    Quality Management System

    Confidential TL-CO-PO 0.4

    IVC Unified ProcessIUP-PD

    Version: 1.0

    Issued Status: Draft

    Issued Date:

    Owner: IUP Process Team

    Author: Pham Thi Phuong Lan

    Location: CMMI-L3 Repository

    Confidential Class: IVC Confidential

    Date:

    Approved by: Takeda Yoichi

    Signature:

  • 8/14/2019 IUP Process Description 1.0 En

    2/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page i

    Review Information

    Reviewer Name Role Required / Suggested Comment

    Phuong Dao Technical Manager Required

    Sang Tan Project Manager Required

    Tuan Nguyen Project Manager Required

    Tam Nguyen Project Leader Required

    Approval Information

    Approver Name RoleDate

    (mm-dd-yyyy)Revision Comment

    Sang Tan SPI Head

    Takeda Yoichi Managing Director 1.0 Final approval

    Revision History

    RevisionDate

    (mm-dd-yyyy) Description Revised byReviewer

    Date(mm-dd-yyyy)

    0.1 03-06-2007 First Version Lan Pham Phuong Dao,

    Sang Tan,

    Tuan Nguyen,Tam Nguyen

    03-26-2007

    0.2 03-27-2007 - Add essential activityImplement prototypes for thesystem into part 3.2.4 ofDefinition Phase.

    - Update introduction text in allphases to focus on their primarygoals.

    - Update part 5.2 Individual rolesto separate Team Lead in projectand Leader at company-level.

    - Add some notes into part 5.3Team Structure for guidanceclearly on structure.

    - Add part 5.4 Staffing Rules forguidance on how to staffmembers into a project.

    Lan Pham Phuong Dao,

    Sang Tan,

    Tuan Nguyen,

    Tam Nguyen,

    Duy Truong

    0.3 08-30-2007 - Modify IUP overview flow

    - Modify [5. Project TeamStructure]

    Lan Pham

    1.0 First approval

  • 8/14/2019 IUP Process Description 1.0 En

    3/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page ii

    TABLE OF CONTENT1 Introduction.........................................................................................................................................1

    1.1 Purpose .......................................................................................................................................11.2 Scope ..........................................................................................................................................11.3 Acronyms & Abbreviations ..........................................................................................................11.4 Definitions....................................................................................................................................11.5 References ..................................................................................................................................21.6 Templates / Forms ......................................................................................................................2

    2 IUP Overview.......................................................................................................................................33 IUP Lifecycle .......................................................................................................................................5

    3.1 Phase: Initiation...........................................................................................................................53.1.1 Objectives.......................................................................................................................53.1.2 Entry Criteria ..................................................................................................................53.1.3 Input ...............................................................................................................................63.1.4 Output.............................................................................................................................63.1.5 Exit Criteria.....................................................................................................................63.1.6 Flow of Activities ............................................................................................................63.1.7 Essential Activities .........................................................................................................8

    3.2 Phase: Definition .........................................................................................................................83.2.1 Objectives.......................................................................................................................83.2.2 Entry Criteria ..................................................................................................................83.2.3 Input ...............................................................................................................................83.2.4 Output.............................................................................................................................83.2.5 Exit Criteria.....................................................................................................................93.2.6 Flow of Activities ............................................................................................................93.2.7 Essential Activities .......................................................................................................11

    3.3 Phase: Execution ......................................................................................................................113.3.1 Objectives.....................................................................................................................113.3.2 Entry Criteria ................................................................................................................113.3.3 Input .............................................................................................................................113.3.4 Output...........................................................................................................................113.3.5 Exit Criteria...................................................................................................................123.3.6 Flow of Activities ..........................................................................................................123.3.7 Essential Activities .......................................................................................................143.4 Phase: Transition ......................................................................................................................143.4.1 Objectives.....................................................................................................................143.4.2 Entry Criteria ................................................................................................................143.4.3 Input .............................................................................................................................143.4.4 Output...........................................................................................................................143.4.5 Exit Criteria...................................................................................................................143.4.6 Flow of Activities ..........................................................................................................143.4.7 Essential Activities .......................................................................................................16

    3.5 Phase: Retirement ....................................................................................................................163.5.1 Objectives.....................................................................................................................163.5.2 Entry Criteria ................................................................................................................163.5.3 Input .............................................................................................................................163.5.4 Output...........................................................................................................................16

  • 8/14/2019 IUP Process Description 1.0 En

    4/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page iii

    3.5.5 Exit Criteria...................................................................................................................163.5.6 Flow of Activities ..........................................................................................................163.5.7 Essential Activities .......................................................................................................17

    4 Software Project Types & Sizes......................................................................................................184.1 Project Types ............................................................................................................................184.1.1 New application development ......................................................................................18

    4.1.2 Enhancement / Upgrading ...........................................................................................184.2 Project Sizes .............................................................................................................................18

    5 Roles & Team Structure in IUP .......................................................................................................185.1 Team roles ................................................................................................................................185.2 Individual roles ..........................................................................................................................195.3 Team Structure..........................................................................................................................195.4 Staffing Rules............................................................................................................................20

    TABLE OF FIGURESFigure 1. Phases and Iterations...................................................................................................................1Figure 2. IVC Unified Process Overview .....................................................................................................3Figure 3. IUP Lifecycle.................................................................................................................................5Figure 4. Initiation Phase Overview.............................................................................................................7Figure 5. Definition Phase Overview .........................................................................................................10Figure 6. Execution Phase Overview ........................................................................................................13Figure 7. Transition Phase Overview ........................................................................................................15Figure 8. Retirement Phase Overview.......................................................................................................17Figure 9. Team Structure...........................................................................................................................20

  • 8/14/2019 IUP Process Description 1.0 En

    5/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 1/13

    1 Introduction

    1.1 Purpose

    This document describes the overview of unified process that is used as standard process forsoftware development to all the software projects in IVC, hereafter called IUP IVC Unified Process.

    The reader can find here how to use the processes in combination during the whole SoftwareDevelopment Life Cycle. Besides, project types and project team structure are also defined in thisdocument.

    1.2 Scope

    IUP is applied to all internal and external software projects in IVC.

    1.3 Acronyms & Abbreviations

    No. Acronyms Description

    1 QA Quality Assurance

    2 QC Quality Control

    3 SQA Software Quality Assurance

    1.4 Definitions

    Baseline: a reviewed and approved release of artifacts that constitutes an agree basis for furtherevolution or development that can be changed only through a formal procedure, such asConfiguration and Change Management.

    Iteration: is a distinct sequence of activities with a baselined plan and valuation criteria resulting in arelease (internal or external). See Figure 1 for example.

    Quality Gate: is the check-point at phase-end to decide to move or not move to next phase.

    Milestone: is the point at which an iteration formally ends, correspond to a release point.

    Phase: is a period of time between two major project milestones, during which a well-defined set ofactivities is met, work product are completed, and decisions are made to move or not move into thenext phase. A phase consists of a set of discipline-based activities those are combined variousproportions, depending on its characteristics and objectives.

    Figure 1. Phases and Iterations

    Release: a subset of end-product that is the object of evaluation at a major milestone. A release is astable, executable version of product, together with any artifacts necessary to use this release, suchas release notes or installation instruction, manuals. A release can be internal or external. Aninternal release is used only by the development organization, as part of a milestone, or for a

    demonstration to customers or users. An external release (or delivery) is delivered to end-users. Arelease is not necessary a complete product, but can just be a part of it.

    Retirement

    E1

    Initiation Definition Execution Transition

    Iterations

    Phases

    I1 D1 D2 E2 E3 T1 T2

    Gate Milestone

    R1

  • 8/14/2019 IUP Process Description 1.0 En

    6/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 2/13

    Discipline: is a collection of related activities that are related to a major 'area of concern'. Thedisciplines mentioned here are also the processes such as Project Management process,Requirement Development process.

    1.5 References

    Rational Unified Process (RUP), Version 2003.06.12.01

    Project Management process, version 1.0

    Supplier Agreement Management process, version 1.0

    Risk Management process, version 1.0

    Requirement Development process, version 1.0

    Analysis & Design process, version 1.0

    Implementation process, version 1.2

    Testing process, version 1.0

    Delivery process, version 1.0Decision Analysis & Resolution process, version 1.0

    Configuration Management process, version 1.0

    Change Request Management process, version 1.0

    Software Quality Assurance process, version 1.0

    Measurement & Analysis process, version 1.0

    1.6 Templates / Forms

    No. Artifact Name Description ChargeRequired

    (Y/N)

    Template

    1 Tailoring Checklist Used to input thetailoring informationfrom the processeswith specifying tailoringcriteria.

    POs Y TL-IUP-TailoringChecklist 0.5-EN.xlt

    2 SelectionDevelopment ModelGuideline

    Used to guide user onhow to select thedevelopment modelbased on somespecific projectscharacteristics.

    IUPprocessteam

    Y IUP- SelectionDevelopmentModel Guideline1.0-EN.doc

  • 8/14/2019 IUP Process Description 1.0 En

    7/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 3/13

    2 IUP Overview

    SoftwareQuality

    Assurance

    Measurement&

    Analysis

    Figure 2. IVC Unified Process Overview

    Phases and Disciplines

    Phases Description Related Disciplines

    Initiation Primarily goal of this phase is to achieveconcurrence among all stakeholders on

    the objectives for the project, address allsignificant businesses and requirementsrisks, and to ensure that the project isworth doing and possible to do.

    This phase also provides a stable basisplans for going to next phases.

    - Project Management,

    - Requirement Development,

    - Analysis and Design,- Delivery,

    - Testing,

    - Configuration Management,

    - Software Quality Assurance,

    - Measurement & Analysis

    - Risk Management

    - Supplier Agreement Management

    Definition This phase aims to baseline therequirements and the architecture of the

    system to provide a stable basis for thebulk of the design and implementationeffort in the execution phase.

    - Project Management,

    - Change Request

    - Risk Management- Requirement Development,

    - Analysis and Design,

    - Testing,

    - Configuration Management,

    - Software Quality Assurance,

    - Measurement & Analysis

    - Supplier Agreement Management

    - Implementation

    Execution The goal of this phase is to complete the

    development of system ready to deliver tothe customer based on the baselineddesigns.

    - Project Management,

    - Change Request- Risk Management

    - Configuration Management,

    - Software Quality Assurance,

  • 8/14/2019 IUP Process Description 1.0 En

    8/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 4/13

    Phases Description Related Disciplines

    - Measurement & Analysis,

    - Implementation,

    - Testing

    Transition The goal of this phase is to deliver theproduct and associated deliverables tothe customers, maintain the product whileit is being used by the customer. Doappropriate fix patches and/or deliverenhanced releases as needed.

    - Project Management,

    - Change Request

    - Risk Management

    - Configuration Management,

    - Software Quality Assurance,

    - Measurement & Analysis,

    - Implementation,

    - Testing,

    - Delivery

    Retirement Goal of this phase is to bring the project

    to an end when the product is accepted toclose by customer and managers.

    - Project Management,

    - Measurement & Analysis,

    - Software Quality Assurance,

    - Testing

    Disciplines Overview

    No. Disciplines Description

    1 Project Management Discipline for estimating, planning, monitoring, controllingand managing all the project activities.

    2 Requirement Development Discipline for developing, maintaining and managingcustomer requirements.

    3 Analysis and Design Discipline for analyzing and designing the software productbased on its requirements specifications.

    4 Implementation Discipline for implementing and integrating the softwareproduct based on its design.

    5 Testing Discipline for testing the software product against itsrequirements and customers expectations.

    6 Delivery Discipline for delivery the package of software product tocustomer.

    7 Configuration Management Discipline for ensuring the integrity of work products throughthe project lifecycle.

    8 Software QualityAssurance

    Discipline for assuring the adherence of project process andthe work products conform to the defined standards.

    9 Risk Management Assist the Project Leader to develop and execute a plan toidentify project risks as early as possible and to periodicallyre-assess and manage those risks.

    10 Supplier AgreementManagement

    Manage the acquisition of products from suppliers for whichthere exists a formal agreement.

  • 8/14/2019 IUP Process Description 1.0 En

    9/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 5/13

    Beside those above processes, there are some processes are joined in the project to support forother activities such as:

    No. Disciplines Description

    1 Decision Analysis and

    Resolution

    Support the project team to provide a methodology and

    framework for formal decision making.

    2 Measurement and Analysis Develop and sustain a measurement capability that is usedto support management information needs in the project.

    3 IUP Lifecycle

    The software lifecycle of the IUP is decomposed over time into five sequential phases. There is firstfour phases concluded by a major milestone; the fifth phase, also the last one, would have theremained tasks in project done successfully leading to an end.

    At each phase-end an assessment is performed to determine whether the objectives of the phase

    have been met. A satisfactory assessment allows the project to move to the next phase. So, there isessentially a span of time between two major milestones to complete all remained tasks of currentphases.

    Figure 3. IUP Lifecycle

    3.1 Phase: Initiation

    Prior to this phase, the Sales department has obtained the initial engagement with the customer, andreceived high level expectation for the product or solution from customer. These initial requirementsshall be transferred to the Project Managers of appropriate sections, Business Application (BA)section and Mobile (MB) section, for an analysis on ensuring that the project is both worth doing andpossible to do.

    This phase focuses mainly on the achievement of the concurrence among all stakeholders on theobjectives for the project.

    3.1.1 Objectives

    Address all potential risks to the project.

    Establish the project's software scope and boundary conditions, product acceptance criteria andwhat is intended to be in the product and what is not.

    Estimate the overall cost and effort for the entire project, and also determine the masterschedule.

    Achieve the commitment of stakeholders on project lifecycle, estimated development effort andresources.

    Then obtain the required resources for the project in case the project is continued.

    3.1.2 Entry Criteria

    Customers engagement is established via the Project Order Sheet.

    High level expectations for the product are specified by the customer.

  • 8/14/2019 IUP Process Description 1.0 En

    10/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 6/13

    3.1.3 Input

    Project Order Sheet

    High level requirements

    3.1.4 Output Project Estimation

    Baselined plans including Project Plan, Risk Management Plan, SQA Plan, MA Plan, DeliveryPlan, CM Plan, Test Plan

    Requirements documents as: Vision, Business Process Model, Requirement Allocation, outlineof SRS, Use-cases

    Some design documents as: Selected Technical Solution, Software Conventions

    Risk List, Risk Log

    CM Audit Report

    NCs Tracking List

    Project Start Report

    Project Detail Schedule

    Some work products are from the monitoring and controlling activities such as: Weekly Report,Project Labor Cost, Commitment Log, and Issues Log.

    3.1.5 Exit Criteria

    The estimation and master schedule for project is accepted by customer.

    Project is accepted to continue.

    A kick-off meeting is hold formally.

    The complete Project Detail Schedule, at least for the first iteration, is reviewed and approvedby Senior Manager.

    Project Resource Request is accepted by Senior Manager.

    Project repository and all requested resources for the project are ready for going to the nextphase.

    3.1.6 Flow of Activities

  • 8/14/2019 IUP Process Description 1.0 En

    11/24

    QualityManagementSystem

    Code:IUP-PD

    IssuedD

    ate:

    IVC

    Unified

    Process

    Version:1.0

    Copyright

    ISBVietnamCorporation.

    (IVC)

    IUP-ProcessDescription

    1.0-EN.doc

    Confidential

    Page7/20

    Figure4.

    InitiationPhaseOverview

  • 8/14/2019 IUP Process Description 1.0 En

    12/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 8/20

    3.1.7 Essential Activities

    Create project repository in file server.

    Analyze problem to have the Vision, Business Process Model, and initial Requirements

    Allocation. Define the system from those above requirements document to have an outline of SRS and

    Use-cases. These will be the input for the estimation activities.

    Do estimation and master schedule for the project.

    Obtain the agreement and commitment from customer and relevant stakeholders on theestimation and master schedule.

    If the project is accepted to be continued, others required plans are developed such as ProjectPlan, Risk Management Plan, SQA Plan, MA Plan, Delivery Plan, CM Plan, Test Plan.

    Then select the technical solution for developing project, and develop software conventions tobe ready for the next phase.

    Beside, the project activities is also monitored and controlled from the early in this phase.

    At the end of this phase, the leader shall conduct a kick-off meeting to inform the information toproject members and also start project formally.

    Among the activities for ending phase, a detail schedule is also prepared for next phase by theleader.

    3.2 Phase: Definition

    The overriding goal of the definition phase is to baseline the architecture of the system to provide astable basis for the execution phase. This does not give an action schedule only, but also aperspective of the product to-be-built to project team.

    3.2.1 Objectives

    Complete planning for the project, and develop a detail schedule.

    Hold a project kick-off meeting.

    Obtain a deep understanding of the customers requirements to develop software requirementsspec.

    Develop the design documents.

    Gain the approval on those documents to provide a stable basis to the next phase.

    3.2.2 Entry Criteria

    Estimation and master schedule are agreed and accepted by customer and all stakeholders.

    The complete Project Detail Schedule, at least for the first iteration, is reviewed and approvedby Senior Manager.

    Project repository and all requested resources for the project are ready for going to the nextphase.

    3.2.3 Input

    Baselined Plans

    Project Detail Schedule

    Business Process Model

    Requirements Allocation

    3.2.4 Output

    Change Requests

  • 8/14/2019 IUP Process Description 1.0 En

    13/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 9/20

    Project plans and schedule are updated or revised upon to the approved change requests.

    Updated Requirements Allocation.

    Baselined requirements that contain complete documents of Vision, Business Process Model,SRS, and Use-cases.

    Baselined design documents that contain System Architecture, System Design, Detail Design,and Database Design.

    Implementation Model

    Testing documents such as: System Test Cases, Integration Test Cases, Test Data, and TestScript if any.

    Updated of Risk List, Risk Log

    CM Audit Report

    NCs Tracking List

    MA Report

    Milestone Report

    Some work products are from the monitoring and controlling activities such as: Weekly Report,Project Labor Cost, Commitment Log, and Issues Log.

    3.2.5 Exit Criteria

    Project plan is approved.

    Project kick-off meeting is held.

    Software requirements spec, System design, Detail design are validated and approved.

    Detail schedule, required resources and environment needed for upcoming project phase areavailable.

    3.2.6 Flow of Activities

  • 8/14/2019 IUP Process Description 1.0 En

    14/24

  • 8/14/2019 IUP Process Description 1.0 En

    15/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 11/20

    3.2.7 Essential Activities

    Request resources as needed for the project.

    Develop the project plan, then review and gain the approval on it.

    Hold the project kick-off meeting.

    Make a detail schedule based upon the approved project plan.

    Collect and analyze the customers requirements to develop SRS, and Use-cases.

    Develop the system design and a part or entire the detail design documents to ensure the inputfor implementation in first iteration of next phase.

    Implement and test the prototypes of system as required for a demonstration to customer.

    3.3 Phase: Execution

    The execution phase covers mainly for entire manufacturing process of the product, including most ofthe implementation and testing efforts to produce the product based upon the designs in Definitionphase.

    3.3.1 Objectives

    Update design document as necessary.

    Plan for system/subsystem integration.

    Implement the product as designed.

    Test the product components and/or entire product.

    Create the builds of product for deployment to customer.

    Finalize the support materials such as user manual, installation guide.

    3.3.2 Entry Criteria

    The software requirements spec and system design and/or detail design are validated andapproved.

    Detail schedule for this phase, required resources and environment needed are available.

    3.3.3 Input

    Baselined requirements (contain complete documents of Vision, Business Process Model, SRS,and Use-cases)

    Baselined design documents (contain System Architecture, System Design, Detail Design, andDatabase Design)

    Integration Test Cases, Test Data, and Test Script if any.

    Baselined plans and schedule.

    3.3.4 Output

    Change Requests

    Project plans and schedule are updated or revised upon to the approved change requests.

    Updated Requirements Allocation.

    Baselined code (build of subsystem).

    Unit Test Log, Code Review Checklist, Code Inspection Log.

    Bugs Tracking List, Test Result Report.

    Updated of Risk List, Risk Log

    CM Audit Report

  • 8/14/2019 IUP Process Description 1.0 En

    16/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 12/20

    NCs Tracking List

    MA Report

    Milestone Report

    Some work products are from the monitoring and controlling activities such as: Weekly Report,

    Project Labor Cost, Commitment Log, and Issues Log.

    3.3.5 Exit Criteria

    Test design is approved.

    The implemented product is tested passed and delivered to customer.

    Support materials are finalized and available.

    Detail schedule, required resources and environment needed for upcoming project phase areavailable.

    3.3.6 Flow of Activities

  • 8/14/2019 IUP Process Description 1.0 En

    17/24

    QualityManagementSystem

    Code:IUP-PD

    IssuedD

    ate:

    IVC

    Unified

    Process

    Version:1.0

    Copyright

    ISBVietnamCorporation.

    (IVC)

    IUP-ProcessDescription

    1.0-EN.doc

    Confidential

    Page13/20

    Figure6.

    ExecutionPhaseOverview

  • 8/14/2019 IUP Process Description 1.0 En

    18/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 14/20

    3.3.7 Essential Activities

    Update system design and detail design for the product components as necessary.

    Make plan for system integration.

    Compose test cases, test scripts, and prepare test data for implement testing.

    Implement the product components based on the design documents.

    Perform unit test for product components and all modules.

    Integrate product components and execute the integration test to product.

    Fix all defects found to ensure that the integrated product is ready for every delivery.

    Deliver components and/or build of product.

    Finalize the support materials.

    3.4 Phase: Transition

    The primary goal of Transition phase is to ensure that the software product is delivered to its enduser successfully.

    This phase also includes maintaining the product and making some minor adjustments based onuser feedback. Any major changes or adjustments from end-user should lead to a new developmentcycle begins with an Initiation phase, or Definition phase, etc.

    3.4.1 Objectives

    To deploy the product and associated deliverables to the customer.

    Maintain and support to make the product passed the acceptance test.

    3.4.2 Entry Criteria

    Final product and associated deliverables are available.

    The final product meets all acceptance criteria defined in the initiation phase.

    3.4.3 Input

    Baselined code

    Baselined plans including Delivery Plan

    All deliverables

    3.4.4 Output

    Delivery Package (Release Notes, support materials, source code files, etc.)

    Bugs Tracking List, Test Result Report.

    Updated of Risk List, Risk Log

    CM Audit Report

    NCs Tracking List

    MA Report, Milestone Report

    Some work products are from the monitoring and controlling activities such as: Weekly Report,Project Labor Cost, Commitment Log, and Issues Log.

    3.4.5 Exit Criteria

    Product is accepted by customer.

    3.4.6 Flow of Activities

  • 8/14/2019 IUP Process Description 1.0 En

    19/24

    QualityManagementSystem

    Code:IUP-PD

    IssuedD

    ate:

    IVC

    Unified

    Process

    Version:1.0

    Copyright

    ISBVietnamCorporation.

    (IVC)

    IUP-ProcessDescription

    1.0-EN.doc

    Confidential

    Page15/20

    PL

    CC

    QC

    CC

    SQA

    PL

    PL

    SQA

    DP

    PL

    Start

    End

    Project

    maintenace

    act.

    Identify&

    analyzerisk

    -Risklist

    -Risklog

    Changes

    requestmgt

    Change

    reques

    t

    1

    -Projectplan

    -Projectdetail

    schedule

    1

    Integrate

    system

    Manage

    baseline

    s

    Newbaseline

    (code)

    WP

    evaluation

    NCstrackinglist

    Manage

    baseline

    s

    Newbaseline

    (Delivery)

    CMaud

    it

    -CMplan

    -CMauditCL

    CMauditreport

    Phase-end

    re

    viewCL

    NCs

    trackinglist

    Phase-end

    meeting

    Project

    records,data

    Milestone

    report

    Monitor&

    contro

    l

    projec

    t

    Projectprogress,

    data

    -Weeklyreport

    -Issueslog

    -Commitmentlog

    -Projectlaborcost

    -Unittestlog

    -Newversionof

    system

    -Systemdesign

    -Integrated

    subsystem

    Test

    execution

    Newversionof

    system

    -B

    ugstrackinglist

    -T

    estresultreport

    -T

    estplan

    -T

    estcases

    -T

    estdata

    -T

    estscripts

    Newversionof

    system

    Supp

    ortmaterials

    Provide

    measurement

    results

    -MAplan

    -Project

    records,data

    MAreport

    Create&deliver

    thedeliverypac.

    -Deliveryplan

    -Deliverables

    -Deliverytracking

    (updated)

    -Deliverypackage

    Receive

    feedbackfrom

    customer

    Deliverypackage

    Deliverytracking

    (updated)

    Phase-end

    review

    Monitor

    risk

    Control

    risk

    Figure7.

    TransitionPhaseOverview

  • 8/14/2019 IUP Process Description 1.0 En

    20/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 16/20

    3.4.7 Essential Activities

    Complete support materials.

    Execute system test to the entire product.

    Make a release notes.

    Package all and deliver them to customer for acceptance test.

    Get user feedback.

    Fix defects and create the final product that passed the acceptance test.

    3.5 Phase: Retirement

    The Retirement phase completes all project activities, and archives the project data preparing forbringing it to an end.

    3.5.1 Objectives

    Bring the project to an end.

    Collect measurement data for improvement.

    3.5.2 Entry Criteria

    Final product is accepted by the customer.

    3.5.3 Input

    SQA Plan,

    SQA Evaluation Report,

    NCs Tracking List

    MA Plan,

    Project data, records,

    Bugs Tracking List,

    Test Result Report

    3.5.4 Output

    Customer Evaluation Survey,

    SQA Summary Report,

    Project End Report,

    Project Index.

    3.5.5 Exit Criteria

    All project activities are done successfully.

    A project post-mortem is held.

    Measurement data is collected and evaluated by Project Manager/Director.

    Project end report is reviewed and evaluated by Project Manager/Director.

    3.5.6 Flow of Activities

  • 8/14/2019 IUP Process Description 1.0 En

    21/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 17/20

    Figure 8. Retirement Phase Overview

    3.5.7 Essential Activities

    Make detail schedule for closure project.

    Collect all measurement data.

    Archive all project documents and data into project defined repository.

    Make a project end report for evaluation from Manager/Director.

    Hold a project post-mortem meeting.

  • 8/14/2019 IUP Process Description 1.0 En

    22/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 18/20

    4 Software Project Types & Sizes

    4.1 Project Types

    There are two types of project at IVC, including: new application development, and enhancement/upgrading application.

    4.1.1 New application development

    There are two types of new application development project:

    1. Designing and developing new application based on provided requirements from customer.

    2. Implementing new application based on requirements spec and design documents provided bythe customer.

    4.1.2 Enhancement / Upgrading

    There are three types of the enhancement/upgrading project:

    1. Adding new functions or updating functions of an existed software product.

    2. Converting coding language of an existed source code to another one.

    3. Port to another environment.

    4.2 Project Sizes

    There are three standard sizes for software project at IVC:

    Size (man-month) Project Level Description

    >= 75 A Large project

    >= 15 and < 75 B Medium project

    < 15 C Small project

    5 Roles & Team Structure in IUP

    There are two kinds of roles involve in the IUP: team roles, and individual roles.

    5.1 Team roles

    A team role consists of several individual roles that work closely in a specific aspect of the projectactivities, such as: project management, development, testing, etc.

    There are six team roles involved on the project activities as following:

    Project Management Team: is responsible for managing project activities. The scope ofmanagement is at:

    - Project-level: managing the overall project plan, and accountable for the project scope,major milestones, resources, and expenses of the project.

    - Team-level: managing the activities of team members, which is responsible for a specificfunctional area assigned by Project Manager/Project Leader.

    Development Team: is responsible for implementing the product and realization of an integratedproduct based on customers requirements.

  • 8/14/2019 IUP Process Description 1.0 En

    23/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Copyright ISB Vietnam Corporation.(IVC)

    IUP-Process Description 1.0-EN.doc

    Confidential

    Page 19/20

    Testing Team: is responsible for testing of the product which is developed by Developmentteam.

    Deployment Team: is responsible for package the product and all required deliverables into adeployment unit, and deploy the product successfully.

    Product Support Team: is responsible for technical supporting and maintaining the productduring its production time.

    Software Quality Assurance Team: is responsible for evaluating the adherence of the processand the compliances to quality standards of IVC from the project team. This team officiallybelongs to QA department and has an independent reporting channel between QA teammembers and section Managers/Director.

    5.2 Individual roles

    An individual role performs specific tasks that he/she is responsible to as assigned in the project byProject Manager/Project Leader.

    There are some individual roles in a project team as following:

    Project Leader: belongs to the Project Management Team, at project-level. This role isresponsible for managing, monitoring and controlling all of project activities directly.

    Team Lead: belongs to the Project Management Team, at team-level. This role is assigned byProject Manager/Project Leader. Upon to specific team roles, this role will have its specific name.See figure 4 of Team Structure for detail.

    Developer: belongs to Development Team, also could be a member of Deployment Team, andProduct Support Team as assigned by Project Leader.

    Quality Control: belongs to Testing Team.

    Quality Assurance: belongs to Software Quality Assurance Team.

    Interpreter: is responsible for supporting project team in translation.

    Aside from these individual roles, there are three roles which have impacts to the project at someaspect of management, technical consulting, quality of the project, including:

    Project Manager:plays role as Management Reviewer who is responsible mainly for:

    - Evaluating project planning, whether the project can be cancelled or not.

    - Evaluating project assessment artifacts at major review points in the project lifecycle toaccept for the entrance into next phase or not.

    Technical Manager: consults techniques for the project as required. This role could belong to

    Product Support Team as well.

    QA Leader: consults and supports SQA team to control the quality of project in adherence of theprocess, and qualified work products to standards.

    QC Leader: consults and supports QC team in testing activities of project.

    Refer to specific job description for more detail.

    5.3 Team Structure

    The project team structure is described in the figure as below:

  • 8/14/2019 IUP Process Description 1.0 En

    24/24

    Quality Management System Code: IUP-PD

    Issued Date: IVC Unified Process

    Version: 1.0

    Development Lead

    (Development Team)

    Support Lead

    (Product Support

    Team)

    Deployment Lead

    (Deployment Team)

    Project Leader

    QC Lead

    (Testing Team)

    QA Lead

    (SQA Team)

    Development

    Team

    Product Support

    Team

    Deployment

    Team Testing Team SQA Team

    Project Team

    Support

    Section Manager

    (Project Manager)

    QA Leader

    Technical

    Manager

    QC Leader

    Figure 9. Team Structure

    Note: in the above structure, some notices are paid attention to as below:

    Technical Manager, Project Manager, QC Leader and QA Leader are all positions atcompany-level.

    Project Leader is a role which is turned up when there is a new project. This role could beplayed by the Project Leader who is officially at this position in company or a person who hasqualified to be assigned to project only.

    Development Lead, Support Lead, Deployment Lead, QC Lead, and QA Lead are roleswhich are just turned up in a project only. When the project is end, these roles are also off.

    Not all of the above team roles always required for every project. Depending on the project size andscope, one or several team roles may not be established. But there are four team roles areindispensables, including:

    Project Management Team

    Development Team

    Testing Team

    Software Quality Assurance Team

    Normally, large and medium sized projects would have team structure as above. This helps tomonitor, manage and control these kinds of project without difficulty.

    5.4 Staffing Rules

    1. Developer who belongs to the Development Team could be assigned as member of DeploymentTeam, and Product Support Team, but MUST NOT be assigned as a QC/QA who belongs toTesting Team/SQA Team, and vice versa.

    2. If there is only one QC assigned to the project, he/she would also play the role of QC Lead in theproject. Otherwise, QC Lead in a project should be assigned by QC Leader.

    3. If there is only one QA assigned to the project, he/she would also play the role of QA Lead in theproject. Otherwise, QA Lead in a project should be assigned by QA Leader.