j g c j b dr g d p j r k y m z agenda j h e d peninsula ...and+minutes/jpb/... · 4/6/2017 · san...
TRANSCRIPT
Note: All items appearing on the agenda are subject to action by the Board. Staff recommendations are subject to change by the Board.
Page 1 of 4
AGENDA PENINSULA CORRIDOR JOINT POWERS BOARD
Bacciocco Auditorium, 2nd Floor
1250 San Carlos Avenue, San Carlos CA 94070
April 6, 2017 – Thursday 10:00 a.m.
1. Pledge of Allegiance
2. Call to Order
3. Swearing-in of Monique Zmuda Representing the City and County
of San Francisco
4. Roll Call
5. Public Comment Public comment by each individual speaker shall be limited to two minutes
6. Consent Calendar Members of the public or Board may request that an item under the Consent Calendar be
considered separately
a) Approval of Minutes of March 2, 2017
b) Acceptance of Statement of Revenues and Expenses for
February 2017
c) Authorize Filing of Applications to the California Governor’s
Office of Emergency Services to Receive $751,397 in State
Proposition 1B Transit Security Grant Program Funds
d) Appointment of CAC Member Julia Welch Representing
San Mateo County to a Term Ending June 30, 2018
e) Resolution of Appreciation to Outgoing Director Josè Cisneros
RESOLUTIONS
7. Chairperson’s Report
a) Appointment of a Nominating Committee for Vice Chair
INFORMATIONAL
MOTION
8. Report of the Citizens Advisory Committee INFORMATIONAL
9. Report of the Executive Director
a) Peninsula Corridor Electrification Project Monthly Report
b) Peninsula Corridor Electrification Project Full Funding Grant
Agreement Update
INFORMATIONAL
INFORMATIONAL
10. Caltrain Business Plan INFORMATIONAL
11. Caltrain Short Range Transit Plan – Draft Elements INFORMATIONAL
BOARD OF DIRECTORS 2017
JEFF GEE, CHAIR
JEANNIE BRUINS
DEVORA “DEV” DAVIS
ROSE GUILBAULT
DAVE PINE
JOÉL RAMOS
KEN YEAGER
MONIQUE ZMUDA
JIM HARTNETT
EXECUTIVE DIRECTOR
Peninsula Corridor Joint Powers Board
April 6, 2017 Agenda
Note: All items appearing on the agenda are subject to action by the Board. Staff recommendations are subject to change by the Board.
Page 2 of 4
12. Key Caltrain Performance Statistics February 2017 INFORMATIONAL
13. Authorize Amendment to the Cooperative Agreement with the
Capitol Corridor Joint Powers Authority to Provide an Additional
$900,000 in Funding and to Expand the Scope of Work to Include
South Terminal Phase III and Los Gatos Creek Bridge Projects
RESOLUTION
14. Amend the Fiscal Year 2017 Capital Budget for the Ravenswood
Avenue Grade Separation Project for a Total Capital Budget from
$526,585,568 to $526,751,568
RESOLUTION
15. Caltrain Triennial Customer Survey Key Findings INFORMATIONAL
16. Legislative Update INFORMATIONAL
17. Correspondence
18. Board Member Requests
19. Date/Time of Next Regular Meeting: Thursday, May 4, 2017,
10 a.m. at San Mateo County Transit District Administrative
Building, Bacciocco Auditorium, 2nd Floor, 1250 San Carlos
Avenue, San Carlos, CA 94070
20. General Counsel Report
a) Closed Session: Conference with Real Property Negotiators
Joan L. Cassman, General Counsel, Brian W. Fitzpatrick,
Manager, Real Estate and Property Development, and
Gary Cardona, Senior Real Estate Officer, pursuant to
Government Code Section 54956.8:
Under negotiation: Price and terms of contract.
Property Location Owner APN JPB Parcel #
200 Berkshire Avenue,
Redwood City
Michael A. Buenrostro/
Michelle Buenrostro
054-201-230 JPB-SM2-138
201 and 205
Dumbarton Avenue,
Redwood City
Caballero Family Trust 054-201-490 JPB-SM2-308
200 Dumbarton
Avenue, Redwood City
Redwood Apartments 054-201-560 JPB-SM2-310
Westside Avenue,
Redwood City
Del Rio Trust 054-201-550 JPB-SM2-311
b) Closed Session: Conference with Legal Counsel - Existing
Litigation Pursuant to Government Code Section 54956.9(d)(1):
Peninsula Corridor Joint Powers Board. v. Parsons
Transportation Group et al; San Mateo County Superior Court
Case No. Case No. 17CIV00888
Peninsula Corridor Joint Powers Board
April 6, 2017 Agenda
Note: All items appearing on the agenda are subject to action by the Board. Staff recommendations are subject to change by the Board.
Page 3 of 4
c) Closed Session: Conference with Legal Counsel - Existing
Litigation Pursuant to Government Code Section 54956.9(d)(1):
Parsons Transportation Group v. Peninsula Corridor Joint Powers
Board et al; San Mateo County Superior Court Case No. Case
No. 17CIV00786
21. Adjourn
Page 4 of 4
INFORMATION FOR THE PUBLIC
All items appearing on the agenda are subject to action by the Board. Staff
recommendations are subject to change by the Board.
If you have questions on the agenda, please contact the JPB Secretary at 650.508.6242.
Agendas are available on the Caltrain website at www.caltrain.com. Communications
to the Board of Directors can be e-mailed to [email protected].
Location, Date and Time of Regular Meetings
Regular meetings are held at the San Mateo County Transit District Administrative
Building located at 1250 San Carlos Avenue, San Carlos, one block west of the
San Carlos Caltrain Station on El Camino Real, accessible by SamTrans bus Routes ECR,
FLX, 260, 295 and 398. Additional transit information can be obtained by calling
1.800.660.4287 or 511.
The JPB meets regularly on the first Thursday of the month at 10 a.m. The JPB Citizens
Advisory Committee meets regularly on the third Wednesday of the month at 5:40 p.m.
at the same location. Date, time and place may change as necessary.
Public Comment
If you wish to address the Board, please fill out a speaker’s card located on the agenda
table and hand it to the JPB Secretary. If you have anything that you wish distributed to
the Board and included for the official record, please hand it to the JPB Secretary, who
will distribute the information to the Board members and staff.
Members of the public may address the Board on non-agendized items under the
Public Comment item on the agenda. Public testimony by each individual speaker
shall be limited to two minutes and items raised that require a response will be deferred
for staff reply.
Accessibility for Individuals with Disabilities
Upon request, the JPB will provide for written agenda materials in appropriate
alternative formats, or disability-related modification or accommodation, including
auxiliary aids or services, to enable individuals with disabilities to participate in public
meetings. Please send a written request, including your name, mailing address, phone
number and brief description of the requested materials and a preferred alternative
format or auxiliary aid or service at least two days before the meeting. Requests should
be mailed to the JPB Secretary at Peninsula Corridor Joint Powers Board,
1250 San Carlos Avenue, San Carlos, CA 94070-1306; or emailed to
[email protected]; or by phone at 650.508.6242, or TDD 650.508.6448.
Availability of Public Records
All public records relating to an open session item on this agenda, which are not
exempt from disclosure pursuant to the California Public Records Act, that are
distributed to a majority of the legislative body will be available for public inspection at
1250 San Carlos Avenue, San Carlos, CA 94070-1306, at the same time that the public
records are distributed or made available to the legislative body.
Page 1 of 13
Peninsula Corridor Joint Powers Board (JPB)
Board of Directors Meeting
1250 San Carlos Avenue, San Carlos CA 94070
MINUTES OF MARCH 2, 2017
MEMBERS PRESENT: J. Bruins, J. Cisneros (Chair), D. Davis, J. Gee, R. Guilbault, D. Pine,
J. Ramos, K. Yeager
STAFF PRESENT: J. Averill, M. Bouchard, J. Cassman, A. Chan, C. Fromson,
J. Hartnett, K. Kelly, M. Martinez, N. McKenna, S. Murphy, M. Simon,
P. Skinner, S. van Hoften, N. Vigil
Chair Josè Cisneros called the meeting to order at 10:04 a.m. and led the Pledge of
Allegiance.
SWEARING IN OF DEVORA “DEV” DAVIS, REPRESENTING SANTA CLARA VALLEY
TRANSPORTATION AUTHORITY (VTA)
Martha Martinez, JPB Secretary, administered the Oath of Office.
PUBLIC HEARING FOR CONSIDERATION OF PROPOSED 2017 WEEKEND SERVICE CHANGES
AND TITLE VI ANALYSIS
Ms. Martinez reported on the steps taken to announce and receive public comment
after the Board called for the public hearing at the December 1, 2016 meeting.
Ms. Martinez said 14 station outreach meetings and 10 community meetings were held.
A detailed list of public outreach is in the reading file. She said 141 weekend service
comments have been received as of March 1 and a summary of the comments are in
the reading file.
Michelle Bouchard, Chief Operating Officer, Rail, presented:
Weekend change background
o Facilitate construction work windows for Peninsula Corridor Electrification
Project (PCEP)
o Supports entire JPB capital program
o Local service headways go from 60 minutes to 90 minutes, a reduction in
eight trains per weekend day
o Service reduction is major service change and requires Title VI Equity
Analysis
o Coordinated with sister transit agencies connections, contractors,
TransitAmerica Services, Inc., stakeholders
o Proposed dates: summer 2017 to winter 2020
Extensive outreach was conducted including drop-in meetings at stations
High-level comment summary
o This is not a popular change as weekend service is very well used both for
regular customers and special event service: this is a short-term impact for
a long-term benefit and a compromise between a complete shutdown
and continuing to provide weekend service
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 2 of 13
o Concerns with impacts to special event service: committed to continuing
special event service
o Concerns with impacts to capacity: all weekend service will be operated
with six-car trains
o Requests for more service: promotion of alternative transportation options
Title VI: as a recipient of Federal funding, Caltrain operates its programs and
services without regard to race, color or national origin
o Slightly more non-minority passengers are impacted than minority: no
disparate impact
o Largely more non-low-income passengers than low-income passengers
impacted: no disproportionate burden
Next steps
o Board action immediately following public hearing
o Executive implementation plan effective summer 2017 consistent when
the electrification project breaks ground; there could be some delays to
the start of construction, so regular service will be provided as long as
possible
o After implementation, monitor ridership
Public Comment
Jeff Carter, Millbrae, said it is unfortunate this has to be done although he understands
why. Even the current one-hour service on the weekends is inadequate. Perhaps this
could be shortened or the project could get done faster. The United States does not
know how to do projects like these. He said stakeholders had concerns about some of
the outreach. People went to station drop-ins and couldn’t find staff, especially during
the rainy days. The Citizen Advisory Committee (CAC) suggested Caltrain should
provide incentives such as fare reduction or free transfers to make this change easier.
Peter Warner, Hanford, said there is more ridership on Saturday than on Sunday and a
split schedule with 75-minute service on Saturday, which would reduce two of the round
trips instead of four round trips with the 90-minute headway, would be a better idea
given the late-night baseball and hockey games. He asked if notes will be in the
schedule that trains will hold for ball games and hockey and keep the current modified
schedules for holidays.
Roland Lebrun, San Jose, said the real reason this is a problem is because crews are
working on two zones at the same time. In Europe crews would work on a 10-mile zone.
Work going on in the other zone has nothing to do with electrification, it has to do with
San Mateo County working on capital projects.
Jack Ringham, Atherton, said he’s concerned about the cost of electrification of
$2 billion to electrify when there is a non-electrification alternative involving Tier 4 diesels
for about $500 million. He has spent 35 years as management consultant in
transportation and manufacturing and many of his assignments involved a comparison
of alternatives. He’s testified before the House of Representatives Transportation
Committee as an expert witness involving transportation alternatives.
Jesse [no last name or city provided], said he came to this building to get his phone,
which he lost on the train. There is no number provided for lost and found. He filled out
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 3 of 13
the online lost and found form, but has not heard back from staff. There are small and
simple things that could be adjusted. He said someone should be at a desk on the
phone with lost and found. He said buying train tickets is on the honor system. He said
it doesn’t make sense to fine a passenger $200 for not having a ticket if they couldn’t
afford the $2 ticket in the first place. He said the station platforms should be labeled
with northbound or southbound.
Joan Cassman, Legal Counsel, said the Board heard the purpose of the meeting, staff
extensively noticed the hearing, the public was afforded the opportunity to provide
feedback, and the Board has have met all applicable legal requirements and may
consider the action before it.
Director Jeannie Bruins commended staff for trying to do the station outreach,
especially during inclement weather. It was a great way to get to the people who are
directly using the service. A tradeoff has to be made because without cutting back
service, the construction period will have to be extended. The JPB is trying to achieve a
balance and it may not be convenient, but it is the best alternative.
Close the public hearing:
Motion/Second: Bruins/Gee
Ayes: Bruins, Davis, Gee, Guilbault, Pine, Ramos, Yeager, Cisneros
Approval of the Title VI Equity Analysis Report and Proposed 2017 Weekend Service
Changes
Motion/Second: Bruins/Guilbault
Ayes: Bruins, Davis, Gee, Guilbault, Pine, Ramos, Yeager, Cisneros
PUBLIC COMMENT
Vaughn Wollfe, Pleasanton, said the governor suggested spending $1.8 billion on streets
and roads, $1.8 billion on highways, and about $400 million on transit. Railroads would
get about 1/10 of what is being spent on roads. If 90 percent of the funding for the last
60 years has been for roads, that may be the reason 90 percent of people drive. This
group and other rail groups in the State should try to emphasize that Cap and Trade
funds should go only to transit, especially rail.
Paul Jones, Atherton, said he is concerned about financing for the PCEP. It is time to
start thinking about an alternative future. He suggested over the period of construction
it will be difficult to increase capacity in the system. The first opportunity would be after
the completion of electrification until high-speed rail (HSR) operates in this area
because the JPB promised to give California High-Speed Rail Authority (CHSRA) four
hourly departures out of the 10 available, which means Caltrain will be limited to six
trains per peak period. This will be the limit of capacity increases until four tracks or
some other massive change is made to the system. Tier 4 locomotives have the
characteristics of the Electric Multiple Units (EMU) that the JPB is buying and have
85 percent less pollution than the current diesels. With these, capacity could be
increased to over 120,000 passengers per day.
Mike Brady, Menlo Park, said the JPB waited until the chaos of the changeover of the
new administration to get the Full Funding Grant Agreement (FFGA) approved. He said
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 4 of 13
Carolyn Flowers, the acting head of the Federal Transit Administration (FTA) submitted
the grant to Congress and then resigned and took a job with a company that will
benefit if the grant is made. United States Department of Transportation Secretary
Elaine Chao seized control and deferred the grant until the president submits his
budget.
Roland Lebrun, San Jose, said at the August 1, 2013 meeting he alerted the Board that
the Federal Railroad Administration (FRA) testified that Communications-Based Overlay
Signal System (CBOSS) could not meet the deadline. Four years later the same
conversation is being had about the PCEP and how it cannot deliver the kind of
congestion relief the peninsula needs. He asked the Board to terminate both
electrification contracts immediately.
Jeff Carter, Millbrae, said the CAC met on the weekend service changes and passed a
motion, but it was not mentioned in the staff report.
Charles Voltz, Burlingame, said technology ideas that were good 50 years ago may not
be the best solution today. The PCEP may not be the best solution. The action of
deferring the FFGA gives the JPB an opportunity to reevaluate the total situation with
what is now-available technology and what is promised technology, such as
Bombardier testing electric battery trains, Alstom testing of hydrogen cell and battery
technology, and the battery possibilities from Elon Musk’s factory where the cost of
batteries for trains will be reduced by 30 percent or more.
Peter Warner, Hanford, said when schedule changes are made the JPB needs to
coordinate with other transit operators.
George Kranen, Belmont, said the coffee is terrible and whoever is making it needs to
learn how to make coffee.
CONSENT CALENDAR
Approval of Minutes of February 2, 2017
Acceptance of Statement of Revenues and Expenses for January 2017
Approval of Enrollment in 100 Percent Renewable Electricity Service Options of
CleanPowerSF, Peninsula Clean Energy, and Silicon Valley Clean Energy, and
City of Palo Alto Utilities and Silicon Valley Power
Approval of Revisions to the Peninsula Corridor Joint Powers Board Procurement
Policy to Incorporate Provisions of Assembly Bill 2030
Motion/Second: Davis/Pine
Ayes: Bruins, Davis, Gee, Guilbault, Pine, Ramos, Yeager, Cisneros
ACCEPTANCE OF THE COMPREHENSIVE ANNUAL FINANCIAL REPORT FOR THE FISCAL YEAR
ENDING JUNE 30, 2016
Removed from Consent Calendar.
Public Comment
Roland Lebrun, San Jose, said the auditors uncovered a significant deficiency in the
internal controls. JPB’s cash balances were not fully reconciled for the fiscal year.
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 5 of 13
Several months out of the fiscal year were not reconciled. This led to significant post-
closing adjustments. He said the San Mateo County Transit District (District) is messing
around with the Caltrain books. This is consistent with the District’s inability to deliver any
project on time or on budget. The District does not have a functional PeopleSoft
system.
Motion/Second: Gee/Guilbault
Ayes: Bruins, Davis, Gee, Guilbault, Pine, Ramos, Yeager, Cisneros
CHAIRPERSON’S REPORT
None.
REPORT OF THE CAC
Brian Shaw, Chair, CAC, said:
The CAC welcomed Catherine Chang representing San Francisco.
There is one vacancy on the CAC for San Mateo County.
Vice chair elections were postponed until March.
The CAC will provide an assessment of Caltrain’s performance given the
improvements staff has implemented over the past year.
The CAC voted five to two against the proposed weekend schedule changes
recommended by staff. The CAC is not convinced the proposed timetable
takes into account all interests of the Caltrain riders. Staff did not offer positive
aspects of the schedule change other than accommodating electrification
construction. The CAC suggests when offering reductions in service, the JPB
needs to offer some positive benefit such as fare reductions, extending service to
underserved areas, or adding bullet service. If the public were to receive some
gain in the schedule, the CAC will reconsider its objection. He would be glad to
appoint a taskforce to identify potential mitigation strategies.
REPORT OF THE EXECUTIVE DIRECTOR
PCEP Monthly Report
Jim Hartnett, Executive Director, said this report is in the reading file.
PCEP FFGA
Mr. Hartnett said the FTA deferred the decision to approve or deny the FFGA, but stated
the FFGA could be signed if the grant is allocated funds in the president’s budget,
which could be submitted by June 15 at the latest or as early as April. All regulatory
and technical requirements have been completed as well as the mandatory 30-day
Congressional waiting period. $73 million in previously appropriated Core Capacity
Funds has been allocated. No pending Core Capacity Grants are in the same status as
the Caltrain grant. No FFGA with the level of rating this grant has been awarded has
ever not been signed. A Limited Notice to Proceed (LNTP) was issued last July to Balfour
Beatty and Staddler. March 1 was the date that was negotiated as the farthest out as
possible with the intent to authorize the Full Notice to Proceed under both contracts on
March 1 with the execution of the FFGA. For any delay past March 1 there was no
obligation for the contractors to hold contract prices. Staff negotiated an extension
through June 30 with both contracts for continuation of the LNTP period. In order to
extend the LNTP and keep the spending within the amounts agreed, design and
related work has been slowed down. The extension of the contract was the cheapest
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 6 of 13
alternative that could be derived. The other alternative would be suspension of the
contract, but would have substantial financial consequences. Termination would also
have the same consequences. A potential cost of up to $20 million could be incurred
because of the extension, but that cost is authorized under the LNTP. This $20 million is in
the contingency amount set within the Executive Director’s authority.
CBOSS/Positive Train Control (PTC) Project Update
Mr. Hartnett said the JPB entered into contract with Parsons Transportation Group (PTG)
in October 2011 for the design and implementation of CBOSS. The contract called for
CBOSS to be in revenue service demonstration (RDS) by October 31, 2015. The JPB
received express representations and assurances as late as fall 2015 from PTG that the
JPB would be in RSD by December 2015. Due to persistent delays in delivering the
project and a lack of progress in moving the project forward consistent with PTG’s
contractual obligations, Caltrain terminated the contract on February 22, 2017. Since
the termination, the JPB began the process of identifying a replacement. This action
will complicate final delivery, but it was done to ensure it does not impede progress on
the PCEP. Progress in the PTC includes the complete installation of wayside and
onboard hardware, installation of fiber optic backbone, the build-out of a control
center facility and a significant amount of field testing. On March 1 the JPB filed a
lawsuit for breach of contract and PTG has also filed a lawsuit against the JPB.
Mr. Hartnett reported:
On-time performance (OTP) for February was 93.8 percent compared to
90.5 percent over last year.
The 2017 Annual Counts is anticipated to be completed by April.
Special event train service includes:
o Sharks
o Giants Fan Fest and baseball service
o Modified schedule on Presidents’ Day
Public Comment
Roland Lebrun, San Jose, said the PCEP will never qualify for the FFGA because the FTA
mandates an increase in seating capacity by 10 percent and the JPB can’t do it unless
it gets money for railcars and for platform lengthening. The PCEP team advanced a
conceptual design to consider alternatives to a modification of the Centralized
Equipment Maintenance and Operations Facility, but a new facility is needed for EMUs.
The first eight miles of tracks will be available for testing six months late. He said if there
is no maintenance facility there will be no place to park the new railcars. The JPB spent
$140 million on electrification design and $18.5 million on EMUs, but there is nothing to
show for it. The EMU design continues to continue, and staff refuses to disclose issues
about capacity of new trains. He asked anyone who disagrees with his numbers to
come up with their own numbers and start a discussion.
George Kranen, Belmont, said Caltrain has pledged 2/3 of the money needed to
complete PCEP. He asked why the JPB doesn’t just proceed. There is plenty of time to
raise the rest of the funding. It will take time to use the money the JPB has. He asked if
there is a legal requirement to wait until all the funding is in. No private enterprise would
work like this.
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 7 of 13
Mike Brady, Menlo Park, said the FTA grant cannot be given to Caltrain if the money is
to the benefit of the CHSRA program, and this money would be used for the direct
benefit of CHSRA. He said the JPB said this is standalone project, but Caltrain is an
integral part of the HSR system. Without PCEP the CHSRA program could not be
implemented. The JPB entered into a contract with CHSRA that if they give $600 million
in Proposition 1A bond funds, the JPB will turn over control of the corridor to them.
Vaughn Wolffe, Pleasanton, asked if the JPB doesn’t get EMUs if it could consider
leasing old trains that are being retired on the east coast. This is a 100-year project and
no matter what the JPB does it will get criticized. In April 1999 the JPB voted for
electrification of Caltrain before the HSR vote had taken place. Electrification is not
dependent on HSR, HSR is piggybacking on the electrification project.
Bruce Jenkins, Rail Passenger Association of California, said his organization has over
500 members and stands with the National Association of Rail Passengers in full support
of Caltrain electrification and HSR.
Paul Jones, Atherton, said CBOSS is and has been in trouble for a long time. When the
prime contractor is fired, it is time to start over. It is a lot of money to scrap, but it is
much cheaper to start anew. He had recommended hiring a railway signaling and
control and communication employee to oversee the project. The JPB needs technical
staff to manage this project.
Jack Ringham, Atherton, said in 1992 California State Department of Transportation
(Caltrans) sponsored an electrification study that found to electrify from San Francisco
to Gilroy would cost $296 million. That never went anywhere because of funding. There
have been five attempts since then to get electrification done, but all failed for lack of
funds. This is the sixth attempt and the price tag is $2 billion. Over $600 million from the
FTA is in jeopardy, and another $600 million is in jeopardy because of a lawsuit. He
suggested the JPB start evaluating alternatives such as modern Tier 4 diesels and
battery-powered trains.
Charles Voltz, Burlingame, said 25 years ago when Caltrain decided to use electric
overhead power, it was not the same world as today. Since then Tier 4 clean diesel
and has been developed. An old problem with EMUs was they had to be built like a
tank to be crashworthy. A waiver was given to Caltrain for lightweight crashworthy
EMUs, and the same waiver is being adopted by the FRA for Diesel Multiple Units (DMU).
Energy prices have changed dramatically: diesel is less expensive and electricity is
more expensive. Depending on how electric power is being created it may or may not
be environmentally friendly.
Jeff Carter, Millbrae, said this is a 100-year project. Diesel trains will be affected by oil
companies and prices, and are less efficient. He is 100 percent behind electrification
and hopes Caltrain can move forward with construction of infrastructure and perhaps
hold off on EMUs until the JPB gets the FFGA. He has expressed concern about CBOSS
and hopes Caltrain would go with a proven PTC such as that used in Europe or
Metrolink or other railroads. He hopes there will be a reevaluation of PTC and a
reasonable resolution that will not cost a lot of money.
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 8 of 13
Paul Wendt, Belmont, said he has been a proponent for electrification with Bay Rail
Alliance and Peninsula Rail 2000. He is looking forward to electrification. He hopes that
people reach out to Congressman Kevin McCarthy. Electrification should proceed
independently of HSR. He hopes there is outreach to the Republican delegation.
Peter Warner, Hanford, said San Diego has 55 miles of electrified track with 56 stations.
He suggested former San Diego Trolley employees be brought onboard who were in
the light-rail operations department for their input.
Mr. Hartnett said a Frequently Asked Question sheet is available on the Caltrain website.
He and Michael Burns, Interim Chief Officer, Caltrain Planning/CalMod Program, are
heading to Washington D.C. on Monday to visit key officials about the project. He has
invited Secretary Chao to visit Caltrain and see firsthand why changes need to be
made.
Director Ken Yeager said he is in support of the extension. The $20 million, even though
it is contingency funds, came from the three partners. He said he wants to make sure
the JPB is spending that money as wisely as possible. Congressman McCarthy is key to
getting the funding through as well as the other 11 Republicans. No one is sure when
the president will say if this project will be included. He has heard the infrastructure bill is
not going to be worked on until next year. It may be well beyond July 1, and if the JPB
hasn’t heard, staff might need to start shutting down the project, but then the Board
might wonder if that was the best way to spend the $20 million. He has been reassured
it will be paid over time and not all at once so if in mid-April things are not looking good
and all hope is lost the JPB can stop spending money. He worries that the JPB just may
not know enough and it will take the Board to another decision point of further
extensions or something else. He asked what reassurances the Board has that the JPB
will spend the $20 million wisely only for projects that are essential and decide later how
much more to spend and what the timelines are going to be. Mr. Harnett said staff
shares these concerns about the unknowns. No work will be done under the extended
LNTP that is in addition to work already authorized. Work has been slowed down and
some has been deferred. The budget has not increased. If staff stopped work
altogether, the JPB would have to suspend the contract, but there would be financial
consequences and schedule and cost implications beyond that, which would be far
more than the potential $20 million. The other option is to terminate the contracts, but if
that was done the JPB would not be able to get the FFGA and would have to go out to
rebid. This is the best alternative.
Director Davis asked how the timeline would be affected by receiving the $647 million
down the road. Mr. Hartnett said the sooner the FFGA is approved the less affect it has
on the schedule. It is not a month-to-month delay because there is already
programmed a potential of delay. There will be some delay for both contractors. It will
depend on where they are in their efforts when the JPB receives the FFGA.
Director Bruins asked if the worst case is a one-month for one-month delay. She said
she hopes the JPB is protecting the back end of the schedule so a four-month delay in
getting the FFGA will not lead to six-month delay in the project. Mr. Hartnett said a one-
month for one-month delay is likely to be true as a worst case scenario.
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 9 of 13
Director Bruins asked if funds are leftover from other things that were not utilized when
the project is done if the contingency will be paid back or if the money will be
reconciled at the end. The contingency is money from the transit agencies that have
other purposes for that money. She said she wants assurances that the contingency is
the backup if the project can’t be funded through project funds. Mr. Hartnett said the
contingency is part of the approved budget and part of the commitment from all of
the funders. There is a total budget that includes a requirement by the FTA of a certain
level of contingency. There is also an agreement between all the funding partners that
at the end of the project if it comes in under budget, the partners will get money back.
Director Bruins asked when the JPB is going to start thinking about Plan B and what
triggers Plan B. She asked if this is about the president submitting his budget or if it has
to be in an approved budget. Mr. Hartnett said he has been told that if the money is in
president’s recommended budget, that is enough to trigger the signing of the FFGA by
the FTA. The FTA Executive Director told him that it is dependent on submission.
Mr. Hartnett said the JPB already has $73 million from prior fiscal years. This is a fully
qualified grant within a well-established program. The trigger point is the budget.
Director Bruins asked for key talking points to use to communicate for consistency of
message. She said a month is a long time to wait for an update and would like to hear
updates sooner.
Director Jeff Gee thanked the team for getting this to where it is. This is not a simple
project. When there are so many funding partners and constraints and fiscal years, this
is not easy. Money comes with different constraints. Part of the reason for the delay is
the Federal government decided they didn’t like the color of money. If the rules were
clear from the beginning, this would have been approved already.
Director Joèl Ramos said he is grateful for the hard work and heavy lifting done for this
project. This project has been in discussions long before HSR was a sure thing. He said
staff should work with captains of industry whose businesses depend on the speed of
the Caltrain service.
Director Dave Pine commended staff for the advocacy efforts.
KEY CALTRAIN PERFORMANCE STATISTICS JANUARY 2017
Ms. Bouchard said:
Ridership is continuing a trend of flat to slightly down from previous year. There
are indicators that Caltrain is faring a little better than some of the regional and
national peers. Staff is focused on finding ways to find ridership growth, which
includes the implementation of the schedule in April, doubling down on fare
enforcement, and looking at where the best bang for the buck can be
obtained.
Another trend is the return to 95 percent OTP on a month-by-month basis. This
month had the lowest number in mechanical delays in several years, which can
be attributed to the implementation of programs that provide for mechanics to
ride onboard trains, mechanics at ends of the line, and incident management.
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 10 of 13
Public Comment
Charles Voltz, Burlingame, said increased ridership and capacity has to be looked at
holistically in terms of the number of riders and the consequences of how it happens
and its impact. The Burlingame grade crossings will cost $250 million for
Broadway Avenue, and Burlingame has five other grade crossings. If there are 40
grade crossings along the system and there will be an increase in trains to increase
capacity and adding up to 10 trains per hour, this will result in a paralysis on the
peninsula. The JPB will have to figure out how to pay for the grade crossings. A solution
is needed for the next few years and what has been proposed for the interim is clean
diesel engines.
Doug Delong, Mountain View, said ridership graphs have a seasonal trend where they
go up in the good weather summer months and down in the winter months. There was
an exceptionally wet winter. He asked if there has been any effort made to see the
wetter winter exacerbated the seasonal variation and caused the decrease in
ridership.
AUTHORIZE THE FILING AND EXECUTION OF ANNUAL CAP AND TRADE FUNDING
APPLICATION WITH THE CALIFORNIA STATE DEPARTMENT OF TRANSPORTATION TO RECEIVE
$502,745 IN CALIFORNIA LOW CARBON TRANSPORTATION OPERATIONS PROGRAM FUNDS
FOR THE PCEP
Peter Skinner, Manager, Grants and Fund Programing, said these funds are proceeds
from Cap and Trade auctions and transit agencies across the State receive a portion of
the funds by formula based on their operating revenue.
Public Comment
Jack Ringham, Atherton, said the JPB has $113 million that it thinks is committed from
Cap and Trade. Cap and Trade is generating far less money than the projection. A
portion of the expected funding in jeopardy is this $113 million. Bay Area Rapid Transit
(BART) has 104 miles of electrified lines and they want 10 miles to extend to Antioch.
They found out to continue electrification for 10 more miles would cost $1.3 billion. He
said the JPB should think about approving only what it can afford.
Charles Voltz, Burlingame, asked if the JPB would make the decision to go with
electrification if the JPB had to pay for it. If the JPB had to pay for it, the JPB would
seriously look at less expensive alternatives that would get the job done. He
recommended the JPB look at solutions for the next five years to meet the growing
capacity and use that time to look at permanent solutions that can be afforded.
Jeff Carter, Millbrae, said there is a huge cost difference building BART and
conventional rail, so it is misleading to say BART used DMUs because electrification was
too expensive.
Roland Lebrun, San Jose, said five years ago he suggested decoupling EMUs from
electrification. If this was done ridership would be going through the roof now.
Motion: Gee/Guilbault
Ayes: Bruins, Davis, Gee, Guilbault, Pine, Ramos, Yeager, Cisneros
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 11 of 13
AWARD OF CONTRACTS TO ARMAND CONSULTING, INC. AND RAIL SURVEYORS AND
ENGINEERS, INC. TO PROVIDE ON-CALL COMMUNICATION AND SIGNAL SERVICES FOR
AN ESTIMATED, AGGREGATE NOT-TO-EXCEED SHARED TOTAL AMOUNT OF $8.5 MILLION
FOR A THREE-YEAR BASE TERM
Nita Vigil, Acting Director, Contracts and Procurement, said the existing contracts will
expire in May. She said 10 proposals were received after a solicitation was issued for a
qualifications-based process. Both firms are identified as Disadvantaged Business
Enterprise (DBE) firms. Work will be issued on a work-directive basis on a project-by-
project case-by-case need.
Public Comment
Roland Lebrun, San Jose, said this is about hiring a firm to babysit CBOSS because PTG
was just fired.
Doug Delong, Mountain View, said it is a shame these contracts to two DBE firms were
issued after Directors Malia Cohen and Sophie Maxwell left the Board and he thanked
those members for their tireless efforts.
Motion: Gee/Ramos
Ayes: Bruins, Davis, Gee, Guilbault, Pine, Ramos, Yeager, Cisneros
AUTHORIZE INCREASE IN THE EXECUTIVE DIRECTOR’S CHANGE ORDER AUTHORITY IN AN
AMOUNT NOT TO EXCEED $719,000 FOR THE SAN MATEO BRIDGES REPLACEMENT PROJECT
Ms. Bouchard said this funding is in order to aid in project closeout. This was a complex
project that involved the replacement of four 100-year-old bridges through San Mateo
that also allowed for a lift in clearance. In order to close out the project there was
additional ballast and grouting needed, and there were weather conditions that led to
increased cost.
Motion: Guilbault/Davis
Ayes: Bruins, Davis, Gee, Guilbault, Pine, Ramos, Yeager, Cisneros
CALTRAIN SHORT RANGE TRANSIT PLAN – DRAFT ELEMENTS
CALTRAIN BUSINESS PLAN
Mr. Hartnett said these will be presented next month.
CAPITAL PROJECTS QUARTERLY STATUS REPORT – 2ND QUARTER FISCAL YEAR 2017
No comments or questions from the Board.
Public Comment
Roland Lebrun, San Jose, said the JPB is at 3.5 percent DBE participation, which is short
of the 15 percent target. The Quint Street Bridge shows a savings of $4 million
presumably because the connector road is not being built, but the Marin Street and
Napoleon Avenue Bridge shows a project estimate at completion increased by
$850,000 due to additional construction management requirements and revised project
estimate, which resulted in a project shortfall of $1.5 million. Additional funding will be
requested. He suggested the $4 million surplus can account for the $1.5 million shortfall.
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 12 of 13
Jack Ringham, Atherton, said he has given handouts on his suggestions and can
provide copies of his presentation to the public.
LEGISLATIVE UPDATE
Casey Fromson, Manager, Government and Community Relations, said the information
is in the reading file.
Public Comment
Roland Lebrun, San Jose, said the Board should read the October 6, 2011 minutes to
understand how the JPB got into a mess about CBOSS. He said the Board should reach
out to Metrolink to see how they reached the 2015 deadline. They did it in partnership
with Wabtec, who was the lowest bidder for CBOSS in 2011 and was in a joint venture
with PTG. The cost of the owner’s team ballooned from $50 million to $80 million. These
are the people who should be fired and sued for cause. The JPB has to engage
Wabtec as soon as possible and work with PTG towards a solution that will meet the
new Federal deadline.
CORRESPONDENCE
No discussion.
BOARD MEMBER REQUESTS
None.
DATE/TIME/PLACE OF NEXT REGULAR MEETING
Thursday, April 6, 2017, 10 a.m. at San Mateo County Transit District Administrative
Building, Bacciocco Auditorium, 2nd Floor, 1250 San Carlos Avenue, San Carlos, CA
94070.
GENERAL COUNSEL REPORT
Closed Session: Conference with Legal Counsel - Anticipated Litigation Pursuant to
Government Code Section 54956.9(d)(2): One Potential Case
Recessed to closed session at 12:15 p.m.
Director Yeager left at 1 p.m.
Reconvened to open session at 1:03 p.m.
Ms. Cassman said the Board met in closed session to discuss litigation regarding the
CBOSS/PTC Project. A contract was recently terminated and the parties are now in
litigation.
Consider Delegation of Authority to the Executive Director to Enter into Agreements
within the Project Budget to Continue Work to Complete the CBOSS Project
Ms. Bouchard, said in light of the termination of the contract with PTG to deliver the
CBOSS Project, this item would authorize the Executive Director to enter into interim
agreements as necessary to continue the CBOSS program for 120 days for an
aggregate of $3 million with the understanding these contracts will be approved by
Joint Powers Board Meeting
Minutes of March 2, 2017
Page 13 of 13
legal counsel and will comply with all Federal funding requirements and are already in
the approved CBOSS budget.
Public Comment
Adina Levin, Friends of Caltrain, said the peer review group had provided valuable
information to Caltrain about how to improve the process for managing complex
technology projects. One opportunity at this time would be to ask the peer review
group what they would recommend as the best way to move this project forward to
completion and if there are any changes.
Motion/Second: Ramos/Guilbault
Ayes: Bruins, Davis, Gee, Guilbault, Pine, Ramos, Cisneros
Absent: Yeager
Adjourned at 1:07 p.m.
AGENDA ITEM # 6 (b)
APRIL 6, 2017
PENINSULA CORRIDOR JOINT POWERS BOARD
STAFF REPORT
TO: Joint Powers Board
THROUGH: Jim Hartnett
Executive Director
FROM: Kathleen Kelly
Interim Chief Financial Officer
SUBJECT: STATEMENT OF REVENUES AND EXPENDITURES FOR THE PERIOD ENDING
FEBRUARY 28, 2017, AND SUPPLEMENTAL INFORMATION
ACTION
Staff proposes the Board of Directors accept and enter into the record the Statement of
Revenue and Expenditure for the month of February 2017 and supplemental
information.
SIGNIFICANCE
Revenues: For February of Fiscal year 2017, Total Operating Revenue (line 7) is
$2,514,087 or 3.8 percent better than budget. Within total operating revenue, Farebox
Revenue (line 1) is 849,344 or 1.4 percent better than budget. Compared to the prior
year, Total Operating Revenue (line 7) is $4,971,185 or 7.9 percent higher.
Expense: Grand Total Expenses (line 50) show a favorable variance of $12,730,293 or
13 percent. Total Operating Expense (line 36) is $10,941,157 or 13.5 percent better than
budget. Total Administrative Expense (line 46) is $1,803,432 or 11.4 percent better than
budget.
Compared to prior year, Grand Total Expenses (line 50) are $4,351,215 or 5.4 percent
higher.
Use of Reserves: For February 2017, the JPB did not use its reserves, mostly due to direct
savings from fuel and lubricants.
BUDGET IMPACT
There are no budget revisions for the month of February 2017.
Prepared By: Jeannie Chen, Senior Accountant 650.508.6259
Sheila Tioyao, Manager, General Ledger 650.508.7752
Statement of Revenue and Expense
Page 1 of 1
% OF YEAR ELAPSED 66.7%
MONTH
CURRENT PRIOR CURRENT REVISED % REV APPROVED REVISED PROJECTION % REV
ACTUAL ACTUAL ACTUAL BUDGET BUDGET BUDGET BUDGET BUDGET
(AS PROJECTED)
REVENUE
OPERATIONS:
1 Farebox Revenue 6,893,722 57,406,131 60,153,447 59,304,103 101.4% 91,679,812 91,679,812 91,679,812 65.6% 1
2 Parking Revenue 437,070 3,229,027 3,659,877 3,119,533 117.3% 4,679,300 4,679,300 5,172,515 78.2% 2
3 Shuttles 200,718 1,016,190 1,185,339 1,633,067 72.6% 2,449,600 2,449,600 2,449,600 48.4% 3
4 Rental Income 186,347 1,141,248 1,229,245 1,154,267 106.5% 1,731,400 1,731,400 1,731,400 71.0% 4
5 Other Income 40,834 359,276 1,895,149 398,000 476.2% 597,000 597,000 1,854,314 317.4% 5
6 6
7 TOTAL OPERATING REVENUE 7,758,692 63,151,872 68,123,057 65,608,970 103.8% 101,137,112 101,137,112 102,887,641 67.4% 7
8 8
9 CONTRIBUTIONS: 9
10 AB434 Peninsula & TA Shuttle Funding 143,273 1,271,536 1,132,689 1,238,502 91.5% 1,895,080 1,895,080 1,895,080 59.8% 10
11 Operating Grants 339,729 3,727,745 2,965,445 2,451,724 121.0% 3,677,586 3,677,586 3,677,586 80.6% 11
12 JPB Member Agencies 1,179,592 15,056,221 15,730,096 15,730,006 100.0% 20,448,014 20,448,014 20,448,014 76.9% 12
13 Use of Reserves 12,881,429 0.0% 19,234,237 19,234,237 8,399,404 0.0% 13
14 14
15 TOTAL CONTRIBUTED REVENUE 1,662,594 20,055,502 19,828,230 32,301,661 61.4% 45,254,917 45,254,917 34,420,084 43.8% 15
16 0
17 GRAND TOTAL REVENUE 9,421,286 83,207,374 87,951,287 97,910,631 89.8% 146,392,029 146,392,029 137,307,725 60.1% 17
18 18
19 19
20 EXPENSE 20
21 21
22 OPERATING EXPENSE: 22
23 Rail Operator Service 7,218,478 49,391,801 51,397,395 53,444,504 96.2% 80,166,756 80,166,756 79,243,962 64.1% 23
24 Rail Operator Service-Other - 600,000 291,138 1,350,000 21.6% 2,025,000 2,025,000 901,933 14.4% 24
25 Security Services 470,106 3,112,112 3,605,755 3,720,422 96.9% 5,582,867 5,578,399 5,468,877 64.6% 25
26 Rail Operator Extra work - - 63,070 114,600 55.0% 125,000 125,000 125,000 50.5% 26
27 Contract Operating & Maintenance 7,688,584 53,103,913 55,357,359 58,629,526 94.4% 87,899,623 87,895,155 85,739,771 63.0% 27
28 Shuttles Services 331,369 2,832,843 2,923,057 3,608,867 81.0% 5,413,300 5,413,300 5,413,300 54.0% 28
29 Fuel and Lubricants 749,187 5,528,570 5,758,886 10,374,651 55.5% 15,606,976 15,516,976 8,588,055 37.1% 29
30 Timetables and Tickets 20,890 84,936 56,288 174,467 32.3% 217,700 217,700 217,700 25.9% 30
31 Insurance 597,724 3,182,804 2,836,393 4,195,993 67.6% 6,293,990 6,293,990 6,293,990 45.1% 31
32 Facilities and Equipment Maint 140,680 1,011,177 1,233,313 1,555,887 79.3% 2,279,824 2,242,824 2,242,824 55.0% 32
33 Utilities 155,550 1,354,079 1,341,242 1,706,119 78.6% 2,559,188 2,559,188 2,559,188 52.4% 33
34 Maint & Services-Bldg & Other 91,099 758,713 812,099 1,014,285 80.1% 1,470,668 1,470,668 1,470,668 55.2% 34
35 35
36 TOTAL OPERATING EXPENSE 9,775,082 67,857,034 70,318,637 81,259,794 86.5% 121,741,269 121,609,801 112,525,497 57.8% 36
37 37
38 ADMINISTRATIVE EXPENSE 38
39 Wages and Benefits 655,147 4,856,354 5,311,942 5,589,201 95.0% 8,790,704 8,214,640 8,214,640 64.7% 39
40 Managing Agency Admin OH Cost 473,890 3,487,049 3,913,847 4,032,528 97.1% 6,048,792 6,048,792 6,048,792 64.7% 40
41 Board of Directors 651 8,453 7,230 9,733 74.3% 14,600 14,600 14,600 49.5% 41
42 Professional Services 596,219 2,481,211 3,085,667 4,040,317 76.4% 5,746,679 6,214,467 6,214,467 49.7% 42
43 Communications and Marketing 5,071 49,101 97,318 219,567 44.3% 234,800 234,800 234,800 41.4% 43
44 Other Office Expenses and Services 242,458 1,235,157 1,576,618 1,904,708 82.8% 2,533,010 2,772,754 2,772,754 56.9% 44
45 45
46 TOTAL ADMINISTRATIVE EXPENSE 1,973,436 12,117,325 13,992,621 15,796,053 88.6% 23,368,585 23,500,053 23,500,054 59.5% 46
47 47
48 Long Term Debt Expense 108,223 854,765 869,081 854,783 101.7% 1,282,175 1,282,175 1,282,175 67.8% 48
49 49
50 GRAND TOTAL EXPENSE 11,856,742 80,829,123 85,180,338 97,910,631 87.0% 146,392,029 146,392,029 137,307,726 58.2% 50
51 51
52 NET SURPLUS / (DEFICIT) (2,435,456) 2,378,250 2,770,949 - - (0) (0) (0) 52
"% OF YEAR ELAPSED" provides a general measure for evaluating overall progress against the
annual budget. When comparing it to the amounts shown in the "% REV BUDGET" column, please
note that individual line items reflect variations due to seasonal activities during the year.
3/24/17 9:51 AM
PENINSULA CORRIDOR JOINT POWERS BOARDSTATEMENT OF REVENUE AND EXPENSE
Fiscal Year 2017
February 2017
YEAR TO DATE ANNUAL
PENINSULA CORRIDOR JOINT POWERS BOARD
INVESTMENT PORTFOLIO
AS OF JANUARY 31, 2017
TYPE OF SECURITY MATURITY INTEREST PURCHASE MARKET
DATE RATE PRICE RATE
------------------------------------------------------ ------------------ ---------------- ------------------ ------------------
Local Agency Investment Fund (Unrestricted) * Liquid Cash 0.751% 72,404 72,404
County Pool (Restricted) ** Liquid Cash 0.945% 1,000,000 1,000,000
County Pool (Unrestricted) ** Liquid Cash 0.945% 1,557,238 1,557,238
Other (Unrestricted) Liquid Cash 0.000% 19,683,497 19,683,497
Other (Restricted) *** Liquid Cash 0.200% 24,092,741 24,092,741
------------------------------------------------------ ------------------ ---------------- ------------------ ------------------
46,405,881$ 46,405,881$
Accrued Earnings for January 2017 4,959.40$
Cumulative Earnings FY2017 39,796.22$
* The market value of Local Agency Investment Fund (LAIF) is calculated annually and is derived from the fair
value factor as reported by LAIF for quarter ending June 30th each year.
** As of January 2017, the total cost of the Total County Pool was $4,936,011,574 and the fair market value
per San Mateo County Treasurer's Office was $4,934,788,246.
*** Prepaid Grant funds for Homeland Security, PTMISEA and LCTOP projects, and funds reserved for debt repayment.
The Portfolio and this Investment Report comply with the Investment Policy and the provisions of SB 564 (1995).
The Joint Powers Board has the ability to meet its expenditure requirements for the next six months.
BOARD OF DIRECTORS 2015
ADRIENNE TISSIER, CHAIR PERRY WOODWARD JOSÉ CISNEROS MALIA COHEN JEFF GEE ROSE GUILBAULT ASH KALRA TOM NOLAN KEN YEAG
BOARD OF DIRECTORS 2017
JOSE CISNEROS, CHAIR
JEFF GEE, VICE CHAIR
MALIA COHEN
JEFF GEE
ROSE GUILBAULT
RAUL PERALEZ
JOÉL RAMOS
ADRIENNE TISSIER
KEN YEAGER
JIM HARTNETT
EXECUTIVE DIRECTOR
Page 1 of 2
13360174.1
AGENDA ITEM # 6 (c)
APRIL 6, 2017
PENINSULA CORRIDOR JOINT POWERS BOARD
STAFF REPORT
TO: Joint Powers Board
THROUGH: Jim Hartnett
Executive Director
FROM: April Chan
Chief Officer, Planning, Grants and Transportation Authority
SUBJECT: AUTHORIZATION TO FILE APPLICATIONS FOR STATE PROPOSITION 1B TRANSIT
SECURITY GRANT PROGRAM FUNDS
ACTION
Staff Coordinating Council recommends the Board:
1. Authorize the Executive Director, or his designee, to submit grant applications,
with concurrent Letter of No Prejudice (LONP) requests, to the California
Governor’s Office of Emergency Services (Cal OES) and
2. Authorize the Executive Director, or his designee, to file and execute
certifications, assurances and other documentation as required to receive
$751,397 in Fiscal Year (FY) 2017 Proposition 1B California Transit Security Grant
Program (CTSGP) funds from the State for transportation security projects.
SIGNIFICANCE
Cal OES requires eligible recipients of Proposition 1B CTSGP funds to submit resolutions
approved by their governing bodies that authorize the designated agency officer(s) to
execute any action necessary for the processing of applications associated with the
programming and receipt of funds. Approval of this item will meet Cal OES’ CTSGP
funding requirement.
In the event the State Controller is unable to sell a sufficient amount of bonds to fund all
Proposition 1B capital projects around the State, including Peninsula Corridor Joint
Powers Board (JPB) projects, the JPB will request a LONP to enable work to proceed,
utilizing JPB funds, which would then be reimbursed by the State once bond proceeds
become available.
BUDGET IMPACT
There is no budget impact related to this action. Safety and security projects proposed
to be funded with Proposition 1B CTSGP funds will be considered through the FY2018
Capital Budget development process.
Page 2 of 2
13360174.1
BACKGROUND
The Highway Safety, Traffic Reduction, Air Quality and Port Security Bond Act of 2006,
otherwise known as Proposition 1B, was approved by California voters on
November 7, 2006. Proposition 1B includes a funding program specifically for transit
safety and security projects, known as the CTSGP. The State Controller develops a list of
eligible transit operators and the amount of funds that each operator is eligible to
receive on an annual basis. Funding allocations are contingent on bond sales and it
has historically taken over one year to receive funds once an allocation request has
been submitted to the State.
Board authorization for the filing of applications by the agency’s appointed agent is a
Cal OES requirement. To allow greater flexibility, Cal OES does not require applicants to
list each project in their governing body resolutions. The JPB's certified resolution will be
filed with Cal OES after adoption by the Board. Cal OES informed all transit agencies
this is the last year of funding as the Proposition 1B program is coming to an end.
Prepared by: Rebecca Arthur, Senior Grants Analyst 650.508.6368
Page 1 of 2
13360123.1
RESOLUTION NO. 2017 -
BOARD OF DIRECTORS, PENINSULA CORRIDOR JOINT POWERS BOARD
STATE OF CALIFORNIA
* * *
AUTHORIZING THE FILING OF APPLICATIONS FOR STATE PROPOSITION 1B
TRANSIT SECURITY GRANT PROGRAM FUNDS
WHEREAS, the California Transit Security Grant Program (CTSGP) is a program for
capital security and safety projects that is part of the Highway Safety, Traffic Reduction,
Air Quality, and Port Security Bond Act of 2006, otherwise known as Proposition 1B,
which was approved by California voters on November 7, 2006; and
WHEREAS, the CTSGP is administered by the California Governor's Office of
Emergency Services (Cal OES); and
WHEREAS, the State Controller develops an annual list with the amounts that
each eligible project sponsor is programmed to receive; and
WHEREAS, Cal OES requires all eligible recipients of CTSGP funds to submit
resolutions approved by their governing bodies that authorize appointed agents to
take any actions necessary for the processing of applications; and
WHEREAS, due to a lack of available bond funding for new projects, the State
Controller’s Office may be unable to allocate CTSGP funds in a timely manner; and
WHEREAS, Assembly Bill 672, signed by the governor on October 11, 2009,
authorizes approval of a Letter of No Prejudice (LONP), which allows an eligible
applicant to expend its own funds to proceed with work on CTSGP-eligible projects and
be reimbursed by the State once CTSGP funds are available; and
WHEREAS, the Peninsula Corridor Joint Powers Board (JPB) is on the list of eligible
applicants for CTSGP funds; and
Page 2 of 2
13360123.1
WHEREAS, Staff Coordinating Council recommends the Board authorize the
Executive Director, or his designee, to submit applications for Fiscal Year (FY) 2017
CTSGP funds, with concurrent requests for LONPs, and to file and execute certifications
and assurances and any other documentation required by Cal OES.
NOW, THEREFORE, BE IT RESOLVED that the Board of Directors of the Peninsula
Corridor Joint Powers Board, hereby:
1. Authorizes the Executive Director, or his designee, to file applications and
concurrent LONP requests with Cal OES for FY2017 Proposition 1B CTSGP funds; and
2. Authorizes the Executive Director, or his designee, to take such actions as
may be necessary to give effect to this resolution, including executing any agreements,
certifications and assurances or other documentation that may be required to receive
the funds.
Regularly passed and adopted this 6th day of April, 2017, by the following vote:
AYES:
NOES:
ABSENT:
______________________
Chair, Peninsula Corridor Joint Powers Board
ATTEST:
_____________________________________
JPB Secretary
Resolution No. 2017-15
Resolution of Appreciation Presented to
Josè cisneros
WHEREAS, since April 2004, DIRECTOR JOSÈ CISNEROS has been an advocate for Caltrain
projects and transportation issues as a member of the Peninsula Corridor Joint Powers Board of
Directors; and
WHEREAS, DIRECTOR CISNEROS provided valuable leadership during his tenure on the
Caltrain Board, which included two terms as Chair; and
WHEREAS, during DIRECTOR CISNEROS’ time on the board, his guidance helped Caltrain
reach unprecedented milestones, achieving record ridership goals while acting as the travel
option of choice for commuters making the journey between San Francisco and Silicon Valley;
and
WHEREAS, DIRECTOR CISNEROS helped coordinate multi-agency funding agreements
vital to the Peninsula Corridor Electrification Project (PCEP); and
WHEREAS, DIRECTOR CISNEROS supported the approval of $1.25 billion in contracts to
begin PCEP;
WHEREAS, during DIRECTOR CISNEROS’ time on the board, he helped Caltrain open its
$140 million Centralized Equipment Maintenance and Operations Facility in September 2007
that provided Caltrain with its first-ever “home” for maintenance and operations; and
WHEREAS, during DIRECTOR CISNEROS’ time on the Board, he helped Caltrain celebrate
150 years of passenger rail service on the Peninsula in 2014, and in 2016, supported Caltrain’s
efforts to provide special service during the NFL’s Super Bowl 50 festivities from San Francisco to
Santa Clara counties; and
WHEREAS, DIRECTOR CISNEROS has championed the prioritization of safety measures on
Caltrain, advocating for efforts to construct grade-separation projects, conduct awareness
campaigns that stress appropriate behavior on the rail corridor, and advance enforcement
efforts to keep vehicles and people off the tracks; and
WHEREAS, as a longtime public servant, DIRECTOR CISNEROS has been a paragon of civic
engagement, providing tireless support and sponsorship for his constituents in the City and
County of San Francisco and beyond;
NOW, THEREFORE, BE IT RESOLVED that Caltrain Joint Power Board of Directors, does thank
and commend JOSÈ CISNEROS for his successful tenure, and wish him good fortunes in her
future endeavors.
UNANIMOUSLY ADOPTED this 6th day of April, 2017.
Chair, Peninsula Corridor Joint Powers Board
AGENDA ITEM # 6 (d)
APRIL 6, 2017
PENINSULA CORRIDOR JOINT POWERS BOARD
STAFF REPORT
TO: Joint Powers Board
THROUGH: Jim Hartnett
Executive Director
FROM: Martha Martinez
Executive Officer, District Secretary
SUBJECT: CITIZENS ADVISORY COMMITTEE APPOINTMENT FOR SAN MATEO COUNTY
REPRESENTATIVE
ACTION
The San Mateo County board representatives, Directors Jeff Gee, Rose Guilbault and
Dave Pine, recommend the Board appoint Julia Welch to the Caltrain Citizens Advisory
Committee (CAC) representing San Mateo County for a partial-term ending
June 30, 2018.
SIGNIFICANCE
The appointment of the San Mateo representative will fill a vacancy left by a
San Mateo County committee member who recently resigned. There will be a full
complement of the committee following the Board’s appointment.
The CAC consist of nine members, three appointed from each constituent county
(San Francisco County, San Mateo County, Santa Clara County). The term is for three
years. Each county selects its county committee members and the Peninsula Corridor
Joint Powers Board (JPB) affirms the appointments.
BUDGET IMPACT
There is no budget impact.
BACKGROUND
The Citizens Advisory Committee acts in an advisory capacity to the JPB. Its activities
shall include seeking the views of various groups of users and potential users of Caltrain
and ancillary transit facilities, and to develop proposals and recommendations for
meeting the needs of these various groups; reviewing and commenting on staff
proposals and actions as requested by the JPB; and assisting the JPB in any matter
which the Board may deem appropriate.
Prepared By: Martha Martinez, Executive Officer, District
Secretary
650.508.6242
Modernization Program Peninsula Corridor Electrification Project (PCEP)
February 2017
Monthly Progress Report
February 28, 2017
Funding Partners
FTA Core Capacity
FTA Section 5307 (Environmental / Pre Development only)
FTA Section 5307 (EMU only)
Prop 1B (Public Transportation Modernization & Improvement Account)
Caltrain Low Carbon Transit Operations Cap and Trade
Prop 1A
High Speed Rail Cap and Trade
Carl Moyer Fund
Bridge Tolls Funds (RM1/RM2)
SFCTA/SFMTA
San Mateo (SMCTA) Contribution
SMCTA Measure A
VTA Measure A
Santa Clara (VTA) Contribution
San Francisco Contribution
THIS PAGE INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Table of Contents i February 28, 2017
Table of Contents Page
1.0 BACKGROUND .......................................................................................................... 1-1
2.0 EXECUTIVE SUMMARY ............................................................................................. 2-1
2.1 Schedule .......................................................................................................... 2-2
2.2 Budget ............................................................................................................. 2-2
2.3 Board Actions .................................................................................................. 2-2
2.4 Government and Community Affairs ................................................................ 2-3
3.0 ELECTRIFICATION – INFRASTRUCTURE ................................................................ 2-1
3.1 Electrification ................................................................................................... 3-1
3.2 Supervisory Control and Data Acquisition (SCADA) ......................................... 3-2
3.3 Tunnel Modification .......................................................................................... 3-2
4.0 ELECTRIC MULTIPLE UNITS .................................................................................... 3-1
4.1 Centralized Equipment Maintenance and Operations Facility (CEMOF) Modifications .................................................................................................... 4-2
5.0 SAFETY ...................................................................................................................... 5-1
6.0 QUALITY ASSURANCE ............................................................................................. 6-1
7.0 SCHEDULE................................................................................................................. 7-1
8.0 BUDGET AND EXPENDITURES ................................................................................ 8-1
9.0 FUNDING .................................................................................................................... 9-1
10.0 RISK MANAGEMENT ............................................................................................... 10-1
11.0 ENVIRONMENTAL ................................................................................................... 11-1
11.1 Permits .......................................................................................................... 11-1
11.2 Mitigation Monitoring and Reporting Program (MMRP) .................................. 11-1
12.0 UTILITY RELOCATION ............................................................................................ 12-1
13.0 REAL ESTATE ......................................................................................................... 13-1
14.0 THIRD PARTY AGREEMENTS ................................................................................ 14-1
15.0 GOVERNMENT AND COMMUNITY AFFAIRS ......................................................... 15-1
16.0 DISADVANTAGED BUSINESS ENTERPRISE (DBE) PARTICIPATION AND LABOR STATISTICS ................................................................................................ 16-1
17.0 PROCUREMENT ...................................................................................................... 17-1
Peninsula Corridor Electrification Project Monthly Progress Report
Table of Contents ii February 28, 2017
18.0 TIMELINE OF MAJOR PROJECT ACCOMPLISHMENTS ....................................... 18-1
List of Tables
Page
Table 2-1 Schedule Milestones ............................................................................................... 2-3 Table 2-2 Budget and Expenditure Status ............................................................................... 2-3 Table 6-1 Quality Assurance Audit Summary .......................................................................... 6-1 Table 7-1 Schedule Status ...................................................................................................... 7-1 Table 7-2 Critical Path Summary ............................................................................................ 7-2 Table 7-3 Near-Term, Near-Critical with Less Than Three Months of Float ............................. 7-2 Table 8-1 Program Baseline Cost Estimate Summary ............................................................. 8-1 Table 8-2 Electrification Budget & Expenditure Status ............................................................ 8-2 Table 8-3 EMU Budget & Expenditure Status ......................................................................... 8-2 Table 10-1 Monthly Status of Risks ....................................................................................... 10-3 Table 10-2 Risk Classification ............................................................................................... 10-3 Table 13-1 Real Estate Acquisition Overview ........................................................................ 13-2 Table 14-1 Third-Party Agreement Status ............................................................................. 14-1
List of Figures Page
Figure 2-1 Working Segments ................................................................................................. 2-1 Figure 9-1 Funding Plan .......................................................................................................... 9-1
List of Appendices
Page
Appendix A – Acronyms .......................................................................................................... A-1
Appendix B – Schedule ........................................................................................................... B-1
Peninsula Corridor Electrification Project Monthly Progress Report
Background 1-1 February 28, 2017
1.0 BACKGROUND
Over the last decade, Caltrain has experienced a substantial increase in ridership and anticipates further increases in ridership demand as the San Francisco Bay Area’s population grows. The Caltrain Modernization (CalMod) Program, scheduled to be implemented by 2020, will electrify and upgrade the performance, operating efficiency, capacity, safety, and reliability of Caltrain’s commuter rail service.
The PCEP is a key component of the CalMod Program and consists of converting Caltrain from diesel-hauled to Electric Multiple Unit (EMU) trains for service between the San Francisco Station (at the intersection of Fourth and King Streets in San Francisco) and the Tamien Station in San Jose. Caltrain will continue Gilroy service and support existing tenants.
An electrified Caltrain will better address Peninsula commuters’ vision of environmentally friendly, fast and reliable service. Electrification will modernize Caltrain and make it possible to increase service while offering several advantages in comparison with existing diesel power use, including:
• Improved Train Performance, Increased Ridership Capacity and Increased Service: Electrified trains can accelerate and decelerate more quickly than diesel-powered trains, allowing Caltrain to run more efficiently. In addition, because of their performance advantages, electrified trains will enable more frequent and/or faster train service to more riders.
• Increased Revenue and Reduced Fuel Cost: An electrified Caltrain will increase ridership and fare revenues while decreasing fuel costs.
• Reduced Engine Noise Emanating from Trains: Noise from electrified train engines is measurably less than noise from diesel train engines. Train horns will continue to be required at grade crossings, adhering to current safety regulations.
• Improved Regional Air Quality and Reduced Greenhouse Gas Emissions: Electrified trains will produce substantially less corridor air pollution compared with diesel trains even when the indirect emissions from electrical power generation are included. Increased ridership will reduce automobile usage, resulting in additional air quality benefits. In addition, the reduction of greenhouse gas emissions will improve our regional air quality, and will also help meet the State’s emission reduction goals.
THIS PAGE INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Executive Summary 2-1 February 28, 2017
2.0 EXECUTIVE SUMMARY
The Monthly Progress Report is intended to provide an overview of the PCEP and provide funding partners, stakeholders, and the public an overall update on the progress of the project. This document provides information on the scope, cost, funding, schedule, and project implementation. Work along the Caltrain Electrification Corridor has been divided into four work segments as shown in Figure 2-1. PCEP activities are described and summarized by work segments.
Figure 2-1 PCEP Work Segments
Peninsula Corridor Electrification Project Monthly Progress Report
Executive Summary 2-2 February 28, 2017
The Federal Transit Administration (FTA) and Peninsula Corridor Joint Powers Board (JPB) completed all administrative and statutory requirements for the Full Funding Grant Agreement (FFGA) of $647 million in Core Capacity. On February 17, JPB was informed by the FTA that a decision was made to defer execution of the pending $647 million FFGA for the PCEP until the Administration developed the President’s Fiscal Year (FY) 2018 Budget. In light of this news, PCEP staff issued letters to Balfour Beatty Infrastructure, Inc. (BBI) for the Electrification Project and Stadler for the EMU Vehicles to extend the existing Limited Notice to Proceed (LNTP) to June 30, 2017. Once negotiations are completed regarding the LNTP extensions, each firm will be issued a contract amendment.
The PCEP team continues work with Balfour Beatty Infrastructure, Inc. (BBI) on 65% design and field investigations. The PCEP team completed review of the 65% OCS foundation and poles design and received 65% layout design for Segment 2 Work Area 5. The PCEP team continues coordination efforts related to signal systems and also conducting utility survey, pothole location layouts, and geotechnical boring layouts.
The PCEP team continues to work with Stadler on the technical aspects of the project. The PCEP team participated in Stadler design review meetings on structural elements and crash energy aspects of the carbody, truck and coupler. The PCEP team continues to address system-wide interface issues involving the emerging EMU design and the existing wayside infrastructure, the Electrification Project, the Communications Based Overlay Signal System (CBOSS) Project, and the Centralized Equipment Maintenance and Operations Facility (CEMOF) Design Upgrade.
2.1 Schedule
The Revenue Service Date (RSD) in the Master Program Schedule (MPS) remains unchanged. Without adjustment for contingency, the RSD is forecast as August 2021. With the addition of approximately five months of contingency to account for potential risk to the project, the RSD is anticipated as December 2021. Table 2-1 provides a summary of the current schedule and milestones. The overall schedule will be updated upon the execution of FFGA
2.2 Budget
A summary of the overall budget and expenditure status for the PCEP is provided in Table 2-2 below.
2.3 Board Actions
At the February 2, 2017 Board meeting, there were several items related to the PCEP:
• Informational item on the Peninsula Corridor Electrification Project Quarterly Update #9.
• Informational item on the Weekday Service Changes.
Peninsula Corridor Electrification Project Monthly Progress Report
Executive Summary 2-3 February 28, 2017
The agenda and meeting minutes for the February meeting can be found at the link below: http://www.caltrain.com/Assets/__Agendas+and+Minutes/JPB/Board+of+Directors/Agendas/2017/2017-02-02+JPB+Agenda.pdf (Note: For viewers accessing the link above electronically, please cut and paste the link into a browser if it does not direct you immediately to the document.)
Table 2-1 Schedule Status
Milestones1,2 Program Plan December January
Full Notice to Proceed to Electrification Contractor N/A 03/01/2017 03/01/2017
Full Notice to Proceed to EMU Manufacturer N/A 03/01/2017 03/01/2017
Start of Electrification Major Construction 03/20/2017 07/24/2017 07/24/2017
First Eight Miles of Electrification Complete to Begin Testing 04/08/2019 10/08/2019 10/08/2019
Delivery of 1st Vehicle 06/25/2019 07/30/2019 07/30/2019
Start Pre-Revenue Operations 09/08/2020 09/22/2020 09/22/2020
Potential Limited Service 12/31/2020 12/31/2020 12/31/2020
RSD (w/ Risk Contingency) 12/30/2021 12/30/2021 12/30/2021 Notes:
1 Milestones reported on this table may differ from the current schedule. As the schedule continues to be refined over the coming months to incorporate approved baseline schedules from the Electrification and EMU contractors, changes to milestones will be thoroughly vetted prior to reflecting those changes in the Monthly Report. 2 Program Plan only considered an NTP. It did not account for an LNTP and FNTP.
Table 2-2 Budget and Expenditure Status
Description of Work Budget Cost This Month Cost To Date Estimate To Complete
Estimate At Completion
(A) (B)1 (C)2 (D) (E) = (C) + (D) Electrification Subtotal $ 1,316,125,208 $ 8,179,189 $ 147,484,773 $ 1,168,640,435 $ 1,316,125,208 EMU Subtotal $ 664,127,325 $ 806,185 $ 19,400,512 $ 644,726,813 $ 664,127,325 PCEP TOTAL $ 1,980,252,533 $ 8,985,374 $ 166,885,285 $ 1,813,367,248 $ 1,980,252,533
2.4 Government and Community Affairs
A number of community relations and outreach events took place during the month of February. PCEP team gave a total of seven presentations to stakeholders.
THIS PAGE INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Electrification - Infrastructure 3-1 February 28, 2017
3.0 ELECTRIFICATION – INFRASTRUCTURE
This section reports on the progress of the Electrification, Supervisory Control and Data Acquisition (SCADA), and Tunnel Modification components. A brief description on each of the components is provided below.
3.1 Electrification
The Electrification component of the PCEP includes the installation of 138 miles of single-track and overhead contact system (OCS) for the distribution of electrical power to the EMUs. The OCS will be powered from a 25-kilovolt (kV), 60-Hertz (Hz), single phase, alternating current supply system consisting of two traction power substations (TPS), one switching station (SS), and seven paralleling stations (PS). Electrification will be performed using a design-build (DB) delivery method.
Activity This Month
• The PCEP team continued working with BBI on the 65% design and field investigations. The PCEP team completed review of the 65% OCS foundation and poles design and received 65% OCS Layout Design for Segment 2, Work Area 5 and 4. The reviews for those design packages are ongoing.
• The PCEP and BBI teams hold regular workshop meetings to discuss design related to the signal system, including the conversion from direct current (DC) to alternating current (AC) and the Constant Warning Time solution. The PCEP team is working with Caltrain Engineering and Construction to provide updated signal drawings to BBI for advancement of 65% design.
• BBI continued conducting utility surveys, pothole location layouts, and geotechnical boring layouts. Physical geotechnical boring and cone penetrometer tests (CPT) on the Caltrain right-of-way (ROW) continued in Segments 1 and 3, with additional borings completed as a result from previous borings.
• Potholing of utilities at proposed OCS locations continued in Segment 2. Results from potholing are used for design purposes in the 65% design submittals.
• Coordination efforts with Pacific Gas and Electric (PG&E) continued for infrastructure improvements and traction power substation interconnects. PCEP team completed review of scoping documents prepared by PG&E.
Activity Next Month
• The PCEP team will continue to work with BBI on design and field investigation activities. The designs will include the continued progression of the OCS and Signal systems along with advancement of design for Traction Power and other civil infrastructures.
• Geotechnical investigations corridor wide and potholing activities will continue in Segments 2.
Peninsula Corridor Electrification Project Monthly Progress Report
Electrification - Infrastructure 3-2 February 28, 2017
• In Segment 4, potholing activities will begin to support design of the signal system.
• Coordination efforts will continue with PG&E on interconnection design and final design for PG&E infrastructure. The PCEP team will complete the final Power Quality Study for PG&E. The PCEP and BBI teams are in the process of designing the 115 kV interconnection between PG&E and Caltrain’s future substations.
3.2 Supervisory Control and Data Acquisition (SCADA)
SCADA is a system that monitors and controls field devices for electrification, including substations, paralleling stations and sectionalization. SCADA will be integrated with the base operating system for Caltrain Operations and Control, which is the Rail Operations Center System (ROCS).
Activity This Month
• Activity continues to be limited to providing technical support on an as needed basis to the Caltrain Contract and Procurement (C&P) Department for the procurement of the SCADA system.
• Final procurement documents submitted to C&P.
Activity Next Month
• PCEP staff will continue to support Caltrain C&P on providing technical support during the procurement process.
3.3 Tunnel Modification
Tunnel modifications will be required on the four tunnels located in San Francisco. This effort is needed to accommodate the required clearance for the OCS to support electrification of the corridor. Outside of the PCEP scope, Caltrain Engineering and Construction has requested the PCEP team to manage completion of design and construction management for the Tunnel 1 and Tunnel 4 Drainage Rehab Project. The Drainage Rehab Project is funded separately from PCEP and will be a Design-Bid-Build (DBB) construction package. Construction will occur concurrently with the Electrification contractor’s efforts in Segment 1.
Activity This Month
• The PCEP team continued coordination efforts with the design team on drawings and specifications on Tunnel 1 and Tunnel 4 Drainage Rehab Project.
• PCEP team continued coordination efforts with Union Pacific Railroad (UPRR) and other stakeholders.
• The PCEP team continues to progress 95% design drawings and specifications for tunnel modification.
Peninsula Corridor Electrification Project Monthly Progress Report
Electrification - Infrastructure 3-3 February 28, 2017
Activity Next Month
• PCEP project team will complete the 95% design submittal for review.
• UPRR will be provided 95% drawings for review and comment.
• PCEP staff will review and resolve comments on 95% design drawings and specifications.
THIS PAGE IS INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Electric Multiple Units 4-1 February 28, 2017
4.0 ELECTRIC MULTIPLE UNITS
The EMU procurement component of the PCEP consists of the purchase of 96 Stadler EMUs. The EMUs will consist of both cab and non-cab units configured as 16 six-car units. Power will be obtained from the OCS via roof-mounted pantographs, which will power the axle-mounted traction motors. The EMUs will replace a portion of the existing diesel locomotives and passenger cars currently in use by Caltrain.
Activity This Month
• The PCEP team participated in Stadler design review meetings on structural elements and crash energy aspects of the carbody, truck and coupler.
• Stadler continued to progress numerous management submittals, including a Master Program Schedule, an updated Contract Deliverables Requirement List (CDRL), and updated System Safety and Quality Assurance Plans. The PCEP team is currently reviewing these submittals and working with Stadler to finalize these deliverables.
• Weekly conference calls were held with Stadler, Caltrain Operations, Maintenance, Quality Assurance members, and Safety and Security group representatives. The PCEP team also conducted a more in-depth Monthly Progress Review Meeting on February 23rd.
• The PCEP team continues to address system-wide interface issues involving the emerging EMU design and the existing wayside infrastructure, the Electrification Project, the CBOSS Project, and the CEMOF design upgrade.
• The PCEP team and Stadler participated in numerous coordination meetings regarding the EMU design to support Caltrain’s Operation and Maintenance objectives plus upcoming public outreach initiatives. Sample passenger seats, as well as interior, exterior, bicycle, toilet and wheel chair lift renderings and videos have been received and are being reviewed.
Activity Next Month
• PCEP team will review for approval several documents including the Quality Plan, the Master Project Schedule, the System Safety Plan and CDRL. PCEP team’s approval of the Master Program Schedule and Quality Plan are prerequisites for upcoming milestone payments to Stadler.
• Conceptual Design Reviews (CDRs) are to be conducted with Stadler for Train Control Networks, Monitoring and Diagnostics, Passenger Information System, Lighting, Positive Train Control (PTC)/CBOSS, and Train Interior appointments.
• An Interior Mockup for engineering review purposes is to be delivered to Caltrain in March.
Peninsula Corridor Electrification Project Monthly Progress Report
Electric Multiple Units 4-2 February 28, 2017
4.1 Centralized Equipment Maintenance and Operations Facility (CEMOF) Modifications
The CEMOF Modifications project will provide safe work areas for performing maintenance on the new EMUs.
Activity This Month
• The PCEP team advanced the conceptual design to consider alternatives for the modification of CEMOF. The alternatives continue to be reviewed with Caltrain Operations.
Activity Next Month
• Caltrain to decide on which alternative shall be pursued for 35% design development purposes.
Peninsula Corridor Electrification Project Monthly Progress Report
Safety 5-1 February 28, 2017
5.0 SAFETY
Safety and Security requirements and plans are necessary to comply with applicable laws and regulations related to safety, security, and emergency response activities. Safety staff coordinates with contractors to review and plan the implementation of contract program safety requirements. Safety project coordination meetings continue to be conducted on a monthly basis to promote a clear understanding of project safety requirements as defined in contract provisions and program safety documents.
• Safety staff continued to review BBI and Stadler’s safety and security contract documentation deliverables to ensure they meet PCEP requirements. Safety staff has been facilitating meetings with BBI and Stadler to advance project safety and security program implementation.
• Field visits were conducted to work sites to ensure that the Site Specific Work Plan (SSWP) was being followed by BBI and their subcontractors.
• A Fire/Life Safety Committee meeting was held on February 9, 2017 for the PCEP project. Monthly meetings will be held as the project continues.
• BBI low-rail and hi-rail equipment were inspected in conjunction with representatives from Transit America Services, Inc. (TASI) Maintenance of Equipment. As specified in Federal Railroad Administration (FRA) regulations, all new equipment is to be inspected prior to being placed in service.
• The PCEP team met with the San Francisco Municipal Transportation Agency (SFMTA) to discuss the 16th street crossing in compliance with environmental mitigation measures, which call for technical coordination with the PCEP and SFMTA regarding re-routing of the 22 electric trolley bus. Internal meetings were held to finalize the projects comments on the analysis.
Activity Next Month
• Monthly meeting for the Safety and Security Certification Review Committee (SSCRC) will be held.
• Monthly meeting for the Fire/Life Safety & Security Committee (FLSSC) will be held.
• A final meeting with SFMTA will be held to discuss 16th Street Preliminary Hazard Analysis (PHA).
• All staff safety meetings will be held with PCEP, BBI employees and subcontractors to reinforce the importance of safety in the field.
• Site visits to BBI subcontractor work areas for potholing operations are planned.
THIS PAGE IS INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Quality Assurance 6-1 February 28, 2017
6.0 QUALITY ASSURANCE
The Quality Assurance (QA) staff performs technical reviews for planning, implementing, evaluating, and maintaining an effective program to verify that all equipment, structures, components, systems, and facilities are designed, procured, constructed, installed, and maintained in accordance with established criteria and applicable codes and standards throughout the design, construction, startup and commissioning of the PCEP.
Activity This Month
• The audit of BBI’s design quality control and the OCS 65% design package remains open until the Design Quality Plan has been revised to include changes prompted by the audit findings.
• An audit of Parikh Geotechnical Labs has been closed. • QA review of Stadler’s BBI’s Quality Management Plan (QMP), which includes a
Design Quality Plan, was conducted with comments outstanding. • Staff meetings with BBI QA/Quality Control (QC) management representatives
continues bi-weekly. • QA staff submitted to PCEP Management a QA Resource Plan for 2017 and
beyond. • A Pre-award audit was conducted at Signet Testing Laboratories and the lab had
one finding.
Table 6-1 below provides details on the status of audits performed through the reporting period.
Table 6-1 Quality Assurance Audit Summary
Quality Assurance Activity This Reporting Period Total to Date
Internal Audits Conducted 0 16
External Audits Conducted 1 3
Audit Findings Issued 1 15
Audit Findings Open 3 3
Audit Findings Closed 5 12
Non-Conformances Open 1 0
Non-Conformances Issued 0 4
Non-Conformances Closed 0 4
Peninsula Corridor Electrification Project Monthly Progress Report
Quality Assurance 6-2 February 28, 2017
Activity Next Month
• Three audits are planned and scheduled: BBI Document Control, Construction Testing Services, and PGH Wong Design Package for Traction Power System at 65%.
• QA review of Stadler’s QMP revision for EMU procurement.
• Regularly scheduled design reviews and surveillances will begin on project design packages and will continue through the late summer.
Peninsula Corridor Electrification Project Monthly Progress Report
Schedule 7-1 February 28, 2017
7.0 SCHEDULE
The schedule provided in this Monthly Progress Report is the approved schedule from January 2017 due to the timeframe necessary to update and approve the schedule. As indicated in Table 7-1, the RSD, which is the date in which the project is deemed completed, remains unchanged in the MPS. Without adjustment for contingency, the RSD is forecast as August 2021. With the addition of approximately five months contingency to account for potential risk to the project, the RSD is anticipated as December 2021. A summary of the overall schedule status for the PCEP is provided in Table 7-1, which provides comparisons between the baseline schedule (Program Plan), the previous update (December 2016) and the current update (January 2017) to capture any potential changes in the schedule. A complete summary schedule can be found in Appendix B.
Items listed in Table 7-2 show the critical path activities/milestones for the PCEP. Table 7-3 lists near-critical activities on the horizon.
Notable Variances There were no notable variances this month.
Table 7-1 Schedule Status
Milestones1,2 Program Plan December January
Full Notice to Proceed to Electrification Contractor N/A 03/01/2017 03/01/2017
Full Notice to Proceed to EMU Manufacturer N/A 03/01/2017 03/01/2017
Start of Electrification Major Construction 03/20/2017 07/24/2017 07/24/2017
First Eight Miles of Electrification Complete to Begin Testing 04/08/2019 10/08/2019 10/08/2019
Delivery of First Vehicle 06/25/2019 07/30/2019 07/30/2019
Start Pre-Revenue Operations 09/08/2020 09/22/2020 09/22/2020
Potential Limited Service 12/31/2020 12/31/2020 12/31/2020
RSD (w/ Risk Contingency) 12/30/2021 12/30/2021 12/30/2021 Notes: 1 Milestones reported on this table may differ from the current schedule. As the schedule continues to be refined over the coming months to incorporate approved baseline schedules from the Electrification and EMU contractors, changes to milestones will be thoroughly vetted prior to reflecting those changes in the Monthly Report. 2 Program Plan only considered an NTP. It did not account for an LNTP and FNTP.
Peninsula Corridor Electrification Project Monthly Progress Report
Schedule 7-2 February 28, 2017
Table 7-2 Critical Path Summary
Activity Start Finish
Electrification Design to Begin Major Construction 09/06/2016 07/21/2017
EMU Design to Delivery of First Carbody 09/06/2016 10/13/2017
Electrification OCS Construction 07/24/2017 02/26/2020
Electrification Acceptance & Integrated Testing 02/26/2020 04/25/2020 PG&E Complete Infrastructure Upgrades to Provide Permanent Power1
08/31/2020 08/31/2020
Vehicle Manufacturing & Assembly to Provide First Five Trainsets
11/13/2017 09/09/2020
Pre-Revenue Operations 09/22/2020 12/10/2020
Potential Limited Service1 12/31/2020 12/31/2020
RSD w/out Risk Contingency1 08/16/2021 08/16/2021
RSD w/ Risk Contingency1 12/30/2021 12/30/2021
Note: 1Milestone activity
Table 7-3 Near-Term, Near-Critical with Less Than Three Months of Float
WBS Activity Responsibility
FTA Path to FFGA Project Delivery
Utilities PG&E Supplemental Agreement #3 for Final Design Approval Project Delivery
Utilities PG&E Final Design Project Delivery
Utilities Overhead Utility Relocation Project Delivery
Peninsula Corridor Electrification Project Monthly Progress Report
Budget and Expenditures 8-1 February 28, 2017
8.0 BUDGET AND EXPENDITURES
The summary of overall budget and expenditure status for the PCEP is shown in the following tables. Table 8-1 reflects the Electrification budget, Table 8-2 reflects the EMU budget, and Table 8-3 reflects the overall project budget.
Table 8-1 Electrification Budget & Expenditure Status
Description of Work Budget Cost This Month Cost To Date
Estimate To Complete
Estimate At Completion
(A) (B)1 (C)2 (D) (E) = (C) + (D)
ELECTRIFICATION Electrification3 $ 696,610,558 $ 6,112,850 $ 69,603,350 $ 627,007,208 $ 696,610,558 Tunnel Notching $ 11,029,649 $ - $ - $ 11,029,649 $ 11,029,649 Real Estate $ 28,503,369 $ 139,550 $ 5,811,305 $ 22,692,064 $ 28,503,369 Private Utilities $ 63,515,298 $ 600,820 $ 4,252,572 $ 59,262,726 $ 63,515,298 Management Oversight4 $ 141,526,164 $ 913,225 $ 64,206,105 $ 77,320,058 $ 141,526,164 Executive Management $ 7,452,866 $ 96,720 $ 2,916,394 $ 4,536,472 $ 7,452,866 Planning $ 7,281,997 $ 70,737 $ 4,326,508 $ 2,955,489 $ 7,281,997 Community Relations $ 2,789,663 $ 17,520 $ 919,797 $ 1,869,866 $ 2,789,663 Safety & Security $ 2,421,783 $ 31,206 $ 529,617 $ 1,892,166 $ 2,421,783 Project Management Services $ 19,807,994 $ 159,451 $ 7,273,286 $ 12,534,708 $ 19,807,994 Engineering & Construction $ 11,805,793 $ 39,970 $ 1,921,558 $ 9,884,236 $ 11,805,793 Electrification Engineering &
Management $ 50,461,707 $ 330,553 $ 15,895,123 $ 34,566,585 $ 50,461,707 IT Support $ 331,987 $ - $ 331,987 $ 0 $ 331,987 Operations Support $ 1,445,867 $ 10,973 $ 393,816 $ 1,052,051 $ 1,445,867 General Support $ 4,166,577 $ 50,411 $ 1,350,670 $ 2,815,908 $ 4,166,577 Budget / Grants / Finance $ 1,229,345 $ 24,229 $ 255,486 $ 973,858 $ 1,229,345 Legal $ 2,445,646 $ 25,763 $ 2,068,553 $ 377,094 $ 2,445,646 Other Direct Costs $ 5,177,060 $ 55,692 $ 1,689,953 $ 3,487,106 $ 5,177,060
Prior Costs 2002 - 2013 $ 24,707,878 $ - $ 24,333,358 $ 374,520 $ 24,707,878 TASI Support $ 55,275,084 $ 346,721 $ 1,453,391 $ 53,821,693 $ 55,275,084 Insurance $ 4,305,769 $ - $ 1,155,769 $ 3,150,000 $ 4,305,769 Environmental Mitigations $ 14,972,645 $ - $ 472,000 $ 14,500,645 $ 14,972,645 Required Projects $ 17,337,378 $ - $ 367,028.00 $ 16,970,350 $ 17,337,378 Maintenance Training $ 1,021,808 $ - $ - $ 1,021,808 $ 1,021,808 Finance Charges $ 5,056,838 $ 66,022 $ 163,253 $ 4,893,585 $ 5,056,838 Contingency $ 276,970,649 $ - $ - $ 276,970,649 $ 276,970,649 Owner's Reserve $ - $ - $ - $ - $ - ELECTRIFICATION SUBTOTAL $ 1,316,125,208 $ 8,179,189 $ 147,484,773 $ 1,168,640,435 $ 1,316,125,208 Notes regarding tables above:
1. Column B "Cost This Month" represents the cost of work performed this month. 2. Column C "Cost To Date" includes actuals (amount paid) and accruals (amount of work performed) to date. 3. Cost To Date for “Electrification” include 5% for Contractor’s retention until authorization of retention release. 4. The agency labor is actual through December 2016 and accrued from January 2017 to current reporting period.
Peninsula Corridor Electrification Project Monthly Progress Report
Budget and Expenditures 8-2 February 28, 2017
Table 8-2 EMU Budget & Expenditure Status
Description of Work Budget Cost This Month Cost To Date Estimate To
Complete Estimate At Completion
(A) (B)1 (C)2 (D) (E) = (C) + (D) EMU $ 550,899,459 $ - $ 1,242,300 $ 549,657,159 $ 550,899,459 CEMOF Modifications $ 1,344,000 $ - $ - $ 1,344,000 $ 1,344,000 Management Oversight3 $ 64,139,103 $ 765,720 $ 18,087,425 $ 46,051,679 $ 64,139,103 Executive Management $ 5,022,302 $ 63,236 $ 1,634,584 $ 3,387,718 $ 5,022,302 Community Relations $ 1,685,614 $ 16,042 $ 308,251 $ 1,377,363 $ 1,685,614 Safety & Security $ 556,067 $ 7,078 $ 162,947 $ 393,121 $ 556,067 Project Management Services $ 13,275,280 $ 95,813 $ 4,887,362 $ 8,387,919 $ 13,275,280 Engineering & Construction $ 89,113 $ - $ 23,817 $ 65,296 $ 89,113 EMU Engineering & Management $ 32,082,556 $ 483,426 $ 8,000,291 $ 24,082,265 $ 32,082,556 IT Support $ 1,027,272 $ 15,383 $ 240,664 $ 786,608 $ 1,027,272 Operations Support $ 1,878,589 $ 2,285 $ 298,097 $ 1,580,491 $ 1,878,589 General Support $ 2,599,547 $ 21,513 $ 648,817 $ 1,950,730 $ 2,599,547 Budget / Grants / Finance $ 712,123 $ 11,072 $ 136,480 $ 575,644 $ 712,123 Legal $ 1,207,500 $ 16,199 $ 705,595 $ 501,905 $ 1,207,500 Other Direct Costs $ 4,003,139 $ 33,673 $ 1,040,521 $ 2,962,618 $ 4,003,139 TASI Support $ 2,740,000 $ - $ - $ 2,740,000 $ 2,740,000 Required Projects $ 4,500,000 $ - $ - $ 4,500,000 $ 4,500,000 Finance Charges $ 1,941,800 $ 40,465 $ 70,787 $ 1,871,013 $ 1,941,800 Contingency $ 38,562,962 $ - $ - $ 38,562,962 $ 38,562,962 Owner's Reserve $ - $ - $ - $ - $ -
EMU SUBTOTAL3 $ 664,127,325 $ 806,185 $ 19,400,512 $ 644,726,813 $ 664,127,325 Notes regarding tables above:
1. Column B "Cost This Month" represents the cost of work performed this month. 2. Column C "Cost To Date" includes actuals (amount paid) and accruals (amount of work performed) to date. 3. The agency labor is actual through December 2016 and accrued for January 2017 to current reporting period.
Table 8-3 PCEP Budget & Expenditure Status
Description of Work Budget Cost This Month Cost To Date Estimate To Complete
Estimate At Completion
(A) (B)1 (C)2 (D) (E) = (C) + (D) Electrification Subtotal $ 1,316,125,208 $ 8,179,189 $ 147,484,773 $ 1,168,640,435 $ 1,316,125,208 EMU Subtotal $ 664,127,325 $ 806,185 $ 19,400,512 $ 644,726,813 $ 664,127,325 PCEP TOTAL $ 1,980,252,533 $ 8,985,374 $ 166,885,285 $ 1,813,367,248 $ 1,980,252,533
Notes regarding tables above: 1. Column B "Cost This Month" represents the cost of work performed this month. 2. Column C "Cost To Date" includes actuals (amount paid) and accruals (amount of work performed) to date.
Peninsula Corridor Electrification Project Monthly Progress Report
Funding 9-1 February 28, 2017
9.0 FUNDING
Figure 9-1 depicts a summary of the funding plan for the PCEP. It provides a breakdown of the funding partners as well as the allocated funds. As previously reported, all non-core capacity funds have been committed to the PCEP project. In February, the FTA informed the JPB it would be deferring execution of the FFGA until the Administration developed the President’s FY2018 Budget.
Figure 9-1 Funding Plan
THIS PAGE INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Risk Management 10-1 February 28, 2017
10.0 RISK MANAGEMENT
The risk management process is conducted in an iterative fashion throughout the life of the project. During this process, new risks are identified, other risks are resolved or managed, and potential impacts and severity modified based on the current situation. The Risk Management team’s progress report includes a summary on the effectiveness of the Risk Management Plan, any unanticipated effects, and any correction needed to handle the risk appropriately.
Risks are evaluated periodically and updated when needed. The Risk Management team has identified the following items as top risks for the project:
• Delay in execution of FFGA would cause a delay in issuing full NTP.
• Relocation of overhead utilities must precede installation of catenary wire and connections to TPSs. Relocation work will be performed by others and may not be completed to meet the DB contractor’s construction schedule.
• Upgrades to the PG&E power stations for permanent power may not be designed and constructed in time for initiation of limited revenue service.
• As-built drawings furnished to DB contractor could be incomplete thus affecting final design.
• Proposal to run a new duct bank from Caltrain ROW to the proposed TPS1 site that runs under UPRR rails would require additional coordination with UPRR, which may cause delays to the installation.
• TASI ability to deliver sufficient resources to support construction and testing for the electrification contract may cause delays to construction schedule.
• Delays to the CBOSS Project could affect testing activities.
• Relocation of underground utilities must precede construction of catenary pole foundations and may not be completed on time to meet the DB Contractor’s construction schedule.
Activity This Month
• Updates were made to risk descriptions, effects, and mitigations based upon weekly input from risk owners. Monthly cycle of risk updating was completed based on schedules established in the Risk Identification and Mitigation Plan.
• Risk retirement dates were updated based upon revisions to the project schedule and input from risk owners.
• Continued weekly monitoring of risk mitigation actions and publishing of the risk register.
Peninsula Corridor Electrification Project Monthly Progress Report
Risk Management 10-2 February 28, 2017
• The PCEP Risk Management Team attended Electrification, Project Delivery, and Systems Integration meetings to monitor developments associated with risks and to identify new risks.
• The Risk Assessment Committee convened to review risks proposed for retirement and major changes to grading of risks. Grading and descriptions of two risks were revised. Two potential new risks were referred for further development, mitigation, and grading. Continued discussion of reputational risk as a potential adjunct to current risk management efforts.
Tables 10-1 and 10-2 show the risks identified for the program. Risks are categorized as: top risk, upcoming risk, long lead, and all other risks. The categories are based on a rating scale composed of schedule and cost factors. Simply put, top risks are considered to have a significantly higher than average risk grade. Upcoming risks are risks for which mitigating action must be taken within 60 days. Long-lead risks are risks for which mitigating action must be taken as much as a year or more into the future. All other risks are risks not falling into other categories.
Table 10-1 Monthly Status of Risks
Total Number of Active Risks = 104
Peninsula Corridor Electrification Project Monthly Progress Report
Risk Management 10-3 February 28, 2017
Table 10-2 Risk Classification
Total Number of Active Risks = 104
Activity Next Month
• Update risk descriptions, effects, mitigations and retirement dates.
• Conduct weekly monitoring of risk mitigation actions and continue publishing risk register.
• Further develop reputational risk analysis and submit recommendation.
Peninsula Corridor Electrification Project Monthly Progress Report
Environmental 11-1 February 28, 2017
11.0 ENVIRONMENTAL
11.1 Permits
The PCEP requires environmental permits from the following agencies/federal regulations: Section 106 of the National Historic Preservation Act of 1966 (NHPA), Section 7 of the Endangered Species Act (ESA), United States Army Corps of Engineers (USACE), San Francisco Bay Regional Water Quality Control Board (SFBRWQCB), the California Department of Fish and Wildlife (CDFW), and the San Francisco Bay Conservation Development Commission (SFBCDC).
Section 106 of the NHPA process as well as Section 7 of the ESA process have concluded.
Activity This Month
• All environmental permits have been obtained.
Activity Next Month
• There are no planned permit activities in the next month.
11.2 Mitigation Monitoring and Reporting Program (MMRP)
The California Environmental Quality Act (CEQA) requires that a Lead Agency establish a program to monitor and report on mitigation measures that it has adopted as part of the environmental review process. The PCEP team has prepared a MMRP to ensure that mitigation measures identified in the PCEP Environmental Impact Report (EIR) are fully implemented during project implementation. PCEP will implement the mitigation measures through its own actions, those of the DB contractor and actions taken in cooperation with other agencies and entities. The MMRP is available on the Caltrain website:
http://www.caltrain.com/Assets/Caltrain+Modernization+Program/Electrification+Documents/MMRP.pdf (Note: For viewers accessing the link above electronically, please cut and paste the link into a browser if it does not direct you immediately to the document.)
Activity This Month
• Biological, archaeological, and Native American monitors continued to be present during design phase investigation activities (geotechnical and potholing activities) occurring in areas that require environmental compliance monitoring. The monitoring was conducted in accordance with measures in the MMRP in an effort to minimize potential impact on sensitive environmental resources.
• Protocol-level surveys for a sensitive avian species continue at previously identified potential habitat locations and inspections of over-passes and bridges
Peninsula Corridor Electrification Project Monthly Progress Report
Environmental 11-2 February 28, 2017
initiated in order to determine the potential for nesting swallows were completed, and surveys for nesting birds ahead of design phase activities were initiated (nesting bird season is February 1st through August 31st).
• An architectural historian continued to take photos and document site conditions at a number of historic railroad stations in support of historic documentation required as part of the MMRP.
Activity Next Month
• Biological, archaeological, and Native American monitors will continue to monitor design phase investigation activities (geotechnical and potholing activities) occurring in areas that require environmental compliance monitoring. Biological surveyors will continue surveys for nesting birds ahead of design phase investigation activities occurring during the nesting bird season (February 1st through August 31st) and will continue to conduct protocol level surveys for sensitive avian species.
Peninsula Corridor Electrification Project Monthly Progress Report
Utility Relocation 12-1 February 28, 2017
12.0 UTILITY RELOCATION
Implementation of the PCEP requires relocation or rerouting of both public and private utility lines and/or facilities. Utility relocation will require coordination with many entities, including regulatory agencies, public safety agencies, federal, state, and local government agencies, private and public utilities, and other transportation agencies and companies. This section describes the progress specific to the utility relocation process.
Activity This Month
• PCEP team continued monthly coordination meetings with telecommunication and power utilities. These meetings focused on overall project and relocation schedules, designation of responsibilities, applicable design standards, and reconciliation of agreements and records.
• Work continued with all utilities on review of overhead utility line relocations based on the current preliminary design. This effort is expected to continue for the next several months to support identification and confirmation, agreements, and design of all relocations.
• PCEP team sent relocation notices and requested design information to PG&E as a part of the relocation process.
• PCEP team continued to work with Verizon on the relocation of fiber optics cable within the Caltrain ROW.
Activity Next Month
• Monthly meetings will continue with telecom and power carriers.
• PCEP team will continue to send relocation notices to utility owners and will also continue to provide design information for relocation designs.
• PCEP team will continue to work with utility owners to update the relocation schedule.
THIS PAGE INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Real Estate 13-1 February 28, 2017
13.0 REAL ESTATE
The PCEP requires the acquisition of a limited amount of real estate. In general, Caltrain uses existing rights-of-way (ROW) for the PCEP, but in certain locations, will need to acquire small portions of additional real estate to expand the ROW to accommodate installation of OCS supports (fee acquisitions or railroad easements ) and associated Electrical Safely Zones (easements). There are two larger full acquisition areas required for wayside facilitates (i.e., traction power stations, switching stations and paralleling stations). The PCEP real estate team (RE team) manages the acquisition of all property rights. Caltrain does not need to acquire real estate to complete the EMU procurement portion of the PCEP.
Activity This Month
Table 13-1 below provides a brief summary of the Real Estate acquisition overview for the project.
• The RE team continues negotiations on offers pending, including working through relocation of two commercial businesses.
• The agency continues to negotiate the cooperative agreement for eminent domain authority with the City & County of San Francisco. The target for completion is May 2017.
• Three appraisals were updated and offers will be made in April.
Activity Next Month
• Negotiations for all outstanding offers will continue.
• The PCEP team issued work directives to appraise and acquire parcels in Segments 1 and 3 and appraisals commenced.
• It is anticipated that properties will close escrow for grantors who have accepted the offers.
Peninsula Corridor Electrification Project Peninsula Corridor Electrification Project Monthly Progress Report
Real Estate 13-2 February 28, 2017
Table 13-1 Real Estate Acquisition Overview
Segment No. of
Parcels Needed*
No. of Appraisals Completed
Offers Presented
Offers Accepted
Acquisition Status
Escrow Closed
Value Litigation
Parcel Possession
Segment 1 8 0 0 0 0 0 0
Segment 2 27 24 21 5 1 0 0
Segment 3 11 0 0 0 0 0 0
Segment 4 10 10 9 0 0 0 0
Total 56 34 30 5 1 0 0 Note: During design development, the real estate requirements may adjust to accommodate design refinements. Parcel requirements will adjust accordingly. The table in this report reflects the current property needs for the Project.
Peninsula Corridor Electrification Project Monthly Progress Report
Third Party Agreements 14-1 February 28, 2017
14.0 THIRD PARTY AGREEMENTS
Third-party coordination is necessary for work impacting public infrastructure, utilities, ROW acquisitions, and others. The table below outlines the status of necessary agreements for the PCEP.
Table 14-1 Third-Party Agreement Status
Type Agreement Third-Party Status
Governmental Jurisdictions
Construction & Maintenance1
City & County of San Francisco In Process City of Brisbane Executed City of South San Francisco Executed City of San Bruno Executed City of Millbrae Executed City of Burlingame Executed City of San Mateo Executed City of Belmont Executed City of San Carlos Executed City of Redwood City Executed City of Atherton In Process County of San Mateo Executed City of Menlo Park Executed City of Palo Alto In Process City of Mountain View Executed City of Sunnyvale Executed City of Santa Clara Executed County of Santa Clara Executed City of San Jose Executed
Condemnation Authority San Francisco In Process San Mateo Executed Santa Clara Executed
Utilities Infrastructure Pacific Gas & Electric (PG&E) Executed
3
Operating Rules California Public Utilities Commission (CPUC) Executed2
Transportation & Railroad
Construction & Maintenance Bay Area Rapid Transit (BART) Executed4 Construction & Maintenance California Dept. of Transportation (Caltrans) Not needed5
Trackage Rights Union Pacific Railroad (UPRR) Executed4
Notes regarding table above: 1. Agreements memorialize the parties’ consultation and cooperation, designate respective rights and obligations
and ensure cooperation between the JPB and the cities and counties in connection with the design and construction of the PCEP. A comprehensive agreement is planned for each of the 17 cities and three counties along the Caltrain ROW and within the PCEP limits.
2. Approved by City Council, or Board of Supervisors, and awaiting signature for execution. 3. The Master agreement and supplemental agreements 1, 2 and 5 have been executed. Supplemental agreements
3 and 4 are to be negotiated and executed. 4. Utilizing existing agreements. 5. Caltrans Peer Process utilized. Formal agreement not needed.
THIS PAGE IS INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Government and Community Affairs 15-1 February 28, 2017
15.0 GOVERNMENT AND COMMUNITY AFFAIRS
The Community Relations and Outreach team coordinates all issues with all jurisdictions, partner agencies, government organizations, businesses, labor organizations, local agencies, residents, community members, other interested parties, and the media. In addition, the team oversees the DB contractor’s effectiveness in implementing its Public Involvement Program. The following PCEP related external affairs meetings took place in February:
• Presentations/Meetings
– Caltrain Accessibility Advisory Committee – City/County Staff Coordinating Group – JPB Citizen Advisory Committee – JPB Bicycle Advisory Committee – SFCTA Citizen Advisory Committee – Local Policy Maker Group – SMCTA Citizen Advisory Committee
• Third Party/Stakeholder Actions
No actions to report this month.
THIS PAGE IS INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
DBE Participation 16-1 February 28, 2017
16.0 DISADVANTAGED BUSINESS ENTERPRISE (DBE) PARTICIPATION AND LABOR STATISTICS
DBE and labor statistics will be reported after construction has commenced.
THIS PAGE INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Procurement 17-1 February 28, 2017
17.0 PROCUREMENT
Contract Activity
• Issued letters to BBI for the DB Electrification Project and Stadler US for the Bi-Level EMU Vehicles to extend the LNTP to June 30, 2017. Once negotiations are completed regarding the LNTP extensions, each firm will be issued a contract amendment.
Invitation for Bid (IFB)/Request for Qualifications (RFQ)/ Request for Proposals (RFP) Advertised this Month:
• RFQ issued for On-Call Ambassador Support Services for six-month term.
IFB/RFQ/RFP Received this Month:
• No IFB/RFQ/RFPs were received for February.
Contract Awards this Month:
• No contract awards were made for February.
Work Directive (WD)/Purchase Order (PO) Awards & Amendments this Month:
• Multiple WDs & POs were issued to support the program needs for February.
Upcoming IFB/RFQ/RFP:
• RFP - SCADA system to support CalMod. (Issue in early April)
• RFP - On-Call Ambassador Support Services. (Issue in Mid-April)
• RFP - On-Call Quality Assurance Independent Testing Laboratory (Late April)
Upcoming Contract Awards:
• No upcoming contract awards.
THIS PAGE IS INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Timeline 18-1 February 28, 2017
18.0 TIMELINE OF MAJOR PROJECT ACCOMPLISHMENTS
Below is a timeline showing major project accomplishments from 2002 to 2017:
Date Milestone 2002 Conceptual Design Completed
2004 Draft NEPA Environmental Assessment (EA)/Environmental Impact
Report (EIR) (2004)
2008 35% design complete
2009 Final NEPA EA/EIR and Finding of No Significant Impact (FONSI)
2014 Request for Qualifications (RFQ) for Electrification Request for Information for EMU
2015 JPB Approves Final CEQA Environmental Impact Report (EIR) JPB Approves Issuance of RFP for Electrification JPB Approves Issuance of RFP for EMU
Receipt of Electrification of Proposal for Electrification FTA approval of Core Capacity Project Development
2016 JPB Approves EIR Addendum #1: PS-7 FTA Re-Evaluation of 2009 FONSI Receipt of Electrification BAFOs Receipt of EMU Proposal Application for Entry to Engineering to FTA Completed the EMU Buy America Pre-Award Audit and Certification Negotiations completed with Stadler for EMU Vehicles Negotiations completed with BBI, the apparent best-value Electrification
firm JPB Approves Contract Award (LNTP) BBI JPB Approves Contract Award (LNTP) Stadler
FTA approval of Entry into Engineering for the Core Capacity Program
2017 FTA finalized the FFGA for $647 million in Core Capacity funding
THIS PAGE INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Appendices February 28, 2017
APPENDICES
THIS PAGE IS INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Appendix A February 28, 2017
Appendix A – Acronyms
THIS PAGE IS INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Acronyms A-1 February 28, 2017
AIM Advanced Information
Management
ARINC Aeronautical Radio, Inc.
BAAQMD Bay Area Air Quality Management District
BBI Balfour Beatty Infrastructure, Inc.
CAISO California Independent System Operator
CalMod Caltrain Modernization Program
Caltrans California Department of Transportation
CBOSS Communication Based Overlay Signal System
CDFW California Department of Fish and Wildlife
CDR Conceptual Design Review
CDRL Contract Deliverables Request List
CEMOF Centralized Equipment Maintenance and Operations Facility
CEQA California Environmental Quality Act (State)
CHSRA California High-Speed Rail Authority
CIP Capital Improvement Plan
CPT Cone Penetrometer Test
CPUC California Public Utilities Commission
DB Design-Build
DBB Design-Bid-Build
DBE Disadvantaged Business Enterprise
DEMP Design, Engineering, and Management Planning
EA Environmental Assessment
EAC Estimate at Completion
EIR Environmental Impact Report
EMU Electric Multiple Unit
ESA Endangered Species Act
ESA Environmental Site Assessments
FEIR Final Environmental Impact Report
FFGA Full Funding Grant Agreement
FLSSC Fire/Life Safety & Security Committee
FONSI Finding of No Significant Impact
FRA Federal Railroad Administration
FTA Federal Transit Administration
GO General Order
HSR High Speed Rail
ICD Interface Control Document
IFB Invitation for Bid
ITS Intelligent Transportation System
JPB Peninsula Corridor Joint Powers Board
Peninsula Corridor Electrification Project Monthly Progress Report
Acronyms A-2 February 28, 2017
LNTP Limited Notice to Proceed
MMRP Mitigation, Monitoring, and Reporting Program
MOU Memorandum of Understanding
MPS Master Program Schedule
NCR Non Conformance Report
NEPA National Environmental Policy Act (Federal)
NHPA National Historic Preservation Act
NMFS National Marine Fisheries Service
NTP Notice to Proceed
OCS Overhead Contact System
PCEP Peninsula Corridor Electrification Project
PCJPB Peninsula Corridor Joint Powers Board
PG&E Pacific Gas and Electric
PHA Preliminary Hazard Analysis
PMOC Project Management Oversight Contractor
PO Purchase Order
PS Paralleling Station
PTC Positive Train Control
QA Quality Assurance
QC Quality Control
QMP Quality Management Plan
QMS Quality Management System
RAMP Real Estate Acquisition Management Plan
RE Real Estate
RFI Request for Information
RFP Request for Proposals
RFQ Request for Qualifications
ROCS Rail Operations Center System
ROW Right-of-Way
RRP Railroad Protective Liability
RSD Revenue Service Date
RWP Roadway Worker Protection
SAMCEDA San Mateo County Economic Development Association
SamTrans San Mateo County Transit District
SCADA Supervisory Control and Data Acquisition
SCC Standard Cost Code
SPUR San Francisco Bay Area Planning and Urban Research Association
SFBCDC San Francisco Bay Conservation Development Commission
SFCTA San Francisco County Transportation Authority
SFMTA San Francisco Municipal Transportation Agency
SFRWQCB San Francisco Regional Water Quality Control Board
Peninsula Corridor Electrification Project Monthly Progress Report
Acronyms A-3 February 28, 2017
SOGR State of Good Repair
SS Switching Station
SSCP Safety and Security Certification Plan
SSCRC Safety & Security Certification Review Committee
SSMP Safety and Security Management Plan
SSWP Site Specific Work Plan
TASI Transit America Services Inc.
TBD To Be Determined
TPS Traction Power Substation
TVA Threat and Vulnerability Assessment
UPRR Union Pacific Railroad
USACE United States Army Corp of Engineers
USFWS U.S. Fish and Wildlife Service
VTA Santa Clara Valley Transportation Authority
WD Work Directive
THIS PAGE IS INTENTIONALLY LEFT BLANK
Peninsula Corridor Electrification Project Monthly Progress Report
Schedule February 28, 2017
Appendix B – Schedule
THIS PAGE IS INTENTIONALLY LEFT BLANK
# Activity Name Duration Start Finish
1 MASTER CPM SCHEDULE C15.07 2001d 05/01/14 A 12/30/21
2 MILESTONES 2001d 05/01/14 A 12/30/21
3 PLANNING / APPROVALS PHASE 929d 05/01/14 A 11/22/17
4 ENVIRONMENTAL 466d 05/01/14 A 02/11/16 A
5 DESIGN/BUILDER PROCUREMENT 596d 05/01/14 A 09/02/16 A
6 AGENCY COORDINATION / APPROVALS 635d 10/01/14 A 03/31/17
7 FEDERAL TRANSIT ADMINISTRATION 466d 04/16/15 A 02/15/17
8 JURISDICTIONAL AGREEMENTS 635d 10/01/14 A 03/31/17
9 CALIFORNIA PUBLIC UTILITIES COMMISSION 515d 11/03/14 A 11/10/16 A
10 PACIFIC GAS & ELECTRIC 612d 11/03/14 A 03/31/17
11 CALIFORNIA DEPARTMENT OF TRANSPORTATION 322d 02/02/15 A 05/05/16 A
12 BAY AREA RAPID TRANSIT DISTRICT 221d 06/18/15 A 04/29/16 A
13 SANTA CLARA VALLEY TRANSPORTATION AUTHORITY 242d 06/18/15 A 05/31/16 A
14 LABOR AGREEMENT 128d 01/02/15 A 07/02/15 A
15 UTILITIES 486d 04/01/15 A 02/28/17
16 PERMITS 468d 12/01/14 A 09/30/16 A
17 RIGHT-OF-WAY 732d 02/02/15 A 11/22/17
18 SCADA 526d 03/30/15 A 04/21/17
19 DESIGN / ENGINEERING PHASE 960d 10/01/14 A 07/12/18
20 PG&E INFRASTRUCTURE 346d 03/03/17 07/12/18
21 TUNNEL MODIFICATION 845d 10/31/14 A 03/01/18
22 CEMOF 804d 10/01/14 A 11/30/17
23 VEHICLES PHASE 1902d 05/01/14 A 08/13/21
24 SPECIFICATION 134d 07/01/14 A 01/12/15 A
25 PROCUREMENT 613d 05/01/14 A 09/06/16 A
26 DETAILED DESIGN (STADLER) 364d 09/06/16 A 02/12/18
27 PROCUREMENT (MATERIAL & EQUIPMENT) (STADLER) 416d 01/09/17 A 08/24/18
28 MOCK-UPS (STADLER) 202d 12/15/16 A 09/29/17
29 ELECTRIC LOCO 834d 03/01/17 06/10/20
30 MANUFACTURING, TESTING, & TAKE OVER (STADLER) 953d 11/13/17 08/13/21
31 CONSTRUCTION / INSTALLATION PHASE 853d 04/21/17 08/31/20
32 PG&E INFRASTRUCTURE 699d 12/01/17 08/31/20
33 TUNNEL MODIFICATION 313d 03/02/18 05/24/19
34 SCADA 764d 04/21/17 04/24/20
35 CEMOF 109d 12/01/17 05/04/18
36 TESTING / STARTUP PHASE 426d 04/27/20 12/30/21
37 PRE-REVENUE OPERATIONS 236d 09/10/20 08/13/21
38 REVENUE OPERATIONS 172d 12/11/20 08/16/21
39 RISK CONTINGENCY 426d 04/27/20 12/30/21
40 OPERATIONAL READINESS PHASE 791d 06/28/17 08/07/20
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 32014 2015 2016 2017 2018 2019 2020 2021 2022
MASTER CPM SCHEDULE C15.07... Data Date: 02/01/17 _PCEP C15.07 Summary FOR INTERNAL USE ONLY 02/28/17 12:55
Prog Plan (C14.02)
Last Months Update
Progress
Remaining
Near Critical
Critical
Start Milestone
Finish Milestone
Prog Plan (C14.02)
Last Months Update
Critical Milestone
Risk Contingency
Page 1 of 2
Filename: _C15.07 022217...
Date Revision Checked Approved02/22/2017 Updates & Revisions Completed By A. Christofas & S. Iyer02/23/2017 Checked By S. Iyer & A. Christofas x02/27/2017 Approved By R. Viswanathan x
# Activity Name Duration Start Finish
41 OPERATIONS & MAINTENANCE STAFFING 543d 06/28/17 08/16/19
42 NON-REVENUE EQUIPMENT 258d 08/05/19 08/07/20
43 SPARES 258d 08/05/19 08/07/20
44 OPERATIONS & MAINTENANCE TRAINING 255d 06/28/17 06/28/18
45 LOCAL AGENCY TRAINING 64d 03/22/18 06/20/18
46 ELECTRIFICATION SCHEDULE (BB) 020117 1606d 09/06/16 A 10/13/20
47 General 1606d 09/06/16 A 10/13/20
48 General 1551d 09/06/16 A 08/23/20
49 Communication 69d 11/22/16 A 02/28/17
50 Sitework 91d 09/07/16 A 12/23/16 A
51 Civil 129d 10/03/16 A 04/03/17
52 Traction Power 45d 12/19/16 A 02/17/17
53 Rail Signal & Comm System 1126d 11/22/16 A 10/08/19
54 Testing & Start-up 639d 02/25/19 10/13/20
55 Deleted Activities 530d 02/01/17 06/11/18
56 Design 1359d 09/06/16 A 02/25/20
57 All Work Areas 1359d 09/06/16 A 02/25/20
58 Segments 2 WA 5 370d 09/07/16 A 08/17/17
59 Segment 2 WA 4 & 5 213d 04/21/17 11/05/17
60 Segment 2 WA 4 430d 09/07/16 A 10/12/17
61 Segment 2 & 4 460d 09/07/16 A 11/10/17
62 Segment 4 654d 09/12/16 A 05/14/18
63 Segment 2 559d 09/07/16 A 02/10/18
64 Segment 2 Wa's 1, 2, & 3- 475d 10/12/16 A 12/28/17
65 Segment 1 & 3 828d 09/19/16 A 10/30/18
66 Segment 1 737d 02/01/17 12/20/18
67 Segment 3 893d 01/17/17 A 04/29/19
68 Submittals 166d 09/06/16 A 02/07/17
69 Procurement 654d 01/30/17 A 10/01/18
70 All Work Areas 268d 01/30/17 A 02/16/18
71 Segment 4 192d 07/25/17 01/20/18
72 Segment 2 174d 06/21/17 11/29/17
73 Segment 1 451d 08/07/17 10/01/18
74 Segment 3 372d 08/07/17 07/19/18
75 Permits 498d 02/01/17 01/18/19
76 Construction / Installation 1298d 11/02/16 A 02/26/20
77 Segment 4 971d 02/13/17 08/09/19
78 Segment 2 974d 11/02/16 A 04/29/19
79 Segment 1 1150d 03/16/17 02/24/20
80 Segment 3 1153d 03/17/17 02/26/20
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 32014 2015 2016 2017 2018 2019 2020 2021 2022
MASTER CPM SCHEDULE C15.07... Data Date: 02/01/17 _PCEP C15.07 Summary FOR INTERNAL USE ONLY 02/28/17 12:55
Prog Plan (C14.02)
Last Months Update
Progress
Remaining
Near Critical
Critical
Start Milestone
Finish Milestone
Prog Plan (C14.02)
Last Months Update
Critical Milestone
Risk Contingency
Page 2 of 2
Filename: _C15.07 022217...
Date Revision Checked Approved02/22/2017 Updates & Revisions Completed By A. Christofas & S. Iyer02/23/2017 Checked By S. Iyer & A. Christofas x02/27/2017 Approved By R. Viswanathan x
Page 1 of 2
AGENDA ITEM # 10
APRIL 6, 2017
PENINSULA CORRIDOR JOINT POWERS BOARD
STAFF REPORT
TO: Joint Powers Board
THROUGH: Jim Hartnett
Executive Director
FROM: Mark Simon
Chief of Staff
SUBJECT: CALTRAIN BUSINESS PLAN
ACTION
This report is for information only. No Board action is required.
SIGNIFICANCE
At the April Board meeting, Peninsula Corridor Joint Powers Board (JPB) staff will make
an informational presentation to seek feedback on the proposed work program for the
development of a Caltrain Business Plan.
The Caltrain Business Plan will be an implementing document for the Caltrain Strategic
Plan (2014) that also builds upon the 10-year, fiscally constrained capital and operating
plans included in the forthcoming Caltrain Short Range Transit Plan (SRTP). When
completed, the Business Plan will:
• Provide a framework for addressing the expanding demands for traffic
congestion relief in the region and begin to define the potential role for Caltrain
in addressing that significant issue
• Develop a framework for addressing JPB’s ongoing and unsustainable operating
and capital funding, including a range of near-term and long-term options for
further consideration
• Outline the potential range of improved Caltrain services that are enabled by
the system’s electrification and articulate the benefits and costs associated with
each
• Identify supplemental capital projects needed to fully modernize the railroad
and realize the full benefit of the public’s investment in electrification
• Develop cost, revenue and funding targets that support improved Caltrain
services and ensure the agency’s ongoing financial stability
• Define opportunities for the long-term expansion of the Caltrain system and
develop a consistent business framework for ongoing coordination with regional
and State projects
• Develop a long-range, unconstrained vision for Caltrain and define the capital
and operating needs necessary to achieve that vision
Page 2 of 2
Critically, the Business Plan will also form the basis for the JPB’s participation in potential
local, regional and state funding initiatives contemplated in the 2018 timeframe.
BUDGET IMPACT
There is no impact on the budget.
BACKGROUND
The Board adopted Caltrain’s Strategic Plan in 2014, setting a vision for the agency to
provide a safe, reliable, sustainable modern rail system that meets the growing mobility
needs of the San Francisco Bay Area region. Within this broad vision, the plan
elaborates a range of focus areas, goals and objectives that provide guidance around
critical policy and business choices.
Since the plan’s adoption, the JPB has significantly advanced its Modernization
Program. The agency has environmentally cleared the Peninsula Corridor Electrification
Project (PCEP) at both the State and Federal levels and has issued limited notice to
proceed contracts for the construction of both the electrified infrastructure and electric
multiple unit trains. During this time the agency has also adopted a SRTP providing a
baseline, 10-year projection of one way that Caltrain’s service and capital plans could
evolve in the context of an electrified system.
As the PCEP moves into construction, the JPB has the opportunity to refocus its business
model and ensure that it is taking full advantage of the public’s investment in an
electrified system. This means evaluating a range of options for improving and
expanding rail services and better understanding their benefits and costs to Caltrain’s
customers and the region. The JPB also needs to identify additional capital investments
that may be needed to supplement and complement electrification to truly enhance
and modernize the entire railroad.
Planning for Caltrain’s business success also means achieving financial stability by
aligning the railroad’s costs and service delivery with available revenue streams.
Lacking a dedicated funding source beyond fare box revenues, Caltrain has struggled
with its annual budgets. The lack of a dedicated funding source has the potential to
undermine Caltrain’s ability to maintain the system and sustain levels of service that
meet the needs of the region. Caltrain’s Business Plan will seek to identify new revenue
streams and funding sources and will establish framework for controlling costs and
ensuring long term financial stability for the railroad and its funding partners.
Prepared by: Sebastian Petty, Senior Policy Advisor 650.622.7831
Page 1 of 2
AGENDA ITEM # 11
APRIL 6, 2017
PENINSULA CORRIDOR JOINT POWERS BOARD
STAFF REPORT
TO: Joint Powers Board
THROUGH: Jim Hartnett
Executive Director
FROM: Michelle Bouchard
Chief Operating Officer, Rail
SUBJECT: CALTRAIN SHORT RANGE TRANSIT PLAN – DRAFT ELEMENTS
ACTION
This report is for information only. No Board action is required.
SIGNIFICANCE
The Metropolitan Transportation Commission (MTC) requires San Francisco Bay Area
transit districts periodically to prepare and submit Short Range Transit Plans (SRTP)
describing their systems and policies and identifying 10-year operating and capital
plans. Caltrain’s most recent SRTP was adopted in 2015 and covers fiscal years 2015-
2024.
Throughout 2016, Caltrain staff has worked to develop an updated SRTP covering fiscal
years 2017-2026. The development of the updated SRTP has been conducted in
accordance with MTC’s published guidelines and has been coordinated with financial
capacity work undertaken as part of Caltrain’s participation in the Federal Transit
Administration’s (FTA) Core Capacity Grant Program.
At its December 2016 meeting the Board directed staff that this SRTP be financially
constrained to ensure consistency with financial plan documents submitted to FTA and
to demonstrate Caltrain’s commitment to maintaining its assets in a State of Good
Repair.
At the April meeting staff will present an overview of key elements in Caltrain’s
forthcoming SRTP including highlights of the proposed FY2017-2026 operating and
capital improvement plans.
Following the April Board meeting, staff will complete and submit a draft SRTP
document to MTC for review and confirmation of conformance with MTC’s guidelines.
This draft will also be provided to the Board and will be posted on Caltrain’s website.
Based on the timing and outcome of MTC’s review, staff anticipates returning to the
Board in the spring of 2017 with a final draft SRTP and to ask the Board to consider
adoption at that time.
Page 2 of 2
BUDGET IMPACT
There is no impact on the budget.
BACKGROUND
Prior to 2010, MTC required Bay Area transit operators to prepare full SRTPs every four
years and shorter, “mini” SRTPS annually. Caltrain last completed a “full” SRTP in 2008
and completed a “mini” SRTP in 2009. In 2010, MTC initiated the Transit Sustainability
Project (TSP) and temporarily suspended the requirement that operators produce SRTPs.
In the fall of 2013, following completion of the TSP, MTC renewed its requirement that
the largest seven transit agencies in the Bay Area (Alameda Contra-Costa Transit, Bay
Area Rapid Transit, Caltrain, Golden Gate Transit, San Francisco Municipal
Transportation Authority, SamTrans, and Santa Clara Valley Transportation Authority)
complete and submit SRTPs. The Board adopted Caltrain’s current SRTP in 2015 and staff
began work on an update to the SRTP in 2016.
The Caltrain SRTP serves as a midterm planning document that is used by MTC to inform
the development of the Regional Transportation Plan (RTP) and Transportation
Improvement Plan (TIP), which fulfills key regulatory requirements of the FTA. In addition
to fulfilling a regional planning function, the SRTP provides Caltrain with a venue to
concisely describe its existing system and policies as well as its future operating and
capital plans for the next 10 years.
Prepared by: Sebastian Petty, Senior Policy Advisor 650.622.7831
Page 1 of 6
AGENDA ITEM # 12
APRIL 6, 2017
PENINSULA CORRIDOR JOINT POWERS BOARD
STAFF REPORT
TO: Joint Powers Board
THROUGH: Jim Hartnett
Executive Director
FROM: Michelle Bouchard
Chief Operating Officer, Rail
SUBJECT: KEY CALTRAIN PERFORMANCE STATISTICS FEBRUARY 2017
In February 2017, Caltrain’s average weekday ridership (AWR) decreased 3.7 percent
to 57,618 from February 2016 AWR of 59,831. The total number of passengers who rode
Caltrain in February 2017 also decreased 7.5 percent to 1,392,561 from 1,506,185 in
February 2016. Ridership was unusually high in February 2016 due to Super Bowl 50
events and festivities which carried 66,582 extra riders along the Caltrain corridor.
Without Super Bowl 50 ridership, February 2016 AWR reduces to 56,974 and
February 2017 AWR increases by 1.1 percent. In addition, inclement weather this winter
attributed to the decrease in ridership for February 2017. This is California’s wettest year
on record. Local rain fall precipitation in February 2017 increased 734 percent to
7.09 inches from 0.85 inches in February 2016. Staff continues to monitor ticket types
sold to identify other potential trends. This month, with the exception of Eligible Discount
(ED) – Monthly ticket sales are up 4.0 percent, all other ticket types sold decreased from
February 2016. Farebox revenue decreased 2 percent from February 2016.
On-time performance (OTP) for February 2017 was 93.8 percent, compared to
90.5 percent OTP for February 2016. Taking into account trains arriving within 10 minutes
of the scheduled arrival time, OTP rises to 96.1 percent. In February 2017 there were 792
minutes of delay due to mechanical issues compared to 1,661 minutes in February 2016.
On customer service statistics, there were 8.0 complaints per 100,000 passengers in
February 2017 which decreased from 9.7 in February 2016.
Shuttle ridership for February 2017 is down 2.2 percent from February 2016. For the
station shuttles, the Millbrae-Broadway shuttle averaged 199 daily riders. The Belmont-
Hillsdale shuttle averaged 43 daily riders. The weekend Tamien-San Jose shuttle
averaged 50 daily riders. When the Marguerite shuttle was removed, the impact to
ridership was a decrease of 10.8 percent.
Page 2 of 6
Caltrain Promotions – February 2017
www.go.caltrain.com launch – With so many fun events and activities going on along
the Peninsula, Caltrain is a great alternative to driving. To help promote these fun
destinations, Caltrain launched a newly designed site to be used as a guide to feature
all the attractions in one location on the Caltrain website. Go.caltrain.com is the one
stop shop of events happening in along the corridor that are accessible by bus and/or
train. From sporting events, street fairs and farmers’ markets, the site connects
customers to the fun. To carry the new design throughout, the Transit Fun Guide was
also redesigned along with the website to display more eye appeal with bigger photos
and easy to read navigation about connecting bus routes and information. Being a
soft launch of the site, communications to promote the site included Peninsula Moves
blog post, newly designed web button on homepage, take-ones onboard buses and
organic social media push. A heavier promotional push will be developed once minor
bugs are flushed out and more content/events come online.
Giants FanFest – The 24th annual Giants FanFest was held on February 11 at AT&T Park.
Giants fans got the opportunity to get up and close to their favorite players and ball
park. Caltrain added extra capacity by operating one extra advanced train prior to
the festival and one extra train after the festival. Caltrain carried an additional 3,140
fans to and from the festival. The communications plan included Peninsula Moves blog,
listing on the go.caltrain.com website and organic social media posts. Media outlets
were heavily encouraging fans to use public transportation.
Partnerships – Caltrain partnered with the Bay Area Travel & Adventure Show held at
the Santa Clara Convention Center February 11 and 12. As part of the partnership, the
co-promoted event was listed on the GoCaltrain Take-One and placed onboard the
train and at select stations, showcased on the gosamtrans.com website, Peninsula
Moves Blog and organic social media posts promoting the event. As part of the
partnership, the event also posted ad cards onboard buses and trains, logos posted on
travel show’s website and offered Caltrain/SamTrans customers a $2 discount if they
took transit to the event.
On-going
San Jose Sharks at SAP Center – For the month of February, the Sharks played four home
games. Caltrain carried an additional 1,485 customers for the month of February. Year-
to-date, additional ridership boarding at San Jose Diridon is 11,080, which represents an
increase of 18 percent increase compared to same number of games in the 2015/2016
season.
Page 3 of 6
Caltrain Social Media Analytics – February 2017
February saw record engagement for Caltrain social media with the ongoing
electrification saga. Issues like transit, jobs and politics are an irresistible conversation for
many. The influx of messages has been non-stop for about two weeks. In addition to
the regular posts, Caltrain is sponsoring social ads to promote the initiative and muster
support.
Caltrain held an exciting contest giving away Cinequest Festival Gold Passes, good for
all 70+ Cinequest movies. There were more than 50 entries from Facebook, Twitter and
Instagram. In other political activity, the Caltrain twitter account was used to inform
passengers of the Proposed Weekday Changes that were finalized based on public
comment received and live-tweeting the board meeting was popular given all the
Federal intrigue.
Page 4 of 6
Prepared by: James Namba, Marketing Specialist 650.508.7924
Jeremy Lipps, Social Media Officer 650.622.7845
Catherine David, Principal Planner 650.508.6471
Page 5 of 6
Table A
Graph A
FY2016* FY2017 % Change
Total Ridership 1,506,185 1,392,561 -7.5%
Average Weekday Ridership 59,831 57,618 -3.7%
Total Farebox Revenue $7,036,741 $6,893,722 -2.0%
On-time Performance 90.5% 93.8% 3.6%
Average Caltrain Shuttle Ridership 10,137 9,910 -2.2%
FY2016* FY2017 % Change
Total Ridership 12,577,846 12,270,064 -2.4%
Average Weekday Ridership 59,359 58,412 -1.6%
Total Farebox Revenue $57,406,131 $60,153,447 4.8%
On-time Performance 88.4% 94.0% 6.3%
Average Caltrain Shuttle Ridership 8,844 9,201 4.0%
*Revised February 2016 Ridership
February 2017
Year to Date
Page 6 of 6
Graph B
Graph C
0
500
1000
1500
2000
2500
Feb
-15
Ap
r-1
5
Ju
n-1
5
Au
g-1
5
Oc
t-1
5
De
c-1
5
Fe
b-1
6
Ap
r-1
6
Ju
n-1
6
Au
g-1
6
Oc
t-1
6
De
c-1
6
Fe
b-1
7
De
lay
Min
ute
s p
er
Mo
nth
MONTHLY MECHANICAL DELAYS
Page 1 of 2
13384230.1
AGENDA ITEM # 13
APRIL 6, 2017
PENINSULA CORRIDOR JOINT POWERS BOARD
STAFF REPORT
TO: Joint Powers Board
THROUGH: Jim Hartnett
Executive Director
FROM: April Chan
Chief Officer, Planning, Grant and
Transportation Authority
SUBJECT: AUTHORIZATION TO AMEND THE COOPERATIVE AGREEMENT WITH THE
CAPITOL CORRIDOR JOINT POWERS AUTHORITY TO PROVIDE AN
ADDITIONAL $900,000 IN FUNDING AND TO EXPAND THE SCOPE OF WORK
TO INCLUDE SOUTH TERMINAL PHASE III AND LOS GATOS CREEK BRIDGE
PROJECTS
ACTION
Staff Coordinating Council (SCC) recommends the Board authorize the Executive
Director, or his designee, to amend the cooperative agreement with the Capitol
Corridor Joint Powers Authority (CCJPA) to allow the Peninsula Joint Powers Board (JPB)
to receive an additional $900,000 in State funding to complete conceptual planning,
preliminary engineering and final design for the South Terminal Phases II, III and
Los Gatos Creek Bridge projects.
SIGNIFICANCE
In 2014, the CCJPA, which operates the Capitol Corridor commuter rail service
between Sacramento and San Jose, provided $1 million to help partially fund
conceptual planning and preliminary engineering for the South Terminal Phase II
Project.
The CCJPA recently identified an additional $900,000 in State funding that will expire if
not expended by April 30, 2017. The CCJPA asked if the JPB could use the funds to pay
for expenses related to planning and engineering work that has been completed on
the South Terminal III and the Los Gatos Creek Bridge projects. These projects benefit
Capital Corridor service on the Caltrain right of way between Santa Clara and
San Jose.
BUDGET IMPACT
The additional $900,000 will be used to fund expenditures made in the South Terminal
Phase III and Los Gatos Creek Bridge projects. There is no need to amend the budgets
for these projects; this action only changes the funding source.
Page 2 of 2
13384230.1
BACKGROUND
The South Terminal Phase II Project will add an additional track along with signal
controls between the Centralized Equipment Maintenance and Operations Facility and
Diridon Station. The South Terminal Phase III Project will provide a tail track south of
Diridon Station. The Los Gatos Creek Bridge Project includes an expanded bridge deck
to support the tail track that is part of the South Terminal Phase III Project. Combined,
these three projects provide additional operational flexibility for Caltrain and tenant
railroads, such as Capitol Corridor.
Prepared By: Peter Skinner, Manager of Grants and Fund
Programming
650.622.7818
Page 1 of 2
13388565.1
RESOLUTION NO. 2017 –
BOARD OF DIRECTORS, PENINSULA CORRIDOR JOINT POWERS BOARD
STATE OF CALIFORNIA
* * *
AUTHORIZING AN AMENDMENT TO THE COOPERATIVE AGREEMENT WITH THE CAPITOL
CORRIDOR JOINT POWERS AUTHORITY TO PROVIDE AN ADDITIONAL $900,000 IN FUNDING
FOR SOUTH TERMINAL PHASE III AND THE LOS GATOS CREEK BRIDGE PROJECTS
WHEREAS, the Peninsula Corridor Joint Powers Board (JPB) is a joint powers
authority and operates commuter rail passenger service (Caltrain) between
San Francisco Station and Gilroy Station; and
WHEREAS, Capitol Corridor Joint Powers Authority (CCJPA) is a joint powers
authority and operates the Capitol Corridor commuter rail service along its route
entirely owned by host railroads; and
WHEREAS, in September 2014, CCJPA agreed to provide $1 million in funding for
planning and preliminary engineering related to the South Terminal Phase II Project; and
WHEREAS, CCJPA desires to provide an additional $900,000 for planning,
preliminary engineering and final design work related to the South Terminal Phase III
and the Los Gatos Creek Bridge Projects.
NOW, THEREFORE, BE IT RESOLVED that the Board of Directors of the Peninsula
Corridor Joint Powers Board:
1. Authorizes the Executive Director, or his designee, to amend the JPB's
cooperative agreement with the CCJPA related to the South Terminal
Phase II Project to provide an additional $900,000 in funding for the
South Terminal Phase III and Los Gatos Creek Bridge Projects, for a total
CCJPA contribution of $1,900,00; and
Page 2 of 2
13388565.1
2. Authorizes the Executive Director, or his designee, to file any other
required documentation and to take any other actions necessary for the
purpose of obtaining this funding from the CCJPA.
Regularly passed and adopted this 6th day of April, 2017 by the following vote:
AYES:
NOES:
ABSENT:
Chair, Peninsula Corridor Joint Powers Board
ATTEST:
JPB Secretary
Page 1 of 2
13364463.1
AGENDA ITEM # 14
APRIL 6, 2017
PENINSULA CORRIDOR JOINT POWERS BOARD
STAFF REPORT
TO: Joint Powers Board
THROUGH: Jim Hartnett
Executive Director
FROM: Kathleen Kelly
Interim Chief Financial Officer
SUBJECT: AMENDMENT TO INCREASE THE FISCAL YEAR 2017 CAPITAL BUDGET BY
$166,000 FOR THE RAVENSWOOD AVENUE GRADE SEPARATION PROJECT
FOR A TOTAL CAPITAL BUDGET OF $526,751,568
ACTION
Staff Coordinating Council recommends the Board amend the Fiscal Year (FY) 2017
Capital Budget to increase budget authority for the Ravenswood Avenue Grade
Separation Project (Project) by $166,000 for a total FY2017 Capital Budget of
$526,751,568.
SIGNIFICANCE
The existing Ravenswood Avenue at-grade crossing of Caltrain is a critical rail crossing
within the city of Menlo Park (City). This crossing is within the City's El Camino Real/
Downtown Specific Plan Area, and falls within the City’s Priority Development Area. A
grade separation would improve both safety and traffic flow on Ravenswood
approaching El Camino Real. The proposed budget amendment will be used to
develop a comprehensive Project Study Report (PSR), which analyzes feasible
alternatives for the construction of the Ravenswood Grade Separation. The PSR would
refine the preliminary concepts identified in the prior 2003-2004 grade separation
studies in order to develop design concepts and gain community consensus around a
preferred alternative. The recommended preferred alternative will reflect the consensus
developed from the City, the Peninsula Corridor Joint Powers Board (JPB), and the City
community regarding a viable grade separation project at Ravenswood Avenue.
JPB will be responsible for joint project oversight and direction, in collaboration with the
City. JPB staff, or a consultant on its behalf, will review documentation to ensure
compliance with JPB standards, operations, the Caltrain Modernization Program and
tenant services.
Page 2 of 2
13364463.1
BUDGET IMPACT
The JPB applied for, and on February 22, 2016 received, $166,000 in the San Mateo
County Transportation Authority (TA) funding for the Project. This $166,000 in TA funding
for the Ravenswood Avenue Grade Separation Project needs to be added to the
FY2017 Capital Budget. The revision increases the FY2017 Capital Budget from
$526,585,568 to $526,751,568.
BACKGROUND
The FY2017 Capital Budget was adopted in the amount of $250,948,910 pursuant to
Resolution No. 2016-30. On October 6, 2016, the Board passed Resolution No. 2016-53,
which increased the Capital Budget by $165,300,000 for the 25th Grade Avenue
Separation Project for a new total of $416,248,910. On November 3, 2016, the Board
passed Resolution No. 2016-59, which increased the Capital Budget by $108,675,991 for
the Peninsula Corridor Electrification Project and by $1,060,667 for the Grade Crossing
State of Good Repair Phase II Project for a revised Capital Budget of $525,985,568. On
January 5, 2017, the Board passed Resolution No. 2017-04, which increased the Capital
Budget by $600,000 for the Caltrain Station Management Toolbox Project for a revised
Capital Budget of $526,585,568.
Prepared by: Sam Le, Manager Budgets 650.508.6426
FY2017 CAPITAL BUDGET |April 6, 2017Attachment A
4/2017
Amount Source Amount Source Amount Source Amount
i. SOGR
Right of Way / Signal & Communications
1 Grade Crossing SOGR - Design - FY17 13 Robert Tam 380,000 0 76,000 76,000 (2) 0 76,000
2 Grade Crossing SOGR - Phase II - FY16 13, 16 Robert Tam 2,499,000 360,000 1,730,133 1,060,667 (9) 263,895 Prop 1B 109,506 (2) 296,065 1,730,133
3 Los Gatos Creek Bridge Replacement 14, 15, 16 Parand Maleki 33,847,800 23,302,000 7,295,800 5,836,640 Sec 5337 1,459,160 7,295,800
4 Marin St. Bridge Rehabilitation and Napoleon St. Bridge
Replacement
13 - 16 Bin Zhang 3,000,000 1,364,000 1,000,000 800,000 Sec 5337 200,000 1,000,000
5 Track SOGR - FY17 16 Pedro Gutierrez 9,663,000 0 3,000,000 2,400,000 Sec 5337 600,000 3,000,000
6 PA Upgrades 13 - 16 Robert Tam 1,073,000 0 488,000 390,400 Sec 5337 97,600 488,000
7 Railroad Communication System SOGR - FY17 13 Uhila Makoni 1,075,000 0 442,000 353,600 Sec 5337 88,400 442,000
8 Signal Rehab - FY17 16 Hubert Chan 1,210,000 0 900,000 720,000 Sec 5337 180,000 900,000
35 25th Avenue Grade Separation 16 Rafael Bolon 179,800,000 14,500,000 165,300,000 94,000,000 (6) 71,300,000 (8) 0 165,300,000
180,231,933 11,561,307 (1) 94,263,895 71,485,506 2,921,225 180,231,933
Rolling Stock
9 F-40 Mid Life Overhaul 16 David Bennett 6,300,000 4,000,000 2,300,000 2,300,000 2,300,000
10 Bombardier Technical Spec. Mid Life Overhaul 11 David Bennett 183,642 0 183,642 183,642 183,642
11 Gallery Spec Mid Life Overhaul 12 David Bennett 183,642 0 183,642 183,642 183,642
12 F-40 SEP-HEP Replacement - FY17 16 David Bennett 2,745,000 223,865 2,130,000 2,130,000 2,130,000
13 F-40 Locomotive SOGR project - FY17 16 David Bennett 1,254,199 0 1,254,199 160,000 Sec 5307 1,094,199 1,254,199
14 Main Engine Rebuild (F40 Inframe Overhaul) 16 David Bennett 1,350,000 0 945,592 945,592 945,592
6,997,075 160,000 (1) 0 0 6,837,075 6,997,075
Station & Intermodal Access
15 Station Enhancements and Renovations 13 - 19 Rob Scorpino 780,000 0 600,000 600,000 600,000
16 Sunnyvale Station Platform Rehabilitation 16 Rob Scorpino 1,300,000 650,000 550,000 550,000 (2) 0 550,000
17 Systemwide SOGR Stations - FY17 13 - 19 Rob Scorpino 950,000 0 300,000 300,000 300,000
1,450,000 0 0 550,000 900,000 1,450,000
ii. CALTRAIN MODERNIZATION
18 Electrification 12 - 13 Raja Viswanathan 1,159,500,000 99,142,587 256,667,737 (7) 256,667,737 EIP (3) 256,667,737
19 EMU Procurement 12 - 15 Raja Viswanathan 821,100,000 44,828,000 59,205,335 (7) 59,205,335 EIP (3) 59,205,335
315,873,072 0 0 315,873,072 0 315,873,072
iii. LEGAL MANDATES AND REQUIRED ENHANCEMENTS
20 CBOSS PTC 16 Sherry Bullock 246,700,000 231,000,000 14,309,789 6,000,000 Prop 1B 8,309,789 TBD 14,309,789
21 MS4 Year 4 11 Hubert Chan 440,000 0 389,000 389,000 389,000
22 HPPL & LLEPM on Passenger Cars 16 David Bennett 743,435 721,294 22,141 22,141 22,141
14,720,930 0 6,000,000 8,309,789 411,141 14,720,930
iv. OPERATIONAL IMPROVEMENTS/ENHANCEMENTS
23 Right of Way Fencing - FY17 16 Rob Scorpino 1,500,000 0 1,174,058 939,246 (5) 234,812 1,174,058
24 Upgrade Equipment Room Cooling 13 - 16 Joe Conn 1,020,000 0 500,000 500,000 (2) 500,000
25 Santa Clara Grade Crossing Medians - FY17 15 - 19 Robert Tam 1,097,000 229,000 868,000 868,000 868,000
26 Train Departure Monitor - FY17 16 - 19 Robert Tam 1,530,000 1,407,000 123,000 92,753 (4) 30,247 123,000
27 New Control Point at Brittan 13 - 16 Eric Stocklmeir 7,715,362 5,000,000 1,562,500 1,250,000 FTA (TPI) 312,500 1,562,500
28 Life Cycle Facilities Equipment Replacement CEMOF 16 David Bennet 365,000 0 200,000 200,000 200,000
29 CTAMS Enhancements - FY17 13 - 19 Rick Peredia 500,000 0 200,000 200,000 200,000
30 MPLS Data Network 13 - 15 Joe Conn 250,000 0 95,000 95,000 95,000
4,722,558 1,250,000 939,246 592,753 1,940,559 4,722,558
TotalEstimated
Total Cost
Previously
Programmed
Proposed
BUDGET
Federal State
Ite
m #
PROJECT TITLE / Description Phase Project ManagerOther Members
1 | 2
Amount Source Amount Source Amount Source Amount
TotalEstimated
Total Cost
Previously
Programmed
Proposed
BUDGET
Federal State
Ite
m #
PROJECT TITLE / Description Phase Project ManagerOther Members
v. PLANNING/STUDIES
31 Capital Project Development 11 1,675,933 0 500,000 500,000 500,000
32 Capital Program Management 11 500,000 0 500,000 500,000 500,000
33 Capital Contingency Funds - Engineering 11 330,000 0 330,000 330,000 330,000
34 Capital Contingency Funds - Rail 11 660,000 0 660,000 660,000 660,000
36 Caltrain Toolbox 11 Sebsastian Petty 750,000 150,000 600,000 600,000 FTA (10) 600,000
37 Ravenswood Grade Separation 11 Elizabeth Ankin 166,000 0 166,000 166,000 (11) 166,000
2,756,000 600,000 0 166,000 1,990,000 2,756,000
GRAND TOTAL 526,751,568 13,571,307 101,203,141 396,977,120 15,000,000 526,751,568
Excluding EIP (CalMOD projects) 196,568,707 13,571,307 95,203,141 72,794,259 15,000,000 196,568,707
Notes:
(1) Assume MTC will release $10.5M in Federal Transit Administration (FTA) Section 5337 (SOGR Grants) and $160k in Section 5307 (Urbanized Area Formula) funds.
(2) Project Savings from prior years, including previously de-obligated Prop K funds.
(3) EIP: The $1.98 billion Early Investment Program is funded through the 2012 nine-party and 2016 seven-party agreements that leverage local, regional and federal funding to match $705 million in voter-approved high-speed rail bond revenues.
(4) Budget savings from Narrow Banding project.
(5) ROW Fencing FY2017: $939,246 will come from Prop 1B, last year of Caltrain Transit Security Grants Program (CTSGP) funds.
(6) Funding from California High Speed Rail Authority (CHRSA) $84M and CPUC Section 190 $10M
(7) Budget increase of $108,675,991 for PCEP Program (Balfour and Stadler contracts) which will support the execution of the FNTP
(8) Funding from SMCTA Measure A $65.3M and City of San Mateo $6M
(9) Funding from FRA of 1.06M is 50% match to local funds from FY 17 and FY 18 Capital Budget
(11) Funding from SMCTA Measure A for $166,000
(10) Budget increased by $600,000 to reflect the FTA funds received and are to be matched by $150,000 in Member Agency funds (SamTrans and VTA with a 50-50 split), originally approved in the FY15 Capital Budget.
2 | 2
Page 1 of 2
13364465.1
RESOLUTION NO. 2017 –
BOARD OF DIRECTORS, PENINSULA CORRIDOR JOINT POWERS BOARD
STATE OF CALIFORNIA
* * *
INCREASING THE FISCAL YEAR 2017 CAPITAL BUDGET BY $166,000
FOR THE RAVENSWOOD AVENUE GRADE SEPARATION PROJECT
FOR A TOTAL CAPITAL BUDGET OF $526,751,568
WHEREAS, the Peninsula Corridor Joint Powers Board (JPB) Board of Directors
(Board) approved Resolution No. 2016-30 on June 2, 2016, adopting the Fiscal Year (FY)
2017 Capital Budget of $250,948,910; and
WHEREAS, the Board approved Resolution No. 2016-53 to amend the FY2017
Capital Budget to increase it by $165,300,000 for the 25th Avenue Grade Separation
Project; and
WHEREAS, the Board approved Resolution No. 2016-59 to amend the FY2017
Capital Budget by $1,060,667 for the Grade Crossing State of Good Repair Phase II
Project, and by $108,675,991 for the Peninsula Corridor Electrification Project; and
WHEREAS, the Board approved Resolution No. 2017-04 to amend the FY2017
Capital Budget to increase it by $600,000 for the Caltrain Station Management Toolbox;
and
WHEREAS, the JPB applied for, and on February 22, 2016 received, $166,000 in
San Mateo County Transportation Authority (TA) funding for completion of a Project
Study Report (PSR) for the Ravenswood Avenue Grade Separation Project (Project);
and
Page 2 of 2
13364465.1
WHEREAS, the Board now desires to amend the FY2017 Capital Budget by
$166,000 to provide the requisite budget authority to receive these allocated funds and
complete a PSR for the Project.
NOW, THEREFORE, BE IT RESOLVED that the Board of Directors of the Peninsula
Corridor Joint Powers Board hereby amends the FY2017 Capital Budget to increase it by
$166,000, for a new total FY2017 Capital Budget of $526,751,568, to fund a Project Study
Report for the Ravenswood Grade Separation Project.
Regularly passed and adopted this 6th day of April, 2017 by the following vote:
AYES:
NOES:
ABSENT:
Chair, Peninsula Corridor Joint Powers Board
ATTEST:
JPB Secretary
Page 1 of 3
AGENDA ITEM # 15
APRIL 6, 2017
PENINSULA CORRIDOR JOINT POWERS BOARD
STAFF REPORT
TO: Joint Powers Board
THROUGH: Jim Hartnett
Executive Director
FROM: Seamus Murphy
Chief Communications Officer
SUBJECT: CALTRAIN TRIENNIAL CUSTOMER SURVEY PRESENTATION
ACTION
This report is for information only. No board action is required.
SIGNIFICANCE
The Caltrain Triennial Customer Survey was conducted between October 4 and
October 26. The results of this survey provide rider and trip characteristics,
demographics, satisfaction ratings, access and egress, barriers to use Clipper and
communications information. The data collected from this study supports Title VI
analysis, development of service and fares, and promotion strategies.
This research project was managed and implemented by Corey, Canapary & Galanis,
a professional market research company. Specific steps were taken to ensure the
highest possible response rate, including the use of professional, experienced onboard
surveyors on the project, making the questionnaire available in English and Spanish,
and providing a business reply mail-back option for persons who did not have time to
complete the survey onboard.
The weekday shifts were allocated to allow for surveying during morning and afternoon
peak periods, as well as off-peak periods. Saturday and Sunday trains were also
surveyed at various times of the day. The dates of the fieldwork were scheduled to
avoid surveying during special events that would unduly impact ridership. A total of 62
weekday routes and 10 weekend routes. Of the 62 weekday routes surveyed, 29 were
Limited trains, 19 were Local trains, and 14 were Bullet trains. For each train sampled, a
specific car was selected, and we attempted to survey every passenger in the
selected car.
Page 2 of 3
5,554 responses were received which equates to a system-wide margin of error of +/-
1.30 percent (at the 95 percent confidence level). This represents a 65 percent
response rate (calculated by dividing the total number of completes by all the eligible
passengers riding on the sampled trains).
Key findings from the study include:
Ridership
More than a third of riders (34 percent) have been riding Caltrain less than one
year.
Nearly two-thirds of riders (62 percent) said they ride Caltrain to avoid traffic. This
is an increase from 57 percent who said they rode Caltrain for this reason in 2013.
Those who have ridden Caltrain less than one year cited a change in company
(31 percent), worsening traffic (29 percent), and lack of access to a car
(21 percent) as the reasons they began riding Caltrain.
Nearly half of respondents (49 percent) travel 10 miles or less to reach their
Caltrain station and more than a third (35 percent) travel 20 or more miles.
Satisfaction with Caltrain
Overall, Caltrain riders rated their experience on Caltrain 4.09 (out of 5.00), an
increase over 2013’s 4.04 (and a return to 2010 satisfaction levels).
Riders rated the effectiveness of station signs 3.90, compared to 2013 rating of
3.81.
Fare Media
Use of Clipper cash value to pay for their Caltrain trip is up (16 percent in 2016 vs.
11 percent in 2013 )
More than one third of respondents (36 percent) paid for their Caltrain trip with a
Clipper Caltrain Monthly Pass. However, this is a decrease from 2013, when
41 percent paid in this way.
The share of riders that paid for their Caltrain trip using a Go Pass rose from
14 percent in 2013 to 21 percent in 2016.
Demographics
Caltrain riders speak one of the 72 languages identified in the survey in their
homes, and while 60 percent say they are born in the United States, 40 percent
were born in one of 105 countries around the world.
Nearly all riders (96 percent) have a high school diploma, while 81 percent have
graduated college, including 38 percent who have a post graduate degree.
BUDGET IMPACT
There is no impact on the budget.
Page 3 of 3
BACKGROUND
Every three years Market Research & Development Department is responsible for the
development, implementation and delivering the Caltrain customer survey. The
department works with communication, operations and planning staff to determine
requirements and ensure that the assigned on-call market research company delivers a
statistically valid survey that meets 95 percent confidence level. The methodology is
established to ensure maximum participation. Data collected through the survey is
confidential to preserve respondent identity and the results are presented in
aggregate.
Prepared by: Christiane Kwok, Manager, Market Research
& Development
650.508.7926
Project Manager: Julian Jest, Market Research Analyst 650.508.6245
Page 1 of 2
AGENDA ITEM # 16
APRIL 6, 2017
PENINSULA CORRIRDOR JOINT POWERS BOARD
STAFF REPORT
TO: Joint Powers Board
THROUGH: Jim Hartnett
General Manager/CEO
FROM: Seamus Murphy
Chief Communications Officer
SUBJECT: STATE AND FEDERAL LEGISLATIVE UPDATE
ACTION
This report is for information only. No Board action is required.
SIGNIFICANCE
Staff will provide regular updates to the Board in accordance with the approved
Legislative Program.
STATE ISSUES
AS OF 3/20/2017:
Governor Jerry Brown and legislative leaders are working to complete a transportation
funding package by April 6, when lawmakers leave for spring recess and before the
annual budget process dominates the Capitol.
The governor’s plan would generate an average of $4.2 billion annually over 10 years,
while Assemblymember Jim Frazier and Senator Jim Beall’s transportation funding bills
would provide almost $6 billion a year (Assembly Bill 1 and Senate Bill 1). The Republican
funding proposal introduced by Assemblymember Paul Fong generates $5.6 billion in
multi-year funding and $2.2 billion in one-time revenues.
The governor’s office, leadership in the Assembly and Senate, as well as key
transportation chairs are meeting on a regular basis to discuss and negotiate a
package that would garner the needed support to pass both chambers.
Leadership Change
On March 14, 2017, Senator Patricia Bates (R-Laguna Niguel) was elected leader of the
Senate Republican Caucus.
Page 2 of 2
FEDERAL ISSUES
As of 3/20/2017:
On March 16, the Office of Management and Budget published the Administration's
Fiscal Year (FY) 2018 "skinny” budget. The budget increases military spending and cuts
many other programs, including those at Department of Transportation (DOT). The “full”
budget that will include more details about department and program budgets is
expected to be released in May.
Information from the skinny budget:
Limits funding for the Federal Transit Administration’s Capital Investment Program
(includes the Core Capacity Program) to projects with existing full funding grant
agreements only.
Terminates Federal support for Amtrak’s long distance train services, which have
long been inefficient and incur the vast majority of Amtrak’s operating losses.
Eliminates funding for the TIGER Discretionary Grant Program.
A copy of the budget document can be viewed here:
https://www.whitehouse.gov/sites/whitehouse.gov/files/omb/budget/fy2018/2018_blue
print.pdf
Although Congress will take this budget proposal under advisement, the House and
Senate will ultimately develop their own FY2018 budget and spending bills to be signed
into law.
Nominations
On March 7, President Donald Trump announced his intent to nominate Jeffrey Rosen
as deputy secretary of the Department of Transportation. Mr. Rosen previously served
as general counsel at DOT from 2003 to 2006, and then as general counsel and senior
policy adviser at the Office of Management and Budget during the Bush 43
administration. Mr. Rosen is currently a senior partner at Kirkland & Ellis LLP, and his
clients have included General Motors and Hyundai. If the Senate confirms Mr. Rosen, he
will be responsible for the day-to-day operations of the DOT.
Prepared By: Lori Low, Government and Community
Relations Specialist
Casey Fromson, Director, Government and
Community Affairs Director
650-508-6391
650-508-6493
Peninsula Corridor Joint Powers Board
State Legislative Matrix as of 3/15/2017
Page 1 of 3
Bill ID/Topic Location Summary Position
AB 1
Frazier D
Transportation
funding.
Assembly
Transportation
Existing law provides various sources of funding for transportation purposes, including funding for the state highway
system and the local street and road system. These funding sources include, among others, fuel excise taxes,
commercial vehicle weight fees, local transactions and use taxes, and federal funds. Existing law imposes certain
registration fees on vehicles, with revenues from these fees deposited in the Motor Vehicle Account and used to fund
the Department of Motor Vehicles and the Department of the California Highway Patrol. Existing law provides for the
monthly transfer of excess balances in the Motor Vehicle Account to the State Highway Account.
This bill would create the Road Maintenance and Rehabilitation Program to address deferred maintenance on the
state highway system and the local street and road system. The bill would require the California Transportation
Commission to adopt performance criteria, consistent with a specified asset management plan, to ensure efficient
use of certain funds available for the program. The bill would provide for the deposit of various funds for the program in
the Road Maintenance and Rehabilitation Account, which the bill would create in the State Transportation Fund,
including revenues attributable to a $0.012 per gallon increase in the motor vehicle fuel (gasoline) tax imposed by the
bill with an inflation adjustment, as provided, an increase of $38 in the annual vehicle registration fee with an inflation
adjustment, as provided, a new $165 annual vehicle registration fee with an inflation adjustment, as provided,
applicable to zero-emission motor vehicles, as defined, and certain miscellaneous revenues described in (7) below
that are not restricted as to expenditure by Article XIX of the California Constitution. This bill contains other related
provisions and other existing laws. Introduced: 12/5/2016
Support
AB 17
Holden D
Transit Pass
Program:
free or
reduced-fare
transit passes.
Assembly
Transportation
Existing law declares that the fostering, continuance, and development of public transportation systems are a matter
of statewide concern. Existing law authorizes the Department of Transportation to administer various programs and
allocates moneys for various public transportation purposes.
This bill would create the Transit Pass Program to be administered by the department. The bill would require the
Controller of the State of California to allocate moneys made available for the program, upon appropriation by the
Legislature, to support transit pass programs that provide free or reduced-fare transit passes to specified pupils and
students. The bill would require the department to develop guidelines that describe the criteria that eligible transit
providers, as defined, are required to use to make available free or reduced-fare transit passes to eligible participants,
as defined, and to ensure that moneys from the program are used to expand eligibility or further reduce the cost of a
transit pass under existing programs. The bill would exempt the development of those guidelines from the
Administrative Procedure Act. The bill would require eligible transit providers and eligible participants to enter into
agreements for the distribution of free or reduced-fare transit passes to students. This bill contains other related
provisions. Introduced: 12/5/2016
Pending
Peninsula Corridor Joint Powers Board
State Legislative Matrix as of 3/15/2017
Page 2 of 3
Bill ID/Topic Location Summary Position
AB 467
Mullin D
Local
transportation
authorities:
transactions
and use taxes.
Assembly Local
Government
4/5/2017
1:30 p.m. - State
Capitol, Room
447 ASSEMBLY
LOCAL
GOVERNMENT,
AGUIAR-CURRY,
Chair
The Local Transportation Authority and Improvement Act provides for the creation in any county of a local
transportation authority and authorizes the imposition by the authority, by ordinance, of a retail transactions and use
tax, subject to approval of the ordinance by 2/3 of the voters. Existing law provides for the authority to adopt a
transportation expenditure plan for the proceeds of the tax, and requires the entire adopted transportation
expenditure plan to be included in the voter information handbook sent to voters.
This bill would exempt an authority from including the entire adopted transportation expenditure plan in the voter
information handbook if the authority posts the plan on its Internet Web site, and the sample ballot and the voter
information handbook sent to voters include information on viewing an electronic version of the plan on the Internet
Web site and for obtaining a printed copy of the plan by calling the county election office. The bill would require the
authority to provide sufficient copies of the plan to the county election office for mailing to each person requesting a
copy. By imposing additional requirements on county election officials, the bill would impose a state-mandated local
program. This bill contains other related provisions and other existing laws. Introduced: 2/13/2017
Pending
AB 496
Fong R
Transportation
funding.
Assembly
Transportation
Existing law provides various sources of funding for transportation purposes, including funding for the state highway
system and the local street and road system. These funding sources include, among others, fuel excise taxes,
commercial vehicle weight fees, local transactions and use taxes, and federal funds. Existing law imposes certain
registration fees on vehicles, with revenues from these fees deposited in the Motor Vehicle Account and used to fund
the Department of Motor Vehicles and the Department of the California Highway Patrol. Existing law provides for the
monthly transfer of excess balances in the Motor Vehicle Account to the State Highway Account.
This bill would create the Traffic Relief and Road Improvement Program to address traffic congestion and deferred
maintenance on the state highway system and the local street and road system. The bill would provide for the deposit
of various existing sources of revenue in the Traffic Relief and Road Improvement Account, which the bill would create
in the State Transportation Fund, including revenues attributable to the sales and use tax on motor vehicles, revenues
attributable to automobile and motor vehicle insurance policies from the insurer gross premiums tax, revenues from
certain diesel fuel sales and use taxes, revenues from certain vehicle registration fees, and certain miscellaneous State
Highway Account revenues. This bill contains other related provisions and other existing laws. Amended: 2/28/2017
Pending
AB 1613
Mullin D
San Mateo
County Transit
District: retail
transactions
and use tax.
Assembly Print Existing law authorizes the board of the San Mateo County Transit District to adopt a retail transactions and use tax
ordinance in accordance with specified provisions of law, including a requirement that the combined rate of all such
taxes that may be imposed in the county not exceed 2%. This bill would authorize the board to exceed that 2% limit to
impose a retail transactions and use tax set at a rate of no more than 0.5%, if approved by the board before
January 1, 2021. Introduced: 2/17/2017
Pending
Peninsula Corridor Joint Powers Board
State Legislative Matrix as of 3/15/2017
Page 3 of 3
Bill ID/Topic Location Summary Position
SB 1
Beall D
Transportation
funding.
Senate
Appropriations
Existing law provides various sources of funding for transportation purposes, including funding for the state highway
system and the local street and road system. These funding sources include, among others, fuel excise taxes,
commercial vehicle weight fees, local transactions and use taxes, and federal funds. Existing law imposes certain
registration fees on vehicles, with revenues from these fees deposited in the Motor Vehicle Account and used to fund
the Department of Motor Vehicles and the Department of the California Highway Patrol. Existing law provides for the
monthly transfer of excess balances in the Motor Vehicle Account to the State Highway Account.
This bill would create the Road Maintenance and Rehabilitation Program to address deferred maintenance on the
state highway system and the local street and road system. The bill would require the California Transportation
Commission to adopt performance criteria, consistent with a specified asset management plan, to ensure efficient
use of certain funds available for the program. The bill would provide for the deposit of various funds for the program in
the Road Maintenance and Rehabilitation Account, which the bill would create in the State Transportation Fund,
including revenues attributable to a $0.12 per gallon increase, phased in over 3 years, in the motor vehicle fuel
(gasoline) tax imposed by the bill with an inflation adjustment, as provided, an increase of $38 in the annual vehicle
registration fee with an inflation adjustment, as provided, a new $100 annual vehicle registration fee with an inflation
adjustment, as provided, applicable to zero-emission motor vehicles, as defined, and certain miscellaneous revenues
described in (7) below that are not restricted as to expenditure by Article XIX of the California Constitution. This bill
contains other related provisions and other existing laws. Amended: 1/26/2017
Support