ITSC Meeting BMS Status Update. IT Team 06-Dec-2004. Vendor Evaluation Status. Completed first phase of Proof of Concept (POC) Narrowed down to two vendors from original 10 vendor list ACGI and Oracle made their presentations IT and user teams evaluated and scored these vendors - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ITSC Meeting BMS Status Update

ITSC MeetingBMS Status Update

IT Team06-Dec-2004

Page 2: ITSC Meeting BMS Status Update

Vendor Evaluation Status• Completed first phase of Proof of Concept

(POC) – Narrowed down to two vendors from original

10 vendor list• ACGI and Oracle made their presentations

– IT and user teams evaluated and scored these vendors

• Oracle was evaluated ahead in preliminary evaluation

Page 3: ITSC Meeting BMS Status Update

Vendor Evaluation Summary

• ACGI – Offers a membership specific solution– Not strategic from forward looking and Enterprise Architecture

perspective– Very small boutique company - financial viability is a concern– Build cost may lower however need to understand vendors

ability to support IEEE time to market/business needs• Oracle

– Robust architecture which offers ability to support business needs beyond membership specific solution

– Offers strategic systems framework and enables Enterprise Architecture

– Build cost higher as it is module based and will require configuration/extensions to align to IEEE’s business needs

• Need to assess upgrade/maintainability required once in production

Page 4: ITSC Meeting BMS Status Update

Vendor Evaluation Summary

• Key Evaluation Points– User Interface

• Support of business capabilities• Streamlined work flow and integration

– Total Cost of Ownership (TCO)• Benchmark build versus ongoing maintenance costs• Licensing considerations

– Strategic Architecture• Extensibility of design for future business needs• Technology framework

Page 5: ITSC Meeting BMS Status Update

BMS Preliminary Capital - estimates($ Thousands)

Vendor 2005 2006 2007 2008 Total

Aug ITSC Model

2,930 1,120 1,120 - 4,620

Nov ITSC Model

3,770 1,120 1,120 - 6,010

Page 6: ITSC Meeting BMS Status Update

BMS Preliminary Expense - estimated ($ Thousands)

Vendor 2005 2006 2007 2008 Total

Aug ITSC Model

443 863 1,074 1,074 3,454

Nov ITSC Model

655 863 1,074 1,074 3,666

Page 7: ITSC Meeting BMS Status Update

Next Steps

• Complete by 31-Jan-2005– Vendor Evaluations and Solution Selection

• Membership Specific Approach– Engage 2 additional vendors - Avectra, Aptify to understand their

membership specific solution to benchmark costs/functionality

• Oracle/Strategic Framework Approach– Rationalize fixed price bid from Oracle

» Understand Oracle consulting cost drivers » Help prioritize, justify and understand estimated future

maintenance costs– Engage 2-3 Oracle partners to benchmark Oracle consulting costs

• Complete by 8-Feb-2005– Confirm Recommendations/High Level Plan/Costs– Prepare recommendation for February Board Meeting