itp for cable tray installation

Upload: ganga-daran

Post on 07-Jul-2018

1.582 views

Category:

Documents


179 download

TRANSCRIPT

  • 8/18/2019 ITP for Cable Tray Installation

    1/4

    21-May-12   Danny J.Y.Jeong K.J.Lim

    Date Drawn Checked Approved

    Owner :

     A

    Owner's Engineer :

    Details of Revision

      AES-VCM MONG DUONG

    POWER COMPANY LIMITED

    For Information

    Rev.

      oosan Heavy Industries

    Vietnam

    Dung Quat Economic Zone,

    Binh Thuan, Binh Son, Quang Ngai,

    Vietnam

    T +84 55 5618 900

    F +84 553 618 950

    Page 1

    Project : PC : T10206

    UAS : QE01

    Unit : PO

    Title :KKS : ZEN

    Reg. No.

    Revision :  A

    Drawing No. : Page-No :

    T10206-QE01-POZEN__-040203 INSPECTION

     AND TEST PLAN FOR

    CABLE TRAYS INSTALLATION

    040203

    T10206-QE01-P0ZEN-040203

    MONG DUONG II 2 X 560MW (NET) COAL FIRED POWER PROJECT

    1 of 4

    Contractor :

    Page 1

  • 8/18/2019 ITP for Cable Tray Installation

    2/4

    Rev. A

    2 of 4

    This note is only applicable for AES-VCM Mong Duong

    Detailed Legend

    S : Surveillance Point / DOOSAN / Subcontractor does not send a notification to AES-VCM Mong Duong

    except for the first or last operation on the basis of each process. AES-VCM Mong Duong

    could check the operation, if he is present at the site during the inspection by Doosan.

    R  : Report Review Point / DOOSAN / Subcontractor is required to prepare a certificate or document

    attesting to the satisfactory performance of the related test or inspection for review by

    -

    T10206-QE01-POZEN-040203

    DOOSAN

    AES-VCMITP for Cable Tray Installation

    Doc. No.

    Contractor 

    Page 2

    - .

    W : Witness Point / DOOSAN / Subcontractor shall submit request for inspection to AES-VCM to

    decide whether they will attend such inspection or not.

    H : Hold Point / Downstream construction and other activities shall not proceed

    without attendance or any written approval of AES-VCM Mong Duong.

    NOTE : The Site ITP and all of the abovementioned reports will be kept available by

      DOOSAN at anytime for control and or review by AES-VCM Mong Duong.

    Page 2

  • 8/18/2019 ITP for Cable Tray Installation

    3/4

    Doc. No.

    Contractor 

     A Sign A Sign A Sign

    R R R

    R R R

    H W WB1Check the installation is according to the designed

    layout drawing & specification.

     Approved Construction

    Drawing T10206-YD04---

     AES-VCM

     A.Material

    Receipt

     A1Check the condition of cable Supports, Racks, Trays

    and Trunking while receiving.Packing List

     A2Check size and type of the Supports, Racks, Trays

    and Trunking with respect to the requisitions.

    Material Technical

    Specification

    Item Name Oper. No. Inspection Process

    Specific Applicable drawing

    number, Standard Code number,Specification

    Inspection & Test Activities

    Subcontractor DOOSAN

    Inspection & Test Plan for Cable Tray

    InstallationAES-VCM

    H W W

    H W W

    H W W

    H W W

    H W W

    H W W

     Abb revi atio n : S: Surveillance R: Report Review W: Witness Inspection H: Hold Inspection

    Note :  All inspection shall be performed in accordance with the approved Site Inspection and Test Plans/Project Specifications

    B. Cable

    Tray

    Installation

    Ensure the cable trays numbered according to

    cable trays route layout on which KKS nos. are

    indicated and explained.

     Approved ConstructionDrawing T10206-YD04---

    B5Ensure there are no sharp 90 degrees bends are

    made.

     Approved Construction

    Drawing T10206-YD04---

    B6

    Ensure the cable trays numbered according to cable

    trays route layout on which KKS nos. are indicated and

    explained.

     Approved Construction

    Drawing T10206-YD04---

    B7

    No sharp edges cut to be permitted. Cutting edges of

    trays/trunkings are touch-up painted.

     Approved Construction

    Drawing T10206-YD04---

    B4Ensure the gap between parallel runs is quite enough

    to accommodate the layer of cables.

     Approved Construction

    Drawing T10206-YD04---

    B3

    B2 

    expansion joints if any are specified are in place.

     

    Drawing T10206-YD04---

  • 8/18/2019 ITP for Cable Tray Installation

    4/4

     Project : Cable Tray Installation Works Ref. No.

     Drawing No. : Date :Specific Location :

    Yes No N/A

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    DOOSAN Electrical Dept.

     Name & Signature Name & Signature Name & Signature Name & Signature

     Position Position Position Position

     Date Date Date Date

    page 4

    Ensure there are no sharp 90 degrees bends are made.

    hecked by : (Subcontractor DOOSAN QA/QC Dept. AES-VCM

    Ensure the cable trays numbered according to cable trays route

    layout on which KKS nos. are indicated and explained.

    Check whether the exclusive earth continuity between the trays /

    trunking / racks where the joints are made.

    Earth jumper cable with crimp type terminals to be fitted to all cable

    tray joints.

    Check the condition of cable Supports, Racks, Trays and Trunking while

    receiving.

    Check size and type of the Supports, Racks, Trays and Trunking with

    respect to the requisitions.

    Check the installation is according to the designed layout drawing &

    specification.

    Check the leveling & alignment of tray & rack and expansion joints if

    any are specified are in place.

     No sharp edges cut to be permitted. Cutting edges of trays/trunkings are

    touch-up painted.

    Ensure the gap between parallel runs is quite enough to accommodate the

    layer of cables.

    Inspection Check List

    CHECK ITEM

     No Inspection elements

    Verification & Approval Observed

    Result

    / Remarks