    Information Technology Project

    Management, Seventh Edition

    Note: See the text itself for full citations.

  • 8/13/2019 ITPM_05

    2/42

    Copyright 2014

    Understand the importance of good project scope

    management

    Describe the process of planning scope management

    Discuss methods for collecting and documenting

    requirements to meet stakeholder needs andexpectations

    Explain the scope definition process and describe thecontents of a project scope statement

    Discuss the process for creating a work breakdownstructure using the analogy, top-down, bottom-up, andmind-mapping approaches

    Information Technology ProjectManagement, Seventh Edition 2

  • 8/13/2019 ITPM_05

    3/42

    Copyright 2014

    Explain the importance of validating scope andhow it relates to defining and controlling scope

    Understand the importance of controlling scope

    and approaches for preventing scope-relatedproblems on information technology (IT) projects

    Describe how software can assist in project scopemanagement

    Information Technology ProjectManagement, Seventh Edition 3

  • 8/13/2019 ITPM_05

    4/42

    Copyright 2014

    Scoperefers to allthe work involved in creating the

    products of the project and the processes used tocreate them

    A deliverableis a product produced as part of a

    project, such as hardware or software, planningdocuments, or meeting minutes

    Project scope management includes the processesinvolved in defining and controlling what is or is not

    included in a project

    Information Technology ProjectManagement, Seventh Edition 4

  • 8/13/2019 ITPM_05

    5/42

    Copyright 2014

    Planning scope: determining how the projects scope

    and requirements will be managed

    Collecting requirements: defining and documenting thefeatures and functions of the products produced during theproject as well as the processes used for creating them

    Defining scope:reviewing the project charter, requirements

    documents, and organizational process assets to create ascope statement

    Creating the WBS:subdividing the major project deliverablesinto smaller, more manageable components

    Validating scope: formalizing acceptance of the projectdeliverables

    Controlling scope: controlling changes to project scopethroughout the life of the project

    Information Technology ProjectManagement, Seventh Edition 5

  • 8/13/2019 ITPM_05

    6/42

    Copyright 2014Information Technology ProjectManagement, Seventh Edition 6

  • 8/13/2019 ITPM_05

    7/42Copyright 2014

    The project team uses expert judgment andmeetings to develop two important outputs: thescope management plan and the requirementsmanagement plan

    The scope management plan is a subsidiary partof the project management plan

    Information Technology ProjectManagement, Seventh Edition 7

  • 8/13/2019 ITPM_05

    8/42

  • 8/13/2019 ITPM_05

    9/42Copyright 2014

    The PMBOK Guide, Fifth Edition, describesrequirements as conditions or capabilities thatmust be met by the project or present in theproduct, service, or result to satisfy an agreementor other formally imposed specification

    The requirements management plan documentshow project requirements will be analyzed,

    documented, and managed

    Information Technology ProjectManagement, Seventh Edition 9

  • 8/13/2019 ITPM_05

    10/42Copyright 2014

    For some IT projects, it is helpful to dividerequirements development into categories calledelicitation, analysis, specification, and validation

    It is important to use an iterative approach to

    defining requirements since they are often unclearearly in a project

    Information Technology ProjectManagement, Seventh Edition 10

  • 8/13/2019 ITPM_05

    11/42Copyright 2014Information Technology ProjectManagement, Seventh Edition 11

  • 8/13/2019 ITPM_05

    12/42Copyright 2014

    Interviewing

    Focus groups and facilitated workshops Using group creativity and decision-making techniques

    Questionnaires and surveys

    Observation Prototyping

    Benchmarking, or generating ideas by comparingspecific project practices or product characteristics to

    those of other projects or products inside or outsidethe performing organization, can also be used tocollect requirements

    Information Technology ProjectManagement, Seventh Edition 12

  • 8/13/2019 ITPM_05

    13/42Copyright 2014

    Eighty-eight percent of the software projects involvedenhancing existing products instead of creating newones

    Eighty-six percent of respondents said that customersatisfaction was the most important metric formeasuring the success of development projects

    Eighty-three percent of software development teams

    still use Microsoft Office applications such as Wordand Excel as their main tools to communicaterequirements

    Information Technology ProjectManagement, Seventh Edition 13

    *John Simpson, 2011: The State of Requirements Management (2011).

  • 8/13/2019 ITPM_05

    14/42Copyright 2014

    Genesys Telecommunications Laboratories usesAccept software, a product planning andinnovation management application and winner ofthe Excellence in Product Management Award

    from 20062008 Accept helps them instill a consistent, repeatable,

    and predictable process for new product definitionand development

    They can define what information comprises arequirement and enforce discipline around thatprocess

    Information Technology ProjectManagement, Seventh Edition 14

  • 8/13/2019 ITPM_05

    15/42Copyright 2014

    A requirements traceability matrix (RTM) is a table

    that lists requirements, various attributes of eachrequirement, and the status of the requirements toensure that all requirements are addressed

    Table 5-1. Sample entry in an RTM

    Information Technology ProjectManagement, Seventh Edition 15

  • 8/13/2019 ITPM_05

    16/42Copyright 2014

    Project scope statements should include at least aproduct scope description, product user acceptancecriteria, and detailed information on all projectdeliverables. It is also helpful to document other

    scope-related information, such as the projectboundaries, constraints, and assumptions. Theproject scope statement should also referencesupporting documents, such as product specifications

    As time progresses, the scope of a project shouldbecome more clear and specific

    Information Technology ProjectManagement, Seventh Edition 16

  • 8/13/2019 ITPM_05

    17/42Copyright 2014

    Information Technology ProjectManagement, Seventh Edition 17

  • 8/13/2019 ITPM_05

    18/42Copyright 2014

    Information Technology ProjectManagement, Seventh Edition 18

  • 8/13/2019 ITPM_05

    19/42Copyright 2014

    Many people enjoy watching television shows likeTrading Spaces, where participants have two days and$1,000 to update a room in their neighbors house. Sincethe time and cost are set, its the scope that has themost flexibility

    Although most homeowners are very happy withwork done on the show, some are obviouslydisappointed. Part of agreeing to be on the showincludes signing a release statement acknowledging that

    you will accept whatever work has been done Too bad you cant get sponsors for most projects tosign a similar release form. It would make project scopemanagement much easier!

    Information Technology ProjectManagement, Seventh Edition 19

  • 8/13/2019 ITPM_05

    20/42Copyright 2014

    A WBSis a deliverable-oriented grouping of the workinvolved in a project that defines the total scope of theproject

    WBS is a foundation document that provides the basis

    for planning and managing project schedules, costs,resources, and changes

    Decompositionis subdividing project deliverables intosmaller pieces

    A work package is a task at the lowest level of the WBS The scope baseline includes the approved project

    scope statement and its associated WBS and WBSdictionary

    Information Technology ProjectManagement, Seventh Edition 20

  • 8/13/2019 ITPM_05

    21/42Copyright 2014

    Information Technology ProjectManagement, Seventh Edition 21

  • 8/13/2019 ITPM_05

    22/42Copyright 2014

    Information Technology ProjectManagement, Seventh Edition 22

  • 8/13/2019 ITPM_05

    23/42

    Copyright 2014Information Technology ProjectManagement, Seventh Edition 23

  • 8/13/2019 ITPM_05

    24/42

    Copyright 2014Information Technology ProjectManagement, Seventh Edition 24

  • 8/13/2019 ITPM_05

    25/42

    Copyright 2014Information Technology ProjectManagement, Seventh Edition 25

  • 8/13/2019 ITPM_05

    26/42

    Copyright 2014

    Using guidelines: Some organizations, like theDOD, provide guidelines for preparing WBSs

    The analogy approach: Review WBSs of similarprojects and tailor to your project

    The top-down approach: Start with the largestitems of the project and break them down

    The bottom-up approach: Start with the specifictasks and roll them up

    Mind-mapping approach: Mind mapping is atechnique that uses branches radiating out from acore idea to structure thoughts and ideas

    Information Technology ProjectManagement, Seventh Edition 26

  • 8/13/2019 ITPM_05

    27/42

    Copyright 2014Information Technology ProjectManagement, Seventh Edition 27

  • 8/13/2019 ITPM_05

    28/42

    Copyright 2014Information Technology ProjectManagement, Seventh Edition 28

  • 8/13/2019 ITPM_05

    29/42

    Copyright 2014

    Many WBS tasks are vague and must beexplained more so people know what to do andcan estimate how long it will take and what it willcost to do the work

    A WBS dictionaryis a document that describesdetailed information about each WBS item

    Information Technology ProjectManagement, Seventh Edition 29

  • 8/13/2019 ITPM_05

    30/42

    Copyright 2014Information Technology ProjectManagement, Seventh Edition 30

  • 8/13/2019 ITPM_05

    31/42

    Copyright 2014

    A unit of work should appear at only one place inthe WBS. The work content of a WBS item is the sum of the

    WBS items below it A WBS item is the responsibility of only one

    individual, even though many people may beworking on it

    The WBS must be consistent with the way in whichwork is actually going to be performed; it should

    serve the project team first, and other purposes onlyif practical

    Information Technology ProjectManagement, Seventh Edition 31

  • 8/13/2019 ITPM_05

    32/42

    Copyright 2014

    Project team members should be involved indeveloping the WBS to ensure consistency andbuy-in

    Each WBS item must be documented in a WBS

    dictionary to ensure accurate understanding of thescope of work included and not included in thatitem

    The WBS must be a flexible tool to accommodate

    inevitable changes while properly maintainingcontrol of the work content in the project accordingto the scope statement

    Information Technology ProjectManagement, Seventh Edition 32

  • 8/13/2019 ITPM_05

    33/42

    Copyright 2014

    A project scope that is too broad and grandiosecan cause severe problems Scope creep and an overemphasis on technology for

    technologys sake resulted in the bankruptcy of a large

    pharmaceutical firm, Texas-based FoxMeyer Drug In 2001, McDonalds fast-food chain initiated a project to

    create an intranet that would connect its headquarterswith all of its restaurants to provide detailed operationalinformation in real time. After spending $170 million onconsultants and initial implementation planning,McDonalds realized that the project was too much tohandle and terminated it

    Information Technology ProjectManagement, Seventh Edition 33

  • 8/13/2019 ITPM_05

    34/42

    Copyright 2014

    It is very difficult to create a good scope statementand WBS for a project It is even more difficult to verify project scope and

    minimize scope changes

    Scope validation involves formal acceptance of thecompleted project deliverables

    Acceptance is often achieved by a customerinspection and then sign-off on key deliverables

    Information Technology ProjectManagement, Seventh Edition 34

  • 8/13/2019 ITPM_05

    35/42

    Copyright 2014

    Many countries have had difficulties controlling thescope of large projects, especially those thatinvolve advanced technologies and many differentusers

    For example, the state government of Victoria,Australia, has a Web site for its publictransportation smart card at www.myki.com.au.

    There were many problems in developing andimplementing the smart card

    Information Technology ProjectManagement, Seventh Edition 35

    http://www.myki.com.au/http://www.myki.com.au/
  • 8/13/2019 ITPM_05

    36/42

    Copyright 2014

    Scope control involves controlling changes to theproject scope

    Goals of scope control are to influence the factors that cause scope changes

    assure changes are processed according to proceduresdeveloped as part of integrated change control, and

    manage changes when they occur

    Varianceis the difference between planned and

    actual performance

    Information Technology ProjectManagement, Seventh Edition 36

  • 8/13/2019 ITPM_05

    37/42

  • 8/13/2019 ITPM_05

    38/42

    Copyright 2014

    Develop a good project selection process and

    insist that sponsors are from the user organization Have users on the project team in important roles

    Have regular meetings with defined agendas, andhave users sign off on key deliverables presented

    at meetings Deliver something to users and sponsors on a

    regular basis

    Dont promise to deliver when you know you cant

    Co-locate users with developers

    Information Technology ProjectManagement, Seventh Edition 38

  • 8/13/2019 ITPM_05

    39/42

    Copyright 2014

    Develop and follow a requirements managementprocess

    Use techniques such as prototyping, use casemodeling, and JAD to get more user involvement

    Put requirements in writing and keep them current Create a requirements management database for

    documenting and controlling requirements

    Information Technology ProjectManagement, Seventh Edition 39

  • 8/13/2019 ITPM_05

    40/42

    Copyright 2014

    Provide adequate testing and conduct testingthroughout the project life cycle

    Review changes from a systems perspective

    Emphasize completion dates to help focus onwhats most important

    Allocate resources specifically for handling changerequests/enhancements like NWA did with ResNet

    Information Technology ProjectManagement, Seventh Edition 40

  • 8/13/2019 ITPM_05

    41/42

    Copyright 2014

    Word-processing software helps create severalscope-related documents

    Spreadsheets help to perform financialcalculations, weighed scoring models, and

    develop charts and graphs Communication software like e-mail and the Web

    help clarify and communicate scope information Project management software helps in creating a

    WBS, the basis for tasks on a Gantt chart Specialized software is available to assist in

    project scope management

    Information Technology ProjectManagement, Seventh Edition 41

  • 8/13/2019 ITPM_05

    42/42

    Project scope management includes theprocesses required to ensure that the projectaddresses all the work required, and only the workrequired, to complete the project successfully

    Main processes include Define scope management

    Collect requirements

    Define scope

    Create WBS

    Validate scope

    Control scope