itp for cable tray installation
TRANSCRIPT
-
8/18/2019 ITP for Cable Tray Installation
1/4
21-May-12 Danny J.Y.Jeong K.J.Lim
Date Drawn Checked Approved
Owner :
A
Owner's Engineer :
Details of Revision
AES-VCM MONG DUONG
POWER COMPANY LIMITED
For Information
Rev.
oosan Heavy Industries
Vietnam
Dung Quat Economic Zone,
Binh Thuan, Binh Son, Quang Ngai,
Vietnam
T +84 55 5618 900
F +84 553 618 950
Page 1
Project : PC : T10206
UAS : QE01
Unit : PO
Title :KKS : ZEN
Reg. No.
Revision : A
Drawing No. : Page-No :
T10206-QE01-POZEN__-040203 INSPECTION
AND TEST PLAN FOR
CABLE TRAYS INSTALLATION
040203
T10206-QE01-P0ZEN-040203
MONG DUONG II 2 X 560MW (NET) COAL FIRED POWER PROJECT
1 of 4
Contractor :
Page 1
-
8/18/2019 ITP for Cable Tray Installation
2/4
Rev. A
2 of 4
This note is only applicable for AES-VCM Mong Duong
Detailed Legend
S : Surveillance Point / DOOSAN / Subcontractor does not send a notification to AES-VCM Mong Duong
except for the first or last operation on the basis of each process. AES-VCM Mong Duong
could check the operation, if he is present at the site during the inspection by Doosan.
R : Report Review Point / DOOSAN / Subcontractor is required to prepare a certificate or document
attesting to the satisfactory performance of the related test or inspection for review by
-
T10206-QE01-POZEN-040203
DOOSAN
AES-VCMITP for Cable Tray Installation
Doc. No.
Contractor
Page 2
- .
W : Witness Point / DOOSAN / Subcontractor shall submit request for inspection to AES-VCM to
decide whether they will attend such inspection or not.
H : Hold Point / Downstream construction and other activities shall not proceed
without attendance or any written approval of AES-VCM Mong Duong.
NOTE : The Site ITP and all of the abovementioned reports will be kept available by
DOOSAN at anytime for control and or review by AES-VCM Mong Duong.
Page 2
-
8/18/2019 ITP for Cable Tray Installation
3/4
Doc. No.
Contractor
A Sign A Sign A Sign
R R R
R R R
H W WB1Check the installation is according to the designed
layout drawing & specification.
Approved Construction
Drawing T10206-YD04---
AES-VCM
A.Material
Receipt
A1Check the condition of cable Supports, Racks, Trays
and Trunking while receiving.Packing List
A2Check size and type of the Supports, Racks, Trays
and Trunking with respect to the requisitions.
Material Technical
Specification
Item Name Oper. No. Inspection Process
Specific Applicable drawing
number, Standard Code number,Specification
Inspection & Test Activities
Subcontractor DOOSAN
Inspection & Test Plan for Cable Tray
InstallationAES-VCM
H W W
H W W
H W W
H W W
H W W
H W W
Abb revi atio n : S: Surveillance R: Report Review W: Witness Inspection H: Hold Inspection
Note : All inspection shall be performed in accordance with the approved Site Inspection and Test Plans/Project Specifications
B. Cable
Tray
Installation
Ensure the cable trays numbered according to
cable trays route layout on which KKS nos. are
indicated and explained.
Approved ConstructionDrawing T10206-YD04---
B5Ensure there are no sharp 90 degrees bends are
made.
Approved Construction
Drawing T10206-YD04---
B6
Ensure the cable trays numbered according to cable
trays route layout on which KKS nos. are indicated and
explained.
Approved Construction
Drawing T10206-YD04---
B7
No sharp edges cut to be permitted. Cutting edges of
trays/trunkings are touch-up painted.
Approved Construction
Drawing T10206-YD04---
B4Ensure the gap between parallel runs is quite enough
to accommodate the layer of cables.
Approved Construction
Drawing T10206-YD04---
B3
B2
expansion joints if any are specified are in place.
Drawing T10206-YD04---
-
8/18/2019 ITP for Cable Tray Installation
4/4
Project : Cable Tray Installation Works Ref. No.
Drawing No. : Date :Specific Location :
Yes No N/A
1
2
3
4
5
6
7
8
9
10
DOOSAN Electrical Dept.
Name & Signature Name & Signature Name & Signature Name & Signature
Position Position Position Position
Date Date Date Date
page 4
Ensure there are no sharp 90 degrees bends are made.
hecked by : (Subcontractor DOOSAN QA/QC Dept. AES-VCM
Ensure the cable trays numbered according to cable trays route
layout on which KKS nos. are indicated and explained.
Check whether the exclusive earth continuity between the trays /
trunking / racks where the joints are made.
Earth jumper cable with crimp type terminals to be fitted to all cable
tray joints.
Check the condition of cable Supports, Racks, Trays and Trunking while
receiving.
Check size and type of the Supports, Racks, Trays and Trunking with
respect to the requisitions.
Check the installation is according to the designed layout drawing &
specification.
Check the leveling & alignment of tray & rack and expansion joints if
any are specified are in place.
No sharp edges cut to be permitted. Cutting edges of trays/trunkings are
touch-up painted.
Ensure the gap between parallel runs is quite enough to accommodate the
layer of cables.
Inspection Check List
CHECK ITEM
No Inspection elements
Verification & Approval Observed
Result
/ Remarks