Page 1: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

ITS Architecture Development in a Regional

Planning Context

Central Ohio Case Study

Erika WitzkePrincipal Engineer

Mid-Ohio Regional Planning Commissionwww.morpc.org

September 29, 2005

Page 2: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

2

MORPC (MPO) Planning Area

Population=1.24 M Major Interstate

Routes: I-71, I-70, I-270, I-670

Ohio’s Capital Home to The Ohio

State University

2 whole + 2 partial counties

41 Member Agencies 24 FT, 3 PT

transportation staff

Page 3: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

3

Prepared by:

The Mid-Ohio Regional Planning Commission285 East Main Street

Columbus, OH 43215

Central Ohio Regional ITS Architecture“ITS components that operate together and as part of a system will enhance safety and mobility and reduce the possibility of

costly incompatible systems in the future.”

April 2004

Prepared by:

The Mid-Ohio Regional Planning Commission285 East Main Street

Columbus, OH 43215

Central Ohio Regional ITS Architecture“ITS components that operate together and as part of a system will enhance safety and mobility and reduce the possibility of

costly incompatible systems in the future.”

April 2004

http://its.morpc.org/regITS.html

Page 4: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

4

Central Ohio Regional ITS Architecture History

1999 - MORPC created the “ITS Integration Strategy for Central Ohio” A good start, but lacking critical components

recognized by FHWA

2004 - MORPC adopted the “Central Ohio Regional ITS Architecture” TurboArchitecture 2.0 Incorporated FHWA recommendations from

Integration Strategy Updated triennially in conjunction with T-Plan

Page 5: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

5

Regional ITS Architecture Development (& Update) Process

Source: Regional ITS Architecture Guidance Document

NeedScope Stakeholders

Champions

Inventory SystemsNeeds and Services

Operational ConceptFunctional Requirements

Project SequencingList of Agency Agreements

ITS Standards

Iter

ativ

e P

roce

ss

Interconnects Information Flows

STEP #1: GET STARTED

STEP #2: GATHER DATA

STEP #3: DEFINE INTERFACES

STEP #4: IMPLEMENTATION

STEP #5:USE THE ARCHITECTURE

STEP #6:MAINTAIN THE ARCHITECTURE

Page 6: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

6

Step #1: Get Started

Source: Regional ITS Architecture Guidance Document

Page 7: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

7

Step #1: Get StartedCentral Ohio Case Study

Original Need Increases in congested

travel & daily travel growth

Driven by numerous MPO funding requests

Declining member budgets

More reasons to update… Desire to incorporate

M&O activities in planning process (SAFETEA-LU)

Congested System (% of lane-miles)

48

49

50

51

52

53

54

55

56

57

58

1996 1997 1998 1999 2000 2001 2002 2003P

erc

en

t (%

)

Large Urban Area Avg

Columbus

source: 2005 TTI Mobilty Study

Page 8: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

8

Step #1: Get StartedCentral Ohio Case Study

Region & Timeframe MPO boundary/AQ conformity area 20 year horizon (T-Plan)

Identify (New) Stakeholders Build off established groups (housed

at MPO), then start adding… Active Outreach/Education with

stakeholders Identify Champion

MPO selected as champion Project champions

Page 9: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

9

Columbus Traffic Signal System Assessment

City boundaries drive the need for close coordination with neighboring jurisdictions (15+) Poor cross-jurisdictional coordination Transit system desires traffic signal priority City and ODOT desire closer relationship between signal and

freeway management systems MORPC has $14.9 M programmed for improvements to

the system over the next 6 years Study will result in new design philosophy and will

conform to architecture standards

“Because upgrades to the Columbus System are fully funded through MORPC, the new system design must

conform to the Regional ITS Architecture.”

Page 10: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

10

Step #2: Gather Data

Source: Regional ITS Architecture Guidance Document

Page 11: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

11

Step #2: Gather DataCentral Ohio Case Study Inventory Systems/Plans

Existing / planned ITS systems ITS Studies

Determine Needs and Services ITS systems will provide Work with stakeholders to

determine Consensus building/visioning -

“What does the region need?” Work together to prioritize regional

projects

MPO’s can assist member govt’s get the information needed to make

informed planning decisions.

Page 12: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

12

Step #2: Gather DataCentral Ohio Case Study

Develop Operational Concepts MPO to provide data on the possibilities ID roles and responsibilities of each stakeholder GET BUY IN!

Central Ohio Freeway Management System Example

Each update to the architecture offers a new regional visioning opportunity.

Page 13: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

13

Step #3: Define Interfaces

Source: Regional ITS Architecture Guidance Document

Page 14: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

14

Step #3: Define InterfacesCentral Ohio Case Study

National ITS Architecture version 4.0 Central Ohio Regional ITS Architecture

Page 15: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

15

Step #3: Define InterfacesCentral Ohio Case Study

Page 16: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

16

Step #4: Implementation

Source: Regional ITS Architecture Guidance Document

Page 17: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

17

Step #4: ImplementationCentral Ohio Case Study

Define Project Sequencing Closely tied to the MPO Planning process Architecture process ensures that projects

are built in a logical sequence CM/AQ – Applications accepted on a 2 year

cycle TIP – 4 year schedule of transportation

improvements updated every 2 years T-Plan – 20 year horizon updated every 3

years

Page 18: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

18

Step #4: ImplementationCentral Ohio Case Study

Develop list of Agency Agreements Existing and ID possible new

agreements Region okay with handshake

agreements - Only a few formal agreements in place: Joint ODOT & City operation of FMS 800 MHz radio system (33+ partners)

Projects have stalled or ended in the pursuit of developing MOUs

Page 19: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

19

Steps #5 & #6: Use & Maintenance of Architecture

Source: Regional ITS Architecture Guidance Document

Page 20: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

20

Why Develop (& Update) a Regional ITS Architecture?

Conclusions: Foundation for incorporating management and

operations into decision-making/planning (SAFETEA-LU emphasis area)

Continue to identify (and develop new) integration opportunities

Assist in identifying gaps in existing services (and finding solutions)

Efficient and effective project implementation structure

Tool to estimate funding needs (opportunity for new projects to get federal funding)

On-going educational opportunities

Page 21: ITS Architecture Development in a Regional Planning Context Central Ohio Case Study Erika Witzke Principal Engineer Mid-Ohio Regional Planning Commission

21

Contact Information

Erika WitzkeMid-Ohio Regional Planning Commission

Voice: 614.233.4149Email: [email protected]

www.morpc.org