeroderivative GT costs (2006 dollar values)
5th Plan Proposed
Overnight construction cost $700/kW $860/kW 2008 NTP/2009 service
Vintage capital cost escalation -0.5%/yr See subsequent slides
Non-fuel Fixed O&M $9.30/kW/yr GRAC discussion
Exclusive of property taxes & insurance
Non-fuel Variable O&M $9.30/MWh GRAC discussion
Startup Cost -- Fuel for 10 min operation at min
load
110 MMBtu/start, w/SCR (NERA)
Shutdown Cost -- Fuel for 5 min operation at min
load
Transmission Cost None Same Assumed load center location
Transmission Losses None Same Assumed load center location
July 17, 2008 7Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Aeroderivative GT construction cost analysis• NPCC database contains reported construction cost for 17
WECC plants comprising 54 units, 2002-08
• Purged plants w/more than four units.
• Purged SF & SCE peakers.
• Remaining: 9 plants, 1 - 4 units ea., 22 units total
• Normalize capital costs using MICROFINAssume cost is vintaged as of beginning of construction (YOL - 1)
2006 dollar values
"Overnight" construction + development cost
Nominal ISO capacity
• Unit (capacity) -weighted (we need an average cost value for a potential mix of plant configurations)
July 17, 2008 8Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Normalized aeroderivative GT costProposed 2008 cost: $860/kW
"Overnight", 2006$, 2009 service
R2 = 0.2749
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
2002 2003 2004 2005 2006 2007 2008 2009
Cost Estimate Vintage
Cap
ital
Co
st 2
006$
/kW
Unit (capacity) weighted
Poly. (Unit (capacity) weighted)
July 17, 2008 9Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Our preliminary thinking on forecast construction cost escalation
0
200
400
600
800
1000
1200
1400
2005 2010 2015 2020 2025 2030
Vintage of construction contract (YOL-1)
Over
nig
ht
con
stru
ctio
n c
ost
(2
006$
/kW
)Escalation continues at declining rate through 2009; levels off 2010 - 11
Real costs decline to ~ 130% of 2004 values 2012 - 15
Recent cost escalation
2015 > Resumption of historical real cost reduction
July 17, 2008 10Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Schedule, Cash Flows & Option phases
Portfolio Risk model development phases >
Development “Optional” Construction
“Committed Construction”
Milestones Feasibility study through completion
of permitting
Notice to proceed to major equipment
foundations complete
Accept major equipment to commercial operation
Time to complete 18 mo 12 mo (3) 6 mo
Cash expended 2 % 93 % 5 %
Cost to suspend ($/kW) Negligible --
Cost to hold ($/kW/yr) $ 1.16 ($95,000/yr) --
Maximum hold time 60 mo 60 mo --
Cost of termination following suspension ($/kW)
Negligible --
Cost of immediate termination ($/kW)
Negligible --
July 17, 2008 11Northwest
Power andConservation
Council
NorthwestPower andConservation
Council
Environmental5th Plan Proposed
Particulates 0.09 T/GWh Values from recent permit?
NPCC does not use & few if any requests
SO2 0.09 T/GWh '' NPCC does not use & few if any requests
NOx 0.009 - 0.01 T/GWh
'' NPCC does not use & few if any requests
CO 0.09 - 0.11 T/GWh
'' NPCC does not use & few if any requests
Hydrocarbons/VOC 0.08 T/GWh '' NPCC does not use & few if any requests
CO2 – Embedded -- ???
CO2 – Direct operation 582 T/GWh Same 117 lb CO2/MMBtu NG
CO2 – Indirect operation -- ???