j c charyk hanna school: modernization. timelines to project completion the timelines shared are...

10
J C Charyk Hanna School: Modernization

Upload: donald-dean

Post on 19-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: J C Charyk Hanna School: Modernization. Timelines To Project Completion The timelines shared are proposed to date and may change slightly as the project

J C Charyk Hanna School: Modernization

Page 2: J C Charyk Hanna School: Modernization. Timelines To Project Completion The timelines shared are proposed to date and may change slightly as the project

Timelines To Project Completion• The timelines shared are proposed to date and may change slightly

as the project unfolds:

• April 9, 10:00 am - PLRD meeting with project architects.

• April 15, 7:00 pm - Community meeting for the sharing of priorities and feedback to support the process of the Building Committee.

• April 22 to April 27 - selection of Architectural team.

• May 2 - Meeting of building committee to consolidate all community, staff, and student input.

• June 2014 - Sharing of the schematic design of the architectural team with the community of Hanna.

Page 3: J C Charyk Hanna School: Modernization. Timelines To Project Completion The timelines shared are proposed to date and may change slightly as the project

Project Timelines continued

• July 2014/August 2014 - Design Development.

• August 2014/November 2014 - Construction Documents Completion.

• November 2014 - Tendering and Award.

• December 2014 - Award Contract to successful Contractor.

Page 4: J C Charyk Hanna School: Modernization. Timelines To Project Completion The timelines shared are proposed to date and may change slightly as the project

Project Timelines continued

• January 2015 to June 2016 - Construction.

• September 2016 to September 2017 - Post Construction. (Hvac balancing/addressing deficiencies)

• September 2016 to December 2016 - Full occupancy (Will depend upon actual project completion.)

• June 2016 to September 2016 - Demolition of Hanna Primary School. (Flexible as per above)

Page 5: J C Charyk Hanna School: Modernization. Timelines To Project Completion The timelines shared are proposed to date and may change slightly as the project

Architectural Visit

• June 2014 - Sharing of the schematic design of the architectural team with the community of Hanna:

• Community meeting involving parents, staff, and students

• Meeting with the building committee

Page 6: J C Charyk Hanna School: Modernization. Timelines To Project Completion The timelines shared are proposed to date and may change slightly as the project

School Observations/Community Input: Big Concepts

• Create a safe, comfortable, welcoming learning environment (Furniture; spacious areas; natural lighting)

• Provide age-appropriate, properly located playground, washroom, eating, and learning spaces;

• Provide common gathering spaces for collaboration and multi-age learning;

Page 7: J C Charyk Hanna School: Modernization. Timelines To Project Completion The timelines shared are proposed to date and may change slightly as the project

Big Ideas Continued

• Provide podded learning spaces with flexibility between classrooms and the podded areas;

• Include adequate computer access points, group and individual work and collaborative spaces, eating and washroom facilities; library function, and teacher collaboration and work spaces within each pod;

• Ensure adequate classroom space for learning with proper consideration for grade-level differences;

• Provide adequate storage facilities in classrooms and throughout the facility for various work functions;

Page 8: J C Charyk Hanna School: Modernization. Timelines To Project Completion The timelines shared are proposed to date and may change slightly as the project

Big Ideas continued

• Provide adequate room and space for traffic flow and locker access;

• Provide specialty learning spaces for fine arts, drama, music, food studies and food services, and for additional CTS and dual credit programs; and high performance fitness facilities

• Ensure the facility is state-of-the-art with integrated technologies that make sense for learning;

Page 9: J C Charyk Hanna School: Modernization. Timelines To Project Completion The timelines shared are proposed to date and may change slightly as the project

Big Ideas continued

• Ensure proper flow for and safety for traffic, pick up, drop off, parking, and walking;

• Provide adequate bulletin boards inside and outside of classrooms;

• Utilize modernized techniques for making good use of space: Bulletin Boards and white Boards that double as blinds;

• Strategically located administrative areas with student work spaces;

Page 10: J C Charyk Hanna School: Modernization. Timelines To Project Completion The timelines shared are proposed to date and may change slightly as the project

Big Ideas continued

• Provide adequate spaces for contracted services, FRW, REACH, special education, and other service providers;

• Provide hot lunch service preparation facilities for primary parents;

• Provide adequate daily physical activity and gym spaces for the school programs K-12; and,

• Separate boot rooms.