Mr. Yoshihiro ITOH Chief Officer
International Projects Dept.
New Energy and Industrial Technology Development Organization (NEDO)
1. Japan’s New and Renewable Energy Targets
2. Policies for Development and Introduction of NRETs
3. RPS-Background, Outline, Explanation
4. ‘Biomass Nippon Strategy’
5. NEDO’s Role in Japan’s New Energy Scheme
6. Measures to Overcome Grid-Connection Obstacles
2
OutlineOutline
-19,100
(about 3%)-
6,900
(about 1.2%)New Energy Total
(Ratio of total primary energy supply)
-580-44Unused Energy (Including Cooling by Snow & Ice)
-4,940-4,460Black Liquor, Waste Wood, etc.
-670--Biomass Thermal
3303407148Biomass Generation
-140-45Waste Thermal
4,1705,5201,1101,250Waste Power
3,0001,340312127Wind Power
-4,390-820Solar Thermal
4,8201,180452110Photovoltaic (Solar Power)
MW1,000 x klMW1,000 x kl
Installed Cap.Oil Equiv.Installed Cap.Oil Equiv.
FY 2010 Target on New Energy Introduction (Revised)
FY 200 1 Results
Energy Sources
Total primary energy supply (in million kl)
588 Mkl -about 602 Mk
l-
1. Japan’s New and Renewable Energy Targets1. Japan’s New and Renewable Energy Targets
3
(Budget for FY2003: about \43.4 billion US$347 million)≒
• Fundamental investigation• Development for practical application
(Budget for FY2003:
about \18.8 billion US$150 million)≒• Field test• Demonstrative research
(Budget for FY2003: about \94.6 billion US$757 million)≒
• Creation of initial demand for inducing market independency• Creation of environment suitable for introducing leading-edge new energy systems• Financial support (Tax system, Fiscal investment and Loans)• The Green Purchase Law• Enlightenment and public information activities• New market development mechanism ~ RPS (Renewable Portfolio Standard) ←Additional Measure
Ⅰ . Technological Development Ⅱ . Demonstrative Testing
Ⅲ. Introduction Promotion (full utilization of market mechanism)
(in million US$)
1,5681,4491,105925875748Budget (in 100 million \)
FY2003FY2002FY2001FY2000FY1999FY1998Fiscal year
598 700 740 884 1,159 1,254※US$1 = \125
※
2. Policies for Development and Introduction of NRETs2. Policies for Development and Introduction of NRETs
4
3-1. Background on the Introduction of RPS3-1. Background on the Introduction of RPS
Japanese government decided to introduce a new measure making use of the market mechanism -Renewable Portfolio Standard (RPS)-.
• Difficulty in achieving the new 2010 target with only current measures.
• To promote power generation by renewable energy, legislation in US, Europe, etc., had already been introduced/enacted for various systems.
Establishment of the Law Concerning the Use of New Energy by Electric Utilities (June 2002)
Necessity of studying the introduction of a new system adapted for Japan.
- Certain effectiveness of new measure- Wide choice of sources for electric power company- Incentive for cost reduction- Maintenance of free competition in the energy market - Effect of financial burden on government, etc.
【 Considerations 】
Background
Conclusion
5
3-2. System Outline--Law Concerning the Use of New E3-2. System Outline--Law Concerning the Use of New Energy by Electric Utilitiesnergy by Electric Utilities
National Government
New Energy Generator Electricity Retailer (A)
(certificate trading)
Electricity Retailer (B)
Requiring use of a certain amount of electricity by New Energy
Accreditation of facilities for New Energy power generation
Electricity supply
Consumers
Electricity supplyby New Energy
FY 2003 2004 2005 2006 2007 2008 2009 2010
TWh 7.32 7.66 8.00 8.34 8.67 9.27 10.33 12.20
The target for 2010 is 12.2 TWh, which would comprise 1.35% of national electric supply.
SolarWind Biomass Small/Medium Hydro (to 1 MW)Geothermal
Dec. 2002 Apr. 2003
6
3-3. Basic Explanation of the RPS System3-3. Basic Explanation of the RPS System
The national government obliges each electric power company to use a certain amount of electricity arising from New Energy, according to its sales of electricity.
An electric power company can select the most advantageous way among the following to carry out its obligation;
a) generating by oneself
b) purchasing from others
c) causing other electric company to subrogate the obligation
The national government verifies electric power companies’ use of electricity arising from New Energy each fiscal year.
7
4-1. Biomass Nippon Strategy4-1. Biomass Nippon Strategy
8
Background1. Prevention of Global Warming
--carbon-neutral energy source; mitigate CO2 emissions--
2. Creation of a ‘Recycling-Oriented Society’ --more effective use of finite resources--
3. Fostering of New and Competitive Strategic Industries --trailblazing business model to revive industrial competitiveness--
4. Activation of Agriculture, Forestry, Fishery Industries and the Associated Rural Communities --effective use of abundant biomass in farm villages--
[http://www.maff.go.jp/biomass/eng/biomass_honbun.htm]
4-2. Biomass Nippon Strategy4-2. Biomass Nippon Strategy
9
Specific Targets
Recycling-Oriented Society(based on regional factors)
Biomass Production
Biomass Collection
Biomass Transformation
Biomass Utilization
National perception Global approach
4-3. Biomass Nippon Strategy4-3. Biomass Nippon Strategy
10
GOALS1) Evolutionary Direction
Today—Waste Biomassca. 2010—Unused Biomassca. 2020—Energy Cropsca. 2050—New Crops
2) Developmental DirectionConstruction of a Biomass RefineryCascaded Utilization of Biomass
Specific goals to be established, e.g. energy conversion efficiency, cost target of process equipment/systems, clear target level of biomass utilization….
4-4. Biomass Nippon Strategy4-4. Biomass Nippon Strategy
11
Promotion of Biomass Utilization Establishment of: Biomass Information Headquarters (infor
mation clearinghouse) and ‘Biomass Nippon Comprehensive Strategy Promotion Council’
Study of new legislation
R&D for designing a social system in which efficient utilization of biomass is encouraged; demonstrative testing
Comprehensive package of measures in model communities under a coordinated program headed by relevant government offices
Evaluation of possible merits and demerits to establishing new competitive conditions for biodiesel fuels
4-5. Biomass Nippon Strategy4-5. Biomass Nippon Strategy
12
Production-Collection-Transport Formulation of an efficient collection/transportation system
Exploration of possible means to expand the boundaries of the recycling qualification of waste biomass which shall meet certain requirements; e.g. the biomass should not decompose so easily
To produce biomass efficiently by utilizing special zones for structural reform
4-6. Biomass Nippon Strategy4-6. Biomass Nippon Strategy
Conversion Development/promotion of conversion technologies
Support of the establishment of a ‘model facility’
Exploration of means to simplify the approval procedure required for the installation of waste treatment facilities intended for handling biomass with similar properties
13
4-7. Biomass Nippon Strategy4-7. Biomass Nippon Strategy
Post-Conversion Utilization Investigation of a procedure to be applied to biomass-derived
plastic materials as specific procurement items covered by the Green Purchasing Law
Arrangements so that biomass power generation can be handled in the same manner as other kinds of new energy under the New Energy Law
Promotion of agriculture which is oriented toward environmental conservation
Facilitation of power supply by means of distributed power sources, including biomass power generation
Quality evaluation of biomass-derived automotive fuels, assessment of their safety and environmental performance, and driving tests on those fuels as well as evaluation of the merits and demerits of their introduction into Japan 14
Private Sector
Plans, FS, Introduction
Local Gov’ts
Visions, FS, Introduction
NEDOAdvisory Activities
• Explanatory Meetings
• Dispatch of Experts
• Consultation
• Workshops
• etc.
Projects & Programs
・for Local Gov’ts
・for Private Sector
・for Both Local Gov’ts and Private Sector (Joint)
Other Related Organizations
Manufacturers, NEF, Think Tanks, Industrial Orgs.
R&D Projects and Programs
5. NEDO’s Role in Japan’s New Energy Scheme5. NEDO’s Role in Japan’s New Energy Scheme
15
6-1. Measures to Overcome Grid-Connection Obstacles6-1. Measures to Overcome Grid-Connection Obstacles
16
Demonstrative Research on Combined Power Generation Systems (PV + Biogas)
ObjectivesObjectives
Early commercial application of a system that maximizes the utilization of RE to promote mass introduction
Establishment of an effective system on the demand side
Resolution of instable PV power generation
Demonstration of a combined system in which instable energy is transferred and utilized to produce stable, renewable energy, while stable PV energy is directly supplied to the grid
6-2. Measures to Overcome Grid-Connection Obstacles6-2. Measures to Overcome Grid-Connection Obstacles
17
Demonstrative Research on Combined Power Generation Systems (PV + Biogas)
Power GenerationPV 50kW; Biogas 60kW
Site:Sihanoukville, Cambodia
~/-
110kV/10kV
Bulk PV Amorphous PV
Switch
Transformer
Medium-Voltage Power Line
System Design
6-3. Measures to Overcome Grid-Connection Obstacles6-3. Measures to Overcome Grid-Connection Obstacles
Demonstrative Research on High-Efficiency PV Power Generation Systems
Site:
Beijing City, PRC Total Power Generation: 180kW18
6-4. Measures to Overcome Grid-Connection Obstacles6-4. Measures to Overcome Grid-Connection Obstacles
Demonstrative Research on Combined Power Generation Systems (PV + Wind + Advanced Battery)
PV
Turbine
Adv. Batt.
Mini GridSystem Design
Site:
Gansu Prov., PRC
PV Power Generation: 100kW
Wind Power Generation: 100kW19
6-5. Measures to Overcome Grid-Connection Obstacles6-5. Measures to Overcome Grid-Connection Obstacles
Demonstrative Research on Combined Power Generation Systems (Water-cooled PV + DG + Advanced Battery)
Water-cooled PVAdv. Batt.
DG
Ballast Load
Mini GridSystem Design
Site:
Xinjiang Prov., PRC
PV Power Generation: 60kW
DG Power Generation: 100kW20